    Developing future Infrastructure Portfolio

    for Sustainable Development

    PIARC International Seminar on Road Infrastructure Management

    Current Practice and Development Prospective

    Cancn (MEX) 31 March to 2 April 2014

    Hamid ZarghampourHamid Zarghampour, Senior Transport Specialist ,

  • 8/11/2019 1-1_Hamid_Zarghampour.pdf

    2/21

    TC 4.1 Management of Road Assets

    CT 4.1 Gestion du patrimoine routier

    PRESENTATION OUTLINE

    From road maintenance to developing societies

    Basic concept of modern Road Asset Management

    The importance of strategy for the realization of the

    activities in the prepared port folio

    Developing Future Infrastructure Portfolios, Hamid Zarghampour - 2014-03-31 PIARC International Seminar Cancn (MEX)

  • 8/11/2019 1-1_Hamid_Zarghampour.pdf

    3/21

    TC 4.1 Management of Road Assets

    CT 4.1 Gestion du patrimoine routier

    From road maintenance to developing societies

    Developing Future Infrastructure Portfolios, Hamid Zarghampour - 2014-03-31 PIARC International Seminar Cancn (MEX)

  • 8/11/2019 1-1_Hamid_Zarghampour.pdf

    4/21

    TC 4.1 Management of Road Assets

    CT 4.1 Gestion du patrimoine routier

    The desired state in future forms the basis for our

    business cases!

    ability to develop effective

    infrastructure portfolios for future

    Developing Future Infrastructure Portfolios, Hamid Zarghampour - 2014-03-31 PIARC International Seminar Cancn (MEX)

  • 8/11/2019 1-1_Hamid_Zarghampour.pdf

    5/21

    TC 4.1 Management of Road Assets

    CT 4.1 Gestion du patrimoine routier

    Common concepts on predicting the future

    Probable Possible Desirable

    What willhappen! What wouldhappen? What would we like to happen?

    Prognoses World scenarios Back casting

    Developing Future Infrastructure Portfolios, Hamid Zarghampour - 2014-03-31 PIARC International Seminar Cancn (MEX)

  • 8/11/2019 1-1_Hamid_Zarghampour.pdf

    6/21

    TC 4.1 Management of Road Assets

    CT 4.1 Gestion du patrimoine routier

    Common concepts on predicting the future

    Probable Possible Desirable

    What willhappen! What wouldhappen? What would we like to happen?

    Prognoses World scenarios Back casting

    Developing Future Infrastructure Portfolios, Hamid Zarghampour - 2014-03-31 PIARC International Seminar Cancn (MEX)

  • 8/11/2019 1-1_Hamid_Zarghampour.pdf

    7/21

  • 8/11/2019 1-1_Hamid_Zarghampour.pdf

    8/21

    TC 4.1 Management of Road Assets

    CT 4.1 Gestion du patrimoine routier

    PRESENTATION OUTLINE

    From road maintenance to developing societies

    Basic concept of modern Road Asset Management

    The importance strategy for the realization of the activit ies

    in the prepared portfolio

    Developing Future Infrastructure Portfolios, Hamid Zarghampour - 2014-03-31 PIARC International Seminar Cancn (MEX)

  • 8/11/2019 1-1_Hamid_Zarghampour.pdf

    9/21

    TC 4.1 Management of Road Assets

    CT 4.1 Gestion du patrimoine routier

    Important elements in Road Asset Management

    E

    F

    F

    E

    CT

    S1

    in relation to

    Road Network modelling, Road

    Classes, descriptions of its type and

    utilization (such as paved roads

    connecting to National Highway,

    commuting, etc.)

    Utilization

    Road condition for different

    sections is described by a number

    of predefined technical parametersCondition

    INPUT

    PRIORITISING OF

    MEASURES

    Estimation of costs for conducting

    effective measures to reach the

    desired condition, assuring safe

    and green mobility for the users

    Cost

    estimation,

    Capital/rec

    urrent

    Estimated effects

    Socioeconmic

    Road user costs

    Cost estimates

    ResultSuitable

    combination of

    measures to

    ensure maximum

    benefits at the

    right cost during

    the plan period

    Developing Future Infrastructure Portfolios, Hamid Zarghampour - 2014-03-31 PIARC International Seminar Cancn (MEX)

  • 8/11/2019 1-1_Hamid_Zarghampour.pdf

    10/21

    TC 4.1 Management of Road Assets

    CT 4.1 Gestion du patrimoine routier

    10

    Example: Objectives in a 5 year maintenance plan (rural Development)

    Target levels and impacts of di fferent budget scenarios, 2013-2017

    Description

    Only routine maintenance & urgent works

    On-going projects which are financed by

    the government and donors helps to keep

    the economic acti vities at the same level

    as today

    No measures for addressing needs for

    safe transportations

    Impact

    Economic

    activities Budget

    Implementation of a 5-Year Rehabilit ation

    program

    Preserving roads in good conditi on and,

    avoiding the roads in satisfactory

    condition deteriorating to poor condition

    Sustainable Regional Development

    Rehabili tation of about 70% of the most

    important links in poor condition

    Modernization of the road infrastructure

    (standard road geometry, non-

    motor ized paths, etc..)

    Improvements for safe transportations

    Positive impact

    No changes

    Road user

    cost

    Traffic

    safety

    Negative impact

    Pursue same

    maintenance works as

    for the past 3 years

    Prioritize the important

    links for connecting rural

    areas to major cities and,

    to National Highways

    Develop and modernize

    the road network to

    encourage the economic

    growth through the use

    of the potentials in the

    province

    1

    2

    3

    Developing Future Infrastructure Portfolios, Hamid Zarghampour - 2014-03-31 PIARC International Seminar Cancn (MEX)

  • 8/11/2019 1-1_Hamid_Zarghampour.pdf

    11/21

    TC 4.1 Management of Road Assets

    CT 4.1 Gestion du patrimoine routier

    11

    Example: Objectives in a 5 year maintenance plan (rural Development)

    Target levels and impacts of di fferent budget scenarios, 2013-2017

    Description

    Only routine maintenance & urgent works

    On-going projects which are financed by

    the government and donors helps to keep

    the economic acti vities at the same level

    as today

    No measures for addressing needs for

    safe transportations

    Impact

    Economic

    activities Budget

    Implementation of a 5-Year Rehabilit ation

    program

    Preserving roads in good conditi on and,

    avoiding the roads in satisfactory

    condition deteriorating to poor condition

    Sustainable Regional Development

    Rehabili tation of about 70% of the most

    important links in poor condition

    Modernization of the road infrastructure

    (standard road geometry, non-

    motor ized paths, etc..)

    Improvements for safe transportations

    Positive impact

    No changes

    Road user

    cost

    Traffic

    safety

    Negative impact

    Pursue same

    maintenance works as

    for the past 3 years

    Prioritize the important

    links for connecting rural

    areas to major cities and,

    to National Highways

    Develop and modernize

    the road network to

    encourage the economic

    growth through the use

    of the potentials in the

    province

    1

    2

    3

    Developing Future Infrastructure Portfolios, Hamid Zarghampour - 2014-03-31 PIARC International Seminar Cancn (MEX)

  • 8/11/2019 1-1_Hamid_Zarghampour.pdf

    12/21

    TC 4.1 Management of Road Assets

    CT 4.1 Gestion du patrimoine routier

    Example: Objectives in a 5 year maintenance plan (rural Development)

    Target levels and impacts of di fferent budget scenarios, 2013-2017

    Description

    Only routine maintenance & urgent works

    On-going projects which are financed by

    the government and donors helps to keep

    the economic acti vities at the same level

    as today

    No measures for addressing needs for

    safe transportations

    Impact

    Economic

    activities Budget

    Implementation of a 5-Year Rehabilit ation

    program

    Preserving roads in good conditi on and,

    avoiding the roads in satisfactory

    condition deteriorating to poor condition

    Sustainable Regional Development

    Rehabili tation of about 70% of the most

    important links in poor condition

    Modernization of the road infrastructure

    (standard road geometry, non-

    motor ized paths, etc..)

    Improvements for safe transportations

    Positive impact

    No changes

    Road user

    cost

    Traffic

    safety

    Negative impact

    Pursue same

    maintenance works as

    for the past 3 years

    Prioritize the important

    links for connecting rural

    areas to major cities and,

    to National Highways

    Develop and modernize

    the road network to

    encourage the economic

    growth through the use

    of the potentials in the

    province

    1

    2

    3

    Developing Future Infrastructure Portfolios, Hamid Zarghampour - 2014-03-31 PIARC International Seminar Cancn (MEX)

  • 8/11/2019 1-1_Hamid_Zarghampour.pdf

    13/21

    TC 4.1 Management of Road Assets

    CT 4.1 Gestion du patrimoine routier

    PRESENTATION OUTLINE

    From road maintenance to developing societies

    Basic concept of modern Road Asset Management

    The importance strategy for the realization of the activit ies

    in the prepared portfolio

    Developing Future Infrastructure Portfolios, Hamid Zarghampour - 2014-03-31 PIARC International Seminar Cancn (MEX)

  • 8/11/2019 1-1_Hamid_Zarghampour.pdf

    14/21

    TC 4.1 Management of Road Assets

    CT 4.1 Gestion du patrimoine routier

    Strategies is about making decisions/ declaring intentions

    Developing Future Infrastructure Portfolios, Hamid Zarghampour - 2014-03-31 PIARC International Seminar Cancn (MEX)

  • 8/11/2019 1-1_Hamid_Zarghampour.pdf

    15/21

    TC 4.1 Management of Road Assets

    CT 4.1 Gestion du patrimoine routier

    Strategic intent example from Volvo

    - Skoda

    - Citroen

    - Renault

    - VW

    - Volvo

    - Ford

    - BMW

    - Mercedez

    - Audi

    Price

    Brand

    Goal

    To sell Volvo for USD 50.000

    Time horizon; 5 years

    Developing Future Infrastructure Portfolios, Hamid Zarghampour - 2014-03-31 PIARC International Seminar Cancn (MEX)

  • 8/11/2019 1-1_Hamid_Zarghampour.pdf

    16/21

    TC 4.1 Management of Road Assets

    CT 4.1 Gestion du patrimoine routier

    Strategic intent example from Volvo

    x

    x

    Quality

    2013 2014 2017

    x

    x

    Service

    Research and Development

    Customer groups

    Brand/ Image

    x

    y

    2,08

    1

    2

    3

    4

    5

    6

    x

    y

    y

    y

    y

    y

    Developing Future Infrastructure Portfolios, Hamid Zarghampour - 2014-03-31 PIARC International Seminar Cancn (MEX)

  • 8/11/2019 1-1_Hamid_Zarghampour.pdf

    17/21

    TC 4 1 M t f R d A t

  • 8/11/2019 1-1_Hamid_Zarghampour.pdf

    18/21

    TC 4.1 Management of Road Assets

    CT 4.1 Gestion du patrimoine routier

    Developing Future Infrastructure Portfolios, Hamid Zarghampour - 2014-03-31 PIARC International Seminar Cancn (MEX)

    TC 4 1 M t f R d A t

  • 8/11/2019 1-1_Hamid_Zarghampour.pdf

    19/21

    TC 4.1 Management of Road Assets

    CT 4.1 Gestion du patrimoine routier

    Developing Future Infrastructure Portfolios, Hamid Zarghampour - 2014-03-31 PIARC International Seminar Cancn (MEX)

    TC 4 1 Management of Road Assets

  • 8/11/2019 1-1_Hamid_Zarghampour.pdf

    20/21

    TC 4.1 Management of Road Assets

    CT 4.1 Gestion du patrimoine routier

    Strategies are needed for doing the right things, the right way!

    Developing Future Infrastructure Portfolios, Hamid Zarghampour - 2014-03-31 PIARC International Seminar Cancn (MEX)

    TC 4 1 Management of Road Assets

  • 8/11/2019 1-1_Hamid_Zarghampour.pdf

    21/21

    TC 4.1 Management of Road Assets

    CT 4.1 Gestion du patrimoine routier

    Thank you!