![Page 1: environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/online/EC/...Ckm crusher 5.16 kms North East Cement bricks Sri ranga lakshmi solid blocks 3.48 kms North Coffee](https://reader033.fdocuments.in/reader033/viewer/2022050612/5fb2cca2b1afc64c1f2cbaf9/html5/thumbnails/1.jpg)
![Page 2: environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/online/EC/...Ckm crusher 5.16 kms North East Cement bricks Sri ranga lakshmi solid blocks 3.48 kms North Coffee](https://reader033.fdocuments.in/reader033/viewer/2022050612/5fb2cca2b1afc64c1f2cbaf9/html5/thumbnails/2.jpg)
![Page 3: environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/online/EC/...Ckm crusher 5.16 kms North East Cement bricks Sri ranga lakshmi solid blocks 3.48 kms North Coffee](https://reader033.fdocuments.in/reader033/viewer/2022050612/5fb2cca2b1afc64c1f2cbaf9/html5/thumbnails/3.jpg)
![Page 4: environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/online/EC/...Ckm crusher 5.16 kms North East Cement bricks Sri ranga lakshmi solid blocks 3.48 kms North Coffee](https://reader033.fdocuments.in/reader033/viewer/2022050612/5fb2cca2b1afc64c1f2cbaf9/html5/thumbnails/4.jpg)
i
TOR Compliance
Project Proponent: M/s Popular Chemical Manufacturer and Supplies.
Project Address: Survey No. 380, Karagada village, Belur Tehsil, Hassan District (Karnataka)
S.
No.
TOR points TOR Compliance
1) Executive Summary Given in chapter – 11
2) Introduction
(i) Details of the EIA
Consultant including
NABET accreditation
EIA Consultant- Wolkem India Ltd.
Details of the EIA Consultant including NABET accreditation is
given in chapter 12.
NABET Certificate is enclosed as Annexure XVII.
(ii) Information about
project proponent
Project proponent- Mr. Vedanth Gowda
Designation- Partner
Address- Hastha Hosamane Extension, Chikmagalur 577 101,
(Karnataka).
E-mail:[email protected]; [email protected]
Mr. Vedanth M P has master’s in business administration (Cardiff University, UK) have an experience more than 2
years in the copper sulphate industry.
(iii) Importance and benefits
of the project
Importance and benefits of the project is given in Chapter-I,
Para 1.3, Page no. 3 of the EIA/EMP report.
3) Project Description
(i) Cost of project and time
of completion
Cost of the project is 5.0 Crores.
Project will be completed within 3 year after grant EC
(ii) Products with capacities
for the proposed project
S.No
.
Name of the
product
Total Capacity (TPA)
1. Aluminium
Phosphide
500
2. Zinc Phosphide 250
Total 750 TPA
(iii) If expansion project,
details of existing
products with capacities
and whether adequate
land is available for
expansion, reference of
earlier EC if any.
This is a new project.
Annexure I
![Page 5: environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/online/EC/...Ckm crusher 5.16 kms North East Cement bricks Sri ranga lakshmi solid blocks 3.48 kms North Coffee](https://reader033.fdocuments.in/reader033/viewer/2022050612/5fb2cca2b1afc64c1f2cbaf9/html5/thumbnails/5.jpg)
ii
S.
No.
TOR points TOR Compliance
(iv) List of raw material
required and their source
along with mode of
transportation.
Transportation of raw materials will be by railways or
roadways. Details of the raw material required is given in
Chapter-II, Table 2.8, Page No. 23 to 24 of the EIA/EMP
report.
(v) Other chemicals and
materials required with
quantities and storage
capacities.
Finished products will be stored in well-designed warehouse.
Same is elaborated in Chapter 2, Para 2.5, Page 23.
(vi) Details of Emission,
effluents, hazardous
waste generation and
their management.
Details elaborated in Chapter – 2, Para 2.7 and 2.9 Page No.
25 to 33.
(vii) Requirement of water,
power, with source of
supply, status of approval,
water balance diagram,
man-power requirement
(regular and contract)
Total Water Requirement- 19.13 KLD
Source- Tanker
Manpower Requirement- 80 nos.
Details elaborated in Chapter – 2 Para 2.7 to 2.8 Page no.
25 to 27.
(viii
)
Process description along
with major equipment’s and machineries, process
flow sheet (quantative)
from raw material to
products to be provided
Details of plant machineries is elaborated in Chapter – 2,
Table no. 2.2 , page, 15 to 16 of EIA/EMP report.
Process description for existing and proposed product is given
on page no. 18 to 22 of EIA/EMP report.
(ix) Hazard identification and
details of proposed safety
systems.
Details is given in Chapter – 7, para 7.7, Table 7.7.1 to 7.76
page No. 174 to 182 of EIA/EMP report.
(x) Expansion/modernization
proposals:
a. Copy of all the
Environmental
Clearance(s) including
Amendments thereto
obtained for the project
from MOEF/SEIAA shall
be attached as an
Annexure. A certified copy
of the latest Monitoring
Report of the Regional
Office of the Ministry of
Not Applicable
![Page 6: environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/online/EC/...Ckm crusher 5.16 kms North East Cement bricks Sri ranga lakshmi solid blocks 3.48 kms North Coffee](https://reader033.fdocuments.in/reader033/viewer/2022050612/5fb2cca2b1afc64c1f2cbaf9/html5/thumbnails/6.jpg)
iii
S.
No.
TOR points TOR Compliance
Environment and Forests
as per circular dated 30th
May, 2012 on the status
of compliance of
conditions stipulated in all
the existing
environmental clearances
including Amendments
shall be provided. In
addition, status of
compliance of Consent to
Operate for the ongoing
existing operation of the
project from SPCB shall
be attached with the EIA-
EMP report.
b. In case the existing
project has not obtained
environmental clearance,
reasons for not taking EC
under the provisions of
the EIA Notification 1994
and/or EIA Notification
2006 shall be provided.
Copies of Consent to
Establish/No Objection
Certificate and Consent to
Operate (in case of units
operating prior to EIA
Notification 2006, CTE
and
CTO of FY 2005-2006)
obtained from the SPCB
shall be submitted.
Further, compliance
report to the conditions
of consents from the
SPCB shall be submitted.
This is a greenfield project.
4) Site Details
![Page 7: environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/online/EC/...Ckm crusher 5.16 kms North East Cement bricks Sri ranga lakshmi solid blocks 3.48 kms North Coffee](https://reader033.fdocuments.in/reader033/viewer/2022050612/5fb2cca2b1afc64c1f2cbaf9/html5/thumbnails/7.jpg)
iv
S.
No.
TOR points TOR Compliance
(i) Location of the project
site covering village,
Taluka/Tehsil, District and
State, Justification for
selecting the site, whether
other sites were
considered.
Location of site is tabulated below:
The current site of pesticide manufacturing unit is satisfying
the screening criteria for the proposed activity. The screening
criteria set by the company are economic & social factors.
Therefore, no alternate site was selected for proposed project
activity.
Khasra No. 380
Village Karagada
Tehsil Belur
District Hassan
State Karnataka
(ii) A toposheet of the study
area of radius of 10km
and site location on
1:50,000/1:25,000 scale on
an A3/A2 sheet.
(including all eco-
sensitive areas and
environmentally sensitive
places)
Toposheet of study area is enclosed as Annexure XII.
Details are elaborated in Chapter 2, Para 2.3, Figure- 2.1
Page No. 13-14 of EIA/EMP report.
(iii) Details w.r.t. option
analysis for selection of
site
The current site of pesticide manufacturing unit is satisfying
the screening criteria for the proposed activity. The screening
criteria set by the company are economic & social factors.
Therefore, no alternate site was selected for proposed project
activity.
(iv) Co-ordinates (lat-long) of
all four corners of the site.
Plot is in triangular shape.
S.No. Latitude Longitude
1. 13°14'50.44"N 75°50'51.65"E
2. 13°14'52.07"N 75°50'54.43"E
3. 13°14'44.86"N 75°50'54.33"E
(v) Google map-Earth
downloaded of the
project site.
Given in Chapter– 3, Figure- 3.13, page no. 69
(vi) Layout maps indicating
existing unit as well as
proposed unit indicating
storage area, plant area,
greenbelt area, utilities
etc. If located within an
Layout Plan attached as Annexure II.
Plot is not located in notified industrial area.
Also, Given in Chapter – 2, Figure 2.2, Page No 17 of
EIA/EMP report.
![Page 8: environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/online/EC/...Ckm crusher 5.16 kms North East Cement bricks Sri ranga lakshmi solid blocks 3.48 kms North Coffee](https://reader033.fdocuments.in/reader033/viewer/2022050612/5fb2cca2b1afc64c1f2cbaf9/html5/thumbnails/8.jpg)
v
S.
No.
TOR points TOR Compliance
Industrial
area/Estate/Complex,
layout of Industrial Area
indicating location of unit
within the Industrial
area/Estate.
(vii) Photographs of the
proposed and existing (if
applicable) plant site. If
existing, show
photographs of
plantation / greenbelt, in
particular.
Photographs of proposed area is given in Chapter – 1, Figure
1.1, -page No. 6 of EIA/EMP report.
(viii
)
Landuse break-up of total
land of the project site
(identified and acquired),
government/ private -
agricultural, forest,
wasteland, water bodies,
settlements, etc. shall be
included. (not required for
industrial area)
Land use breakup is mentioned in Chapter3, Table No. 3.21,
Page No. 74.
![Page 9: environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/online/EC/...Ckm crusher 5.16 kms North East Cement bricks Sri ranga lakshmi solid blocks 3.48 kms North Coffee](https://reader033.fdocuments.in/reader033/viewer/2022050612/5fb2cca2b1afc64c1f2cbaf9/html5/thumbnails/9.jpg)
vi
S.
No.
TOR points TOR Compliance
(ix) A list of major industries
with name and type
within study area (10 km
radius) shall be
incorporated. Land use
details of the study area
Industries in 10 Km radius of project site is as follows:
Type of
Industry
Name of
Industry
Distance Direction
Cement
bricks
Cubics cement
blocks
650 m. South East
Stone
crusher
Ckm crusher 5.16 kms
North East
Cement
bricks
Sri ranga lakshmi
solid blocks
3.48 kms North
Coffee
curing
CNS coffee
curing
3.78
North West
Cement
blocks
Vasuki solid
blocks
4.41 kms
North West
Coffee
curing
CN coffee curing
works
4.4 kms
North West
Biomass
fire
briquettes
CNT briquette
industries
5.3 kms
North West
Coffee
curing
Seven beans
coffee curing
works
5.2 kms
North West
Coffee
curing
Vasavi coffee
curing works
5.9 kms North West
Wood saw
mill
Manjunatha saw
mill
8.07 kms
North West
Plywood
industry
Rushil decor Pvt
ltd
8kms
North West
Poultry
industry
Life line feeds
India Pvt ltd
8.2 kms
North West
Land use details of the project is given in chapter 3, Page 68-
77.
(x) Geological features and Geological features and Geo-hydrological status of the study
![Page 10: environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/online/EC/...Ckm crusher 5.16 kms North East Cement bricks Sri ranga lakshmi solid blocks 3.48 kms North Coffee](https://reader033.fdocuments.in/reader033/viewer/2022050612/5fb2cca2b1afc64c1f2cbaf9/html5/thumbnails/10.jpg)
vii
S.
No.
TOR points TOR Compliance
Geo-hydrological status
of the stud y area shall be
included.
area is given Chapter-III, Para 3.9 and 3.10, Page no.77 to
87 of EIA/EMP report.
(xi) Details of Drainage of the
project upto 5 km radius
of study area. If the site is
within 1 km radius of any
major river, peak and lean
season river discharge as
well as flood occurrence
frequency based on peak
rainfall data of the past 30
years. Details of Flood
Level of the project site
and maximum Flood Level
of the river shall also be
provided. (mega green
field projects)
Details is elaborated in Chapter–3, Para 3.8.7, Figure 3.15. -
Page No. 71 to 73 of EIA/EMP report.
(xii) Status of acquisition of
land. If acquisition is not
complete, stage of the
acquisition process and
expected time of
complete possession of
the land.
Land is already acquired.
Land Documents are attached as Annexure I.
(xiii
)
R&R details in respect of
land in line with state
Government policy.
There is no house in plot area therefore R&R plan is not
required.
5) Forest and wildlife
related issues
(if applicable)
Not Applicable
(i) Permission and approval
for the use of forest land
(forestry clearance), if any,
and recommendations of
the State Forest
Department. (if
applicable)
(ii) Landuse map based on
High resolution satellite
![Page 11: environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/online/EC/...Ckm crusher 5.16 kms North East Cement bricks Sri ranga lakshmi solid blocks 3.48 kms North Coffee](https://reader033.fdocuments.in/reader033/viewer/2022050612/5fb2cca2b1afc64c1f2cbaf9/html5/thumbnails/11.jpg)
viii
S.
No.
TOR points TOR Compliance
imagery (GPS) of the
proposed site delineating
the forestland (in case of
projects involving forest
land more than 40 ha)
(iii) Status of Application
submitted for obtaining
the stage I forestry
clearance along with
latest status shall be
submitted.
(iv) The projects to be located
within 10 km of the
National Parks,
Sanctuaries, Biosphere
Reserves,
Migratory Corridors of
Wild Animals, the project
proponent shall submit
the map duly
authenticated by Chief
Wildlife Warden showing
these features vis-à-vis
the project location and
the recommendations or
comments of the Chief
Wildlife Warden-thereon.
(v) Wildlife Conservation Plan
duly authenticated by the
Chief Wildlife Warden of
the State Government for
conservation of Schedule
I fauna, if any exists in the
study area.
(vi) Copy of application
submitted for clearance
under the Wildlife
(Protection) Act, 1972, to
the Standing Committee
of the National Board for
![Page 12: environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/online/EC/...Ckm crusher 5.16 kms North East Cement bricks Sri ranga lakshmi solid blocks 3.48 kms North Coffee](https://reader033.fdocuments.in/reader033/viewer/2022050612/5fb2cca2b1afc64c1f2cbaf9/html5/thumbnails/12.jpg)
ix
S.
No.
TOR points TOR Compliance
Wildlife.
6) Environmental Status
(i) Determination of
atmospheric inversion
level at the project site
and site-specific
micrometeorological data
using temperature,
relative humidity, hourly
wind speed and direction
and rainfall.
Details are elaborated in Chapter – 3 Para 3.3.1 –Table 3.2,
Page No. 38-40 of EIA/EMP report.
(ii) AAQ data (except
monsoon) at 8 locations
for PM10, PM2.5, SO2,
NOX, CO and other
parameters relevant to
the project shall be
collected. The monitoring
stations shall be based
CPCB guidelines and take
into account the pre-
dominant wind direction,
population zone and
sensitive receptors
including reserved forests.
AAQ data (except monsoon) at 8 locations for PM10, PM2.5,
SO2, NOX, CO is given in Chapter- III, Section 3.4, page no.-
40 to 51 of the EIA report.
(iii) Raw data of all AAQ
measurement for 12
weeks of all stations as
per frequency given in the
NAQQM Notification of
Nov. 2009 along with -
min., max., average and
98% values for each of
the AAQ parameters from
data of all AAQ stations
should be provided as an
annexure to the EIA
Report.
Minimum, Maximum value and 98 percentile is given in
chapter 3, page 43 to 44 of EIA/EMP report.
Raw data for all monitoring stations will be submitted at the
time of EC presentation.
(iv) Surface water quality of
nearby River (100m
Surface water quality of the study area given in is given in
Chapter- III, Para 3.6.2, Page No. 58 o 59 of the EIA report.
![Page 13: environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/online/EC/...Ckm crusher 5.16 kms North East Cement bricks Sri ranga lakshmi solid blocks 3.48 kms North Coffee](https://reader033.fdocuments.in/reader033/viewer/2022050612/5fb2cca2b1afc64c1f2cbaf9/html5/thumbnails/13.jpg)
x
S.
No.
TOR points TOR Compliance
upstream and
downstream of discharge
point)
and other surface drains
at eight locations as per
CPCB/MoEF&CC
guidelines.
(v) Whether the site falls near
to polluted stretch of river
identified by the
CPCB/MoEF&CC, if yes
give details.
No
(vi) Ground water monitoring
at minimum at 8 locations
shall be included.
Details of Ground water Monitoring along with monitoring
locations is given in Chapter- III, Section 3.6.1 , page No. 54
to 58 of the EIA report.
(vii) Noise levels monitoring at
8 locations within the
study area.
Details of Noise Monitoring along with monitoring locations is
given in Chapter- III, Section 3.5, Page 51 to 54 of the EIA
report.
(viii
)
Soil Characteristic as per
CPCB guidelines.
Details of Soil Characteristic as per CPCB guidelines is given in
Chapter- III, Para 3.7, Page 59 to 67 of the EIA report.
(ix) Traffic study of the area,
type of vehicles,
frequency of vehicles for
transportation of
materials, additional
traffic due to proposed
project, parking
arrangement etc.
Traffic density report is attached as Annexure XXIV.
( x) Detailed description of
flora and fauna (terrestrial
and aquatic) existing in
the study area shall be
given with special
reference to rare, endemic
and endangered species.
If Schedule- I fauna are
found within the study
area, a Wildlife
Conservation Plan shall be
prepared and furnished.
Detailed description of flora and fauna existing in the study
area is given in Chapter-III, Para 3.11, Page No. 87 to 95 of
the EIA report.
![Page 14: environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/online/EC/...Ckm crusher 5.16 kms North East Cement bricks Sri ranga lakshmi solid blocks 3.48 kms North Coffee](https://reader033.fdocuments.in/reader033/viewer/2022050612/5fb2cca2b1afc64c1f2cbaf9/html5/thumbnails/14.jpg)
xi
S.
No.
TOR points TOR Compliance
(xi) Socio-economic status of
the study area.
Detail of Socio-economic status of the study area is given in
Chapter-3 Section 3.12, Page No. 95 to 110 of the EIA/EMP
report.
7) Impact and
Environment
Management Plan
(i) Assessment of ground
level concentration of
pollutants from the stack
emission based on site-
specific meteorological
features. In case the
project is located on a
hilly terrain, the AQIP
Modelling shall be done
using inputs of the
specific terrain
characteristics for
determining the potential
impacts of the project on
the AAQ. Cumulative
impact of all sources of
emissions (including
transportation) on the
AAQ of the area shall be
assessed. Details of
the model used and the
input data used for
modelling shall also be
provided. The air quality
contours shall be plotted
on a location map
showing the location of
project site, habitation
nearby, sensitive
receptors, if any.
Details are given in Chapter 4, Para 4.3., Page No. 114 to
121 of the EIA/EMP report.
(ii) Water Quality modelling -
in case of discharge in
water body
This is Zero Discharge project.
(iii) Impact of the transport of Proper mitigation measures will be taken so, there will be no
![Page 15: environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/online/EC/...Ckm crusher 5.16 kms North East Cement bricks Sri ranga lakshmi solid blocks 3.48 kms North Coffee](https://reader033.fdocuments.in/reader033/viewer/2022050612/5fb2cca2b1afc64c1f2cbaf9/html5/thumbnails/15.jpg)
xii
S.
No.
TOR points TOR Compliance
the raw materials and end
products on the
surrounding environment
shall be assessed and
provided. In this regard,
options for transport of
raw materials and finished
products and wastes
(large quantities) by rail or
rail-cum road transport or
conveyorcum- rail
transport shall be
examined.
impact of the transportation of raw materials on surrounding
environment.
Details are given in Chapter – 7, Para 7.8, page No. 182 to
186 of the EIA/EMP report.
(iv) A note on treatment of
wastewater from different
plant operations, extent
recycled and reused for
different purposes shall
be included. Complete
scheme of effluent
treatment. Characteristics
of untreated and treated
effluent to meet the
prescribed standards of
discharge under E(P)
Rules
Details of waste water treatment scheme is elaborated in
Chapter – 2, Para 2.9, Page No. 27 to 28.
Proposed waste water characteristics area tabulated below:
Inlet Characteristics Outlet Characteristics
Particulars Value Particulars Value
pH 6-7 pH More than 7
TDS 1800-2000 TDS Less than 2000
TSS 100-200 TSS Nil
COD 600-500 COD Less than250
BOD 40-45 BOD Less than 30
(v) Details of stack emission
and action plan for
control of emissions to
meet standards.
Multi- cyclone with dry scrubber will be installed at boiler
Details are given in Chapter – 2, Para, 2.9.2., Table 2.12,
Page No. 29.
(vi) Measures for fugitive
emission control
Details are given in Chapter – 2,Para 2.9.2.5, Page No. 32
(vii) Details of hazardous
waste generation and
their storage, utilization
and management. Copies
of MOU regarding
utilization of solid and
hazardous waste in
cement plant shall also be
Details is given in Chapter – 2,Table No.-2.13, Page No. 33
An agreement copy of TSDF is attached as Annexure XXII.
![Page 16: environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/online/EC/...Ckm crusher 5.16 kms North East Cement bricks Sri ranga lakshmi solid blocks 3.48 kms North Coffee](https://reader033.fdocuments.in/reader033/viewer/2022050612/5fb2cca2b1afc64c1f2cbaf9/html5/thumbnails/16.jpg)
xiii
S.
No.
TOR points TOR Compliance
included. EMP shall
include the concept of
waste-minimization,
recycle/reuse/recover
techniques, Energy
conservation, and natural
resource conservation.
(viii
)
Proper utilization of fly
ash shall be ensured as
per Fly Ash Notification,
2009. A detailed plan of
action shall be provided.
MOU with cement manufacturer will be obtain after grant of
EC.
(ix) Action plan for the green
belt development plan in
33 % area i.e. land with
not less than 1,500 trees
per ha. Giving details of
species, width of
plantation, planning
schedule etc. shall be
included. The green belt
shall be around the
project boundary and a
scheme for greening of
the roads used for the
project shall also be
incorporated.
Green belt action plan is given in Chapter-10, Para 10.5.8,
Table 10.3 Page No. 227 to 228 of EIA/EMP report.
(x) Action plan for rainwater
harvesting measures at
plant site shall be
submitted to harvest
rainwater from the roof
tops and storm water
drains to recharge the
ground water and also to
use for the various
activities at the project
site to conserve fresh
water and reduce the
water requirement from
Details is given in Chapter – 4, Para 4.5.5 Page no. 126 to
130 of EIA/EMP report.
![Page 17: environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/online/EC/...Ckm crusher 5.16 kms North East Cement bricks Sri ranga lakshmi solid blocks 3.48 kms North Coffee](https://reader033.fdocuments.in/reader033/viewer/2022050612/5fb2cca2b1afc64c1f2cbaf9/html5/thumbnails/17.jpg)
xiv
S.
No.
TOR points TOR Compliance
other sources.
(xi) Total capital cost and
recurring cost/annum for
environmental pollution
control measures shall be
included.
Total Capital Cost: 25 lacs/-
Total Recurring Cost-1.5 Lacs /-
Same is mentioned in Chapter No. 10, Table No. 10.1, Page
No. 223.
(xii) Action plan for post-
project environmental
monitoring shall be
submitted.
Action plan for post- project environmental monitoring is
mentioned in Chapter 6, Table No. 6.1 Page No. 145 to 147
of EIA/EMP report.
(xiii
)
Onsite and Offsite
Disaster (natural and
Man-made) Preparedness
and Emergency
Management Plan
including Risk Assessment
and damage control.
Disaster management
plan should be linked
with District Disaster
Management Plan.
Given Chapter – 7 para 7.9 Page No. 187 to 195 of EIA/EMP
report.
8) Occupational Health
(i) Plan and fund allocation
to ensure the
occupational health &
safety of all contract and
casual workers
Action plan for safety and health along with budget is given
Chapter – 7 para 7.10, Page No 195 to 197 of EIA/EMP
report.
(ii) Details of exposure
specific health status
evaluation of worker. If
the workers' health is
being evaluated by pre
designed format, chest x
rays, Audiometry,
Spirometry, Vision testing
(Far & Near vision, colour
vision and any other
ocular defect) ECG, during
pre placement and
periodical examinations
Action plan for safety and health is give Chapter – 7 para
7.11, Page No. 197 to 201 of EIA/EMP report.
![Page 18: environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/online/EC/...Ckm crusher 5.16 kms North East Cement bricks Sri ranga lakshmi solid blocks 3.48 kms North Coffee](https://reader033.fdocuments.in/reader033/viewer/2022050612/5fb2cca2b1afc64c1f2cbaf9/html5/thumbnails/18.jpg)
xv
S.
No.
TOR points TOR Compliance
give the details of the
same. Details regarding
last month analysed data
of above mentioned
parameters as per age,
sex, duration of exposure
and department wise.
(iii) Details of existing
Occupational & Safety
Hazards. What are the
exposure levels of hazards
and whether they are
within Permissible
Exposure level (PEL). If
these are not within PEL,
what measures the
company has adopted to
keep them within PEL so
that health of the workers
can be preserved,
Not Applicable
(iv) Annual report of health
status of workers with
special reference to
Occupational Health and
Safety.
Annual report of health status of workers with special
reference to Occupational Health and Safety will be submit at
the time of EC compliance.
9) Corporate Environment
Policy
(i) Does the company have a
well laid down
Environment Policy
approved by its Board of
Directors? If so, it may be
detailed in the EIA report.
Enclosed as Annexure XV.
(ii) Does the Environment
Policy prescribe for
standard operating
process / procedures to
bring into focus any
infringement / deviation /
violation of the
Yes, Incorporated in Chapter – 10, para 10.4, Page No. 225
of EIA/EMP report..
![Page 19: environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/online/EC/...Ckm crusher 5.16 kms North East Cement bricks Sri ranga lakshmi solid blocks 3.48 kms North Coffee](https://reader033.fdocuments.in/reader033/viewer/2022050612/5fb2cca2b1afc64c1f2cbaf9/html5/thumbnails/19.jpg)
xvi
S.
No.
TOR points TOR Compliance
environmental or forest
norms / conditions? If so,
it may be detailed in the
EIA.
(iii) What is the hierarchical
system or Administrative
order of the company to
deal with the
environmental issues and
for ensuring compliance
with the environmental
clearance conditions?
Details of this system may
be given.
Following is the hierarchical system or administrative order of
the company to deal with the Environmental issues and for
ensuring compliance with the EC conditions.
(iv) Does the company have
system of reporting of
non-compliances /
violations of
environmental norms to
the Board of Directors of
the company and / or
shareholders or
stakeholders at large?
This reporting mechanism
shall be detailed in the
EIA report
10) Details regarding
infrastructure facilities
such as sanitation, fuel,
restroom etc. to be
provided to the
labour force during
construction as well as to
the casual workers
including truck drivers
during
operation phase.
Local workers will be employed. Proper safe drinking water
facilities, toilets, driver restroom will be provided during
construction period as well as operation period.
Manager
Environment
Officer
Environment
Executive
Environment
Vice President- Operations
Mr. Vedanth M.P
Patner
![Page 20: environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/online/EC/...Ckm crusher 5.16 kms North East Cement bricks Sri ranga lakshmi solid blocks 3.48 kms North Coffee](https://reader033.fdocuments.in/reader033/viewer/2022050612/5fb2cca2b1afc64c1f2cbaf9/html5/thumbnails/20.jpg)
xvii
S.
No.
TOR points TOR Compliance
11) Enterprise Social
Commitment (ESC)
i. Adequate funds (at least
2.5 % of the project cost)
shall be earmarked
towards the Enterprise
Social Commitment based
on Public Hearing issues
and item-wise details
along with time bound
action plan shall be
included. Socio-economic
development activities
need to be elaborated
upon.
2 % of the project cost i.e. Rs 10,00000 /- will be spend under
CER as per MoEF&CC OM dated 01.05.2018.
Given in Chapter – 7, Table No 7.6 Page No 214 of EIA/EMP
report.
12) Any litigation pending
against the project and/or
any direction/order
passed by any Court of
Law against the project, if
so, details thereof shall
also be included. Has the
unit received any notice
under the Section 5 of
Environment (Protection)
Act, 1986 or relevant
Sections of Air and Water
Acts? If so, details thereof
and compliance/ATR to
the notice(s) and present
status of the case.
No litigation is pending against the project.
13) A tabular chart with index
for point wise compliance
of above TOR.
Complied
B. SPECIFIC TERMS OF REFERENCE FOR EIASTUDIES FOR PESTICIDES
INDUSTRY AND PESTICIDE SPECIFIC INTERMEDIATES (EXCLUDING
FORMULATIONS)
1. Commitment that no
banned pesticides will be
manufactured.
We as Popular Chemicals Manufacturers and Suppliers commit
that no banned pesticides will be manufactured. An affidavit
regarding this will be submitted at the time of presentation.
![Page 21: environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/online/EC/...Ckm crusher 5.16 kms North East Cement bricks Sri ranga lakshmi solid blocks 3.48 kms North Coffee](https://reader033.fdocuments.in/reader033/viewer/2022050612/5fb2cca2b1afc64c1f2cbaf9/html5/thumbnails/21.jpg)
xviii
S.
No.
TOR points TOR Compliance
2. Details on solvents to be
used, measures for
solvent recovery and for
emissions control.
No solvent will be used.
3. Details of process
emissions from the
proposed unit and its
arrangement to control.
Details are given in Chapter – 2,para 2.9.2.3 page 30-31 of
EIA/EMP report.
4. Ambient air quality data
should include VOC, other
process-specific
pollutants* like NH3*,
chlorine*, HCl*, HBr*,
H2S*, HF*,etc.,(*-as
applicable)
No pollutants like NH3, chlorine, HCl, HBr, H2S, HF,etc. will be
released from proposed project manufacturing process.
Details are given in Chapter – 3, Table 3.10, Page 48 to 50 of
EIA/EMP report.
5. Work zone monitoring
arrangements for
hazardous chemicals.
Details is elaborated in Chapter – 7, para 7.12.3 Page no.
203 to 204 of EIA/EMP report.
6. Detailed effluent
treatment scheme
including segregation of
effluent streams for units
adopting
'Zero' liquid discharge.
Details is elaborated in Chapter – 2, Para 2.9, Page No. 27 to
28 of EIA/EMP report.
7. Action plan for odour
control to be submitted.
Details is elaborated in Chapter – 4, Para 4.3.12, Page No.
120 of EIA/EMP report.
8. A copy of the
Memorandum of
Understanding signed
with cement
manufacturers indicating
clearly that they co-
process organic
solid/hazardous waste
generated.
Brick manufacturer agreement for use of fly ash will be
submitted at the time of EC presentation.
9. Authorization/Membershi
p for the disposal of
liquid effluent in CETP
and solid/hazardous
waste in TSDF, if any.
TSDF Agreement is enclosed as Annexure XXII.
![Page 22: environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/online/EC/...Ckm crusher 5.16 kms North East Cement bricks Sri ranga lakshmi solid blocks 3.48 kms North Coffee](https://reader033.fdocuments.in/reader033/viewer/2022050612/5fb2cca2b1afc64c1f2cbaf9/html5/thumbnails/22.jpg)
xix
S.
No.
TOR points TOR Compliance
10. Action plan for utilization
of MEE/dryers salts.
The facility does not have MEE, hence not applicable.
11. Authorization/Membershi
p for the disposal of
solid/hazardous waste in
TSDF.
TSDF Agreement is enclosed as Annexure XXII.
12. Details of incinerator if to
be installed.
No incinerator will be installed.
13. Risk assessment for
storage and handling of
hazardous
chemicals/solvents. Action
plan for handling & safety
system to be
incorporated.
Details is given in Chapter -7, Para 7.14 Page No. 207 to
212 o EIA/EMP report.
14. Arrangements for
ensuring health and
safety of workers
engaged in handling of
toxic materials.
Details is given in Chapter -7, Para 7.15 Page No. 212 to 213
of EIA/EMP report.
*********
![Page 23: environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/online/EC/...Ckm crusher 5.16 kms North East Cement bricks Sri ranga lakshmi solid blocks 3.48 kms North Coffee](https://reader033.fdocuments.in/reader033/viewer/2022050612/5fb2cca2b1afc64c1f2cbaf9/html5/thumbnails/23.jpg)
Annexure III Annexure II Annexure II
![Page 24: environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/online/EC/...Ckm crusher 5.16 kms North East Cement bricks Sri ranga lakshmi solid blocks 3.48 kms North Coffee](https://reader033.fdocuments.in/reader033/viewer/2022050612/5fb2cca2b1afc64c1f2cbaf9/html5/thumbnails/24.jpg)
Type your textType your textType your text
Annexure III
Type your textType your textType your text
![Page 25: environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/online/EC/...Ckm crusher 5.16 kms North East Cement bricks Sri ranga lakshmi solid blocks 3.48 kms North Coffee](https://reader033.fdocuments.in/reader033/viewer/2022050612/5fb2cca2b1afc64c1f2cbaf9/html5/thumbnails/25.jpg)
Type your text
I
![Page 26: environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/online/EC/...Ckm crusher 5.16 kms North East Cement bricks Sri ranga lakshmi solid blocks 3.48 kms North Coffee](https://reader033.fdocuments.in/reader033/viewer/2022050612/5fb2cca2b1afc64c1f2cbaf9/html5/thumbnails/26.jpg)
![Page 27: environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/online/EC/...Ckm crusher 5.16 kms North East Cement bricks Sri ranga lakshmi solid blocks 3.48 kms North Coffee](https://reader033.fdocuments.in/reader033/viewer/2022050612/5fb2cca2b1afc64c1f2cbaf9/html5/thumbnails/27.jpg)
![Page 28: environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/online/EC/...Ckm crusher 5.16 kms North East Cement bricks Sri ranga lakshmi solid blocks 3.48 kms North Coffee](https://reader033.fdocuments.in/reader033/viewer/2022050612/5fb2cca2b1afc64c1f2cbaf9/html5/thumbnails/28.jpg)
![Page 29: environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/online/EC/...Ckm crusher 5.16 kms North East Cement bricks Sri ranga lakshmi solid blocks 3.48 kms North Coffee](https://reader033.fdocuments.in/reader033/viewer/2022050612/5fb2cca2b1afc64c1f2cbaf9/html5/thumbnails/29.jpg)
![Page 30: environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/online/EC/...Ckm crusher 5.16 kms North East Cement bricks Sri ranga lakshmi solid blocks 3.48 kms North Coffee](https://reader033.fdocuments.in/reader033/viewer/2022050612/5fb2cca2b1afc64c1f2cbaf9/html5/thumbnails/30.jpg)
![Page 31: environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/online/EC/...Ckm crusher 5.16 kms North East Cement bricks Sri ranga lakshmi solid blocks 3.48 kms North Coffee](https://reader033.fdocuments.in/reader033/viewer/2022050612/5fb2cca2b1afc64c1f2cbaf9/html5/thumbnails/31.jpg)
![Page 32: environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/online/EC/...Ckm crusher 5.16 kms North East Cement bricks Sri ranga lakshmi solid blocks 3.48 kms North Coffee](https://reader033.fdocuments.in/reader033/viewer/2022050612/5fb2cca2b1afc64c1f2cbaf9/html5/thumbnails/32.jpg)
![Page 33: environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/online/EC/...Ckm crusher 5.16 kms North East Cement bricks Sri ranga lakshmi solid blocks 3.48 kms North Coffee](https://reader033.fdocuments.in/reader033/viewer/2022050612/5fb2cca2b1afc64c1f2cbaf9/html5/thumbnails/33.jpg)
![Page 34: environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/online/EC/...Ckm crusher 5.16 kms North East Cement bricks Sri ranga lakshmi solid blocks 3.48 kms North Coffee](https://reader033.fdocuments.in/reader033/viewer/2022050612/5fb2cca2b1afc64c1f2cbaf9/html5/thumbnails/34.jpg)
![Page 35: environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/online/EC/...Ckm crusher 5.16 kms North East Cement bricks Sri ranga lakshmi solid blocks 3.48 kms North Coffee](https://reader033.fdocuments.in/reader033/viewer/2022050612/5fb2cca2b1afc64c1f2cbaf9/html5/thumbnails/35.jpg)
![Page 36: environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/online/EC/...Ckm crusher 5.16 kms North East Cement bricks Sri ranga lakshmi solid blocks 3.48 kms North Coffee](https://reader033.fdocuments.in/reader033/viewer/2022050612/5fb2cca2b1afc64c1f2cbaf9/html5/thumbnails/36.jpg)
S.No. Name of the product/ raw material
Physical State Product Consumption (MTPA)
Storage Mitigations
1. Aluminum Powder Solid Powder 35 Bags 1) Store away from all sources of heat, sparks and flammable things
2) Do not keep it in open 3) Keep the container tightly closed in a
cool, dry, well ventilated place 4) Proper grounding procedures to be
followed to avoid static electric charges.
5) To safely handle empty containers as residues vapors are flammable
2. White Phosphorous Solid 50.25 Bags 1) Keep the container tightly closed in a well ventilated area
2) Store it away from incompatible materials such as alkaline hydroxides, Halogens, Oxidizing agents as white phosphorous catches fire easily.
3. Groundnut Oil Liquid 0.5 Drums 1) Keep the container tightly closed in a dry, cool, well ventilated area away from incompatible materials such as strong oxidants
2) Store away from all sources of heat, flame and direct contact of sunlight
4. Paraffin Wax Solid 2.9 Bags 1) Keep the container tightly closed in a cool, dry, well ventilated area
2) Keep it away from all sources of heat and ignition as it is a flammable.
3) Ground all the equipments including metals
4) Store away from incompatibles such as oxidizing agents
5) Empty containers may pose a fire so to evaporate the residue under a fume hood
MITIGATION MEASURES DURING TRANSPORTATION
OF RAW MATERIALS
Annexure VI Annexure V
![Page 37: environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/online/EC/...Ckm crusher 5.16 kms North East Cement bricks Sri ranga lakshmi solid blocks 3.48 kms North Coffee](https://reader033.fdocuments.in/reader033/viewer/2022050612/5fb2cca2b1afc64c1f2cbaf9/html5/thumbnails/37.jpg)
5. Urea Solid 4.20 Bags 1) Keep the container tightly closed and store in a cool, dry area
2) Store it in a dust free area and away from incompatible materials such as strong oxidizing agents, liquid chlorine, calcium hypochlorite etc
3) Wear personal protective equipments as urea dust is harmful if inhaled.
6. Ammonium Carbamate Solid 19.50 Bags 1) Keep the container tightly closed in a cool, dry well ventilated place
2) To use proper personal protective equipments
3) Store away from all incompatible materials
4) Store away from all sources of ignition as its dust may remain in the empty container and may explode when comes in contact with fire
7. Zinc Stearate Solid 4.5 bags 1) Keep the container tightly closed in a cool, dry, well ventilated area
2) Avoid to store where dust is formed 3) Keep away from all sources of heat
and ignition 4) Store away from incompatibles such
as strong oxidizing agents, alkalis, peroxides, acids
8. Graphite powder Solid 5.80 Bags 1) Keep the container tightly closed in a dry, cool well ventilated area and store away from moisture and direct sunlight
2) Wear Personal protective equipments e.g. dust masks while handling powder to avoid inhaling of graphite dust.
![Page 38: environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/online/EC/...Ckm crusher 5.16 kms North East Cement bricks Sri ranga lakshmi solid blocks 3.48 kms North Coffee](https://reader033.fdocuments.in/reader033/viewer/2022050612/5fb2cca2b1afc64c1f2cbaf9/html5/thumbnails/38.jpg)
9. Zinc Dust (powder) Solid 39.90 Bags 1) Keep the container in a well ventilated area
2) Keep away from moisture 3) Keep away from all sources of
ignition 4) Store away from incompatibles such
as strong oxidizing agents, acids and bases
10. Aluminum Phosphide Solid Bags 1) Store away from incompatibles such as water and oxidizing agents
2) Wear proper personal protective equipment’s while handling this chemical as it is highly poisonous & toxic material
3) Store it away from all flammable materials as this material can easily catch fire.
11. Zinc Phosphide Solid bags 1) Keep the container tightly closed in cool, well ventilated place.
2) Use proper PPEs while handling this chemical as it is a toxic powder.
3) Store it away from moisture and all sources of heat and ignition as this is hygroscopic and flammable solid.