01 Plan of Development
Transcript of 01 Plan of Development
-
8/17/2019 01 Plan of Development
1/17
PODPOD
Plan of DevelopmPlan of Developmeentnt
Dr. Ir.Dr. Ir. TutukaTutuka AriadjiAriadji
PETROLEUM ENGINEERINGPETROLEUM ENGINEERING
INSTITUT TEKNOLOGI BANDUNGINSTITUT TEKNOLOGI BANDUNG
20201212
-
8/17/2019 01 Plan of Development
2/17
Plan of Development:
A comprehensive plan involving
Geophysics, Geology, Reservoir
Engineering, Production Engineering,
Drilling Engineering, Environment and
Economics knowledge and practices to best
develop a field.
Plan of DevelopmentPlan of Development
-
8/17/2019 01 Plan of Development
3/17
What are in the processes ?
How to do the processes?
Essential of Essential of Plan of DevelopmentPlan of Development
-
8/17/2019 01 Plan of Development
4/17
Evaluation
Planning
Looking for Highest NPV
Seek lowest cost
Environmentally friendly
Objectives of Objectives of Plan of DevelopmentPlan of Development
-
8/17/2019 01 Plan of Development
5/17
Proceed
With
Development?
N P V
Well
Opening
Cost
Facility
Op.Cost
Transport
Cost
Overhead
Opening
Cost
Field
Management
Cost
Workover
Cost
Terminal&
Base
Flowlines
&
Pipelines
Proceed
With
Development
FacilityCapital
Plugging
Cost
Number
Of
Well
Cost
Revenue
Production
Profile
Reserves
Oil
Price
Gas
Price
Recovery
Factor
Figure 1. Influence Factors in Field
Development Optimization
-
8/17/2019 01 Plan of Development
6/17
Design Basis
Exploitation
Operations and Maintenance
Engineering
Economic
SSystematics of ystematics of Plan of DevelopmentPlan of Development
-
8/17/2019 01 Plan of Development
7/17
Exploration andExploration and
Prospective ProjectProspective Project
Appraisal andAppraisal and
DevelopmentDevelopment
ProductionProduction
Project Initiation
Feasibility Study
Plan of Development
Design Basis Memorandum
Project Execution Plan
Project Stage, Completion,
Cost, Exception Report
Yearly Field Reviews
-
8/17/2019 01 Plan of Development
8/17
Study of Geology and Geophysics (G&G)
Study of Reservoir and Production Development Scenarios
Economics Analysis
General Scope ofGeneral Scope of Plan ofPlan of
DevelopmentDevelopment
-
8/17/2019 01 Plan of Development
9/17
Tectonic Frame
Regional Stratigraphic
Petroleum System
Geology Reconstruction
Well Data Intrepretation
Interpretasi Data Seismik (2D/3D)
Integration of Well Data and Seismic
Volumetric Calculation
GeologGeologyy andand GeoGeophysicsphysics
-
8/17/2019 01 Plan of Development
10/17
Reservoir EngineeringReservoir Engineering
PVT Analysis
Rock Properties
Welltest Analysis
Material Balance
Original Oil In Place (OOIP) /OGIP
ReservoirReservoir andand ProduProductctiionon
EngineeringEngineering
-
8/17/2019 01 Plan of Development
11/17
Production EngineeringProduction Engineering
Inflow Performance Relationship
Tubing Wellbore Outflow Nodal Analysis
Well Diagram
-
8/17/2019 01 Plan of Development
12/17
Well Completions
Production History and Completion
Production Splitting
Lifting Methode
Forecasting Production Performance
Using Decline Curve
-
8/17/2019 01 Plan of Development
13/17
Data Gathering
Reservoir Modelling
Inisialization
History Matching
Forecasting Future Performance
Reservoir Reservoir SimulaSimulationtion
-
8/17/2019 01 Plan of Development
14/17
Well Drilling Schedule
Drilling
Production Facilities Production Problems
Transportation
Environment
DevelopmentDevelopment SSccenarioenarioss
-
8/17/2019 01 Plan of Development
15/17
Rate of Return (ROR)
Pay Out Time (POT)
Profit to Investment Ratio (PIR)
Net Present Value (NPV)
EcEconomionomicscs AnalisAnalisysys
-
8/17/2019 01 Plan of Development
16/17
-
8/17/2019 01 Plan of Development
17/17
Work Schedule
1 2 3 4 5 6 7 8 10
Start
Geological
Model
Geological Modelling :
Geophysics, Geology,
Petrophysics, Res. and
Prod. Eng.
Reservoir Characterization using
Geostatistical Modelling
Strart of Res
Simulation
Surface Fac
9 11 12
Economic
Analysis
Reservoir
Model
ForecastingFinish