1. Control de Operación
-
Upload
alexander-primo -
Category
Documents
-
view
223 -
download
0
description
Transcript of 1. Control de Operación
27
Substation
Remote terminal unit
SCADA Master Station
Com
mun
icat
ion
link
Energy control center with EMS
EMS alarm displayEMS 1-line diagram
Simple basics• What is SCADA?
– Supervisory Control– Data Acquisition
• Purpose of SCADA?• What else now needed
– Controls – Look into future & able to control future events
• What is EMS?• Need for EMS?
Simple basics
• How to look into the future?• How to know present problems/state?• How & what actions to take?• Which are best actions?• Optimisation?• How can we control the events?
Simple basics
• What is State Estimation (SE)?• Why is it required?• How is it achieved?
– Techniques?– Process?
Need of the Modern Load Dispatch Center
• A robust Energy Management System capable of meeting the requirements of changed scenarios of deregulated market mechanisms.
• The EMS system shall be capable of being easily integrated with Market Management System.
7
Requirement of EMS Functions.
• Why do we need EMS functions?• Help grid operators in decision making .• Gives scientific logic for any actions.• Gives warning for any emergency situation.• Power system can be analysed for different
operating conditions.• To get a base case for further Analysis• ….
EMS functions objective
• Power system monitoring
• Power system control
• Power system economics
• Security assessment
EMS Functions : Classification Based on Function
1. State Estimation
2. Power Flow Analysis
3. Contingency Analysis
4. Security enhancement
EMS Functions : Classification Based on Time Domain
• Pre Dispatch Functions• Load Forecasting/Inflow
forecasting• Resource Scheduling And
Commitment• Network Outage Planning
• Real Time Operation• State Estimator (RTNET)• Real Time contingency analysis
(RTCA)• Real Time Security Enhancement
(RTSENH)• Real Time Generation Control
(RTGEN)• Voltage Var Dispatch
• Post Dispatch / off line activities
• Dispatcher training Simulator
• Other features like– Historicar Data Recording,– Historical Information
Management,– Sequence Of Events,– Load Flow Studies ( STNET)– ….
Quantity to be
telemetered
Transducer A/D converter
Telemeter transmitter
Telemeter receiver
Computer
D/A converter
Indicating meter
Recording meter
Signal circuit (wire line, PLC, microwave, etc.)
Figure 5b: Bus-branch representation Figure 5a: Breaker-switch representation
DyLiacco’s operational decision paradigm
Normal (secure)
Emergency
Restorative
Extreme emergency.Separation, cascading
delivery pointinterruption,
load shedding
Alert,Not secure
Transmission loading reliefprocedures
SCADA
Overloads & Voltage Problems
Potential Overloads &
Voltage Problems
Breaker/Switch Status Indications
System Model Description
Telemetry & Communications equipment
State Estimator
Network Topology program
AGC
Economic Dispatch
Calculation
OPF
Contingency Selection
Contingency Analysis Security Constrained OPF
Display Alarms
Updated System Electrical Model
Analog Measurements
Display to Operator
Power flows, Voltages etc.,
Display to Operator
Bad Measurement Alarms
Generator Outputs Generation Raise/Lower Signals
State Estimator Output
Substation RTUs
Mediciones
Filtracion
Estimacion deEstado
Topologia de lared
Pronostico decarga en la barra
Modelamientoexterno de la red
Flujo de carga enlinea
Evaluacion deContingencia
Seleccion deContingencia
verificacion delimites
Procesamiento dedatos erroneos
Analisis deObservabilidad
Estadonormal
Estadoemergencia
Estadorestauracion
SISTEMA DE POTENCIA
OPERADOR DEL SISTEMA
CONFIGURADOR ESTIMADOR PREDICCION DE LA CARGA
AGC
PLANEAMIENTO OPERATIVO
SUPERVISION TIEMPO REAL
EVALUACION DE CONTINGENCIA
ESTRATEGIAS CORRECTIVAS
OPERACIÓN ECONOMICA
EQUIVALENTES EXTERNOS
SELECTOR CONTINGENCIAS
PREDICCION DE CARGA
FLUJO DE CARGA EN LINEA FLUJO DE CARGA
OPTIMO