02 Final Paper Northern Blvd Crossing Frozen Soil Arch - Curry Ziegler

11
ARTIFICIAL GROUND FREEZING FOR EAST SIDE ACCESS NORTHERN BOULEVARD CROSSING FROZEN SOIL ARCH QUEENS, NEW YORK Adam Curry, P.E., Moretrench American Corporation, Rockaway, NJ, USA Gregory Ziegler, V.P., P.E., Moretrench American Corporation, Rockaway, NJ, USA Abstract: The CQ039 Northern Boulevard Crossing Contract was one part of the larger MTA Capital Construction’s East Side Access Project connecting the Long Island Railroad with NYC’s Grand Central Station. This contract required the construction of a SEM tunnel between two 85-ft deep access shafts. Difficulties included working as deep as 55 feet below the groundwater table while mining through variable subsurface conditions with preclusions to dewatering and settlement. In addition, the tunneling would occur directly beneath an active subway line, an elevated rail line (both supported on piles), and Northern Boulevard, a main artery through Queens, New York. In order to create both a groundwater cutoff and a temporary excavation support during the tunneling operations, the tunneling contractor selected an artificially frozen soil arch, installed horizontally from the two access shafts. In addition to a discussion of the overall approach, this paper includes a detailed description of the drilling and surveying procedures used for the installation of the horizontal freeze pipes. It also summarizes the results of the various tests performed at the site to verify the performance of the freeze system and the data collected while monitoring the freeze formation. The paper closes with a synopsis of the results and an update on the project. I INTRODUCTION The New York City Metropolitan Transit Authority awarded the CQ-39 contract to Schiavone Kiewit JV to construct a new tunnel structure below Northern Boulevard connecting the Queens open-cut area to the existing bellmouth north of Northern Boulevard. The CQ-39 contract was part of the larger East Side Access Project. The goal of the project is to connect the Long Island Railroad (LIRR) lines in Queens to a new LIRR terminal beneath Grand Central Terminal in Manhattan. The main intent is to increase the LIRR’s capacity and shorten travel time for Long Island commuters traveling to the east side of Manhattan. The proposed tunnel utilized Sequential Excavation Method (SEM) tunneling methods with a frozen arch to act as temporary structural support and groundwater cutoff. The SEM method was developed in the 1950’s for work in consolidated formations and has been advanced and adapted to become suitable for an array of soft ground conditions. As its name implies, SEM construction utilizes excavations in short incremental lengths with benches sequenced to maintain weight against the face and reduce the span of the crown. Initial support is provided with a spray-on shotcrete lining, typically reinforced with steel arches applied immediately upon excavation. Generally completed by hand, there is no mobilization and setup of a Tunnel Boring Machine (TBM).

description

Underground structures

Transcript of 02 Final Paper Northern Blvd Crossing Frozen Soil Arch - Curry Ziegler

  • ARTIFICIAL GROUND FREEZING FOR EAST SIDE ACCESS NORTHERN

    BOULEVARD CROSSING FROZEN SOIL ARCH QUEENS, NEW YORK

    Adam Curry, P.E., Moretrench American Corporation, Rockaway, NJ, USA

    Gregory Ziegler, V.P., P.E., Moretrench American Corporation, Rockaway, NJ, USA

    Abstract: The CQ039 Northern Boulevard Crossing Contract was one part of the larger MTA Capital

    Constructions East Side Access Project connecting the Long Island Railroad with NYCs Grand

    Central Station. This contract required the construction of a SEM tunnel between two 85-ft deep

    access shafts. Difficulties included working as deep as 55 feet below the groundwater table while

    mining through variable subsurface conditions with preclusions to dewatering and settlement. In

    addition, the tunneling would occur directly beneath an active subway line, an elevated rail line (both

    supported on piles), and Northern Boulevard, a main artery through Queens, New York. In order to

    create both a groundwater cutoff and a temporary excavation support during the tunneling

    operations, the tunneling contractor selected an artificially frozen soil arch, installed horizontally from

    the two access shafts.

    In addition to a discussion of the overall approach, this paper includes a detailed description of the

    drilling and surveying procedures used for the installation of the horizontal freeze pipes. It also

    summarizes the results of the various tests performed at the site to verify the performance of the

    freeze system and the data collected while monitoring the freeze formation. The paper closes with a

    synopsis of the results and an update on the project.

    I INTRODUCTION

    The New York City Metropolitan Transit Authority awarded the CQ-39 contract to Schiavone Kiewit

    JV to construct a new tunnel structure below Northern Boulevard connecting the Queens open-cut

    area to the existing bellmouth north of Northern Boulevard. The CQ-39 contract was part of the

    larger East Side Access Project. The goal of the project is to connect the Long Island Railroad

    (LIRR) lines in Queens to a new LIRR terminal beneath Grand Central Terminal in Manhattan. The

    main intent is to increase the LIRRs capacity and shorten travel time for Long Island commuters

    traveling to the east side of Manhattan.

    The proposed tunnel utilized Sequential Excavation Method (SEM) tunneling methods with a frozen

    arch to act as temporary structural support and groundwater cutoff. The SEM method was developed

    in the 1950s for work in consolidated formations and has been advanced and adapted to become

    suitable for an array of soft ground conditions. As its name implies, SEM construction utilizes

    excavations in short incremental lengths with benches sequenced to maintain weight against the

    face and reduce the span of the crown. Initial support is provided with a spray-on shotcrete lining,

    typically reinforced with steel arches applied immediately upon excavation. Generally completed by

    hand, there is no mobilization and setup of a Tunnel Boring Machine (TBM).

  • Figure 1: SEM Excavation East Side Access Northern Boulevard Crossing

    Artificial ground freezing is the conversion of in situ pore water into ice through the circulation of cold

    liquid through a system of pipes installed in the ground to impart compressive strength and

    impermeability to a soil. The frozen in situ pore water acts as a bonding agent creating a frozen soil

    mass with noticeably improved compressive strength and decreased permeability compared to the

    surrounding unfrozen soils (Powers, Corwin, Schmall, Kaeck, 2007).

    A typical ground freezing system for a shaft consists of a series of freeze pipes installed along the

    perimeter of the proposed excavation, extending into the subsurface strata. Within each of the freeze

    pipes, a smaller diameter feed pipe is installed permitting the downward circulation of the cooling

    liquid which then flows back to the surface through the annulus of the larger pipe. Calcium chloride

    (brine) is chilled by a series of electrically powered refrigeration plants. As the circulation of the brine

    progresses, cylindrical columns of frozen soil grow around each pipe. The diameter of the columns

    increases with time, forming a virtually water-tight impermeable barrier.

  • II DESIGN OF GROUND FREEZING SYSTEM

    The design process was a joint effort between the Owners Engineers and the Construction Team.

    The design process included several independent yet integrated components summarized below:

    Thermal analysis to determine the required freeze pipe spacing and temperature

    profile.

    Structural analysis to ensure the frozen mass will have sufficient strength to act as

    temporary structural support during excavation prior to shotcrete.

    The geology in the general area in sequence was Fill (Stratum 1), Organic Deposits (Stratum 8),

    Mixed Glacial Deposits (Stratum 2, 3, and 4), Glacial Till (Stratum 5), Decomposed Rock (Stratum 6)

    and Bedrock (Stratum 7). Figure 2 provides a geologic profile.

    Figure 2: Geologic Profile

    The predominant soil unit in the frozen arch was Stratum 4. Other partial components were Stratum

    3 at higher elevations, in parts of the crown; and Stratum 5 closer to the base of the arch. Stratum 6

    consisted of decomposed or weathered rock. The base of the arch was keyed into rock (Stratum 7).

    From generally established knowledge of the relevant strengths of frozen soils, it was evident that

    Stratum 3 and Stratum 5 (both sands/silts, with gravel) would have greater frozen strength properties

    to those in Stratum 4. Frozen soil strength testing was therefore limited to Stratum 4.

  • In order to describe the stress and deformation behavior, the following tests were performed by CDM

    Consultants in Bochum Germany.

    Testing of unfrozen and thawed samples

    o Uniaxial compression tests

    o Triaxial undrained, consolidated compression tests

    Testing of frozen samples

    o Uniaxial compression tests (T = -10 C, T = -15 C)

    o Triaxial compression tests (T = -15 C)

    o Uniaxial creep tests (T = -15 C)

    The following table summarizes the results of the lab tests on Stratum 4:

    TemperatureUniaxial Compressive

    Strength

    Shear

    Parameters

    2 week 2 month 3 months 6 months 2 week 2 month 3 months 6 months 2 week 2 month 3 months 6 months

    Stratum 4 -10 4.95 10.0 / 2.14 330 325 320 320 1.18 1.13 1.08 1.05 0.49 0.47 0.45 0.44

    Stratum 4 -15 6.85 10.0 / 2.2 390 385 380 375 1.63 1.55 1.5 1.45 0.68 0.65 0.63 0.61

    Layer

    o/MN/m2MN/m2

    Time dependent values

    Time Dependent Frozen Soil Parameter

    Youngs Modulus of Elasticity Compressive Strength (allowable) cohesion intercept (allowable)

    MN/m2 MN/m2

    Short term values

    (Lab Conditions)

    oC MN/m2

    Table 1: Results of Frozen Soil Tests

    Based on the results of the soil investigation the following criteria needed to be met to achieve an

    acceptable frozen arch:

    Arch minimum thickness of 6 feet

    Arch temperature of -32 degrees Celsius at the freeze pipes and -1 degrees Celsius at the

    intrados and extrados

    The thermal analysis on this project was conducted using the finite element (FEM) heat transfer

    program Temp/W, developed and distributed by GeoSlope of Calgary, Alberta. Several models were

    evaluated as part of the thermal analyses for this project. The results of the analyses are

    summarized below:

    4.0 ft. nominal spacing yields closure in 16 days and a 6 ft. thickness in 35 days.

  • 5.0 ft. nominal spacing yields closure in 25 days and a 6 ft. thickness in 46 days.

    6.0 ft. nominal spacing yields closure in 34 days and a 6 ft. thickness in 55 days.

    7.0 ft. nominal spacing yields closure in 46 days and a 6 ft. thickness in 64 days.

    Based on the results it was determined that 43 freeze pipes on approximately 3.5 foot spacing would

    be the basis for the design.

    III CONSTRUCTION

    The initial ground freezing approach required the installation of (81) horizontally drilled holes

    approximately 120 feet in length from the newly constructed Queens open-cut area to the existing

    excavation located to the north of Northern Blvd. The arrangement consisted of 43 freeze pipes, 3

    temperature monitoring pipes, 22 compensation grout holes/heat pipes, 3 draining wells, and 10 void

    grout holes. In addition, 4 vertical freeze pipes were also required. The purpose of the void grout,

    compensation grout, and heat pipes were to mitigate heave or settlement during the construction

    process.

    Combinations of track mounted geotechnical dual rotary drill rigs and horizontal skid mounted coring

    rigs were utilized to drill the holes. The contractor anticipated encountering obstructions that included

    boulders, jet grout, concrete filled steel pipe piles, slurry wall reinforcement, and rock. In the event

    that an obstruction was encountered and was not able to be penetrated, the contractor had the

    ability to telescope drill casing giving a higher chance of success. As a contingency, the contractor

    supplied a horizontally mounted sonic drill rig to penetrate the obstructions in the event that

    traditional rotary or coring methods were unsuccessful.

    Horizontal boreholes penetrated the slurry wall in varying depths from 20 to 55 feet below the water

    table. Given the nature of the silty sands to flow under these conditions it was critical for the drilling

    to be performed utilizing a groundwater control device (GWCD). The GWCD consisted of a steel

    trumpet cored and mounted in the slurry wall. Attached to each trumpet was a combination of

    chambers, valves, and seals that allowed drilling to occur with minimal to no soil loss.

  • Figure 3: Groundwater Control Device

    It was important to accurately survey the borehole upon completion to ensure that adequate pipe to

    pipe spacing was achieved. The contractor chose to utilize a Reflex Gyroscope to perform the

    borehole surveys. Several factors needed to be considered when choosing the correct instrument. In

    addition to accuracy, the gyroscope needed to be able to survey on a flat horizontal plane as well as

    inside a steel casing. These criteria eliminated standard inclinometers and magnetic survey

    instruments. The reflex gyro utilized a digital micro gyro which consisted of a silicon microchip and

    an integrated circuit assembled inside a nonmagnetic package. This combination allowed the

    instrument to provide both azimuth and dip on any plane and in any environment. The probe

    transmitted the data to a field PC utilizing Bluetooth technology. Once processed the output could be

    plotted in AutoCad for easy interpretation.

  • Figure 4: Surveying Using Gyroscope

    Prior to any freeze pipe installation it was required by specification that the contractor demonstrate

    the chosen means and methods for settlement control. A trial grout program was established which

    consisted of a combination of void grouting and compensation grouting. Void grouting was

    conducted utilizing a non-cementitious grout injected through the end of the drill casing in stages as

    the casing was retracted. Compensation grout consisted of repeat injections of both cementitious

    and non-cementitious grout through Tube-A-Manchette (TAM) pipes. The trial grout program was

    considered successful once the contractor demonstrated the ability to lift the subway structure as

    measured by total stations with prisms inside the subway structure.

    In addition to the trial grout program, an additional eight (8) void grout holes were completed prior to

    the start of freeze pipe installation. It was believed based on previous work in the area that voids

    existed underneath the subway structure that would result in uneven heave or settlement during the

    construction work. The void grouting would reduce the number and size of voids allowing for more

    predictable settlement and heave. In total 19,100 gallons of non-cementitious grout was injected

    prior to the start of freeze pipe installation.

    The first freeze pipe was installed utilizing high speed rotation coring methods. Subsequent survey of

    the pipe indicated a much higher deviation downward than would be accepted based on the design

    and that the soils near the top of the arch were less dense than anticipated. It was determined to do

    an additional 10 void grout holes to consolidate the soils prior to continuing with the freeze pipe

    installation. An additional 40,000 gallons of non-cementitious grout was injected beneath the subway

    box.

  • Figure 5: Freeze Pipe Installation High Speed Coring Rig

    Freeze pipe installation was completed after approximately twelve months including the time

    required by the general contractor to excavate and brace a portion of the bellmouth that was

    previously unexcavated. In total 62 freeze pipes were installed utilizing several different types of drill

    rigs to overcome access and different strata.

  • Figure 6: Installing Freeze Pipes with Geotechnical Drill Rig

    In addition to freeze pipes, it was necessary to install several temperature monitoring pipes.

    Generally, these pipes are drilled and constructed similar to freeze pipes but instead of circulating

    brine they are equipped with RTD sensors, thermocouple wire, or fiber optic wire. The temperature

    probes were used to measure the change in the ground temperature as the freezing progressed.

    Typically, the locations of the temperature pipes were selected based on the as-built surveys of the

    pipes and installed in areas which had the greatest pipe deviation so that the worst case scenario

    could be monitored. Given the excavation sequence, the monitoring pipes had to be chosen before

    all of the freeze pipes were drilled. In total five temperature monitoring pipes were installed.

    The drill casing used to advance the borehole was left in place and a 4 inch schedule 40 steel pipe

    with welded joints was installed inside each casing. The pipe was pressure tested to safeguard

    against leaks and the annulus between the casing and the pipe was grouted with a non-shrink grout.

    The grout provided proper heat transfer between the circulating brine and the surrounding soils.

    All of the freeze pipes were connected to a common supply and return header pipe which could

    circulate the chilled brine back to the refrigeration plant at a rate of approximately 20 gpm through

    each freeze pipe. A single refrigeration plant with a rating of 312 tons of refrigeration was utilized.

    The freeze plant used ammonia as a primary refrigerant to chill the 28% calcium chloride solution to

    temperatures ranging between -25 to -30 degrees Celsius. Refrigeration was accomplished with two,

    400 horesepower electrically-powered compressors contained within the custom-made freeze plant

    manufactured specifically for ground freezing operations.

  • The actual freezing took approximately 20 weeks to achieve the closure. During that time, constant

    data acquisition was maintained. The key components to the freezing were temperatures and

    groundwater levels. For this project, the pressure inside the frozen arch was monitored with the use

    of pressure transducers hooked up to wells installed within the arch footprint. A gradual increase in

    groundwater pressure inside the arch would indicate that the frozen mass had achieved closure

    resulting from the frozen soil mass growing inwards increasing the pore pressure on the unfrozen

    soils. Groundwater levels were also measured in a series of vertical piezometers across the entire

    site. Daily records of the ground temperatures recorded in the temperature pipes provided data that

    could be used to verify assumptions made in the initial thermal model. The use of actual ground

    temperatures in revised calibrated models aided in the determination of the in-situ wall thickness and

    temperature.

    IV CONCLUSION

    The General Contractor completed the final lining for the SEM tunnel on February 25, 2013. The

    freezing system operated as designed for approximately 455 days.

    Figure 7: Completed Tunnel

    This project represents the ability for artificial ground freezing to act as both structural support and

    groundwater cutoff in highly variable urban soils.

  • REFERENCES

    Powers, J., Corwin, A., Schmall P., and Kaeck W., 2007. Construction Dewatering and Groundwater

    Control New Methods and Applications. John Wiley & Sons Inc, United States, pp 491-500

    Andersland, O.B., and Ladanyi, B. 2004. Frozen Ground Engineering, Second Edition. John Wiley &

    Sons, Inc., Hoboken, NJ.