03 - Jaringan Kerja Proyek
-
Upload
uud-achmad -
Category
Documents
-
view
225 -
download
3
description
Transcript of 03 - Jaringan Kerja Proyek
1
MEMBANGUN RENCANA JARINGAN KERJA
PROYEK
4
Project Network
• Tool used for planning, scheduling, and
monitoring project progress
• Developed from WBS
• Graphic flowchart of the project job plan
• Depicts the project activities, the
interdependencies of activities that must be
completed, start time and finish of activities
and critical path
5
Rollup of Network Plans
WP-2
A
B
C
D
E
F
WP-1
WP-4
WP-3
Level 1 - Milestone Plan
Level 2 - Plans
Level 3 - Plans
6
WBS/Work Packages to Network
Circuit
board
Design
cost
account
Production
cost
account
Test
cost
account
Software
cost
account
Lowest
element
O
r
g
a
n
i
z
a
t
i
o
U
n
i
t
s
DesignWP D-1-1 Specifications
WP D-1-2 Documentation
ProductionWP P-10-1 Proto 1
WP P-10-2 Final Proto 2
Test systemsWP T-13-1 Test
SoftwareWP S-22-1 Software preliminary
WP S-22-1 Software final version
B
Proto 1
5
D
Final
proto 2
4
A
Specifications
and documentation
2
C
Preliminary
software
3
F
Final
software
2
K
Test
3
A
D-1-1
D-1-2
B
P-10-1
D
P-10-2
F
S-22-2
K
T-13-1
C
S-22-1
7
Constructing a Project Network
• Two Approaches:– Activity on Node
– Activity on Arch
• Basic rules:– Network flows typically from the left to right
– An activity cannot begin until all preceding connected activities have been completed
– Arrows on network indicate precedence and flow. Arrows can cross over each other
– Each activity should have a unique identification number
– An activity identification number must be larger than that of activities that precede it
– Looping is not allowed
– Conditional statements is not allowed
– Experience suggest that when there are multiple starts, a common start node can be used to indicate a clear project beginning on the network. Similarly, a single project end node can be used to indicate a clear ending.
8
Activity on Arch
Menggambarkan
kejadian/event
Menggambarkan Aktivitas
9
Contoh 1
Aktivitas Aktivitas yang Mendahului
A B C D
- - A B
1
2
3
4
10
Contoh 2
Aktivitas Aktivitasyang
mendahului
Aktivitas Aktivitasyang
mendahului
ABCD
--AB
EFGH
C, DDEF
11
NETWORK
52
3 4
1
6
7
A
B
C
D
E
F
G
H
D
Dummy
Activity
12
Analisa Lintasan Kritis
13
Tujuannya adalah menentukan :
• ES : Earliest activity start time
• LS : Latest activity start time
• EF : Earliest activity finish time
• LF : Latest activity finish time
• S : Activity slack time (LS - ES) atau (LF - EF)
EF = ES + t
LF = LS + t
S = LS - ES
atau
S = LF - EF
14
No.
Node/
Event
ES
LS
15
Perhitungan Maju & Mundur
1
2
3 4
5
6
7
A
B
C
D
E
F
G
H
D
DU
MM
Y A
CT
IVIT
Y
0
5
4
8
6 7
5
3
4
0
5
4 12
11 / 12
12 19
17
21 / 22
22
22
18
1912
12/13
124
0
6
1/0
ES
LSID
16
Lintasan Kritis
1
2
3 4
5
6
7
A
B
C
D
E
F
G
H
D
DU
MM
Y A
CT
IVIT
Y
0
5
4
8
6 7
5
3
4
0
5
4 12
12 19
17
22
22
18
1912
124
0
6
Activity-on-Node Network Fundamentals
X
Y
Z
Y and Z are preceded by X
Y and Z can begin at the
same time, if you wish
(B)
A B C
A is preceded by nothing
B is preceded by A
C is preceded by B
(A)
J
K
L
M
J, K, & L can all begin at
the same time, if you wish
(they need not occur
simultaneously)
All (J, K, L) must be
completed before M can
begin
but
X Z
AAY
(C)
(D)
Z is preceded by X and Y
AA is preceded by X and Y
18
Example
Activity Description Preceding
Activity
Activity
Time
A Application approval None 5
B Construction plan A 15
C Traffic study A 10
D Service availabiality check A 5
E Staff report B, C 15
F Commision approval B, C, D 10
G Wait for construction F 170
H Occupancy E, G 35
ES ID EF
SL
LS Dur LF
Description
Simbol
Activity-on-Node Network Fundamentals
KOLL BUSINESS CENTER
County Engineers Design Department
B
15
Construction
plans
C
10
Traffic
study
D
5
Service
check
A
5
Application
approval
ES ID EF
SL
LS Dur LF
Description
F
10
Commission
approval
G
170
Wait for
construction
H
35
Occupancy
E
15
Staff report
EF
Activity-on-Node Network with Slack
ES ID EF
SL
LS Dur LF
Description
LS EF
KOLL BUSINESS CENTER
County Engineers Design Department
20
15
185
185
10
15
5
20
20
10
20
15
0 A 5
0
0 5 5
Application
approval
5 D 10
10
15 5 20
Service
check
5 B 20
0
5 15 20
Construction
plans
5 C 15
5
10 10 20
Traffic
study
20 F 30
0
20 10 30
Commission
approval
20 E 35
165
185 15 200
Staff report
30 G 200
0
30 170 200
Wait for
construction
200 H 235
0
200 35 235
Occupancy
Air Control Inc., Custom Order
Project—Network Diagram
1 Order
review2
0 2
0 2
2
3
4
5
Software
development
Order
standard
parts
Produce
standard
parts
Design
custom parts
18
2 20
22 40
15
2 17
15 30
10
2 12
5 15
13
2 15
2 15
6
7 8
Manufacture
custom
hardware
Assemble Test
Activity8#
Legend
15
15 30
15 30
10
30 40
30 40
5
40 45
40 45
Duration
ES EF
LS LF
Air Control Inc., Custom Order
Project—Gantt Chart
0 7 14 21 28 35 42 49
2
13
15
10
18
15
10
5
Order review
Design custom parts
Order standard parts
Produce standard parts
Software development
Manufacture custom
hardware
Assemble
Test
23
Air Control Inc., Custom Order
Project—Network with Dates
1 Order
review2
1-Jan 2-Jan
1-Jan 2-Jan
2
3
4
5
Software
development
Order
standard parts
Produce
standard parts
Design
custom parts
18
2-Jan 20-Jan
22-Jan 9-Jan
15
2-Jan 17-Jan
15-Jan 30-Jan
10
2-Jan 12-Jan
5-Jan 15-Jan
13
2-Jan 15-Jan
2-Jan 15-Jan
6
7 8
Manufacture
custom
hardware
Assemble Test
Activity8#
Legend
15
15-Jan 30-Jan
15-Jan 30-Jan
10
30-Jan 9-Jan
30-Jan 9-Jan
5
9-Jan 14-Jan
9-Jan 14-Jan
Duration
ES date EF date
LS date LF date
24
Example of Laddering Using
Finish-to-Start Relationship
Trench
1/3
Trench
2/3
Trench
3/3
Lay pipe
1/3
Lay pipe
2/3
Lay pipe
3/3
Refill
1/3
Refill
2/3
Refill
3/3
AON network
25
Finish-to-Start Relationship
X YLag 2
26
Start-to-Start Relationship
Activity
M
Activity
N
Activity
P
Activity
Q
Lag 5
A B
27
Use of Lags to Reduce Detail
Trench
1 mile
Lay pipe
1 mile
Lag 3
Refill
1 mile
Lag 3
28
Lag 4Prototype
Testing
Finish-to-Finish Relationship
29
Start-to-Start Relationship
Lag 3
System
documentation
Testing
30
Lag 2
Code
Debug
Lag 4
Combination Relationships
31
5 B 15
00
5 10 15
10 D 25
1111
21 15 36
0 A 5
0 0
0 5 5
ES ID EF
SL SL
LS Dur LF
15 E 30
05
30 10 45
30 F 40
05
30 10 45
40 H 50
5 0
45 5 50
15 C 20
5 5
20 5 25
Legend25 G 40
110
36 4 40
Lag 5
Lag 10
Lag 10
Lag 5Lag 10
Network Using Lags
32
5 B 6
0
5 1 6
11 E 21
0
11 10 21
0 A 5
0
0 5 5
ES ID EF
SL
LS Dur. LF
Description
6 D 10
8
14 4 18
10 F 13
8
18 3 21
21 F 25
0
21 4 25
6 C 11
0
6 5 11
Legend5 G 13
Hammock
8
Hammock Activity Example