Post on 06-Feb-2018
Environment and Social Impact Assessment of
Federally Administered Tribal Areas Emergency Rural Roads Project (FATA ERRP)
in Bajaur and Orakzai Agencies
GOVERNMENT OF PAKISTAN WORKS & SERVICES DEPARTMENT (FATA)
PESHAWAR
AUGUST 2012
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Government of Khyber Pakhtunkhwa
Works & Services Department
Peshawar
Environment and Social Impact Assessment
of
Federally Administered Tribal Areas Emergency Rural Roads Project (FATA ERRP)
in
Bajaur and Orakzai Agencies
August 2012
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
i
List of Acronyms
AASHTO American Association of State Highway and Transportation Officials ACE Associated Consulting Engineers ACI American Concrete Institute ADB Asian Development Bank AIDS Acquired immune deficiency syndrome ASTM American Society for Testing and Material BHU Basic Health Unit BOD Biochemical Oxygen Demand BOQ Bill of Quantities COD Chemical Oxygen Demand COI CSC
Corridor of Impact Construction Supervision Consultants
DDE Deputy Director Environment DEMM Donors Environmental Monitoring Mission EA Environmental Assessment EIA Environmental Impact Assessment EIRR Economic Internal Rate of Return EMMP Environment Mitigation and Monitoring Plan EMP Environment Management Plan EPC Environmental Protection Council ERRP Emergency Rural Roads Project ESIA Environmental and Social Impact Assessment ESMP ESSAF
Environment and Social Management Plan Environment and Social Screening and Assessment Framework
FATA Federally Administered Tribal Areas FHA Frontier Highways Authority FIDIC Fédération Internationale Des Ingénieurs-Conseils
(International Federation of Consulting Engineers) GoKP Government of Khyber Pakhtunkhwa GoP Government of Pakistan HIV Human Immunodeficiency Virus HSE Health Safety Equipment IEE Initial Environmental Examination IEM Independent Environmental Monitor ISMZ Indus Suture Melange Zone JUI Jamiat-i-Ulmai-Islam KP Khyber Pakhtunkhwa M&E Monitoring and Evaluation MBT Main Boundary Thrust MDTF Multi Donor Trust Fund MMT Main Mantle Thrust NCS National Conservation Strategy NDIR Non Dispersive Infra-Red NEQs National Environment Quality Standards NGOs Non–Government Organizations NHA National Highway Authority NOC No Objection Certificate
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
ii
NWFP North West Frontier Province O&M Operation and Maintenance OP Operational Policy Pak–EPA Pakistan Environment Protection Agency PCO Public Call Office PEPA Pakistan Environmental Protection Agency PEPC Pakistan Environment Protection Council PHED Public Health Engineering Department PKR Pak Rupees PM Project Manager PMAP Pakhtunkhwa Milli Awami Party PMC Project Management PML Pakistan Muslim League PPC Pakistan Penal Code PPE Personal Protective Equipment PPP Pakistan People’s Party PR Public Relations
PSC Project Steering Committee PSDP Public Sector Development Project PSQCA Pakistan Standards Quality Control Authority PTCL Pakistan Telecommunication Limited PTV Pakistan Television RE Resident Engineer RoW Right of Way SFA Social Framework Agreement
SPM Suspended Particulate Matter SRO Statutory Regulation Order UBC Uniform Building Code VOC Vehicle Operating Cost WAPDA Water and Power Development Authority WB World Bank WHO World Health Organization XEN Executive Engineer
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
iii
Executive Summary
The Government of Pakistan (GoP) through the Work & Service Department (W&SD) intends to
develop road infrastructure in the Bajaur and Orakzai agencies of Federally Administered Tribal
Areas (FATA). Both agencies are in dire need of development initiatives as these have been badly
affected by political situation and militancy in the area. The proposed project is called the FATA
Emergency Rural Roads Project (FATA ERRP). It is assisted by the World Bank administered Multi
Donor Trust Fund (MTDF) for Khyber Pakhtunkhwa, FATA and Balochistan.
This document presents the findings of Environmental and Social Impact Assessment (ESIA) of
the construction and operation of fifteen stretches of roads in the Orakzai and Bajaur agencies
of the Federally Administered Tribal Areas (FATA), Pakistan. The document was prepared
following the broader principles laid down in the Environment and Social Screening Assessment
Framework (ESSAF) which has been prepared for all emgency operations under MDTF. It has
been shared with W&SD of FATA and earlier with FATA Secretariate. And also disclosed locally
by FATA secretariat on December 15, 2010 on its website and on MTDF website. This ESIA
report includes the Environment and Social Management Plans (ESMPs) for both phases of the
project and has been cleared by the Bank for implementation.
This project will be completed in about two years from the award of contract for construction.
For execution and maintenance, the project has been assigned to the Works and Services
Department, FATA, which has engaged Associated Consulting Engineers (ACE) as its Consultant
for the design of the proposed roads. The proposed project has been divided into four packages.
Package 1 consists of one road in Bajaur (20 km) and four roads in Orakzai (2 km, 2 km, 2 km, 3
km), package 2 comprises of two sections of road in Bajaur (20 km and 3 km) and four sections
of the road in Orakzai (4 km, 3 km, 2km and 2km), package 3 (3 km and 2km) and package 4 (4.5
km and 2 km) each consists of two stretches of road in Bajaur. The total length of road that has
to be constructed is 75.5 km, out of which 55.5 km will be located in Bajaur and 20 km in
Orakzai. The project will be implemented in two phases; phase I includes package 1 only,
whereas packages 2, 3 and 4 constitute Phase II of the proposed project.
The purpose of this ESIA is to ensure that the proposed project complies with all national
environmental and social legislations as well as the WB Operational Policies on environment,
social assessment and management. However, the ambit of the legal framework of Pakistan
does not directly apply to the FATA. The region is recognized as a semi-autonomous region and
is regulated through Frontier Crimes Regulations 1901 (FCR) which is the prime source of judicial
system. There is no formal existence of a department such as Environmental Protection Agency
(EPA), which ensures regulation of environmental issues and matters. Prior to the 18th
Amendment in the Constitution of Pakistan the Federal EPA or the EPA of KP were authorized for
issuance of environment related approvals for FATA region. The jurisdiction of Federal EPA is
now limited only to the capital territory and other matters of national concern. The legal
authority of the KP EPA for granting approvals in FATA has not been documented clearly.
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
iv
Therefore, the NOC issuing authority for this ESIA has to be identified by the FATA Secretariat. At
the moment an environmental office within the FATA Secretariat is being established.
Owing to the fragile security situation and deteriorating law and order in the project area,
collection of primary environmental and social data is a daunting task. In addition, tribal norms
and cultural ethos, such as taboo on holding consultations with the women in the project area,
impedes the effort to get first hand information about the area.
The roads selected for rehabilitation in the project area are mostly unpaved and dirt tracks with
variable widths, high gradients and serpentine curves. These tracks stretch along rolling terrains,
mountainous and escarpment areas. The project under FATA ERRP proposes
construction/improvement of these roads with 3.65m bituminous paved carriageway and up to
10.85m formation width, with improved horizontal road curvature and reduced gradients of no
more then 10-15%. The project has been designed to meet international roads/highway
standards envisaged by World Bank. Based on these design criteria, the constructed roads will
have safety features, signage and appropriate drainage structures. Most of the construction
material, including sub-grade filling materials, pavement crushed stones, bricks, bitumen,
cement, concrete aggregate, asphalt, reinforcement steel, galvanized iron elements and water,
is locally available or can be procured form other locations in Khyber Pakhtunkhwa (KP) and
Pakistan.
Secondary data on the specific environmental resources of the project area is limited as there is
no real precedence of such rural infrastructure projects in the region requiring ESIA studies. As a
part of this ESIA study, primary and secondary data was collected through field surveys, public
consultations and literature research. For social data of nearby communities, a structured survey
was conducted. For Rapid Rural Survey of the area another questionnaire was used. For
information on any resettlement issues, a separate stand-alone study has been carried out, and
its key findings will be submitted separately.
The project area comprises of mostly mountainous terrains within the Bajaur and Orazkai
agencies. The proposed road sections of the FATA ERRP lie on both flat valley land as well as hill
slopes, with a majority of the proposed road lying on a mountainous terrain. Climatically the
area has cold winter and relatively mild summers. Rainfall is mainly received during monsoons
and spring sessions. Extremely cold winds blow during winters. Ambient air is generally clean.
According to the list of protected area defined in National Conservation Strategy (NCS) there is
no protected area along the project road and in the FATA region.
The project area is located in the dry sub-tropical temperate semi-evergreen scrub vegetation
area of Pakistan1. Based on the geomorphology and floral attributes, the project has
mountain/hill slope, riparian, stream-bed, stony plain and agricultural habitats, with diverse flora
and fauna. There are no less than 48 species of mammals2, 7 species of pheasants3, various
birds, reptiles, insects and other fauna. Additionally the region has considerable variety of flora,
1 T.J Roberts (1991) The Mammals of Pakistan
2 CAMP, IUCN (2003) Status and Red List of Pakistan’s Mammals
3 Iftikhar uz Zamana (2008) Conservation of Pheasants in North West Frontier Province (NWFP), Pakistan
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
v
with no less the 170 identified species4. Though not globally, but the project area does have
nationally critically endangered and endangered species5 of Striped Hyaena (Hyaena hyaena),
Leopard6 (Panthera pardus), Wolf (Canis lupus), Blue Sheep (Pseudois nayaur) and Hairy-armed
Bat (Nyctalus leisleri). In terms of flora Withania root (Withania samnifera) and bush species
(Aerva pseudo-tomentosa) are regarded as rare, but they are frequently seen at different
locations in the area. The main threat to the wild flora and fauna in the region is habitat
destruction and low forest cover. Currently Bajaur has 8.76% and Orakzai has 3.25% reported
forest area.
The communities of the project area lead their lives under strict tribal code and cultural
practices. The traditional tribal governance structure of local Maliks (tribal chiefs), Jirga
(committee of tribal elders) and the political agent (representative of the government of
Pakistan) is in place. The population in the area is divided into distinct sectarian and tribal
groups. Major tribes in the project area are Iman Khel, Miangan, Sahibzadagan, Salarzai and
Mamund adhering to Sunni Sect in Bajaur; and Syed, Abdulaziz Khel, Hwedat Khel, Mani Khel and
Saparis following Shia Sect in Orakzai agency. The project area is quite poor and under-
developed with sustenance agriculture being the main occupation. Another major cause of
poverty in the area is the high population density with 671 and 177 persons per sq. km in Bajaur
and Orakzai respectively. These figures are higher than overall figures for FATA that is 141
persons per sq. km.7 Due to the social structure and lack of education facilities, the literacy ratio
in the area is also very low. Male literacy ratio is no more than 23% and female literacy ratio is
even lower, being less than 4%. All these factors contribute to the low quality of life in terms of
health, housing and other services. Additionally poverty, tribal system and lack of education also
contribute to the conflict, violence and restriction of role of women in the area.
Analysis of alternatives has shown that project as proposed in the detailed design and feasibility
with suitable readjustments where necessary, is the best option, compared to the ‘no-project
option’ and the option of not adding any new roads and only improving the existing ones with
no deviation. Logistically, the best option is to locate all facilities of the contractor on state-
owned land as it could potentially reduce the cost of the EPC contract (land being offered free of
cost) as well as reduce the environmental and social impact of locating the construction facilities
on privately owned land. The best option from the labor point of view is to have a mixture of 100
percent unskilled local labor, subject to the availability of the requisite skills and experience, to
the extent possible semi-skilled local labor and free choice of hiring technical / skilled workers
from either within or outside of the project area.
Stakeholder consultation for this project entails meetings with individuals, groups, relevant
organizations and government departments, which are in some way linked to the project and
therefore considered stakeholders. Besides, the communities inhabiting the project area, other
4 H. Ahmad, S. Khan, A. Khan and M. Hamayun (2003) Ethnobotanical Resources of Manikhel Forests,
Orakzai Tirah, Pakistan 5 CAMP, IUCN (2003) Status and Red List of Pakistan’s Mammals
6 Unconfirmed sightings
7 Based on socio-economic indicators projected for 2006-07 in “Shaheed Bhutto Foundation FATA Figures”
whereas census data from 1998 shows population density in Bajaur 461 persons per sq. km. Orakzai 147 persons per sq. km and overall FATA 117 persons per sq. km.
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
vi
departments of government of FATA and political administration were also consulted during
project planning and their concerns were already incorporated in the project design and
management. Secondary stakeholder’s consultation with local NGOs was also carried out. Some
of the major concerns raised by the stakeholders regarding the environmental implications of
the FATA ERRP during construction and operations are as follows:
• Alignment of the route and associated structures should be designed in consultation
with local communities and elders.
• Existing traffic on the road shall not be affected.
• Noise and air pollution associated with trucking can potentially cause disturbance to
residents along the road. Adequate measures should be taken to avoid such
disturbances.
• If new roads disturb rain fed agricultural production systems, it would increase water
shortages and may result in increased poverty.
• Project related traffic causing congestion should be avoided.
• Road safety measures such as speed breakers and speed limits should be implemented
so that accidents avoided.
• Provision of sanitation awareness programs in camping facilities.
• Due consideration should be paid to privacy related matters and cultural sensitivities.
• Blasting should not be carried out near settlements.
• Relocating/dismantling of mosques and other permanent structures should be avoided.
• Job opportunities should be provided to the locals during construction activities.
The feedback, collected from the communities, has been incorporated in the impact assessment
and mitigation plan. It also contributes to the conditions of the proposed social framework
agreement (SFA) between the project proponents, construction contractor and the
communities.
The present ESIA has shown the possibility of mitigation of all adverse impacts. It is seen that
construction related impacts are likely to be related to contractor’s work practices, cooperation
between contractor and local communities, inclusion of ESIA prescriptions in the project
management and a good Social Framework Agreement (SFA).
As a means to address the environmental and social impacts of the project, comprehensive
Environment and Social Management Plans (ESMPs) have been devised. The Environment
Management Monitoring Plan (EMMP) accompanies the ESMPs. The EMMP is a system to
monitor the project activities to ensure that the responsible persons carry out the mitigation
measures proposed in this ESIA. The requirements of the contractor for undertaking the
proposed mitigation actions stated in the ESMPs and subsequent EMMPs will be integrated in
the tender and bid documents to ensure that the contractor is not only contractually bound to
undertake the necessary mitigation actions, but also his payments are linked to the compliance
with the proposed mitigation actions. To ensure maximum compliance to environmental and
social mitigation measures, the contractor’s payments are also linked to fulfillment of the
measures the contractor is responsible for as per the tender documents.
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
vii
The ESMP and the EMMP will be conducted under the following management structure and
institutional arrangement.
Furthermore, in order to ensure that the proposed project is carried out in the most
environmentally and socially responsible way, the project proponents will conduct a host of
environmental and social trainings for various target groups. These will, among others, include
trainings for selected management persons on topics such as general environmental and socio-
economic awareness, environmental and social sensitivities of the project area. Mitigation
measures, community dealings and safety issues for all site personnel, environmentally
acceptable waste disposal practices for the construction crew, road safety and defensive driving
for drivers, etc.
Similarly, environmental monitoring will be carried out with the help of proposed checklists
prepared on the basis of potential impacts and their mitigation plans in the ESMP. The
contractor’s environment specialist will monitor the compliance of ESMP against a set of
mitigation measres given in these checklists, on a regular basis, and provid to the Construction
Supervision Consultants (CSC). All non-compliances recorded in the filled checklists will be
followed up for remediation. Works and Services Department will engage a competent
consultant to conduct effects monitoring, with some parameters being monitored both ex-ante
and ex-post and others being monitored on several intervals. The objective of the effects
monitoring is to ensure that the key environmental parameters in the project area remain within
the acceptable limits throughout the project execution. Finally, the Works and Services
Department will engage a suitable consultant to carry out environmental audit of the project on
a bi-annual basis. During these audits, the ESMP compliance and its effectiveness will be
assessed. This monitoring will help identify weaknesses in the ESMP implementation and also
recommend the corrective measures. The overall budget allocated for the environmental and
social management of the project is a little over 20.6 million Pakistan rupees.
WS&D (FATA), Project Management Unit
Field Implementation Units Executive Engineer (XEN)
Sub Divisional Officer (SDO)
Supervision Consultant Environmental Specialist
Independent Environment Monitor
Deputy Director Environment (DDE)
Contractor
Contractor’s Environmentalist
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
viii
This ESIA has shown that potentially negative impacts resulting from the FATA ERRP are mostly
moderate and reversible in nature, and can be easily addressed with the help of appropriately
designed and effectively implemented mitigation measures proposed in this report.
The management of the environmental and social impacts for the project is further made easier
by the fact that the project area does not fall in an ecologically sensitive area and does not have
any significant archaeological or cultural resources that stand to be affected during the project-
related activities. The environmental and social impacts associated with construction are
temporary and, if the mitigations proposed in this ESIA were adhered to, would leave no residual
impact on the project area. The ESIA and ESMPs assessed all the major impacts and include
numerous proposed mitigation measures, and an analysis of the institutional and training
requirements for their implementation, and related costs. The mitigation measures concerning:
design issues (pre-construction); site preparation and land issues; ecology and biodiversity
disturbance; contamination and pollution; construction management; employment and
workforce policies; social issues and community support measures; waste management plan;
and monitoring programme are proposed. The major impacts and key mitigation measures are
as under:
Design and alignment of the roads will directly affect the local environment and social
activities. To mitigate these impacts, design process will ensure minimum cut-and-fill,
damage to permanent structures, alteration in water channelssprings and passages
through agricultural land/vegetation, and disturbance to community activities.
Cutting and filling operations during construction may have a geophysical impact; it is
proposed the unnecessary widening beyond the proposed design of the road shall be
avoided and natural drainage pattern will not be disturbed.
Location of camps near sensitive receptors like water resources, private lands without
prior consent of landowners and dumping and storage of construction material
equipment in private lands can ignite adverse sentiments among local populace. The
contractor will ensure that site facilities will be established on a flat land without much
natural vegetation, at least 500 m away from the communities.
Contractor will apply strict rules on his workers and labor to ensure that no spill or
leakages are caused. All fuels, oils and bitumen will be stored appropriately, with
concrete padding and bunding for containment in case of leakage.
A large quantity of earth will be removed from borrow pits potentially causing slope
instability, loss of soil/land productivity, uneven terrain, and altered drainage, so
contractors will select the area after approval for RE and these places will be leveled and
planted with appropriate trees. These borrow sites will to the extent possible not be
located on land used for agriculture, however, if borrowing fill material from land used
for agriculture is inevitable, the 30 cm top layer of the soil will be preserved and put
back to ensure that there is a minimal impact on land fertility.
The source of the project’s water will be mainly from the nearby rivers and small
tributaries, for the living camps can also be supplied by digging wells. To minimize
impact on water resources, water will be extracted only from a major source or main
stream, community will be consulted for using water resources and for ground water
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
ix
depth of the aquifer water table will be monitored. Additionally, strict measures will be
taken to ensure that no contamination is caused to water resources.
During the work on the road, the main environmental impact envisaged is the exhaust
and particulate matter emissions resulting from the vehicles. Due to the intermitted
nature of traffic flow and the fact that traffic would be mild, no irreversible impact on
the ambient air quality of the project area would take place.
Though machinery noise/vibrations will be within normal limits, the use of blasting will
be kept to an absolute minimum. Blasting near the communities will be avoided to the
great extent possible. A detailed protocol for management and monitoring of blasting
operation will be established.
Construction of road will lead to direct and indirect ecological disturbance. To minimize
such disturbance no clearance of vegetation or killing/hunting/trapping of wild animal
will be allowed. Additionally, compensatory measures will be implemented to reverse
tree cutting and ecological damages.
To minimize the effect on the existing traffic on the roads, at least one passage will
always be open for traffic. Wherever, this is not possible, contractor will schedule and
announce construction works, to allow a temporary passage of traffic.
Socially, the main concern would be the road safety issues for the community. To
mitigate this, proper signage and speed limits, while traveling through settled areas,
have been proposed.
Being a tribal area employment of alien workers may cause conflict with the locals. So
contractor will ensure the maximum un-skilled and semi-skilled labour is employed
locally.
Although the potential environmental and social issues associated with the project and their
mitigation options have been discussed in detail, however, there may be a chance for any project
affected person, an individual or group who may not be satisfied with the measures adopted to
address the issues under the project. In order to deal with such issues a Grievance
Redress/Complaint Handling Committee (GRC) will be notified both at PIU level. The GRC will be
formed in consultations with the political administration, W&S department (EA), PMU, and tribal
elders/maliks. The GRC will provide a public forum to the aggrieved to raise their objections and
have their grievances resolved through conflict resolution mechanism provided to them in the
form of GRCs.
The FATA ERRP project would be hugely beneficial for the communities located in the project
area as it offers them improved access to health and educational facilities located outside the
settlements, improved connection with outside areas and a host of possibilities for income
generation activities. Due to its mountainous terrain and other socio-political factors, FATA has
been facing unrest and violence. A prime cause for the unrest is its remote location and
minimum interaction with outside world. Construction of roads will not only create economic
opportunities, but will also expose the people to modernity. The project complies with all the
requirements of the environmental and social regulations of Pakistan as well as those prescribed
by the World Bank. The communities of the project area urgently need the project and its
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
x
benefits far outweigh the limited temporary environmental and social footprint the project is
likely to leave.
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
xi
Table of Contents
1 Introduction ................................................................................................................ 1-1
1.1 The Study Objectives ..................................................................................................... 1-1
1.2 Project Overview ........................................................................................................... 1-1
1.3 Project Area ................................................................................................................... 1-2
1.4 Implementation ............................................................................................................. 1-6
1.5 Basic Features of the Proposed Project......................................................................... 1-7
1.6 Study Methodology ....................................................................................................... 1-7
1.6.1 Environmental Assessment Process ................................................................................... 1-8
1.6.2 Field Surveys ....................................................................................................................... 1-8
1.7 Project Classification ..................................................................................................... 1-9
1.8 The Report Structure ..................................................................................................... 1-9
2 Legal, Regulatory, Policy Framework and Protocols ...................................................... 2-1
2.1 Pakistan legal requirements .......................................................................................... 2-1
2.1.1 Environmental legislation ................................................................................................... 2-1
2.1.2 Water law ........................................................................................................................... 2-4
2.1.3 Labour and health and safety legislation ........................................................................... 2-4
2.1.4 International law ................................................................................................................ 2-5
2.1.5 Customary law .................................................................................................................... 2-5
2.1.6 Judicial decisions ................................................................................................................ 2-6
2.1.7 Treaties ............................................................................................................................... 2-6
2.2 The World Bank Safeguard Policies ............................................................................... 2-7
2.2.1 Environmental Assessment (OP 4.01) ................................................................................ 2-7
2.2.2 Involuntary Resettlement (OP 4.12) ................................................................................... 2-8
2.2.3 Forestry (OP 4.36) .............................................................................................................. 2-8
2.2.4 Natural Habitat (OP 4.04) ................................................................................................... 2-9
2.2.5 Pest Management (OP 4.09) .............................................................................................. 2-9
2.2.6 Safety of Dams (OP 4.37).................................................................................................... 2-9
2.2.7 Projects on International Waterways (OP 7.50) ................................................................. 2-9
2.2.8 Cultural Property (OP 4.11) ................................................................................................ 2-9
2.2.9 Indigenous People (OP 4.10) ............................................................................................ 2-10
2.2.10 Projects in Disputed Areas (OP 7.60) ............................................................................... 2-10
2.2.11 Disclosure ......................................................................................................................... 2-11
2.3 Other Related Statutes and Laws ................................................................................ 2-11
2.3.1 The Constitution of Pakistan 1973 ................................................................................... 2-11
2.3.2 Frontier Crimes Regulations 1901 .................................................................................... 2-11
2.3.3 Pakistan Penal Code (PPC) ................................................................................................ 2-12
2.3.4 The Drainage Act 1973 ..................................................................................................... 2-12
2.3.5 Local Government Ordinance 1979.................................................................................. 2-12
2.3.6 The West Pakistan Fisheries Act 1961 .............................................................................. 2-12
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
xii
2.3.7 The Forest Act 1927 ......................................................................................................... 2-12
2.3.8 The Antiquities Act 1976 .................................................................................................. 2-12
2.3.9 The Public Health (Emergency Provision Act 1954 read with West Pakistan Epidemic Control Act 1958) Act......................................................................................................................... 2-13
2.3.10 Explosive Act 1884............................................................................................................ 2-13
2.4 Interaction with Other Agencies ................................................................................. 2-13
2.4.1 FATA Secretariat ............................................................................................................... 2-13
2.4.2 Political Agents ................................................................................................................. 2-13
2.4.3 Federal EPA ...................................................................................................................... 2-14
2.4.4 Departments of Forestry, Wildlife and Fisheries .............................................................. 2-14
2.4.5 Local Government and Municipalities .............................................................................. 2-14
2.4.6 Levies/Scouts .................................................................................................................... 2-14
2.5 Conventions, Protocols, Agreements and Understandings at International Level ..... 2-14
2.6 International Federation of Consulting Engineers (FIDIC) Clauses .............................. 2-15
3 Description of the Project ............................................................................................ 3-1
3.1 Location ......................................................................................................................... 3-1
3.2 Road Length ................................................................................................................... 3-1
3.3 Existing Road Dimensions and Description ................................................................... 3-2
3.3.1 Kharkano to Kulala, Length 20 Km. (Bajaur Package 1) ...................................................... 3-2
3.3.2 Dag Qilla Bypass Road, Length 3 Km. (Bajaur Package 2)................................................... 3-2
3.3.3 Road from Bado to Serisar, Length 20 Km.(Bajaur Package 2) ........................................... 3-2
3.3.4 Road from Shukrata to Pampokha, Length 3 Km. (Bajaur Package 3)................................ 3-3
3.3.5 Tangi Adda toBagoriBridge,Length4.5Km. (Bajaur Package 3) ........................................... 3-3
3.3.6 Road from Loia Kanda to Ghalishah, Length 3 Km. (Bajaur Package 4) ............................. 3-3
3.3.7 Road from Shagai to Karkanai Charmang, Length 2 Km. (Bajaur Package 4) ..................... 3-3
3.3.8 Road from Largri Tan to Dop Sana, Length 2 Km. (Orakzai Package 1) .............................. 3-3
3.3.9 Road from Dargai to Shamim Jan Killi, Length 2 Km. (Orakzai Package 1) ......................... 3-4
3.3.10 Road from Palosia to Hakim Killi Khawari, Length 3 Km. (Orakzai Package 1) ................... 3-4
3.3.11 Road from Dargai to Sharo Doghal, Length 2 Km. (Orakzai Package 1) ............................. 3-4
3.3.12 Road from Sam Feroz Khel to Dara Ghari, Length 3 Km. (Orakzai Package 2) ................... 3-4
3.3.13 Road from Dara Ghari to Sangrani, Length 2 Km. (Orakzai Package 2) .............................. 3-4
3.3.14 Road from Kalaya to Saboora Khel, Length 4 Km. (Orakzai Package 2).............................. 3-4
3.3.15 Road from Kadda Bazar to Aso Khel Khapa, Length 2 Km. (Orakzai Package 2)................. 3-5
3.4 Project Components ...................................................................................................... 3-5
3.5 Drainage Structures ....................................................................................................... 3-8
3.6 Scope of work of Proposed Project ............................................................................. 3-11
3.6.1 Design Work Items ........................................................................................................... 3-11
3.6.2 Construction Work Items ................................................................................................. 3-11
3.7 Existing Road Condition ............................................................................................... 3-12
3.8 Work and Material ...................................................................................................... 3-14
3.8.1 Estimated Work / Major Work Items ............................................................................... 3-14
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
xiii
3.8.2 Materials Requirement .................................................................................................... 3-14
3.9 Construction Resources Procurement, and Transportation ....................................... 3-14
3.9.1 Construction Materials ..................................................................................................... 3-14
3.9.2 Filling Materials of Sub grade ........................................................................................... 3-15
3.9.3 Broken Stones for Base Course (Coarse Aggregate)......................................................... 3-15
3.9.4 Broken Stones for Concrete (Coarse Aggregate) .............................................................. 3-15
3.9.5 Sand .................................................................................................................................. 3-15
3.9.6 Cement, Steel, and Asphalt .............................................................................................. 3-15
3.10 Raw Material Availability ............................................................................................. 3-15
3.11 Machinery to be Used ................................................................................................. 3-16
3.12 Equipment and Installations ........................................................................................ 3-16
3.13 Construction Schedule ................................................................................................. 3-17
3.14 Construction Logistics .................................................................................................. 3-17
3.14.1 Work Base ........................................................................................................................ 3-17
3.14.2 Labor Supply ..................................................................................................................... 3-17
3.14.3 Labor Camps ..................................................................................................................... 3-19
3.14.4 Machinery Maintenance and Equipment Yards ............................................................... 3-20
3.14.5 Material Depots................................................................................................................ 3-20
3.14.6 Machinery Repair Workshops .......................................................................................... 3-20
3.14.7 Approach to Work Bases .................................................................................................. 3-20
3.14.8 Camp Offices .................................................................................................................... 3-20
3.14.9 Healthcare ........................................................................................................................ 3-20
3.14.10 Labor Reporting Office ..................................................................................................... 3-20
3.14.11 Labor Transport ................................................................................................................ 3-21
3.14.12 Water Supply .................................................................................................................... 3-21
3.14.13 Work Uniform and Health Safety Equipment .................................................................. 3-21
3.14.14 Signage ............................................................................................................................. 3-21
3.14.15 Lighting and Illumination .................................................................................................. 3-21
3.14.16 Layout of Waste Disposal System .................................................................................... 3-21
3.15 Safe Design Criteria ..................................................................................................... 3-22
3.16 Institutional Arrangements ......................................................................................... 3-22
3.17 Grievance Redress Mechanism/Complaint Handiling System .................................... 3-23
3.18 Estimated Project Cost ................................................................................................ 3-24
4 Baseline Study of Project Area ..................................................................................... 4-1
4.1 The Project Area of Impact .......................................................................................... 4-19
4.2 Physical Environment .................................................................................................. 4-19
4.2.1 Geography ........................................................................................................................ 4-19
4.2.2 Geology and Soil ............................................................................................................... 4-19
4.2.3 Seismicity .......................................................................................................................... 4-20
4.2.4 Land Use ........................................................................................................................... 4-21
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
xiv
4.2.5 Water Resources .............................................................................................................. 4-22
4.2.6 Climate and Air Quality .................................................................................................... 4-24
4.2.7 Ambient Air Quality .......................................................................................................... 4-25
4.2.8 Noise Level ....................................................................................................................... 4-25
4.2.9 Minerals............................................................................................................................ 4-25
4.2.10 Physical Cultural Heritage ................................................................................................ 4-26
4.3 Biological Environment ................................................................................................ 4-26
4.3.1 Habitat Types ................................................................................................................... 4-26
4.3.2 Fauna ................................................................................................................................ 4-27
4.3.3 Flora.................................................................................................................................. 4-29
4.3.4 Protected Areas ................................................................................................................ 4-31
4.3.5 Endangered Species ......................................................................................................... 4-31
4.3.6 Forest ............................................................................................................................... 4-31
4.4 Social Environment ...................................................................................................... 4-32
4.4.1 Social Setting .................................................................................................................... 4-33
4.4.2 Population ........................................................................................................................ 4-33
4.4.3 Community/Social Structure ............................................................................................ 4-35
4.4.4 Poverty Status .................................................................................................................. 4-36
4.4.5 Industries and Livelihoods ................................................................................................ 4-37
4.4.6 Education.......................................................................................................................... 4-39
4.4.7 Political Parties ................................................................................................................. 4-40
4.4.8 Marriages ......................................................................................................................... 4-40
4.4.9 Social and Administrative Organization ........................................................................... 4-41
4.4.10 Religious Beliefs ................................................................................................................ 4-41
4.4.11 Conflict Resolution ........................................................................................................... 4-42
4.4.12 Custom of Carrying Fire Arms .......................................................................................... 4-42
4.4.13 Role, Position and Status of Women ................................................................................ 4-42
4.4.14 Migration .......................................................................................................................... 4-43
4.4.15 Housing ............................................................................................................................. 4-43
4.4.16 Services and Amenities Available in the Area .................................................................. 4-45
4.4.17 Transport and Accessibility .............................................................................................. 4-46
4.4.18 Health ............................................................................................................................... 4-46
5 Analysis of Alternatives ............................................................................................... 5-1
5.1 Road Alternatives .......................................................................................................... 5-1
5.1.1 No Project Option ............................................................................................................... 5-1
5.1.2 Project Road to Follow Exactly the Existing Route with No Alteration .............................. 5-2
5.1.3 Project as Proposed in Feasibility with Alterations Where Necessary ............................... 5-3
5.2 Logistic Sites .................................................................................................................. 5-3
5.2.1 Location of Contractor’s Facilities on Public Land .............................................................. 5-3
5.2.2 Siting of Contractor’s Facilities on Private Lands ............................................................... 5-4
5.2.3 Siting the Contractor’s Facilities at Appropriate Site, be it Public Land or Private Land .... 5-5
5.3 Labor .............................................................................................................................. 5-5
5.3.1 All Labor Local .................................................................................................................... 5-5
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
xv
5.3.2 All Labor from Outside ....................................................................................................... 5-6
5.3.3 An Admixture of Local and Outside Labor as per Skill Required ........................................ 5-6
5.4 Summary of Alternatives ............................................................................................... 5-7
6 Stakeholder Consultations ........................................................................................... 6-1
6.1 General .......................................................................................................................... 6-1
6.2 Identification of Stakeholders ....................................................................................... 6-1
6.3 Stakeholder Consultation Process ................................................................................. 6-1
6.4 Primary Stakeholders Consultation ............................................................................... 6-2
6.4.1 Topics for Discussion .......................................................................................................... 6-3
6.4.2 Outcomes of Consultations ................................................................................................ 6-3
6.5 Secondary Stakeholder Consultations ........................................................................... 6-4
6.5.1 Consultation with NGOs ..................................................................................................... 6-4
6.5.2 Consultation with EPA Khyber Pakhtunkhwa (KP) ............................................................. 6-4
6.5.3 Consultation with Pak- EPA ................................................................................................ 6-5
6.6 Land Acquisition and Resettlement–Related Concerns ................................................ 6-5
6.7 Addressing Stakeholders Concerns ............................................................................... 6-5
7 Environmental Impact Assessment and Mitigation Measures ........................................ 7-1
7.1 Potential Impact Sources ............................................................................................... 7-2
7.2 Explanation of the Impact Assessment ......................................................................... 7-7
7.2.1 Soil and Landscape ............................................................................................................. 7-7
7.2.2 Location of Labor Camps, Material Depots, Equipment Yards and Approach Roads ........ 7-9
7.2.3 Oil Spills from Construction Machinery ............................................................................ 7-10
7.2.4 Earthen Embankments or Concrete Work, Edge Scouring ............................................... 7-11
7.2.5 Impact of Borrowing Material from Earth Borrow Sites and Stone Quarrying ................ 7-11
7.2.6 Water Resources .............................................................................................................. 7-11
7.2.7 Contamination of Soil and Water ..................................................................................... 7-13
7.2.8 Releases to Air .................................................................................................................. 7-14
7.2.9 Noise and Vibrations ........................................................................................................ 7-15
7.2.10 Ecology and Biodiversity Disturbance .............................................................................. 7-16
7.2.11 Acquisition of Private Assets and Compensation ............................................................. 7-17
7.2.12 Increased Risk of Accidents Caused by Partial Closure of Road during Construction ...... 7-17
7.2.13 Safety and Health Hazards ............................................................................................... 7-18
7.2.14 Restricted Mobility of Local Population ........................................................................... 7-19
7.2.15 Gender Issues ................................................................................................................... 7-19
7.2.16 Social Conflicts and Employment of Locals on the Project .............................................. 7-20
7.2.17 Rise in the Prices of Essential Commodities ..................................................................... 7-20
7.2.18 Use of Local Water Supplies and Other Common Resources ........................................... 7-21
7.2.19 Adverse Effects on Archaeological Sites ........................................................................... 7-21
7.2.20 Graveyards ....................................................................................................................... 7-22
7.2.21 Spread of Communicable Diseases amongst the Project Labor and Adjoining Population . 7-22
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
xvi
7.2.22 Recreational Facilities for Public ...................................................................................... 7-22
7.2.23 Operational and Management Phase .............................................................................. 7-23
7.2.24 Socioeconomic Impacts on the Overall Project Area ....................................................... 7-23
8 Environmental and Social Management Plan (Phase I) .................................................. 8-1
8.1 General .......................................................................................................................... 8-1
8.2 Mitigation through Avoidance of Adverse Impacts by Suitable Design ........................ 8-1
8.3 Tender and Construction Phase .................................................................................... 8-1
8.3.1 Impact Reduction Measures .............................................................................................. 8-1
8.3.2 Pre–Tender Conference ..................................................................................................... 8-3
8.3.3 Pre-Construction Coordination Meeting ............................................................................ 8-3
8.4 Operational Phase - Management of Operational Impact ............................................ 8-3
8.5 Management of Social Impacts ..................................................................................... 8-4
8.6 Environmental Mitigation and Monitoring Plan (EMMP) ............................................. 8-4
8.7 Visits / Inspection Authorization ................................................................................... 8-5
8.8 ESMP Implementation Arrangements ........................................................................... 8-6
8.8.1 Institutional Arrangements ................................................................................................ 8-6
8.8.2 Management Responsibility ............................................................................................... 8-7
8.8.3 Summary of Finances for Various Agencies ....................................................................... 8-8
8.8.4 Reporting and Supervision ................................................................................................. 8-9
8.9 Mitigation Plans ........................................................................................................... 8-10
8.10 Environmental Monitoring .......................................................................................... 8-25
8.10.1 Compliance Monitoring .................................................................................................... 8-25
8.10.2 Effects Monitoring ............................................................................................................ 8-25
8.10.3 Third Party Monitoring ..................................................................................................... 8-25
8.10.4 Checklists for Environmental Monitoring......................................................................... 8-25
8.11 Environmental and Social Trainings ............................................................................ 8-30
8.12 Environmental and Social Management Budget ......................................................... 8-30
8.13 Recommendations ....................................................................................................... 8-31
8.13.1 Avoidance ......................................................................................................................... 8-31
8.13.2 Contractor’s Obligations................................................................................................... 8-31
8.13.3 Social Frame Work Agreement (SFA) ............................................................................... 8-35
8.13.4 Social Frame Work Agreement ........................................................................................ 8-36
8.13.5 Operational Manual ......................................................................................................... 8-39
9 Environmental Management Plan (Phase II) ................................................................. 9-1
9.1 General .......................................................................................................................... 9-1
9.2 Mitigation through Avoidance of Adverse Impacts by Suitable Design ........................ 9-1
9.3 Tender and Construction Phase .................................................................................... 9-2
9.3.1 Impact Reduction Measures .............................................................................................. 9-2
9.3.2 Pre-Tender Conference ...................................................................................................... 9-3
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
xvii
9.3.3 Pre-Construction Coordination Meeting ............................................................................ 9-4
9.4 Operational Phase – Management of Operational Impact ........................................... 9-4
9.5 Management of Social Impacts ..................................................................................... 9-4
9.6 Environmental Mitigation and Monitoring Plan (EMMP) ............................................. 9-4
9.7 Visits / Inspection Authorization ................................................................................... 9-5
9.8 ESMP Implementation Arrangements ........................................................................... 9-6
9.8.1 Institutional Arrangements ................................................................................................ 9-6
9.8.2 Management responsibility ............................................................................................... 9-7
9.8.3 Summary of Finances for Various Agencies ....................................................................... 9-8
9.8.4 Reporting Supervision ........................................................................................................ 9-9
9.9 Mitigation Plans ........................................................................................................... 9-10
9.10 Environmental Monitoring .......................................................................................... 9-25
9.10.1 Compliance Monitoring .................................................................................................... 9-25
9.10.2 Effects Monitoring ............................................................................................................ 9-25
9.10.3 Third Party Monitoring ..................................................................................................... 9-25
9.10.4 Checklist for Environmental Monitoring .......................................................................... 9-25
9.11 Environmental and Social Trainings ............................................................................ 9-30
9.12 Environmental and Social Management Budget ......................................................... 9-30
9.13 Recommendations ....................................................................................................... 9-31
9.13.1 Avoidance ......................................................................................................................... 9-31
9.13.2 Contractor’s Obligations................................................................................................... 9-31
9.13.3 Social Frame Work Agreement (SFA) ............................................................................... 9-35
9.13.4 Social Frame Work Agreement ........................................................................................ 9-36
9.13.5 Operational Manual ......................................................................................................... 9-39
10 References ................................................................................................................ 10-1
Annexures ............................................................................................................................. 1
Annexure 1: Flora of FATA ............................................................................................................ 1
Annexure 2: Socio-Economic Indicators of FATA ......................................................................... 5
Annexure 3: Checklists for ESMP .................................................................................................. 8
Annexure 4: Survey Instruments ................................................................................................ 14
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
xviii
List of Tables and Figures
List of Tables
Table 1.1: Road Packages and Lengths for the Proposed Package ............................................... 1-6
Table 1.2: Environmental and Social Assessment Process ............................................................ 1-8
Table 2.1: Selected NEQS for Waste Effluents ............................................................................ 2-16
Table 2.2: NEQS for Industrial Gaseous Emissions ...................................................................... 2-17
Table 2.3: National Environmental Quality Standards for Ambient Air ...................................... 2-18
Table 2.4: NEQS for Motor Vehicles Exhaust and Noise for In-use Vehicles ............................... 2-19
Table 2.5: NEQS for Motor Vehicles Exhaust and Noise for New Diesel Vehicles, Passenger Cars
and Light Commercial Vehicles (g/Km) ....................................................................................... 2-19
Table 2.6: NEQS for Motor Vehicles Exhaust and Noise for New Diesel Vehicles, Heavy Duty
Diesel Engines and Large Goods Vehicles (g/Kwh) ...................................................................... 2-20
Table 2.7: NEQS for Motor Vehicles Exhaust and Noise for New Petrol Vehicles (g/km) ........... 2-20
Table 2.8: National Standards for Drinking Water Quality .......................................................... 2-21
Table 2.9: National Environmental Quality Standards for Noise ................................................ 2-22
Table 3.1: Package Details and Road Lengths ............................................................................... 3-1
Table 3.2: Main Technical Indicators of Geometrical Design ........................................................ 3-5
Table 3.3: Key Drainage Features / Structures .............................................................................. 3-8
Table 3.4: Estimated Works and Work Features ......................................................................... 3-14
Table 3.5: Estimated Construction Material Requirement ......................................................... 3-14
Table 3.6: Raw Material Availability ............................................................................................ 3-15
Table 3.7: Estimated Machinery Requirement ............................................................................ 3-16
Table 3.8: Estimated Requirement for Equipment and Installations .......................................... 3-16
Table 3.9: Illustrative Distribution of Labor ................................................................................. 3-18
Table 3.10: Construction Team and Personal for the Proposed Project ..................................... 3-18
Table 3.11: Proposed Camp Sites for Project Roads ................................................................... 3-19
Table 4.1:Land Utilization Statistics............................................................................................. 4-21
Table 4.2: Water Resources in the Project Area ......................................................................... 4-22
Table 4.3: Mean Monthly Temperature, Precipitation, and Relative Humidity Recorded at Kohat
Station ......................................................................................................................................... 4-25
Table 4.4: Annually Minerals Extracted from the FATA Region .................................................. 4-25
Table 4.5: Fauna of Tribal Areas of Pakistan ............................................................................... 4-28
Table 4.6: Common Flora in FATA ............................................................................................... 4-29
Table 4.7: Land Use and Forest Area in FATA and Project Agencies ........................................... 4-31
Table 4.8: Villages/Settlements in the Project Area .................................................................... 4-32
Table 4.9: Population Data for Bajaur and Orakzai ..................................................................... 4-34
Table 4.10: Age/Gender Distribution in the Project Area ........................................................... 4-35
Table 4.11: Major Tribes/Clans in Bajaur Agency Project Area ................................................... 4-36
Table 4.12: Major Tribes/Clans in Orakzai Agency Project Area ................................................. 4-36
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
xix
Table 4.13: Income and Landholding in the Project Area ........................................................... 4-37
Table 4.14: Livelihoods in the Project Area ................................................................................. 4-38
Table 4.15: Education Facilities in the Project Area .................................................................... 4-39
Table 4.16: Literacy Rate and Enrollment in the Project Area .................................................... 4-40
Table 4.17: Housing Data in the Project Area ............................................................................. 4-44
Table 4.18: Services and Amenities Available in the Area .......................................................... 4-46
Table 4.19: Roads in the FATA Region ......................................................................................... 4-46
Table 4.20: Health Facilities and Coverage in the Project Area .................................................. 4-47
Table 4.21: Major Ailments and Prevalence Reported in the Project Area ................................ 4-47
Table 4.22: Sanitation Facilities in the Project Area .................................................................... 4-48
Table 6.1: Summary of Public Consultations ................................................................................. 6-2
Table 7.1: Summary of Evaluated Significant Environmental Impacts .......................................... 7-1
Table 7.2: Evaluation of Environmental and Social Impacts ......................................................... 7-4
Table 8.1: Minimum Monitoring Plan ........................................................................................... 8-5
Table 8.2: Environmental Impacts during Construction Phase ................................................... 8-10
Table 8.3: Social Impacts ............................................................................................................. 8-18
Table 8.4: Operational Phase ...................................................................................................... 8-24
Table 8.5: Effects Monitoring Plan .............................................................................................. 8-28
Table 8.6: Environmental and Social Trainings............................................................................ 8-30
Table 8.7: Cost Estimates for Environmental Management ....................................................... 8-31
Table 9.1: Minimum Monitoring Plan ........................................................................................... 9-5
Table 9.2: Environmental Impacts during Construction Phase ................................................... 9-10
Table 9.3: Social Impacts ............................................................................................................. 9-18
Table 9.4: Operational Phase ...................................................................................................... 9-24
Table 9.5: Effects Monitoring Plan .............................................................................................. 9-28
Table 9.6: Environmental and Social Trainings............................................................................ 9-30
Table 9.7: Cost Estimates for Environmental Management ....................................................... 9-31
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
xx
List of Figures
Figure 1.1: Project Area ................................................................................................................. 1-3
Figure 1.2: Project Surroundings for Bajaur Agency ..................................................................... 1-4
Figure 1.3: Project Surroundings for Orakzai Agency .................................................................... 1-5
Figure 3.1: Typical Cross-Section in Rolling Terrain and Built-up Areas ........................................ 3-6
Figure 3.2: Typical Cross-Section in Mountainous Terrain and ECSCarpment Areas .................... 3-7
Figure 3.3: Plan for Culverts for the Proposed Project .................................................................. 3-9
Figure 3.4: Sections for Road Side Covered Drain ....................................................................... 3-10
Figure 3.5: Pictorial View of Project Road ................................................................................... 3-12
Figure 3.6: Land Use beside the Start Point of the Project Road ................................................ 3-12
Figure 3.7: A View of the Proposed Road at KM. 5+000 ............................................................. 3-12
Figure 3.8: Another View of the Proposed Road at KM. 8+000 .................................................. 3-12
Figure 3.9: A View of the Proposed Road at KM. 10+000 ........................................................... 3-13
Figure 3.10: Proposed Road Condition at KM. 12+000 ............................................................... 3-13
Figure 3.11: View of the Proposed Road at KM. 15+000 ............................................................ 3-13
Figure 3.12: Another View of the Proposed Road at KM. 18+000 .............................................. 3-13
Figure 4.1: Environmental Settings of the Project Area in Bajaur Agency .................................... 4-2
Figure 4.2: Environmental Settings of the Project Area in Orakzai Agency .................................. 4-3
Figure 4.3: Environmental Setting of Bajaur Agency Phase 1 Kharkano to Kulala Road, Length 20
Km. ................................................................................................................................................. 4-4
Figure 4.4: Environmental Setting of Orakzai Agency Phase1 Dargi to Shamim Jan Killi Road,
Length 2 Km. .................................................................................................................................. 4-5
Figure 4.5: Environmental Setting of Orakzai Agency Phase1 Dargai to Sharo Doghal Road, Length
2 Km. .............................................................................................................................................. 4-6
Figure 4.6: Environmental Setting of Orakzai Agency Phase1 Largri Tan to Dop Sana Road, Length
2 Km. .............................................................................................................................................. 4-7
Figure 4.7: Environmental Setting of Orakzai Agency Phase1 Palosia to Hakim Kalli Khawari Road,
Length 3 Km. .................................................................................................................................. 4-8
Figure 4.8: Environmental Setting of Bajaur Agency Phase2 Dag Qilla Bypass Road, Length 3 Km.
....................................................................................................................................................... 4-9
Figure 4.9: Environmental Setting of Bajaur Agency Phase2 Bado to Serisar Road, Length 20 Km.
..................................................................................................................................................... 4-10
Figure 4.10: Environmental Setting of Orakzai Agency Phase2 Dara Ghari to Sangrani Road,
Length 2 Km. ................................................................................................................................ 4-11
Figure 4.11: Environmental Setting of Orakzai Agency Phase2 Kadda Bazar to Aso Khel Khapa
Road, Length 2 Km. ...................................................................................................................... 4-12
Figure 4.12: Environmental Setting of Orakzai Agency Phase2 Kalaya to Saboora Khel Road,
Length 4 Km. ................................................................................................................................ 4-13
Figure 4.13: Environmental Setting of Orakzai Agency Phase2 Sam Feroz Khel to Dara Ghari Road,
Length 3 Km. ................................................................................................................................ 4-14
Figure 4.14: Environmental Setting of Bajaur Agency Phase2 Shukrata to Pampokha Road, Length
3 Km. ............................................................................................................................................ 4-15
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
xxi
Figure 4.15: Environmental Setting of Bajaur Agency Phase2 Tangi Adda to Bagori Bridge Road,
Length 4.5 Km. ............................................................................................................................. 4-16
Figure 4.16: Environmental Setting of Bajaur Agency Phase2 Loia Kanda to Ghalishah Road,
Length 3 Km. ................................................................................................................................ 4-17
Figure 4.17: Environmental Setting of Bajaur Agency Phase2 Shagai to Karkanai Charmang Road,
Length 2 Km. ................................................................................................................................ 4-18
Figure 4.18: Cropped Fields in the Project Area .......................................................................... 4-21
Figure 4.19: An Operation Tube Well in the Project Area ........................................................... 4-23
Figure 4.20: Brick Lined Water Channel for Irrigation ................................................................. 4-23
Figure 4.21: A Typical Dense Settlement in FATA ....................................................................... 4-44
Figure 4.22: Settlement with Agricultural Land in FATA ............................................................. 4-44
Figure 8.1: Organogram for Implementation of ESMP.................................................................. 8-7
Figure 9.1: Organogram for Implementation of ESMP...................... Error! Bookmark not defined.
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 1-1
1 Introduction
This document presents the Environmental and Social Impact Assessment (ESIA) of the
construction and operation of fifteen stretches of road in the Orakzai and Bajaur agencies of the
Federally Administered Tribal Areas (FATA), Pakistan. The proposed project has been divided
into four packages: package 1 is comprised of one road in Bajaur and four roads in Orakzai,
package 2 entails two roads in Bajaur and 4 roads in Orakzai, package 3 and Package 4 each
consists of two stretches of road in Bajaur. The project will be implemented in two phases;
Phase I includes Package 1 only, whereas packages 2, 3 and 4 constitute Phase II of the proposed
project.
The document also includes the Environment and Social Management Plans (ESMPs) one each
for the two phases of the project (the details of the phases are explained later in Section 1.3).
The proposed project is called the FATA Emergency Rural Roads Project (FATA ERRP) and is
assisted by the World Bank administered Multi Donor Trust Fund for Khyber Pakhtunkhwa, FATA
and Baluchistan.
1.1 The Study Objectives
The ultimate objective of the study is to make the project environmentally responsible and
socially acceptable. The specific objectives of this study can be identified as follows:
To collect the baseline data on physical, biological and socio–economic conditions of the
project area using primary as well as secondary sources.
To carryout environmental and social assessment, including the supporting
administrative and legal framework of the proposed road infrastructure.
To identify mitigation measures for the potential environmental impacts
To propose institutional responsibilities and methods of monitoring the mitigation
measures and monitoring procedures.
To prepare the Environmental and Social Management Plan.
1.2 Project Overview
The Government of Pakistan (GoP) through the Work & Service Department intends to develop
road infrastructure in the Bajaur and Orakzai agencies of FATA. Both these agencies are in dire
need of development as they have been greatly affected by political structure and militancy.
For this purpose the FATA Work & Service Department has applied for financing from the MTDF
to help respond to the post conflict situation by carrying out emergency building of priority rural
roads infrastructure in FATA. Given the crisis situation prevailing in FATA the main focus of first
set of priorities is the improvement of pedestrians and vehicular access to some of poorest
neighborhoods especially in mountainous and escarpment terrain of Bajaur and Orakzai
Agencies of FATA.
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 1-2
This ambitious road development project comprises the construction of 75.5 Km. of rural roads
out of which 55.5 km. are located in Bajaur Agency and 20 km. lie in Orakzai Agency. The roads
development shall improve connectivity within the Bajaur and Orakzai Agencies as well as with
neighboring areas of FATA.
Although about 20 km. length of roads are located in rolling terrain of Bajaur and Orakzai
Agencies, the major length of project roads i.e. 55.5 km. lie in rugged mountainous terrain as
well as escarpment areas with steep gradients and sharp, serpentine horizontal curves.
The project lies in FATA where there is no formal department i.e. an Environmental Protection
Agency, exists for regulating environment matters and issues. Prior to the 18th Amendment in
the Constitution of Pakistan the Federal EPA or the EPA of KP were authorized for issuance of
environment related approvals for FATA. The jurisdiction of Federal EPA is now limited only to
the capital territory and other matters of national concern. The legal authority of the KP EPA for
granting approvals in FATA is not clearly documented. Therefore, the NOC issuing authority for
this ESIA has to be identified by the FATA Secretariat. At this moment establishment of an
environmental office within the FATA Secretariat is under process.
1.3 Project Area
The project area is defined as the geographical region where the environmental and social
impacts of the proposed project, both during construction and operation are likely to occur. For
this ESIA and ESMP, the project area is defined as the area located within 2 km of either side of
the proposed roads as the proposed roads are not located within any ecologically sensitive,
archaeologically significant or socially and culturally important area. It is therefore expected that
the environmental and social impact of the proposed project on the project areas would be fairly
temporary and would mainly occur during the construction phase. Maps of the project area and
the project surroundings are presented as Figures 1.1, 1.2 and 1.3.
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 1-3
Figure 1.1: Project Area
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 1-4
Figure 1.2: Project Surroundings for Bajaur Agency
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 1-5
Figure 1.3: Project Surroundings for Orakzai Agency
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 1-6
1.4 Implementation
The project proponents will carry out the project in two phases, I and II. Phase I, comprises of a
stretch of road totaling 29 km. Out of which 20 km would be located within the Bajaur Agency
whereas the remaining 9 km in Orakzai agency. Phase II consists of a total of 46.5 km of roads,
out of which 35.5 km is located in Bajaur and 11 km in Orakzai agencies. The road packages for
the proposed project are presented in Table 1.1.
Table 1.1: Road Packages and Lengths for the Proposed Package
Pkg.
Bajaur Orakzai Total Length
(km) Road Section
Lgth. (km)
Road Section Lgth. (km)
1 Kharkano to Kulala (34°46'21.73"N 71°38'2.47"E) 20
Dargai to Ghakhi to Sharo Doghal (33°43'48.05"N 70°54'0.39"E) 2
Dargai to Shamim Khel (33°43'48.96"N 70°53'40.50"E) 2
Largri Tan to Dop Sana (33°43'48.90"N 70°54'3.29"E) 2
Palosia to Hakim Killi (33°44'8.76"N 70°56'37.00"E) 3
Sub Total 20 Sub Total 9 29
2 Dak Qilli By-Pass (34°43'54.31"N 71°31'38.85"E) 3
Kada Bazaar to Aso Khel Khapa (33°43'51.95"N 70°52'13.97"E) 2
Bado to Serisar Blacktop (34°42'10.45"N 71°39'24.03"E) 20
Sam Feroz Khel to Dara Ghari (33°46'36.93"N 70°57'58.89"E) 3
Dara Ghari to Sangrani (33°46'46.67"N 70°57'43.83"E) 2
Kalaya to Saboora (33°44'42.31"N 70°56'25.06"E) 4
Sub Total 23 Sub Total 11 34
3 Shukrata to Pampokha (34°48'0.69"N 71°39'5.20"E) 3
Tangi Adda to Bagori Bridge (34°42'28.72"N 71°21'0.22"E) 4.5
Sub Total 7.5 Sub Total
7.5
4 Loia Kanda to Ghalishah (34°48'35.29"N 71°39'39.29"E) 3
Shagai to Karkanai Charmang (34°44'29.03"N 71°18'56.17"E) 2
Sub Total 5 Sub Total
5
Grand Total 55.5 Grand Total 20 75.5
The responsibility and ownership for the implementation and operation of the World Bank
assisted FATA ERRP is with the FATA Works & Service Department that have procured the
services of Associated Consulting Engineers (Pvt.) Ltd. (ACE) for the Detailed Engineering Design,
Economic Feasibility Study and preparation of PC–I
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 1-7
1.5 Basic Features of the Proposed Project
The scope of work of the FATA ERRP comprises of detailed engineering design, economic
feasibility studies and the preparation of PC–I for the 75.5 km length roads in Bajaur and Orakzai
agencies. The proposed project entails following activities:
i. Inventories of roads and existing infrastructure
ii. Collection of existing traffic pavement structure data (where available)
iii. Field topographic survey (Traverse and Leveling)
iv. Soil investigation along the proposed road alignments
v. Hydrological and hydraulic studies
vi. Traffic forecasts
vii. Design of pavement structure
viii. Highway geometric design, preparation of plan, profile and general drawings
ix. Design of cross drainage structure and preparation of structural drawings
x. Tender documents, bill of quantities and cost estimates
xi. Preparation of PC–I
1.6 Study Methodology
The purpose of this ESIA is to ensure that the proposed project complies with all national
environmental and social legislations as well as the environmental and social guidelines of the
World Bank. However, the jurisdiction of the legal framework of Pakistan does not extend to the
FATA as this region is recognized as a semi-autonomous region. As a result, the guidelines for
conducting environmental assessments are not binding on projects implemented in FATA.
However, in the absence of any specific FATA based regulations, this ESIA has been conducted as
per the national environmental regulations and guidelines.
Conducting this ESIA in the project area was a challenging task mainly due to the deteriorating
law and order situation and other tribal norms and cultural ethos associated with the region.
Experts from other parts of Pakistan are not allowed to conduct field related activities in the
region due to precarious security situation, local expertise in the field of environmental and
social impact assessment is rarely available. As a result, locals from the project area were
brought to Islamabad. They were trained in the data collection and surveying techniques for ESIA
studies and subsequently sent to field for data collection and holding the primary stakeholder
consultations.
Secondary data on the specific environmental resources of the project area is limited as there is
no real precedence of such rural infrastructure projects in the region requiring ESIA studies. As a
part of this ESIA study, primary and secondary data was collected through field surveys, public
consultations and literature review. For social data of nearby communities, a structured survey
was conducted. For Rapid Rural Survey of the area another questionnaire was used. For
information on any resettlement issues, a separate stand-alone study has been carried out, and
its key findings will be submitted separately.
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 1-8
1.6.1 Environmental Assessment Process
The environmental and social assessment was carried out according to the process shown in
Table 1.2.
Table 1.2: Environmental and Social Assessment Process
Phase Activities Status Responsibility
Screening and Scoping
Reconnaissance and initial site visit and consultations, identification of issues & applicable safeguard policy, categorization and working out an action plan.
Carried out during the present ESIA
Construction Supervision Consultants (CSC)
ESMP Preparation
Draft ESMP including SFA
Carried out during/prepared as part of the present ESIA
CSC
Disclosure and SFA Agreement
Disclosure of Draft ESMP and SFA
Pending till final approval of project. Draft SFA ready
Works and Services Department and communities assisted by CSC
Signing of SFA Pending till the commencement of the project.
Works and Services Department and communities assisted by CSC
Final EMP Final version of ESMP produced
Included in the present ESIA.
CSC
Implementation and Monitoring
Monitoring and Reporting on Environmental and Social Mitigation
Will be carried out during construction and operational phase.
XEN, CSC
1.6.2 Field Surveys
A well-trained local team of four experts carried out the field survey. They collected the relevant
environmental data and also undertook a two-phase stakeholder consultation program, as
described below.
Phase–I comprised of the meetings and discussions with local and regional officials. These
meetings were helpful in achieving multiple and diverse objectives such as:
Provision of forum for the initial definition of critical environmental issues.
Establishment of their interpretation as official stakeholders, the key sector
development issues and linkage to the environmental and social development.
Confirmation of the suitability of initial list of communities selected for consultation.
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 1-9
Phase–II involved the understanding of the program through semi–structured discussion in
communities of the project area of influence. The program included both community
consultations and discussions with the Tribal Development Network (TDN), a local network of
organizations working in 7 agencies and 6 frontier regions and having 62 local CBOs and NGOs as
its members in the project area.
1.7 Project Classification
The project only involves construction of several roads totaling to 75.5 km in an area with little
environmental and/or social sensitivity. As per the World Bank’s Operational Policies it is a
Category “B” project.
1.8 The Report Structure
This ESIA document is structured as follows:
Chapter - 1: Introduction containing general information about the project and process of
carrying out the study.
Chapter - 2: Legislative and Policy Framework describes the policy, laws and regulations
governing this ESIA.
Chapter - 3: The Project Description describes overall details of the proposed activities to be
carried out under the two phases of this project.
Chapter - 4: The Baseline Study gives information on physical, biological and social conditions
collected through survey of the project area.
Chapter - 5: Analysis of Alternatives describes and analyses various alternatives to establish the
feasibility of the modernization and construction of the proposed road infrastructure.
Chapter - 6: Public Consultation and Disclosure explains the process of public consultation and
disclosure of the report at the District Council Office as well as important public library(s). It
makes this document a legal public document.
Chapter - 7: Environmental and Social Impact Assessment identifies various environmental and
social impacts and their suggested mitigations. This provides the basis for the Environment and
Social Management Plan.
Chapter – 8 and 9: Environment and Social Management Plan (ESMP) contains comprehensive
prescriptions regarding environmental and social impacts and their mitigation. This also includes
institutional arrangements and Environmental Management Monitoring Plan. This chapter is
included in the Tender as well as the Contract Document. A draft Social Framework Agreement
(SFA) has also been suggested.
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 2-1
2 Legal, Regulatory, Policy Framework and
Protocols
This chapter outlines the environmental and social legislation, standards, codes of practice and
protocols governing this ESIA and the project. The purpose of this ESIA is to ensure that the
proposed project complies with all national environmental and social legislations as well as the
environmental and social requirements of the World Bank. The jurisdiction of the legal
framework of Pakistan does not extend to FATA region where the project is to be executed. This
region is controlled through a special regulation called the Frontier Crimes Regulation (FCR) and
is recognized as a semi-autonomous region. As a result the national guidelines for conducting
environmental assessments are not directly binding on projects implemented in FATA. However,
this ESIA has been conducted as per the national environmental regulations and guidelines in
accordance with Section 12 of the Pakistan Environmental Protection Act 1997.The project at
the same time has to conform to the operational manuals of the donor and the environmental
safeguards provided therein.
2.1 Pakistan legal requirements
The following sections summarize the environmental and social obligations arising from
Pakistan’s environmental, highways, water, labour and health and safety legislation.
2.1.1 Environmental legislation
The subject of ‘environmental pollution and ecology’ is included in the constitution of Pakistan,
enabling both the national and provincial governments to enact laws on the subject. The
Ministry of Climate Change regulates the environment and wildlife at the national level, with
two organizations primarily responsible for administering the provisions of the Pakistan
Environmental Protection Act 1997 (PEPA 1997), namely:
Pakistan Environmental Protection Council (PEPC), which oversees the functioning of the
Pakistan Environmental Protection Agency with representatives from the government,
industry, non-governmental organizations and the private sector; and
Pakistan Environmental Protection Agency or EPA (established in 1984), which is the
primary implementing agency ensuring compliance with National Environmental Quality
Standards (NEQS), establishing monitoring and evaluation systems, and both identifying
the need to and initiating legislation when necessary.
Significant work on developing environmental policy was carried out in the late 1980s, which
culminated in the Pakistan National Conservation Strategy in 1992. Provincial environmental
protection agencies were established at about the same time and the NEQS were established in
1993. The national EPA is authorized to delegate powers to its provincial counterparts. With the
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 2-2
enactment of PEPA in 1997, broad-based enforcement powers were conferred to the national
and provincial EPAs8.
2.1.1.1 National Conservation Strategy
The Pakistan National Conservation Strategy (NCS) that was approved by the federal cabinet in
March 1992, is the principal policy document on environment issues in the country. The NCS
outlines the country’s primary approach towards encouraging the sustainable development and
management of natural resources. The NCS has 68 specific programs in 14 core areas in which
policy investment is considered crucial for preservation of Pakistan’s natural and physical
environment. The core areas that are relevant in the context of the project are pollution
prevention and abatement concerning biodiversity, supporting land, water and air resources and
preservation of the physical cultural heritage.
2.1.1.2 The Pakistan Environmental Protection Act, 1997
The Pakistan Environmental Protection Act, 1997, empowers the Pak-EPA to:
Develop guidelines for conducting the Initial Environmental Examination (IEE) and
Environmental Impact Assessment (EIA) studies and procedures for the submission,
review and approval of the same.
Develop environmental emission standards for various parameters such as water and
noise.
Enforce the provisions of the Environment Protection Act 1997 through environmental
protection order and environmental tribunals headed by magistrates with wide ranging
powers including the right to impose fine for violence against the Environment
Protection Act 1997.
Under the provisions of the Environment Protection Act 1997, the Pak-EPA has empowered the
four provincial EPAs to manage the environmental concerns of their respective provinces. The
provincial EPAs can frame environmental regulations tailored for the requirements of the
province provided that these regulations meet or exceed the minimum standards set by Pak –
EPA. They are also at time required to review and approve EIAs of all development projects
undertaken in the respective province and areas, including those projects which are
implemented by federal agencies.
Section 12(1) of PEPA requires that: “No proponent of a project shall commence construction or
operation unless he has filed with the Federal Agency an initial environmental examination (IEE)
or, where the project is likely to cause an adverse environmental effect, an environmental
impact assessment (EIA), and has obtained from the Federal Agency approval in respect
thereof.” The Pakistan EPA has delegated the power of review and approval of IEEs and EIAs to
the provincial EPAs. A number of supporting rules and regulations relevant to the Project have
been promulgated under the PEPA 1997.
8 The applicability of PEPA, 1997 in FATA is not clear. Usually the Governor of KP issues a notification for this purpose;
however it is not clear whether or not such notification has been issued for these laws. Nonetheless, for the purpose of this ESMP, these laws and regulations are deemed to be applicable for FATA also.
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 2-3
The NEQS prescribe effluent and emission limits for various activities and have been amended,
in 1995, 2000 and 2010, since they were first promulgated in 1993.
The scope of environmental law implied by the legal definition of ‘environment’ given in PEPA
1997 results in numerous laws enacted since the nineteenth century being classified as
environmental laws. These include laws pertaining to forests, water resources, wildlife, land,
agriculture, health and town planning. In addition, the Pakistan authorities have issued guideline
documents supporting specific pieces of legislation or relevant to a particular industry, for
example, the Guidelines for the Preparation and Review of Environmental Reports (GoP 1997)
and the Sectoral Guidelines for Environmental Reports: Major Thermal Power Stations (GoP
1997).
2.1.1.3 Regulations for Environmental Assessment
The Pak-EPA Regulations 2000 requires proponent to file an Initial Environment Examination
(IEE) report with concerned provincial or federal agency (Pak – EPA). Projects falling under any
category specified in schedule the proponent will submit an EIA with the Provincial Agency.
Within 10 working days of IEE or EIA having been deposited, the empowered agency will confirm
that the document submitted is complete for the purpose of review. During this time should the
empowered agency require the proponent for revision, clearly citing those aspects that need
further discussion the proponent will carry out necessary revision. Subsequently, the federal
agency will make every effort to complete process for an IEE review within 40 days and an EIA
within 90 days of filing.
Pak – EPA regulation (SRO 339(1)/2000) states that an IEE is required for federal or provincial
projects (except in case of maintenance, rebuilding or reconstruction case) with a total cost of
less than 45 million. An EIA on the other hand is required for federal or provincial project (except
in the cases of maintenance, rebuilding or reconstruction) with a total cost of 50 million or more.
EIAs are also required where projects are to be implemented in environmentally sensitive areas,
or are likely to cause adverse environmental effects.
Recognizing that the Pak – EPA has delegated powers to provincial EPAs to enforce the provision
of Environment Protection Act 1997, wherever required an EIA must be submitted to the
provincial agencies in whose jurisdiction the project falls. In the instant case the EIA will be
submitted to Work & Service Department (FATA) implementing the project as the concerned
agency.
2.1.1.4 Guidelines for Environmental Assessment
Pak – EPA has published a set of environmental guidelines for preparation and review of
environmental reports which include the nature of information to be included in the project.
These guidelines have been followed in combination with the World Bank Guidelines, while
preparing this report.
2.1.1.5 National Environmental Quality Standards (NEQS)
The National Environmental Quality Standards (NEQs) specify the following standards:
Maximum allowable contamination of pollutants (32 parameters) in emission and liquid
industrial effluents discharged to inland water.
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 2-4
Maximum allowable concentration of pollutant (16 parameters) in gaseous emission
from sources other than vehicles.
Maximum allowable concentration of pollutants in gaseous emissions from vehicle
exhaust and noise emission from vehicles.
Maximum allowable noise level from vehicles.
Ambient noise standards
Ambient air quality standards.
These standards apply to gaseous emissions and liquid effluents discharged by batching plants,
asphalt plants, camp sites, construction machinery, and vehicles. The standards for vehicle, noise
wastewater and drinking water will apply during the construction as well as operational phase of
the project.
These NEQS are presented in Tables 2.1 to 2.9.
2.1.2 Water law
Historically and throughout Pakistan, the law links groundwater rights to the surface right
holders. The laws on water allocations and use in Pakistan are mostly applicable on water
needed for irrigation therefore these are not relevant to the project.
In the last decade, water law in Pakistan has been under review with a draft National Water
Policy published in 2003, which identifies the following needs for the regulation of industrial use
of water:
make available and reserve sufficient supplies of water for industry on priority basis to
promote industrial development and economic growth; and
enact legislation to formally allow and define the use of water abstraction licenses and
water rates for industrial use.
Historically in FATA, water use is managed according to local customs and practices by the users.
2.1.3 Labour and health and safety legislation
The Constitution of Pakistan contains a range of provisions with regards to labour rights, in
particular:
Article 11 of the Constitution prohibits all forms of slavery, forced labour and child
labour;
Article 17 provides for a fundamental right to exercise the freedom of association and
the right to form unions;
Article 25 lays down the right to equality before the law and prohibition of
discrimination on the grounds of sex alone; and
Article 37(e) makes provision for securing just and humane conditions of work, ensuring
that children and women are not employed in vocations unsuited to their age or sex,
and for maternity benefits for women in employment.
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 2-5
Labour law is enforced at both provincial and national levels .The employment agreement must
comply with the applicable labour laws. There are various laws containing health and safety
requirements including: Factories Act 1934; Provincial Factories Rules; Hazardous Occupations
Rules 1963; Provincial Employees Social Security Ordinance 1965; Workmen’s Compensation Act
1923 and Dock Laborers Act 1934.No single comprehensive piece of legislation deals with
occupational or community safety and health.
2.1.4 International law
International law pertinent to the environment and sustainable development comprises:
customary international law, which results from general and consistent practice
followed by states out of a sense of legal obligation;
judicial decisions of international courts and tribunals, and the teachings of highly
qualified jurists, including articles by eminent lawyers decisions of the International Law
Commission and other United Nations Organizations, decisions of the conference of
parties to a treaty and also decisions and directives of the European Union; and
treaties (the term “treaty” encompasses “agreements, covenants, conventions, pacts,
protocols, and statutes”) that are generally intended to be implemented through
enactment and enforcement of laws at national levels.
2.1.5 Customary law
Several declarations profoundly influence accepted international approaches to environmental
management and sustainable development. Declarations are generally not immediately legally
binding, but can acquire the force of international customary law if they continue to express an
international consensus that states adhere to over time. Those that influence environmental
management and sustainable development are listed below in order of their relative importance
to these fields.
The 1992 Declaration on Environment and Development (or “Rio Declaration) - the Rio
Declaration and Agenda 21, which were both products of the 1992 United Nations
Conference on Environment and Development, effected the introduction and/or revision
of environmental legislation in countries throughout the world resulting in the ESIA
process becoming established as a key tool for environmental decision making.
According to the United Nations Environment Programme or UNEP (UNEP 2005), many
of the Rio Declaration principles are acquiring the force of international customary law,
including: transparency, public participation and access to information and remedies;
precaution, prevention of environmental harm and polluter pays principles; and good
governance.
The 1972 Declaration on the Human Environment (or “Stockholm Declaration”) –
Principle 21 (repeated in Principle 2 of the Rio Declaration) has the status of customary
law and asserts that States have responsibility to ensure activities within their
jurisdiction or control do not cause damage to the environment of other States.
The 1948 Universal Declaration of Human Rights - the principles contained in this
Declaration are considered as international customary law and do not require signature
or ratification by the state to be recognized as a legal standard (UNEP 2005).
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 2-6
The 1998 Declaration on Fundamental Principles and Rights at Work - requires both
states and businesses to observe International Labour Organisation (ILO) Conventions
that are of fundamental importance from a human rights perspective. These
conventions pertain to: freedom of association, collective bargaining, and industrial
relations; forced labour; elimination of child labour and protection of children and young
persons; and equality of opportunity and treatment/ elimination of discrimination in
respect of employment and occupation.
There are also two conventions of the United Nations Economic Commission for Europe (UNECE)
considered to have global significance, even though they are only regional in scope. These are:
the UNECE Convention on Environmental Impact Assessment in a Trans-boundary
Context (Espoo 1991), which sets an international precedent on transboundary impact
assessment and public involvement; and
the UNECE Convention on Access to Information, Public Participation in Decision Making
and Access to Justice in International Environmental Matters (Aarhus 1998, entered into
force 2001), which is considered to be of global importance as an elaboration of
Principle 10 of the Rio Declaration.
2.1.6 Judicial decisions
No specific judicial decisions of relevance to the project were identified.
2.1.7 Treaties
Pakistan follows the “dualist” approach whereby legislation is required to give effect to
international treaties and conventions to which Pakistan is a party, failing which they do not
have the force of law in Pakistan (Shehla Zia and others v. WAPDA (PLD 1994 Supreme Court
693; SGS Societe Generale v. Pakistan 2002 CLD 790).
In the context of international law related to the environment, Section 31 of the Pakistan
Environmental Protection Act 1997, read with the schedule thereto, provides that the Federal
Government may make rules for carrying out the purposes of that Act including rules for
implementing the provisions of the following international environmental agreements:
International Plant Protection Convention, Rome, 1951;
Plant Protection Agreement for the South-East Asia and Pacific Region (as amended),
Rome1956;
Agreement for the Establishment of a Commission for Controlling the Desert Locust in
the Eastern Region of its Distribution Area in South-West Asia (as amended), Rome,
1963;
Convention on Wetlands of International Importance Especially as Waterfowl Habitat,
Ramsar, 1971 and its amending Protocol, Paris, 1982;
Convention Concerning the Protection of World Cultural and Natural Heritage (World
Heritage Convention), Paris, 1972;
Convention on International Trade in Endangered Species of Wild Fauna and Flora
(CITES), Washington, 1973;
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 2-7
Convention on the Conservation of Migratory Species of Wild Animals, Bonn, 1979;
Convention on the Law of the Sea, Montego Bay, 1982;
Vienna Convention for the Protection of the Ozone Layer, Vienna, 1985;
Montreal Protocol on Substances that Deplete the Ozone Layer, Montreal, 1987 and
amendments thereto;
Agreement on the Network of Aquaculture Centres in Asia and the Pacific, Bangkok,
1988;
Convention on the Control of Transboundary Movements of Hazardous Waste and Their
Disposal, Basel, 1989;
Convention on Biological Diversity, Rio De Janeiro, 1992; and
United Nations Framework Convention on Climate Change, Rio de Janeiro, 1992.
Of the 25 United Nations treaties on human rights listed in the United Nations Treaty Series,
nine have been signed by Pakistan. The nine treaties concern: genocide; racial discrimination;
economic, social and cultural rights; apartheid; discrimination against women; and the rights of a
child.
Workplace conventions promulgated by the ILO (International Labor Organization), an agency of
the United Nations, are treaties subject to ratification by member states. According to the ILO,
Pakistan has ratified 34 of the ILO conventions of relevance to Pakistan (ILO 2008).The ILO
Indigenous and Tribal Peoples Convention 1989 (No. 169), is considered relevant to the Project
due to the tribal nature of the local communities. It requires the adoption of special measures to
protect and preserve the environment of indigenous and tribal people. It contains numerous
references to lands, resources and the environmental of indigenous people.
2.2 The World Bank Safeguard Policies
The World Bank is the donor for this project. Therefore, it is obligatory for the project
proponents, Work and Service Department FATA, to abide by the World Bank safeguard policies,
which are discussed below:
2.2.1 Environmental Assessment (OP 4.01)
The World Bank requires environmental assessment (EA) of projects proposed for Bank financing
to help ensure that they are environmentally sound and sustainable, and thus to improve
decision making.9The OP defines the EA process and various types of the EA instruments.
The proposed project consists of activities that have environmental and social consequences,
including:
Deterioration of air quality,
Water contamination and consumption,
Damage to top soil, land erosion,
Safety hazard.
9Excerpts from WB OP 4.12. WB Operational Manual. January 1999.
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 2-8
Since none of the potential impacts of the project are likely to be large scale, unprecedented
and/or irreversible, the project has been classified as Category B, in accordance with OP 4.01.
Furthermore, the present environmental and social assessment has been carried out in
accordance with this OP, to identify the extent and consequences of these impacts, and to
develop an ESMP for their mitigation.
2.2.2 Involuntary Resettlement (OP 4.12)
The WB’s experience indicates that involuntary resettlement under development projects, if
unmitigated, often gives rise to severe economic, social, and environmental risks: production
systems are dismantled; people face impoverishment when their productive assets or income
sources are lost; people are relocated to environments where their productive skills may be less
applicable and the competition for resources greater; community institutions and social
networks are weakened; kin groups are dispersed; and cultural identity, traditional authority,
and the potential for mutual help are diminished or lost. This policy includes safeguards to
address and mitigate these impoverishment risks.10
The overall objectives of the Policy are given below.
Involuntary resettlement should be avoided where feasible, or minimized, exploring all
viable alternative project designs.
Where it is not feasible to avoid resettlement, resettlement activities should be
conceived and executed as sustainable development programs, providing sufficient
investment resources to enable the persons displaced by the project to share in project
benefits. Displaced persons should be meaningfully consulted and should have
opportunities to participate in planning and implementing resettlement programs.
Displaced persons should be assisted in their efforts to improve their livelihoods and
standards of living or at least to restore them, in real terms, to pre-displacement levels
or to levels prevailing prior to the beginning of project implementation, whichever is
higher.
The resettlement impacts of the project will be managed in accordance with this OP and a
Resettlement Action Plan will be prepared.
2.2.3 Forestry (OP 4.36)
The objective of this Policy is to assist the WB’s borrowers to harness the potential of forests to
reduce poverty in a sustainable manner, integrate forests effectively into sustainable economic
development, and protect the vital local and global environmental services and values of forests.
Based on the field surveys of phase 1 of the project and satellite imagery for the project area
none of the project components would be located inside any forested areas. Hence the OP 4.36
is not triggered.
10
Excerpts from WB OP 4.12. WB Operational Manual. December 2001.
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 2-9
2.2.4 Natural Habitat (OP 4.04)
The conservation of natural habitats, like other measures that protect and enhance the
environment, is essential for long-term sustainable development. The Bank therefore supports
the protection, maintenance, and rehabilitation of natural habitats and their functions.11
All of the proposed project components would be located in areas where the natural habitat has
already been significantly modified, as a result of road construction and associated activities.
Therefore the OP 4.04 is not triggered for the proposed project.
2.2.5 Pest Management (OP 4.09)
Through this OP, the WB supports a strategy that promotes the use of biological or
environmental control methods and reduces reliance on synthetic chemical pesticides. This OP is
not relevant since the Project does not involve purchase or use of pesticides or fertilizers.
2.2.6 Safety of Dams (OP 4.37)
The Policy seeks to ensure that appropriate measures are taken and sufficient resources
provided for the safety of dams the WB finances. However this OP is not relevant since the
proposed project does not involve construction of dams.
2.2.7 Projects on International Waterways (OP 7.50)
This OP defines the procedure to be followed for projects the WB finances that are located on
any water body that forms a boundary between, or flows through two or more states. However,
no project components will be located on any such waterways; hence this OP is not triggered.
2.2.8 Cultural Property (OP 4.11)
The World Bank’s general policy regarding cultural properties is to assist in their preservation,
and to seek to avoid their elimination. The specific aspects of the Policy are given below. 12
The Bank normally declines to finance projects that will significantly damage non-
replicable cultural property, and will assist only those projects that are sited or designed
so as to prevent such damage.
The Bank will assist in the protection and enhancement of cultural properties
encountered in Bank-financed projects, rather than leaving that protection to chance. In
some cases, the project is best relocated in order that sites and structures can be
preserved, studied, and restored intact in situ. In other cases, structures can be
relocated, preserved, studied, and restored on alternate sites. Often, scientific study,
selective salvage, and museum preservation before destruction is all that is necessary.
Most such projects should include the training and strengthening of institutions
entrusted with safeguarding a nation’s cultural patrimony. Such activities should be
directly included in the scope of the project, rather than being postponed for some
possible future action, and the costs are to be internalized in computing overall project
costs.
11
Excerpts from WB OP 4.04. WB Operational Manual. June 2001. 12
Excerpts from the OP 11.03. WB Operational Manual. September 1986.
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 2-10
Deviations from this policy may be justified only where expected project benefits are
great, and the loss of or damage to cultural property is judged by competent authorities
to be unavoidable, minor, or otherwise acceptable. Specific details of the justification
should be discussed in project documents.
This policy pertains to any project in which the Bank is involved, irrespective of whether
the Bank is itself financing the part of the project that may affect cultural property.
Since the project activities will be carried out along an existing road, it is unlikely that any sites of
cultural, archeological, historical, or religious significance will be affected. However, in case of
discovery of any such sites or artifacts during the project implementation, the work will be
stopped at that site. The provisions of this Policy will be followed. Additionally, the provincial
and federal archeological departments will be notified immediately, and their advice sought
before resumption of the construction activities at such sites.
2.2.9 Indigenous People (OP 4.10)
For purposes of this policy, the term “Indigenous Peoples” is used in a generic sense to refer to a
distinct, vulnerable, social and cultural group possessing the following characteristics in varying
degrees:13
self-identification as members of a distinct indigenous cultural group and recognition of
this identity by others;
collective attachment to geographically distinct habitats or ancestral territories in the
project area and to the natural resources in these habitats and territories;
customary cultural, economic, social, or political institutions that are separate from
those of the dominant society and culture; and
an indigenous language, often different from the official language of the country or
region.
The OP defines the process to be followed if the project affects the indigenous people.
No indigenous people with a social and cultural identity distinct from the dominant society that
makes them vulnerable to being disadvantaged in the development process – are known to exist
in the two FATA agencies. Therefore this OP is not triggered.
However if such groups are identified during the project implementation, the proponents will
develop an Indigenous People Development Plan, in compliance with the OP and get it approved
by the Bank.
2.2.10 Projects in Disputed Areas (OP 7.60)
Projects in disputed areas may raise a number of delicate problems affecting relations not only
between the Bank and its member countries, but also between the borrower and one or more
neighboring countries. In order not to prejudice the position of either the Bank or the countries
concerned, any dispute over an area in which a proposed project is located is dealt with at the
earliest possible stage.
13
Excerpts from the OP 4.10. WB Operational Manual. July 2005.
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 2-11
The Bank may proceed with a project in a disputed area if the governments concerned agree
that, pending the settlement of the dispute, the project proposed for country A should go
forward without prejudice to the claims of country B.14
This OP is not triggered since no part of the project area in FATA is located in any disputed
territory.
2.2.11 Disclosure
Following the National Laws on Access to information and the World Bank’s Policy on Access to Information of July 2010, this ESIA will be shared with all relevant agencies, works and services department FATA, concerned nongovernmental organizations, and development partners. Subsequently, the ESIA and Urdu translation of its executive summary (in the form of a brochure) will be disclosed by the Works and Services Department, FATA to the project affected persons/concerned communties, and also made available at the websites of GoP, FATA Secretariat and the relevant line departments. Copies of ESIA will also be sent to Federal EPA, KP EPA and placed in the offices of W&S department and agency offices to facilitate easy access to the public and concerned communities. It will also be made available at the World Bank’s project specific InfoShop.
2.3 Other Related Statutes and Laws
This section outlines statutes apart from Pakistan Environment Protection Act, 1997, which are
relevant to this project. Apart from The Constitution of Pakistan, 1973 and Frontier Crimes
Regulations, 1901 none of the statutes and laws mentioned below are directly applicable to
FATA, but President of Pakistan is empowered to issue regulations under The Constitution of
Pakistan:
2.3.1 The Constitution of Pakistan 1973
It contains concurrent legislative powers to federation and provinces to legislate in respect of
environment and ecology (Article 142(b), Clause 24). Any gaps in the environmental law can be
referred to National as well as the provincial assembly for passage of an appropriate law. Under
the Constitution, FATA is included among the territories of Pakistan (Article 1). It is represented
in the National Assembly and the Senate but remains under the direct executive authority of the
President (Articles 51, 59 and 247). Laws framed by the National Assembly do not apply here
unless so ordered by the President, who is also empowered to issue regulations for the peace
and good government of the tribal areas. Currently, FATA continues to be governed primarily
through the Frontier Crimes Regulation 1901. It is administered by Governor of the KP in his
capacity as an agent to the President of Pakistan, under the overall supervision of the Ministry of
States and Frontier Regions in Islamabad.
2.3.2 Frontier Crimes Regulations 1901
The Frontier Crimes Regulations 1901, popularly known as FCR is one of major component of the
administrative system of justice in Tribal Areas. The judicial system in FATA is a hybrid colonial-
era legal framework that mixes traditional customs and norms with executive discretion. The
regulations do not specifically provide any environment related directives, but it outlines the
14
Excerpts from the OP 7.60. WB Operational Manual. November 1994.
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 2-12
administrative setup and the judicial system in the area. Additionally it is the supreme law in
FATA and other civil and criminal laws are not extended to the area. It serves all purposes both
of procedural as well as substantive law. Neither criminal procedure code (Cr.,P.C) nor civil
procedure code (C.P.C) or law of evidence is applicable. No right of appeal to the High Court or
Supreme Court exist under the provisions of these regulations. Until 1997, the Commissioner
acted as a provisional court but in 1997 it was amended and turned into appellate forum and the
powers of revision of the Commissioner’s verdict were given to the tribunal consisting of
secretaries of Home and Law Department. But all these belong to the same executive and are
usually hand in glove for all practical purposes.
Though FCR is the primary source of judicial system in FATA, but over a hundred national, local
and specific laws stand extended to FATA including such enactments as The Pakistan Penal Code
and The Criminal Procedure Code which are the two major laws of Pakistan, The Evidence Act,
the various Hadood Ordinances, The Custom Act, The Foreigners Act, The Control of Narcotics
Substances Act, The Arms Act, The Companies Act, The Passport Act, The Pakistan Army Act, The
Defence of Pakistan Ordinance, The Representation of the People Ordinance, etc..
2.3.3 Pakistan Penal Code (PPC)
It treats pollution and destruction of ecology as a mischief and makes it a public offence. The
PPC further prohibits corrupting and fouling water, any public spring, reservoir or river or
rendering it less fit for the purpose for which it is ordinarily used.
2.3.4 The Drainage Act 1973
The Act binds the public water users to restore the environment of the water bodies, should
there be any damage by the community in any way.
2.3.5 Local Government Ordinance 1979
The ordinance empowers Zila Councils to control environmental pollution by preparing and
implementing appropriate schemes to protect air, water and land in their respective
jurisdictions.
2.3.6 The West Pakistan Fisheries Act 1961
The Fisheries Act requires protection of public waters as habitat of fish and other aquatic life.
This supports the Provincial Fisheries Department to effectively protect the fish and other
aquatic life in water streams nearby the roads. Fish and small aquatic life is food to a good
number of birds as well as a protein supply to local people.
2.3.7 The Forest Act 1927
The Act provides full protection to the reserved forests as well as to wildlife habitats. The Act
also prohibits certain acts in protected forests.
2.3.8 The Antiquities Act 1976
The Act provides full protection and safety to archives, monuments, physical cultural heritage or
chance finds and binds communities to cooperate, collaborate and report to the archaeological
department.
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 2-13
2.3.9 The Public Health (Emergency Provision Act 1954 read with West
Pakistan Epidemic Control Act 1958) Act
These two laws cover the preservation of human health by prohibition of any disease,
safeguarding the public health and providing and maintaining adequate medical services and
other services essential to the health of communities in the project area. Protection against
HIV/AIDS and infectious diseases like Cholera and Hepatitis B in labor camps would come under
the same preview.
2.3.10 Explosive Act 1884
Under the Explosive Act 1884, the Project Contractors are bound by regulation on properly and
securely handling, transporting and using explosives during quarrying, blasting and any other
purpose. A prior notice has to be given to local public and road users in collaboration with
Resident Engineer.
2.4 Interaction with Other Agencies
The roads in this project are responsibility of Work & Service Department (FATA) on behalf of
the FATA Administration. The Work & Service Department (FATA) is therefore responsible for
ensuring the implementation, controlling and monitoring of the environmental concerns of the
road at preconstruction, construction and the operational stage. In doing so, the Work & Service
Department (FATA) will have interactions with a large number of organizations and government
departments. Some of those are as follows:
2.4.1 FATA Secretariat
The FATA Secretariat is the main administrative body for the FATA region dealing with
administration, finance, law & order, planning & development, projects and social welfare. In
Pakistan all issues pertaining to land use and land ownership are a provincial subject. In FATA for
the rural roads, the Works and Services Department (W&SD) through Political Agents of
concerned agencies is empowered to carry out the acquisition of private land or any built up
property for public purposes after paying compensation as per the agreed rates or practice in
vogue in other settled areas15. For making a double road, straightening the curves, making
diversions, establishing labor camps and setting up machinery yards some temporary land
acquisition and resettlement of families may have to be undertaken.
2.4.2 Political Agents
The FATA region is administered by political agents (PA). Each agencies PA is assisted by a
number of assistant political agents, tehsildars (administrative head of a tehsil) and naib
tehsildars (deputy tehsildar), as well as members from various local police (khassadars) and
security forces (levies, scouts). As part of administrative functions, the political agent oversees
the working of line departments and service providers. PA is responsible for handling inter-tribal
disputes over boundaries or the use of natural resources, and for regulating the trade in natural
resources with other agencies or the settled areas.
15
Amendment in FCR Law 1901, By the President of Pakistan August 2011
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 2-14
The political agent plays a supervisory role for development projects and chairs an agency
development sub-committee, comprising various government officials, to recommend proposals
and approve development projects. He also serves as project coordinator for rural development
schemes. In this supervisory role PA is the primary authority in implementation and overall
supervision of the ESIA
2.4.3 Federal EPA
Principally the Federal EPA would monitor the process and implementation of the ESIA.
2.4.4 Departments of Forestry, Wildlife and Fisheries
The Forest Department KP initiated forestry activities in FATA during 1976 with subsequent
creation of FATA Forest Circle in 1991. The department is headed by conservator forest with
divisional officer forest in each agency. Additionally there is Department of Fisheries for FATA
headed by a director and each agency has an assistant director. It is expected that project
implementation will require a limited clearances of vegetation or trees in the right-of-way (RoW)
of the road. Also no major impact is going to be caused to any wildlife or fisheries present in the
project area. But it is possible that while making diversions, establishing machinery yards or
setting up labor camps, these departments come in contact and a No-objection Certificate (NoC)
from them becomes necessary. Also during resettlement the assessment of compensation for
trees will have to be endorsed by the local Forest Department.
2.4.5 Local Government and Municipalities
The directorate of Local Government and Rural Development (LG & RD) is headed by a director
with representatives, Assistant Directors, in each agency. The directorate has access to
communities at the grassroots level and works closely with the elders, maliks, counselors and PA
of the respective agencies. The department is attached with the office of the Political Agents in
the respective agencies, therefore all projects are undertaken through the Political
Administration (the PA also acts as the project director of the local government schemes). If
during resettlement or mitigating an environmental hazard, a conflict situation may emerge, it
will become necessary for the project proponents to contact the union council, local government
and / or municipalities.
2.4.6 Levies/Scouts
To cool down any law and order situation and to ensure security assistance from the scouts and
the levies may be necessitated. It is advisable that these departments are pre–alerted about the
security requirements.
2.5 Conventions, Protocols, Agreements and Understandings at
International Level
On international level Pakistan is a signatory to a number of conventions, agreements, protocols
and understandings. Not all of these may be directly applicable to this project but most
important of these are listed below for any possible reference.
Convention on Biological Diversity popularly called the Earth Charter (1992)
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 2-15
Convention on wetlands of international importance especially wetland habitats
(Ramsar 1971).
Convention on conservation of Migratory Species of Wild Animals (Bonn 1979) a follow
up of Ramsar 1971.
ILO convention No. 62 regarding ergonomic limitation of labor.
2.6 International Federation of Consulting Engineers (FIDIC)
Clauses
Keeping in view the national laws and international obligations, specific steps are taken to
mitigate the adverse impacts while processing the detailed design, tender document and
carrying out the monitoring and evaluation of the work of the contractor. Following FIDIC
clauses are invariably provided in a standard construction contract like this project.
Clause 8.2: Site operation and methods of construction.
Clause 19.1: Safety, Security of Environment in general (including biota).
Clause 27.1: Fossils
Clause 42.1: Possession of site and access thereto (for life forms)
Clause 42.3: Right of ways and facilities in the project area
The Work & Service Department (FATA) will ensure that the above FIDIC clauses are
appropriately reflected in the tender document(s), bid documents and the contract
document(s).
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 2-16
Table 2.1: Selected NEQS for Waste Effluents
Parameter Unit Standards (maximum allowable
limit)
Temperature increase C < 3
pH value (acidity/basicity) pH 6/9
5-day biochemical oxygen demand (BOD) at 20 °C
mg/l 80
Chemical oxygen demand (COD) mg/l 150
Total suspended solids mg/l 200
Total dissolved solids mg/l 3,500
Grease and oil mg/l 10
Phenolic compounds (as phenol) mg/l 0.1
Chloride (as Cl) mg/l 1,000
Fluoride (as F) mg/l 10
Sulfate (SO4) mg/l 600
Sulfide (S) mg/l 1.0
Ammonia (NH3) mg/l 40
Cadmium mg/l 0.1
Chromium (trivalent and hexavalent) mg/l 1.0
Copper mg/l 1.0
Lead mg/l 0.5
Mercury mg/l 0.01
Selenium mg/l 0.5
Nickel mg/l 1.0
Silver mg/l 1.0
Total toxic metals mg/l 2.0
Zinc mg/l 5.0
Arsenic mg/l 1.0
Barium mg/l 1.5
Iron mg/l 8.0
Manganese mg/l 1.5
Boron mg/l 6.0
Chlorine mg/l 1.0 Notes:
1. The standard assumes that dilution of 1:10 on discharge is available. That is, for each cubic meter of treated effluent, the recipient water body should have 10 m3 of water for dilution of this effluent.
2. Toxic metals include cadmium, chromium, copper, lead, mercury, selenium, nickel and silver. The effluent should meet the individual standards for these metals as well as the standard for total toxic metal concentration. Source: Government of Pakistan (2000) (SRO 549 (I)/2000).
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 2-17
Table 2.2: NEQS for Industrial Gaseous Emissions
Parameter Source of Emission Standards (maximum
allowable limit)
Smoke Smoke opacity not to exceed 40% or 2 Ringlemann Scale
or equivalent smoke number
Particulate matter 1
(a) Boilers and furnaces:
i. Oil fired 300
ii. Coal fired 500
iii. Cement Kilns 300
(b) Grinding, crushing, clinker coolers and related processes, metallurgical processes, converters, blast furnaces and cupolas
500
Hydrogen Chloride Any 400
Chlorine Any 150
Hydrogen fluoride Any 150
Hydrogen sulphide Any 10
Sulphur Oxides 2, 3
Sulfuric acid/Sulphonic acid plants 5,000
Other Plants except power Plants operating on oil and coal
1,700
Carbon Monoxide Any 800
Lead Any 50
Mercury Any 10
Cadmium Any 20
Arsenic Any 20
Copper Any 50
Antimony Any 20
Zinc Any 200
Oxides of Nitrogen 3
Nitric acid manufacturing unit 3,000
Other plants except power plants operating on oil or coal:
i. Gas fired 400
ii. Oil fired 600
iii. Coal fired 1,200 Explanations:
1. Based on the assumption that the size of the particulate is 10 micron or more. 2. Based on 1% sulphur content in fuel oil. Higher content of sulphur will cause standards to be pro-rated. 3. In respect of emissions of sulphur dioxide and nitrogen oxides, the power plants operating on oil and coal as
fuel shall in addition to NEQS specified above, comply with the standards provided separately. 4. Units are in mg/Nm
3 unless otherwise stated
Source: Government of Pakistan (2000) (SRO 549 (I)/2000).
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 2-18
Table 2.3: National Environmental Quality Standards for Ambient Air16
Pollutants Time-
Weighted Average
Concentration in Ambient Air
Method of Measurement Effective from1st
July 2010
Effective from 1
st January 2013
Sulfur Dioxide (SO2)
Annual Average*
80 µg/m3 80 µg/m
3
Ultraviolet Fluorescence
24 hours** 120 µg/m3 120 µg/m
3
Oxides of Nitrogen as (NO)
Annual Average*
40 µg/m3 40 µg/m
3 Gas Phase
ChemiluminescCence 24 hours** 40 µg/m
3 40 µg/m
3
Oxides of Nitrogen as (NO2)
Annual Average*
40 µg/m3 40 µg/m
3 Gas Phase
Chemiluminescence 24 hours** 80 µg/m
3 80 µg/m
3
Ozone (O3) 1 hour 180 µg/m3 130 µg/m
3
Non dispersive UV absorption
Suspended Particulate Matter
(SPM)
Annual Average*
400 µg/m3 360 µg/m
3
High Volume Sampling, (Average flow rate not
less than1.1 m3/minute). 24 hours** 550 µg/m
3 500 µg/m
3
Respirable Particulate Matter.
PM10
Annual Average*
200 µg/m3 120 µg/m
3
β Ray absorption
24 hours** 250 µg/m3 150 µg/m
3
Respirable Particulate Matter.
PM2.5
Annual Average*
25 µg/m3 15 µg/m
3
β Ray absorption 24 hours** 40 µg/m
3 35 µg/m
3
1 hour 25 µg/m3 15 µg/m
3
Lead (Pb)
Annual Average*
1.5 µg/m3 1.0 µg/m
3
ASS Method after sampling using EPM
2000 or equivalent Filter paper
24 hours** 2.0 µg/m3 1.5 µg/m
3
Carbon Monoxide (CO)
8 hours** 5 mg/m3 5 mg/m
3 Non Dispersive Infra-Red
(NDIR) 1 hour 10 mg/m3 10 mg/m
3
* Annual arithmetic mean of minimum 104 measurements in a year taken twice a week 24 hourly at uniform interval.
** 24 hourly /8 hourly values should be met 98% of the in a year. 2% of the time, it may exceed but not on two consecutive days. Source: Government of Pakistan (2010) (SRO 1062 (I)/2010).
16
Full text of the Standards is available at the Pak-EPA website: (http://www.environment.gov.pk/info.htm).
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 2-19
Table 2.4: NEQS for Motor Vehicles Exhaust and Noise for In-use Vehicles17
Sr. No.
Parameter Standard (Maximum
Permissible Limit) Measuring Method Applicability
1 Smoke 40% or 2 on the Ringlemann
Scale during engine acceleration mode.
To be compared with Ringlemann Chart at a distance 6 or more. r
Immediate effect 2
Carbon Monoxide
6% Under idling conditions: Non-dispersive infrared detection
through gas analyzer.
3 Noise 85 dB (A). Sound meter at 7.5 meters from
the source.
Table 2.5: NEQS for Motor Vehicles Exhaust and Noise for New Diesel Vehicles, Passenger Cars and Light Commercial Vehicles (g/Km)
Type of Vehicle
Category/Class Tiers CO HC+ NOx
PM Measuring
Method Applicability
Passenger Cars
M 1: with reference mass (RW) up to 2500 kg. Cars with RW over
2500 kg to meet NI category standards.
Pak-II IDI 1.00 0.70 0.08 NEDC (ECE
15+ EUDCL)
All imported and local
manufactured diesel
vehicles with effect from 01-07-2012
Pak-II DI 1.00 0.90 0.10
Light Commercial
Vehicles
NI-I (RW<1250 kg) Pak-II IDI 1.00 0.70 0.08
Pak-II DI 1.00 0.90 0.10
NI-II (1250 kg< RW <1700 kg0
Pak-II IDI 1.25 1.00 0.12
Pak-II DI 1.25 1.30 0.14
NI-III (RW>1700 kg) Pak-II IDI 1.50 1.20 0.17
Pak-II DI 1.50 1.60 0.20
Parameter Standard (maximum permissible limit) Measuring Method
Noise 85 dB (A) Sound meter at 7.5 meters from the
source.
17
Full text of the Standards is available at the Pak-EPA website: (http://www.environment.gov.pk/info.htm).
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 2-20
Table 2.6: NEQS for Motor Vehicles Exhaust and Noise for New Diesel Vehicles, Heavy Duty Diesel Engines and Large Goods Vehicles (g/Kwh)
Type of Vehicle
Category/ Class
Tiers CO HC NOx PM Measuring
Method Applicability
Heavy Duty Diesel
Engines
Trucks and Buses
Pak-II 4.0 1.1 7.0 0.15 ECE-R-49
All Imported and local manufactured diesel vehicles with the effect 1-7-2012
Large goods
Vehicles
N2 (2000 and up
Pak-II 4.0 7.0 1.1 0.15 EDC
Parameter Standard (maximum permissible limit) Measuring Method
Noise 85 dB (A) Sound meter at 7.5 meters from the
source.
Table 2.7: NEQS for Motor Vehicles Exhaust and Noise for New Petrol Vehicles (g/km)
Type of Vehicle
Category / Class Tiers CO HC+ NOx
Measuring Method
Applicability
Passenger
M 1: With reference mass (RW) up to 2500 kg. Cars with RW over 2500 kg. to meet N1 category standards
Pak-II 2.20 0.50
NEDC (ECE 15 + EUDCL)
All imported and new models* locally manufactured petrol vehicles with effect from 1
st July, 2009**
Light Commercial Vehicles
N1-I (RW<1250 kg) Pak-II 2.20 0.50
N1-II (1250 kg>RW <1700 kg)
Pak-II 4.00 0.65
N1-III (RW>1700 kg) Pak-II 5.00 0.80
Motor Rickshaws & motor Cycles
2.4 strokes <150 cc Pak-II 5.50 1.50
ECER 40 2.4 strokes>150 cc Pak-II 5.50 1.30
Parameters Standard (maximum permissible limit) Measuring Method
Noise 85 dB (A) Sound meter at 7.5 meters from the
source Explanations for Table 2.4 to 2.7: DI: Direct Injection IDI: Indirect Injection EUDCL: Extra Urban Driving Cycle NEDC: New Urban Driving Cycle M: Vehicles designed and constructed for the carriage of passengers and comprising no more than eight seats
in addition to the driver's seat N: Motor vehicles with at least four wheels designed and constructed for the carriage of goods. * New model means both model and engine type change ** The existing models of petrol driven vehicles locally manufactured will immediately switch ever to Pak-II
emission standards but not later than 30th June, 2012 Source: Government of Pakistan (2009) (SRO 72 (KE)/2009).
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 2-21
Table 2.8: National Standards for Drinking Water Quality18
Properties/Parameters Standard Values for Pakistan
Bacterial
All water intended for drinking (E. Coli or Thermo tolerant Coliform bacteria)
Must not be detectable in any 100 ml samples
Treated water entering the distribution system (E. Coli or thermo-tolerant coliform and total coliform bacteria)
Must not be detectable in any 100 ml samples
Treated water in the distribution system (E. Coli or thermo tolerant coliform and total coliform bacteria)
Must not be detectable in any 100 ml samples In case of large supplies, where sufficient samples are examined, must not be present in 95% of the samples
taken throughout any 12- month period.
Physical
Color ≤15 TCU
Taste Non objectionable/Accept able
Odor Non objectionable/Accept able
Turbidity < 5 NTU
Total hardness as CaCO3 < 500 mg/l
TDS < 1000
pH 6.5 – 8.5
Chemical
Essential Inorganic mg/Liter
Aluminum (Al) ≤0.2
Antimony (Sb) ≤0.005 (P)
Arsenic (As) ≤ 0.05 (P)
Barium (Ba) 0.7
Boron (B) 0.3
Cadmium (Cd) 0.01
Chloride (Cl) <250
Chromium (Cr) ≤0.05
Copper (Cu) 2
Toxic Inorganic mg/Liter
Cyanide (Cn) ≤0.05
Fluoride (F)* ≤1.5
Lead (Pb) ≤0.05
Manganese (Mn) ≤ 0.5
Mercury (Hg) ≤0.001
Nickel (Ni) ≤0.02
Nitrate (NO3)* ≤50
Nitrite (NO2)* ≤3 (P)
Selenium (Se) 0.01 (P)
Residual chlorine 0.2-0.5 at consumer end; 0.5-1.5 at source
Zinc (Zn) 5.0
Organic
Pesticides mg/l PSQCA No. 4639-2004, Page No. 4 Table No. 3 Serial
No. 20- 58 may be consulted**
Phenolic compound (as phenols) mg/l WHO standards: ≤ 0.002
Polynuclear Aromatic hydrocarbon (as PAH) g/L WHO standards: ≤ 0.01v(by GC/MS method)
18
Full text of the Standards is available at the Pak-EPA website: (http://www.environment.gov.pk/info.htm).
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 2-22
Properties/Parameters Standard Values for Pakistan
Radioactive
Alpha Emitters bq/L or pCi 0.1
Beta Emitters 1 * indicates priority health related inorganic constituents which need regular monitoring. ** PSQCA: Pakistan Standards Quality Control Authority.
Source: Government of Pakistan (2010) (SRO 1063(I)/2010).
Table 2.9: National Environmental Quality Standards for Noise19
Category of Area/Zone
Limit in dB(A) Leq*
Effective from 1st
July 2010 Effective from 1st
July 2012
Day time Night time Day time Night time
Residential area 65 50 55 45
Commercial area 70 60 65 55
Industrial area 80 75 75 65
Silence zone 55 45 50 45 Notes: 1. Day time hours: 6:00 a.m. to 10:00 p.m. 2. Night time hours: 10:00 p.m. to 6:00 a.m. 3. Silence zone: Zones that are declared as such by the competent authority. An area comprising not less than
100 m around the hospitals, educational institutions, and courts. 4. Mixed categories of areas may be declared as one of the four above-listed categories by the competent
authority. * dB(A) Leq: Time weighted average of the level of sound in decibels on scale A which is relatable to human
hearing. Source: Government of Pakistan (2010) (SRO 1064(I)/2010).
19
Full text of the Standards is available at the Pak-EPA website: (http://www.environment.gov.pk/info.htm).
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 3-1
3 Description of the Project
3.1 Location
The proposed project is located in the Bajaur and Orakzai Agencies of Federally Administered
Tribal Areas of Pakistan. In total the project will construct/upgrade/improve 15 roads, amongst
these 7 are located in Bajaur Agency, mainly in Utman Khel, Barang and Khar Tehsils and 8 in
Lower Orakzai Tehsil of Orakzai Agency. Though the total length of roads in Bajaur is about 55.5
Km but the project is spread in an area of more than 500 sq. Km, likewise in Orakzai agency a
total of 8 roads will be constructed with a total length of 20 Km spreading over an area of more
than 500 sq. km. (see maps in Figures 1.1. 1.2 and 1.3).
The total length of 75.5 Km. is divided into 4 No. of Packages for Bajaur Agency and 2 No. of
Packages for Orakzai Agency (see Table 3.1), depending upon the priority of roads packages.
About 20 Km. length of roads are located in rolling terrain of Bajaur Agency, but the major length
of project roads amounting to 55.5 Km. lie in rugged mountainous terrain as well as escarpment
areas of Bajaur and Orakzai agencies. Existing roads and tracks under the improvement project
area are generally narrow and have steep gradients and sharp, serpentine horizontal curves.
The region of FATA is faced with conflict and security risks, in the form of bomb blasts and
terrorism. The roads improvement project will provide relief to the poor and affected peoples of
Bajaur and Orakzai by involving them in project activities on one hand whereas on other hand it
will improve the mobility of law enforcing agencies.
3.2 Road Length
The roads under the proposed project are in total 75.5 Km long. This total length is distributed in
various roads lengths averaging about 2 to 4 Km in Bajaur and Orakzai agencies, except for two
stretches 20 Km each in Bajaur agency (namely Kharkano to Kulala and black topping of Bado to
Serisar). The complete length details are given in Table 3.1.
Table 3.1: Package Details and Road Lengths
Pkg.
Bajaur Orakzai Total Length
(km) Road Section
Lgth. (km)
Road Section Lgth. (km)
1 Kharkano to Kulala (34°46'21.73"N 71°38'2.47"E) 20
Dargai to Ghakhi to Sharo Doghal (33°43'48.05"N 70°54'0.39"E) 2
Dargai to Shamim Khel (33°43'48.96"N 70°53'40.50"E) 2
Largri Tan to Dop Sana (33°43'48.90"N 70°54'3.29"E) 2
Palosia to Hakim Killi (33°44'8.76"N 70°56'37.00"E) 3
Sub Total 20 Sub Total 9 29
2 Dak Qilli By-Pass (34°43'54.31"N 71°31'38.85"E) 3
Kada Bazaar to Aso Khel Khapa (33°43'51.95"N 70°52'13.97"E) 2
Bado to Serisar Blacktop 20 Sam Feroz Khel to Dara Ghari 3
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 3-2
Pkg.
Bajaur Orakzai Total Length
(km) Road Section
Lgth. (km)
Road Section Lgth. (km)
(34°42'10.45"N 71°39'24.03"E) (33°46'36.93"N 70°57'58.89"E)
Dara Ghari to Sangrani (33°46'46.67"N 70°57'43.83"E) 2
Kalaya to Saboora (33°44'42.31"N 70°56'25.06"E) 4
Sub Total 23 Sub Total 11 34
3 Shukrata to Pampokha (34°48'0.69"N 71°39'5.20"E) 3
Tangi Adda to Bagori Bridge (34°42'28.72"N 71°21'0.22"E) 4.5
Sub Total 7.5 Sub Total
7.5
4 Loia Kanda to Ghalishah (34°48'35.29"N 71°39'39.29"E) 3
Shagai to Karkanai Charmang (34°44'29.03"N 71°18'56.17"E) 2
Sub Total 5 Sub Total
5
Grand Total 55.5 Grand Total 20 75.5
3.3 Existing Road Dimensions and Description
The existing roads selected in the project are mostly unpaved and foot tracks with variable
widths, high gradients and serpentine curves. Majority of these tracks are foot tracks which are
not accessible for vehicles. A brief description of the proposed roads in the Bajaur and Orakzai
agencies are described hereunder.
3.3.1 Kharkano to Kulala, Length 20 Km. (Bajaur Package 1)
The existing road is a dirt track of 2.0 m to 3.0 m in width which starts from Khar-Zulam Road
and ends at Kulala-Arang Valley. The Construction of this road is extremely necessary because it
will serve approximately half the population of Tehsil Salarzai, Utman Khel and some population
of Khar. These areas are deprived from communication facilities and facing great hardships.
After construction of the road better communication facilities will be available to the inhabitants
of the area. The land on both side of the road is highly fertile on which people grow cash crops
such as Wheat, maize, barley and vegetables. Furthermore the road will help people get
connected to the education hub at Head Quarter of the Agency.
3.3.2 Dag Qilla Bypass Road, Length 3 Km. (Bajaur Package 2)
This Road connects Khar-Zulam Road with Khar-Nawgai road. The current road is mostly dirt
track and missing in parts. After construction of this road it will serve as Khar By pass Road and
the traffic load on the busy Bazaar of Agency Head Quarter will be minimized.
3.3.3 Road from Bado to Serisar, Length 20 Km.(Bajaur Package 2)
This road starts from Khar-Zulam Road at K.M 14 and ends at Ghari Shamozai area of Barang
Valley. The road is already constructed as shingled road by NAS in 1993-94 but presently is in un-
satisfactory condition and the inhabitants of the area are facing great hardships. After
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 3-3
blacktopping of this road the population of Tehsil Utman Khel and Barang will benefit by having
better communication facilities. The people of the area will be able to bring their daily
commodities to the nearby markets to the agency headquarter Khar and Timargara District Dir.
People will also be able to access better education and health services with speedy and reliable
communication.
3.3.4 Road from Shukrata to Pampokha, Length 3 Km. (Bajaur Package 3)
The road will start from K.M 5 of Munda-Khar Road at Shukrata and will lead to Pampokha via
Waheedabad Pandokay. This road will connect with Qazafi-Pampokha Road on Kandarow point,
which could be used as by pass road from Qazafi to Shukrata in emergency situations. The
villages/settlements near the proposed road are Pampokha, Kandarow, Shabqader Mohalla,
Pandokay (Waheedabad) and Gulo Kandow. The inhabitants of these Villages will be able to
bring their daily commodities to the nearby markets and access better health and education
facilities.
3.3.5 Tangi Adda toBagoriBridge,Length4.5Km. (Bajaur Package 3)
The road starts from loesum-Nawapass Road at Tangi-Charmang and will connect with main
Khar-Nawagai Road at Bagori Bridge. This will provide an easy approach for the local people as
well as facilitate students of Charmang valley to access the education hub and health institutions
at Nawagai.
3.3.6 Road from Loia Kanda to Ghalishah, Length 3 Km. (Bajaur Package 4)
The Road starts from Munda-Khar Road and will lead to Ghalishah. This Road will serve villages
like Marano Shah, Mian Shah, Loia Kanda and Landai Shah, etc. The Land is highly fertile and the
main crops are wheat, barley, Maize and vegetables. The inhabitants of these Villages will be
able to avail the facilities of Education and health in the other parts of the Agency.
3.3.7 Road from Shagai to Karkanai Charmang, Length 2 Km. (Bajaur
Package 4)
The roads starts from Loesum-Nawapass Road at Shagai-Charmang and will connect with Tangi-
Hasham Road at Karkanai. After the Construction of this Road law and order situation will be
improve as the law enforcing Agencies will be able to monitor the un-accessible areas.
3.3.8 Road from Largri Tan to Dop Sana, Length 2 Km. (Orakzai Package 1)
This road is starts from Main Kadda-Kurez Road to Dop Sana. There is no blacktop (BT) road and
the people of the area are using dirt tracks. After construction of this road, the communication
problem of the people will be solved. They will also be able to bring their crops / vegetables and
other commodities to the local and nearby markets. This is the only stretch of road in the project
that is located near a forest cover area, but the proposed alignment does not affect the forest
cover. The proposed road will be mostly constructed along the existing dirt track and the final
750 m of the road will be extended clear of the forested area, near the agricultural lands.
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 3-4
3.3.9 Road from Dargai to Shamim Jan Killi, Length 2 Km. (Orakzai Package
1)
This road starts from Main Kadda Kurez Road and lead to Shamim Jan Killi via Dargai. There is no
BT road and the people of the area are using dirt tracks. After construction of this road, the
communication problem of the people will be solved. They will also be able to bring their
crops/vegetables and other commodities to the local and nearby markets.
3.3.10 Road from Palosia to Hakim Killi Khawari, Length 3 Km. (Orakzai
Package 1)
This road also starts from main Katcha Packa to Mitta Khan Palosia road via Khawara Baba Lamso
to Hakim Khan Killi. The law & order situation in the area is normal but no better communication
facilities have been provided to the area. On completion of this road, the inhabitants of the area
will be facilitated with better communication facilities and their economic conditions will
improve.
3.3.11 Road from Dargai to Sharo Doghal, Length 2 Km. (Orakzai Package 1)
This road starts from main Kadda-Kurez Road via Ghakhi to Sharo Doghal. There is no black top
road in the area and the people are using dirt tracks. This is a backward area. After construction
of this black top road, the socio economic conditions of the people will improve as they will be
able to access markets, better health and educational facilities.
3.3.12 Road from Sam Feroz Khel to Dara Ghari, Length 3 Km. (Orakzai
Package 2)
The Road starts from Marai Daulatzai road at Feroz Khel Mela Sam Feroz Khel via Adam Khel,
Shah Khel to Dara Ghari. The area is deprived of communication facilities and people face great
hardships. Furthermore, the road will enable people to connect to the Education hub of the
Agency.
3.3.13 Road from Dara Ghari to Sangrani, Length 2 Km. (Orakzai Package 2)
This road starts from Marai-Daulatzai Road to Kalaya headquarters via Dara Ghari to Sangrani.
After construction of this road, Law & Order situation will improve as the Law Enforcing Agencies
will be able to cover the un-accessible areas. On completion of this road, better communication
facilities will be provided to the inhabitants of the area.
3.3.14 Road from Kalaya to Saboora Khel, Length 4 Km. (Orakzai Package 2)
This road starts from Main Kalaya Bazar at Agency headquarters Hospital junction point via Ain
Push to Saboora Khel. The construction of this road is extremely necessary because it will serve
the entire population of "Mani Khel" tribe. The area is totally deprived from communication
facilities and people face great hardships. After construction of this road, the inhabitants of the
area will be able to bring their daily commodities to the nearby markets and will also have access
better health and education facilities.
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 3-5
3.3.15 Road from Kadda Bazar to Aso Khel Khapa, Length 2 Km. (Orakzai
Package 2)
This road starts from main Kalaya to Kadda-Kurez Road at junction point Kadda Bazar via Stara
Khpa to Aso Khel Khpa. There is no black top road in the area and as a result people face great
hardships. After construction of this road, the inhabitants of the area will be able to transport
their daily commodities to the nearby markets and will be linked to Kalaya Headquarters.
3.4 Project Components
For the total 77.5 Km length of the road the main technical indicators for geometrical design are
shown in the Table 3.2.
Table 3.2: Main Technical Indicators of Geometrical Design20
Sr. No Parameter Unit Revised Criteria
1 Design Speed Km/Hr 50 (30/20)
Design Speed for Plain Rural Areas Km/Hr 50
Design Speed for Mountainous and Hilly Areas Km/Hr 30-20
2 Formation Width General M 7.65-10.85 (3.65)
Formation Width in Rolling Terrain M 7.65-8.65
Formation Width in Built Up Areas M 8.65
Formation Width in Mountainous Terrain Requiring Safety Parapet M 9.2
Formation Width in Escarpment Requiring Breast/Retaining Walls
8.60m to 10.85m
3 Width of travelled (Carriageway) M 3.65
Width shoulders M 1.5-2.0
4 Cross slopes/Cross Fall (Where applicable)
Carriageway % 2
Shoulders % 4
5 Minimum Horizontal Curvature
Rolling M 50
Hilly M 30
Mountainous M 10
6 Maximum Super Elevation % 7.9
Desirable Gradient % 2-3
Maximum Gradient % 10-15
7 Minimum Embankment Height Above N.G.L M 0.5
8 Cut Slopes :
Ordinary Soil (As Per Site Condition) Ratio 2:1-1.5:1
Rock (As Per Site Condition) Ratio 1.5:1-1:0.2
9 Clearance above road surface M 5.5
A plan for general construction layout and sections are is shown in Figure 3.1 and 3.2.
20
The Geometrical Design Specifications are based on the Inception Report for the proposed project.
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 3-6
Figure 3.1: Typical Cross-Section in Rolling Terrain and Built-up Areas
21
21
Used from Design Drawings for Bajaur Package-I, Road 1-1, Kharkano to Kulala (Package-NCB-BAJ-01)
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 3-7
Figure 3.2: Typical Cross-Section in Mountainous Terrain and Escarpment Areas
22
22
Used from Design Drawings for Bajaur Package-I, Road 1-1, Kharkano to Kulala (Package-NCB-BAJ-01)
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 3-8
3.5 Drainage Structures
The roads in the proposed project are 3.65 m carriageway therefore surface drainage will be
provided instead of median drainage. The side drains will be provided to protect the
embankment area, if required. The side drains will be designed such that flooding of the
pavement and the resulting flow towards embankment slope does not damage the
embankment, the pavement shoulder shall have a dyke (or curb) which will restrict the flow
towards the unprotected embankment slope and this dyke shall have drainage outlets at
designed intervals to dispose of the run-off generated by the rainfall falling on the pavement.
Roadside drainage facilities to dispose-off the surface runoff of adjacent built-up area and dual
carriageway pavement surface will be designed using Lloyd -Davis version of the Rational
Method.
In general the drainage structures contraction joints shall be at an interval of 9m to 12m along
the length of culverts. Expansion joints shall be provided at the culvert ends where it meets the
wing walls and apron slabs. Lean concrete layer 75 mm thick will be provided under culvert,
apron, wing walls and cut-off walls. For culverts located below firm ground the excavation shall
be carried out in trenches and backfilling and compaction shall be carried out in layers, not
exceeding 15 cm. Figure 3.
Key structures for the finalized road sections in the proposed project are given in Table 3.3 and
Figure 3.3 illustrates typical culvert plan and Figure 3.4 presents covered drain design.
Table 3.3: Key Drainage Features / Structures
Feature / Structure
Bajaur (Kharkano to
Kulala)
Orakzai (Largri Tan to Dop
Sana)
Orakzai (Dargai to
Shamim Khel)
Orakzai (Palosia to Hakim Killi)
Orakzai (Dargai to
Sharo Doghal)
Bridges (total) 0 0 0 0 0
Slab Culverts 53 6 2 6 9
Causeways 1 0 1 0 0
Open Side Drain On one side of road
Covered Side Drain
On one both sides of roads in the built up areas
Foot Path Covered side drain will be used as foot path
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 3-9
Figure 3.3: Plan for Culverts for the Proposed Project
23
23
Used from Design Drawings for Bajaur Package-I, Road 1-1, Kharkano to Kulala (Package-NCB-BAJ-01)
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 3-10
Figure 3.4: Sections for Road Side Covered Drain
24
24
Used from Design Drawings for Bajaur Package-I, Road 1-1, Kharkano to Kulala (Package-NCB-BAJ-01)
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 3-11
3.6 Scope of work of Proposed Project
The Scope of work for the proposed project is described below:
Construction and up gradation of roads in Bajaur and Orakzai Agencies in Federally
Administered Tribal Areas of Pakistan.
Longitudinal drain has been proposed throughout the length of the section on hill side.
Provision of culverts at suitable locations will be made in the design to carry the load of
the hill side drain for their outfalls at the valley side.
Retaining wall will be provided on valley side to check the erosion of embankment by
rains or failure of the slopes due to river Scouring or otherwise.
Guard rail will be provided for embankment heights greater than 3 m.
No particular public facilities have been proposed except road furniture and signage.
Intersection of earthen/paved tracks will be improved.
Additionally the main design and construction work items in the proposed project are described
below.
3.6.1 Design Work Items
Following items are included in design related activities of the proposed project;
Topographic survey
Geotechnical investigation
Culverts structures Design
Retaining wall design
Traffic Signs design
Road Markings design
Guard-rail, Edge-marker and Culvert Marker Posts design
Quality management program of implementation
Design Documents
Issue of construction drawings
Record drawings of As Built plans
3.6.2 Construction Work Items
Following construction related items are included in the proposed project:
Construction of the road to Bituminous pavement standard,
Site clearance and top soil stripping
Earthworks
Demolish and removal of substandard structures and vented Causeways
Constructing Culverts
Construction of Minor and Major drainage works
Constructing Bituminous pavement
Construction of Road furniture
Construction of any other operation ancillary to the main works
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 3-12
Maintenance of works during construction.
3.7 Existing Road Condition
The existing roads traverse through various small villages and towns in Bajaur and Orakzai
Agencies. The proposed roads pass through cultivated plain lands, rolling terrain in the villages
and through ridged and mountainous terrain for most of the road lengths. The existing roads in
the area are mostly narrow, unpaved and in poor condition especially in the small settlement
areas. Overall condition of the proposed roads is very poor. Road width is not wider than 3 m at
most location. Pictorial view of existing road condition in Bajaur shows the overall road
conditions. (See Figures 3.5 to 3.12).
Figure 3.5: Pictorial View of Project Road
Figure 3.6: Land Use beside the Start Point of the
Project Road
Figure 3.7: A View of the Proposed Road at KM.
5+000
Figure 3.8: Another View of the Proposed Road at
KM. 8+000
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 3-13
Figure 3.9: A View of the Proposed Road at KM.
10+000
Figure 3.10: Proposed Road Condition at KM.
12+000
Figure 3.11: View of the Proposed Road at KM.
15+000
Figure 3.12: Another View of the Proposed Road at
KM. 18+000
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 3-14
3.8 Work and Material
3.8.1 Estimated Work / Major Work Items
Estimated total quantity of work involved in project, based on the projects of similar size and
Scale is given in Table 3.4.
Table 3.4: Estimated Works and Work Features
Works Quantity / Value
Road Length 75.5 km
Carriageway Width 3.65 m
Surface Dressing Bitmac
Water Bound Macadam (WBM) Class B 15 cm
Sub Base 15 to 20 cm
Sub Grade 30 cm
Average Embankment Height 1.5 m
Culverts 190
Causeways 5
3.8.2 Materials Requirement
An estimate of quantities of different materials required for construction of road project is given
in Table 3.5. These estimates are based on the previous projects of similar size and scale.
Table 3.5: Estimated Construction Material Requirement
Material / Item Unit Quantity
Earth Work Excavation for Road and Structure Works cubic meters 288,000
Formation of Embankment from Roadway Excavation and Borrow Material cubic meters 461,500
Granular and Common Backfill for structures cubic meters 121,700
Granular Sub-base Course cubic meters 99,300
Aggregate Base Course cubic meters 89,700
Asphaltic Base course Plant Mix (Class–A) cubic meters 49,996
Asphaltic Concrete for Wearing Course (Class–B) cubic meters 50,000
Concrete cubic meters 27,500
Reinforcement Steel Ton 1,700
3.9 Construction Resources Procurement, and Transportation
3.9.1 Construction Materials
Construction materials for this project shall include sub-grade filling materials, pavement
crushed stones, concrete aggregate, asphalt aggregate, masonry mineral aggregate, and water
etc. All these materials shall be mainly collected at the site, processed, and then transported to
the construction site by trucks. Slab culverts can be prefabricated at the site. The roads under
the proposed project are located in the varied terrain of rolling plains to mountain area where
there are many rocks available for quarrying and sand is sporadically distributed at river sites. All
building materials shall be either purchased or exploited and processed according to the
progress of the project construction.
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 3-15
3.9.2 Filling Materials of Sub grade
The majority of soil along the existing tracks is suitable as filling material of sub grade, however,
soil test are required for the usage. There are borrowed filling materials available within average
transport distance of 5km at the overwhelming majority of points along the line. A reasonably
economical transport distance shall be taken into account in the case of utilization of soil and
rocks of adjacent sections.
3.9.3 Broken Stones for Base Course (Coarse Aggregate)
Excavated rocks shall be processed and broken in accordance with the requirements of
unscreened broken stones for base course. Furthermore, the riverbed is a potential source of
coarse aggregate. In some areas, broken stones maybe available from the riverbed in limited
quantity.
3.9.4 Broken Stones for Concrete (Coarse Aggregate)
Rocks shall be processed, broken, and screened at the worksite and cannot be used until they
are tested and inspected to meet the standard requirements of broken stones for concrete.
3.9.5 Sand
Sand is distributed in the river basins and mountain sand could also be utilized. Sand from both
sources shall be tested and inspected before actual use in construction.
3.9.6 Cement, Steel, and Asphalt
Cement is made in Kohat which has the large cement works in Pakistan. It could be purchased
from Peshawar, Kohat or any location economical for the contractor and transported to the
construction site by land.
Steel could also be purchased from Peshawar or Kohat. Asphalt shall be bought from Karachi or
imported from china and transported to the construction site by land and could also be
purchased from Attock Oil Refinery in Rawalpindi. Specialized asphalt is produced by Pak Hyoil, a
subsidiary of Attock Petroleum Limited.
3.10 Raw Material Availability
Sources of different raw materials required for construction are given in Table 3.6.
Table 3.6: Raw Material Availability
Raw Material Availability
Borrow material Along the Road
Stones for retaining walls and rip rap.
Available along the project sites, in the rolling areas and build up areas stone will be acquired form nearest site.
Stone for sub-base, aggregate base course, asphalt courses
River Pit Run Gravel for sub-base. Aggregate base courses and asphalt courses will be procured from crushing plant located near the project sites.
Bitumen Refineries in Karachi or Rawalpindi
Asphalt Refineries in Karachi or Rawalpindi
Brick Peshawar, Kohat or Khar
Sand River flood plains along or near the project sites.
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 3-16
Raw Material Availability
Clean water for specific uses. Arrangements will be made to have access to tube wells or River water
Other water for compaction and sprinkling.
Seasonal streams crossings the road and rivers passing along the roads
Reinforcement Steel Nearby Market
G.I. Pipes Nearby Market
Cement Nearby factories
3.11 Machinery to be Used
An estimate of machinery of different types like graders, batching plants, asphalt mixing plants
and others is given in Table 3.7. These maximum estimates are based on the fact that all the
projects are initiated in a single phase. Otherwise if the projects are carried out in distinct phases
the machinery requirement can be reduced to the lower limit.
Table 3.7: Estimated Machinery Requirement
Machinery Quantity (Maximum) Quantity (Minimum)
Graders 6 2
Tractors 26 6
Vibratory Rollers 13 3
Asphalt Mixing Plants 6 2
Stone Crushers 6 2
Batching Plants 6 2
Water Browsers 13 3
Oil Tankers 6 2
Water Sprinkling Water Carcass 26 6
Haulage Trucks 32 7
Excavators / Loaders 13 3
Small Vehicles 26 6
Dozer 13 3
Shift Roller 19 4
Asphalt Machine 6 2
3.12 Equipment and Installations
The equipment and installation required for project is given in Table 3.8:
Table 3.8: Estimated Requirement for Equipment and Installations
Equipment / Installation Quantity (Maximum) Quantity (Minimum)
Fire Extinguishing Equipment 13 3
Electricity Generator 13 3
Water Pumping Equipment 13 3
Telephone System 26 6
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 3-17
3.13 Construction Schedule
According to the proposed schedule the construction / up-gradation / rehabilitation of roads in
the Package 1 of project will commence on October 2012 under the Phase 1 of project. Under
the Phase 2 the roads in Package 2, 3 and 4 will be implemented later. The expected completion
time of the project is two years i.e. by October 2014.In case of any delays at the outset, the
completion date can be delayed accordingly.
3.14 Construction Logistics
3.14.1 Work Base
Since the project is comprised of multiple road lengths, each road will require its own work base.
In total the project will require no less than 11 work bases, though at one given time the number
will be lower. Preferably the work bases will be established away from the local settlements.
Additionally the work bases should not interfere with the water resource used by locals for
domestic and the agricultural activities. For the proposed project following work bases are
suggested. For Bajaur Package 1, Kharkano to Kulala road a suitable site is near the road start
point between Kharkano and Soorbat, as the location offers both resources and access to Khar-
Zulam road. A suitable location is available along the Kadda-Kuraz road at the start point of Dargi
to Shamim Jan Killi road under Orakzai Package 1, the work base can also be used for Dargai to
Ghakhi to Sharo Doghal. For Orakzai Package 1 Largri Tan to Dop Sana road, a suitable location is
west of Largi Tan along Kadda-Kuraz road at the start point. For Palosia to Hakim Kalli Khawari
road, Palosia town is the most suitable site available for Orakzai Package 1. For Orakzai Package
2 Kadda Bazar to Aso Khel Khapa no suitable locations are available, the work base needs to be
established on agricultural land with local cooperation. In Orakzai Package 2 Dara Ghari to
Sangrani road and Sam Feroz Khel to Dara Ghari road, the work base can be established along
the Marai-Daulatzai road at Feroz Khel, the base can serve both the road lengths. For Dak Qilla
By-Pass in Bajaur Package 2 suitable locations are available near Khar Nawgai road and Khar
Zulam road connection points. Again for Bajaur Package 2 Bado to Serisar road the best suited
location is near Bado along Khar-Zulam road, as most of the area in the proposed section is
rugged and mountainous. For Bajaur Package 3 Shukrata to Pampokha and Loia Kanda to
Ghalishah road sections suitable base location is along Munda-Khar road, the location also
provides easy access to Mian Kaley and Munda towns. Finally for Tangi Adda to Bagori Bridge
and Shagai to Karkanai Charmang roads under Bajaur Package 4 the base locations are available
at Loesum-Nawapass Road at Tangi Charmang and Loesum-Nawapass Road at Shagai Charmang
respectively.
3.14.2 Labor Supply
The contractor will be contractually bound to employ maximum local people except for jobs for
which expertise is not available locally. The contractor will also keep a record of the employment
from the local population to validate compliance and also monitoring purpose. The contractor(s)
will be responsible for providing safety and security to its workers/staff. Table 3.9 illustrates the
labor employment.
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 3-18
Table 3.9: Illustrative Distribution of Labor
Type of Labor Local Non–local Total
Skilled 40% 60% 100%
Semiskilled 50% 50% 100%
Unskilled 100% 0% 100%
By and large the daily wage rates fixed by the local commissioner will be used. In total the
projects will require a significant amount of technical and unskilled labor. The estimated average
staffing requirement for the projects is presented in Table 3.10.
Table 3.10: Construction Team and Personal for the Proposed Project
Category of Worker
Sub-grade Construction
Personnel
Road Surface Construction
Personnel
Protection & Drainage
Construction Team
Testing and Inspection Personnel
Personnel for Camp
Management
Category
Total
Headman/Director
2 1
1 1 5
Site/Test Engineer
2 2 2 2
8
HSE Engineer
1 1 1
3
Quality Engineer
1 1 1 1
4
Surveying/Testing worker
2 2
1
5
Air Drill Worker
4
4
Air Compressor Worker
2
2
Electrician 1 1
2
Repairman 2 1
3
Electric Welder
1
1
Carpenter
3
3
Mechanical Operation Worker
9
3
12
Mixing Worker
5 5
10
Painter
5
5
Equipment Operator
5
5
Security Guard
5
5
Blaster 2
2
Explosive Keeper
2
2
Explosive Carrier
2
2
Driver 18 7 5
3 33
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 3-19
Category of Worker
Sub-grade Construction
Personnel
Road Surface Construction
Personnel
Protection & Drainage
Construction Team
Testing and Inspection Personnel
Personnel for Camp
Management
Category
Total
Unskilled Labor
75 82 47
5 217
Total 130 114 67 5 17 333
3.14.3 Labor Camps
Although a majority of the labor force will come from local sources, they will be transported to
the works site by contractors transport. Some semiskilled and most skilled workers may have to
be brought in by contractor from far off towns; this work force will live in camps. Being located
near the work base, the camps will make the work access easy to the camp dwellers. Like the
work bases, the labor camps should also be more than 500 m away from the nearest habitation.
The exact area of land that they will occupy, the measures to be taken to manage potable water,
wastewater and solid waste are yet to be finalized. The proposed locations for campsite use are
presented in Table 3.11, after remote screening of project locations. The final campsites will be
selected by the contractor with XEN’s consultation and based on the checklist provided in
Annexure 3.
Table 3.11: Proposed Camp Sites for Project Roads
Road Project Proposed Location
Bajaur Package 1 Kharkano to Kulala road
Near the road take off point between Kharkano and Soorbat along the Khar-Zulam road.
Orakzai Package 1 Dargi to Shamim Jan Killi road
Along the north west side Kadda-Kuraz road at the takeoff point of Dargi to Shamim Jan Killi road
Orakzai Package 1 Dargai to Ghakhi to Sharo Doghal road
Along the north west side Kadda-Kuraz road at the takeoff point of Dargi to Shamim Jan Killi road
Orakzai Package 1 Largri Tan to Dop Sana road West of Largi Tan along Kadda-Kuraz road at the take off point
Orakzai Package 1 Palosia to Hakim Kalli Khawari road Near Palosia town
Bajaur Package 2 Dak Qilla By-Pass Along Khar Nawgai road and Khar Zulam road connection points
Bajaur Package 2 Bado to Serisar road
Near Bado along Khar-Zulam road, as most of the area in the proposed section is raged and mountainous
Orakzai Package 2 Kadda Bazar to Aso Khel Khapa road
The camp needs to be established on agricultural land with local cooperation
Orakzai Package 2 Dara Ghari to Sangrani road Along the Marai-Daulatzai road at Feroz Khel
Orakzai Package 2 Sam Feroz Khel to Dara Ghari road Along the Marai-Daulatzai road at Feroz Khel
Bajaur Package 3 Shukrata to Pampokha road
Location is along Munda-Khar road, the location also provides easy access to Mian Kaley and Munda towns
Bajaur Package 3 Loia Kanda to Ghalishah road
Location is along Munda-Khar road, the location also provides easy access to Mian Kaley and Munda towns
Bajaur Package 4 Tangi Adda to Bagori Bridge road Along west side of loesum-Nawapass Road at Tangi Charmang
Bajaur Package 4 Shagai to Karkanai Charmang roads
Along the north east side of Loesum-Nawapass Road at Shagai Charmang
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 3-20
3.14.4 Machinery Maintenance and Equipment Yards
Machinery and equipment yard will be provided near each work base. The yard will have enough
storage, haulage, ample moving and working space. The yard will be walled, gated and provided
with adequate security staff. These machinery maintenance and equipment yards should not
affect the environment in terms of waste and soil pollution. After the completion of project the
contractor will make adequate arrangements to reverse any impacts resulting from these
facilities.
3.14.5 Material Depots
A material depot will be required for storing construction material near each work base. It will
have temporary sheds for storing cement, iron bass, asphalt and open space for storing stones
shingles and bricks. The material depots will be walled, gated and provided with adequate
security staff. A store keeper will keep account of incoming and outgoing material.
3.14.6 Machinery Repair Workshops
With a large number of vehicles and other similar machinery a repair workshop is essential. The
contactor may establish its own workshop at a secure place. While establishing such workshops
the contractor will follow all the required environmental guidelines for protection of air, soil and
water. Additionally the workshops should have fully compliant safety standards.
3.14.7 Approach to Work Bases
Since, the work base will be established close to the road under construction, existing road can
provide easy access to these work bases. Where required, supplementary access roads and
paths for the work bases can be provided with the prior approval of local authorities and
communities.
3.14.8 Camp Offices
Adjacent to labor camp and work base, the contractor will be allowed to set up a camp office to
run his day to day affairs. For that the local land can be used by the contractor with prior
approval of local authorities and community.
3.14.9 Healthcare
With a large number of labor and employees working in road construction projects, small
accidents are expected to take place at construction sites. Two dispensaries will be set by the
contractor in each agency’s base camp. These dispensaries will have services of a full time
doctor. At least two ambulances will support the dispensaries. For major cases the patients will
be shifted to fully equipped hospitals in Kohat and Peshawar under a pre-coordinated
arrangement.
3.14.10 Labor Reporting Office
Along the road and in work bases special areas will be marked where the labor can gather at the
time of pick and drop, emergency or briefing and places will be clearly marked and kept open
and clean and as per requirement equipped with public address system.
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 3-21
3.14.11 Labor Transport
Almost entire unskilled labor will be employed from local sources. Contractor will provide
vehicle(s), preferably a bus to pick and drop local labor every day. That will help them to spend
nights in their households and render some services at home. This will also keep the camps less
pressurized and manageable.
3.14.12 Water Supply
The availability of water for the project will mainly be from the local rivers and small seasonal
streams in the area. In some cases the only source of water for the living camps will be ground
water and will obtained through hand pumps and by digging wells. The contractor will ensure
provision of safe drinking water to the labor and other employees.
3.14.13 Work Uniform and Health Safety Equipment
Road construction is a special job and the labor working on such work requires special protective
uniforms and special HSE measures. It will be ensured that the labor engaged in breaking of
stones, handling bricks, mixing concrete or mixing and laying asphalt will have long boots overall
dresses, goggles and safety hats. As an overall HSE measure anyone going into the construction
area will also wear safety hat.
3.14.14 Signage
During construction at the construction site in particular and for the entire road length in
general, suitable signboards and traffic signs will be displayed at all along the length of the road.
This will help in forestalling any possible accidents.
3.14.15 Lighting and Illumination
Suitable lighting arrangement will be made by the contractor at all work bases, work sites, camp
sites machinery yard and material depots. This can help the contractor for extended working
hours as well as security. If grid electric supply is not available, electricity generators or solar
lights will have to be arranged on all spots where lighting is required.
3.14.16 Layout of Waste Disposal System
Solid waste generated from offices and residential areas shall be collected through waste bins at
source and segregated. Designated personal for handling waste shall be employed. The
recyclable waste shall be handed over to waste dealers (if available the approved dealers in
Peshawar and Kohat shall be identified). The non-recyclable waste shall be incinerated or land
filled properly.
Wastewater from camps shall be treated through septic tanks and discharged into soaking pits.
Grease collection pits shall be installed for gray water from kitchens and washing areas. No
wastewater shall be discharged into any water bodies. The septic tanks shall be removed at the
completion of the project and the area shall be restored to the original state, to the extent
possible.
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 3-22
3.15 Safe Design Criteria
The design and implementation of the Project follow the AASHTO standard. According to the
analysis of the annual average daily traffic (AADT), the traffic grade to be adopted is T5, the
grade of the sub grade is S5. The main design speed proposed is 50(20-30)km/h, the
corresponding road sub-base width is 7.65(9.65)m, the carriageway width is 3.65m. For special
difficulties sections it shall be properly reduced design standard.
To meet international standards envisaged by the World Bank, the following design criteria have
been adopted in the project:
Geometric Design : AASHTO
Material Testing : ASTM
Structure : ACI
Structure Loads : Class A – AA as per approval of the relevant authority
Seismic Design : UBC 97 and Sarhad Interim Seismic Building Code Base
on Seismic Study Zone Maps
Curve Widening : 0.6 to 1.6 depending upon length
3.16 Institutional Arrangements
The overall institutional arrangements for the implementation of project are given below,
butspecific arrangements for the implementation, monitoring and reporting of ESMP
implementation are detailed in sections 8.8 and 8.10 of this report
Implementation Period – 2 years and 6 months: The project is being prepared by W&SD, FATA
and shall be implemented by it. The W&SD is headed by a Chief Engineer (CE) and supported by
a Superintending Engineer (SE). The W&SD Headquarters in Peshawar comprises of General &
Administration Cell. The W&SD has Highway Divisional Offices in each of the seven FATA
Agencies. An Executive Engineer (XEN) heads the Divisional Offices. Other staff at Divisional
Offices includes Sub Divisional Officers (SDO) and Divisional Accounts Officer (DAO). W&SD is
custodian of about 6,600 km of rural roads.
Overall Oversight Arrangements – Project Steering Committee: A Project Steering Committee
(PSC) headed by the Chief Engineer, W&SD and comprising Project Director (FATA ERRP), and
Executive Engineers (XENs) of Bajaur and Orakzai Agencies will be overall responsible for
ensuring timely implementation of the Project. The PSC will be responsible for overall
coordination including with Political Agents of Bajaur and Orakzai Agencies. The PSC shall ensure
that the FATA ERRP is reflected in the FATA’s FY 12/13 Annual Development Plan (ADP) and in
subsequent fiscal years budgets. The CSC shall also facilitate timely opening of a segregated
Designated Account (DA) in US$ at the National Bank of Pakistan in accordance with accounting
procedures for Revolving Fund Accounts (Foreign Currency Assignment Account) issued by the
Finance Division, Government of Pakistan on June 30, 2010.
Project Management Unit: There shall be a Project Management Unit (PMU) at W&SD
Headquarters in Peshawar, headed by the Project Director (FATA ERRP) and supported by a
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 3-23
Deputy Project Director (FATA ERRP) and Finance Manager/Accounts Officer (FATA ERRP). The
PMU functioning as the Project Secretariat shall support the Project Steering Committee. The
PMU will liaise with the representatives of Political Agents of Bajaur and Orakzai Agencies and
shall be responsible for internal/external processing of all approvals including PC-I, procurement
and implementation of civil works, procurement and management of consultant services.
Field Implementation Unit: There shall be a Field Implementation Unit (FIU) within each of the
divisional offices of at W&SD in Bajaur and Orakzai Agencies, headed by the respective Executive
Engineer (XEN) and supported by Sub Divisional Officer (SDO) and Divisional Accounts Officer
(DAO). It shall be responsible for general administration, land acquisition through Political
Agent/Additional Political Agent and/or their representatives, coordination with other
authorities to ensure timely relocation of various utility services, handing over of sites to
contractors, field-level oversight of environmental safeguards, management of social safeguards,
and performance monitoring of civil works and ESMP implementation.
Project Engineer: A professional consulting firm will be responsible for Contract Administration
& Construction Supervision. The firm will be fully empowered as the ‘Engineer’ in accordance
with International Federation of Consulting Engineers (FIDIC) stipulations. W&SD will act as the
Employer. The Project Director will be designated as the Employer’s Representative. The
Resident Engineer (RE) will act as the Engineer’s Representative. The ‘Engineer’ will administer
the civil works contracts, make engineering decisions, be responsible for quality assurance,
provide general guidance and furnish timely responses to the Contractors in all matters relating
to the civil works, and ensure that all clauses of the Contract Agreement between the civil works
Contractors' and W&SD are respected. The ‘Engineer’ will advise W&SD on all matters relating to
the efficient and successful execution of the civil works contracts, and will act at all times to
protect the interests of the project and will take all reasonable steps to keep the construction
costs to a minimum, consistent with sound economic and engineering practices; and will prepare
a "Contract Administration and Construction Supervision Manual" outlining routines and
standard operating procedures to be applied in contract administration and construction
supervision, based on sound internationally recognized practice.
3.17 Grievance Redress Mechanism/Complaint Handiling System
The potential environmental and social issues associated with the project and their mitigation
measures have been discussed in the ESMP. However, by doing all possible and best efforts,
there is a possibility that an individual or a group may be unsatisfied with the measures adopted
or have certain queries/suggestions for the project.
In order to address such concerns and grievances/complaints, and for the smooth and timely
implementation of ESMP, a Grievance Redress/Complaint Handling Mechanism(GRM) is
proposed at the project level. Under the GRM, a Grievance Redress Committee (GRC) will be
formed at the PIU Level. The committee will be formed in consultations with the political
administration, W&S department (EA), PMU, and RAP Consultants. The GRC will constitute of the
PA, XEN, tehsildar and the chairman of the project affected persons committee.
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 3-24
The GRC will provide a public forum to the aggrieved to raise their objections and through
conflict resolution, address these issues adequately. The main objective of the GRM will be to
investigate charges of irregularities and complaints received from the PAPs and provide an early,
transparent and fair resolution of their complaints.
The contractor will also maintain a complaint registration to maintain record of such complaints
where the name & address of complainant, date, description of complaint and action taken will
be entered. If the GRC is unable to resolve the issues of the complainant then the case will be
forwarded to the Chief Engineer, W&S department FATA through the PIU where the matter
would be resolved.
3.18 Estimated Project Cost
Final design and drawings of the road project has been finalized: The World Bank has agreed to
provide a financial assistance to the tune of US$ 16 million which is equivalent to about PKR. 1.5
billion.
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 4-1
4 Baseline Study of Project Area
Baseline studies were undertaken for environmental aspects that may be affected by project
activities. The environmental baseline studies provide a database of physical, biological and
social parameters that are used to predict and monitor the effects of the project on the
environment. The overall environmental settings of the project area in the Bajaur and Orakzai
agencies are shown in Figures 4.1 to 4.17.
The description provided in this section is based on published information and field survey data
that was collected specifically for this study. The purpose of reviewing published literature was
to gather information on the environmental setting and the work already carried out in the area.
The relevant literature was of the previous studies conducted in the project area or in areas with
a similar geographical and ecological setting. The proposed project components lie in the
Federally Administrated Tribal Areas (FATA) of Pakistan therefore there were many limitations
involved in undertaking this assignment. Some of the major limitations include:
Poor law and order situation of the area inhibited experts of the team to physically visit
the area.
There were no local environmental or social experts available for the study.
Avoiding major public areas for security reason during surveys.
Very limited or no secondary literature available for the area on environment.25
Other cultural constraints including prohibition for photography and access to women of
the area for consultations and acceptance for an outsider female to participate in the
study etc.
A survey and data-collection team belonging to the FATA area was formed and especially trained
for this project.
25
No records of previous reports on environmental assessments are available at Federal EPA or any Provincial EPA. A summary IEE was conducted in one of the agencies by Asian Development Bank, but with a very brief baseline information on environment. Not a single recognized institute for higher education and research is available in the entire FATA. There were very few non-governmental organizations involved in the area. Of which only one organization “Community Appraisal and Motivation Program (CAMP)” has published a few reports. Extensive internet searching was carried out to obtain relevant literature.
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 4-2
Figure 4.1: Environmental Settings of the Project Area in Bajaur Agency
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 4-3
Figure 4.2: Environmental Settings of the Project Area in Orakzai Agency
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 4-4
Figure 4.3: Environmental Setting of Bajaur Agency Phase 1 Kharkano to Kulala Road, Length 20 Km.
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 4-5
Figure 4.4: Environmental Setting of Orakzai Agency Phase1 Dargi to Shamim Jan Killi Road, Length 2 Km.
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 4-6
Figure 4.5: Environmental Setting of Orakzai Agency Phase1 Dargai to Sharo Doghal Road, Length 2 Km.
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 4-7
Figure 4.6: Environmental Setting of Orakzai Agency Phase1 Largri Tan to Dop Sana Road, Length 2 Km.
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 4-8
Figure 4.7: Environmental Setting of Orakzai Agency Phase1 Palosia to Hakim Kalli Khawari Road, Length 3 Km.
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 4-9
Figure 4.8: Environmental Setting of Bajaur Agency Phase2 Dag Qilla Bypass Road, Length 3 Km.
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 4-10
Figure 4.9: Environmental Setting of Bajaur Agency Phase2 Bado to Serisar Road, Length 20 Km.
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 4-11
Figure 4.10: Environmental Setting of Orakzai Agency Phase2 Dara Ghari to Sangrani Road, Length 2 Km.
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 4-12
Figure 4.11: Environmental Setting of Orakzai Agency Phase2 Kadda Bazar to Aso Khel Khapa Road, Length 2 Km.
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 4-13
Figure 4.12: Environmental Setting of Orakzai Agency Phase2 Kalaya to Saboora Khel Road, Length 4 Km.
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 4-14
Figure 4.13: Environmental Setting of Orakzai Agency Phase2 Sam Feroz Khel to Dara Ghari Road, Length 3 Km.
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 4-15
Figure 4.14: Environmental Setting of Bajaur Agency Phase2 Shukrata to Pampokha Road, Length 3 Km.
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 4-16
Figure 4.15: Environmental Setting of Bajaur Agency Phase2 Tangi Adda to Bagori Bridge Road, Length 4.5 Km.
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 4-17
Figure 4.16: Environmental Setting of Bajaur Agency Phase2 Loia Kanda to Ghalishah Road, Length 3 Km.
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 4-18
Figure 4.17: Environmental Setting of Bajaur Agency Phase2 Shagai to Karkanai Charmang Road, Length 2 Km.
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 4-19
4.1 The Project Area of Impact
The project area of impact is a linear corridor through which proposed road components pass
and is defined as the geographical region where the environmental and social impacts of the
proposed project, both during construction and operation are likely to occur. For this ESIA and
ESMP, the project area is defined as the area located within 2 km of either side of the proposed
roads (shown in Section 1).
4.2 Physical Environment
4.2.1 Geography
The components of the proposed project are located in two agencies of the Federally
Administered Tribal Areas (FATA) of Pakistan, Bajaur and Orakzai. Bajaur, the smallest agency in
FATA in terms of total area, has a predominantly hilly terrain. To the south of Bajaur is a
mountain district of the Mohmand agency. To the east are the hills of the Swat valley. To the
north is an intervening watershed between Bajaur and the small state of Dir. It borders
Afghanistan's Kunar Province in the west. The headquarters of the Bajaur agency administration
is located in the town of Khar.
The terrain of the Bajaur agency is mountainous and hilly. In the northern part, the mountain
ranges are up to 3,000 m above sea level. Towards the south the height gradually decreases and
peaks on the southern border are slightly over 2,500 m high. In the central part, the altitudes
further decrease. In the north – western half, the land slopes down to the south – east direction
while in the central parts the land slopes to the north – east through the Jandol Khwar and
Panjkora river. An interesting feature in the topography of Bajaur is a mountain spur from the
Kunar range, which curves eastwards and culminates in the well-known peak of Koh-i-Mor,
visible from the Peshawar valley.
There are two valleys Khanki and Mastura bounded by parallel ranges in the same directions.
The valleys are in general 12 kilometers apart at the maximum. Important passes having heights
of 1500 to 2400 m interpose these valleys. Among the seven tribal agencies, the Orakzai Agency
is the second smallest in area after the Bajaur Agency. It is bounded by Kurram Agency in the
west, Khyber in the north, Kohat District on the south and Peshawar in the east. The whole of
the territory of Orakzai agency is a mountainous tract dissected by numerous dry watercourses,
especially in the southwestern part of the agency.
4.2.2 Geology and Soil
The project area is noted for its interesting geological formations. Typical rocks of the FATA
region are of the mélange zone and there is a variety of alteration zones. Various types of
sedimentary, igneous and different grades of metamorphic rocks ranging in age from Pre-
Cambrian to Paleocene are found in this region. The presence of these geological features
designate FATA with having the most suitable of geological environments in comparison with the
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 4-20
rest of world where mineral deposits of economic grade including metallic, non-metallic, energy
minerals, precious / dimension stones and different rocks of industrial use are being extracted.26
The Bajaur Agency consists of diorite rocks, which indicates a continuation of metamorphic and
igneous rocks consistent with the northern mountain chain. Valley beds of Bajaur Agency
exhibits young alluvium soil deposits, with varying organic contents, moisture-retention
characteristics, and acidity values.27
The rock units of Kohat Potohar, varying in age from lower Jurassic to Eocene, surround the area
that forms the Orakzai Agency. The rocks are mainly composed of shale, marble, limestone and
sand stone. The structural formation in the Orakzai Agency is east-west, with marked deviation
visible in Sepeh and the Utman Khel area, where the general trend is to the North West. Strictly
speaking in geological terms, 13 different rock units have been identified in Orakzai Agency, and
these are related to the Kohat hills and salt range. The following three units predominate in the
Agency.
1. Lockhart Limestone
2. Hangu Formation
3. Samana Suk Limestone
Samana suk lime stone is exposed in the southwestern part of Feroz Khel plain and has direct
contact with Hangu formation. The lower part of Hangu formation is ferruginous sand-stone and
the upper part is thin to medium budded limestone, shale and marl. The Hangu formation is
mostly unfossiliferous, and based on this, the formation is thought to date from the Paleocene
age.
The Hangu formation is overlaid by Lockhart limestone having faulted contact with each other.
On the eastern part of the Feroz Khel plain, some rock formations are exposed with a general
castwest trend.
Soils in the project area vary from silty loamy to silty clay and clay (Atlas of Pakistan, 1997). Soil
is used for dry farming and torrent water cultivation. Soils in the Bajaur Agency are considered
to be generally fertile, varying from silt loam to loam containing a medium degree of organic
matter. It has also been observed that the soils of Orakzai Agency are fertile and good for
agriculture. These soils are well drained except in a few areas.
4.2.3 Seismicity
The Orakzai Agency is located in seismic zone “2B” (moderate) and Bajaur Agency is located in
seismic zone “3” (high) as per seismic zoning maps drawn by UN-Habitat.28
26
Physical Features and Climate http://fata.gov.pk/index.php?option=com_content&view=article&id=51&Itemid=85
27 Mian Sayed Badshah (Undated) Geology of Bajaur and Northern part of Mohmand Agency
28 UN-Habitat (2010) Seismic Zoning Map Paksitan - UN-HABITAT Pakista
http://www.unhabitat.org.pk/Maps-updated/UNH-PAKOV_SZ_A3_02122010.pdf
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 4-21
4.2.4 Land Use
There are following general categories of land use in the area;
Rain-fed agriculture
Irrigated agriculture
Rangeland (Denuded Hills)
Shrubs & bushes
Forest
Figure 4.18: Cropped Fields in the Project Area
Government has identified the cultivated area, cultivable waste, cultivable area, irrigated area
and forest area in the entire FATA region. The same for the Bajaur and Orakzai agencies are
shown in.
Table 4.1:Land Utilization Statistics
Type Unit FATA Bajaur Orakzai
Cultivated Area 1000 hectares 216.18 75.1 16.31
Cultivable Waste 1000 hectares 173.99 11.19 3.45
Cultivable Area 1000 hectares 390.17 86.29 19.76
Irrigated Area 1000 hectares 83.24 19.92 2.21
Forest Area 1000 hectares 43.18 11.3 5
Cultivated Area as % of Reported % 7.94 58.2 10.61
Irrigated Area as % of Cultivated % 38.5 26.52 13.55
Forest Area as % of Reported Area, % 1.59 8.76 3.25
Land Use Intensity % 55.14 87.03 82.54 Source: Land Utilization Statistics, FATA- 2005-06 and SBF Mainstreaming FATA, 2009
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 4-22
4.2.5 Water Resources
According to the Survey of Pakistan Atlas, the area consists mostly of hills that consist
predominantly of sedimentary rocks belonging to the tertiary and quaternary periods. The
percentage of plain area in these catchments is small (Geological Survey of Pakistan, 1997).There
are no major water bodies in the area. None of the area’s major rivers are located within the
project area. The lack of a potable drinking water supply system is a major problem experienced
in the area, where the majority of the inhabitants do not have access to safe drinking water
supplies. The ill effects of this situation were noted by the health service facilities operating in all
agencies, which indicated that many patients suffer from waterborne diseases. Irrigation
patterns of the area are shown in Table 4.2.
Table 4.2: Water Resources in the Project Area
Total land
cultivated(kanals): Type of
Irrigation: Drinking Water
Source House-hold Use Water Source
Bajaur Agency Settlements
Soorbat Kali 2,000.00 Rain fed/Tube
well Tube well Tube well
Pataselay 3,040.00 Rain fed/Tube
well Tube well Tube well
Landay 1,920.00 Rain fed/Tube
well Tube well Tube well
Tarry 5,200.00 Rain fed/Tube
well Tube well Tube well
Islam Dehrai 1,680.00 Rain fed/Tube
well Tube well Tube well
Khayathy 15,040.00 Rain fed/Tube
well Tube well Tube well
Bandegi 5,440.00 Rain fed/Tube
well Tube well Tube well
Kulala 13,200.00 Rain fed/Tube
well Tube well Tube well
Project Area Total 47,520.00
-
Orakzai Agency Settlements
Dop Sana 1,440.00 Rain fed Tube well Tube well
Largi Tan 2,080.00 Rain fed/Tube
well Tube well Tube well
Sharo Doghal 720.00 Water Channel Pipeline Water Channel
Dargi 2,240.00 Rain
fed/Channel Water Channel Water Channel
Shamim Jan Kali 360.00 Rain
fed/Channel Pipeline Pipeline
Otti Kali 1,040.00 Rain
fed/Channel Pipeline Pipeline
Palosia 4,160.00 Rain
fed/Channel Pipeline Pipeline
Mama Masai, Amber Khel & Hindikali
2,880.00 Rain
fed/Channel Pipeline Pipeline
Brado Sam, Lalpura & Twekali
2,480.00 Rain
fed/Channel Pipeline Pipeline
Project Area Total 17,400.00
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 4-23
4.2.5.1 Surface Water
The overall water resources cannot be evaluated due to the lack of hydrological data available
for the FATA area. No rivers or major streams were identified in project area in Bajaur during
field surveys. Mastura River is located close to project area. Only limited information on the
discharge of this river is available which is not sufficient for any assessments. It has been
observed that the ground water potential of the area is also limited. Dirt (kaccha) or temporary
channels have been taken from rivers for irrigation purposes. These surface irrigation systems
have long been constructed, managed and maintained by the beneficiaries through their tribal
elders. Floods often destroy the earthen channels and erode farmland. FATA Development
Corporation (FATA-DC) has been involved in the construction and improvement of surface
irrigation schemes since 1980s.
4.2.5.2 Ground Water
The groundwater is the major source of drinking and irrigation water of the area both in Bajaur
and Orakzai agencies. According to FATA-DC statistics in Orakzai Agency, as of September 1,
1990, 22 test wells have been drilled. Of these, 7 have been abandoned, 11 have been energized
and 4 test wells are in the process of conversion to tube wells. These test wells/ tube wells are
only in the Lower Sub-Division. Good prospects for ground water development exist in Feroz
Khel and on the plain that lies on the right side of the Mastura river.
The successful tube wells are located in the Kalaya, Feroz Khel, and Mishti plains. Out of 11
operating tube wells, 9 are in Upper Orakzai subdivision and 2 are in Lower Orakzai subdivision.
In Upper Orakzai, 3 are in Kalaya, 1 in Aiim Khan Khel, 1 in Kadda and 4 in Feroz Khel while 2 are
in the Mishti area in Lower Orakzai. Four test wells drilled in the Tanda plains will be converted
to tube wells after successful yield tests. These four are being funded by the United States
Agency for International Development (USAID). Of the abandoned wells, 2 are in Feroz Khel, 4
are in Mishti and one at Chapri.
Figure 4.19: An Operation Tube Well in the Project Area
Figure 4.20: Brick Lined Water Channel for Irrigation
4.2.5.3 Potable water
Potable water for FATA inhabitants is provided through four separate sources. These sources are
spring water, infiltration gallery, tube wells and open wells. There was one Afghan refugee
scheme at Ghaljo, Upper Tehsil headquarters, near project area and it was supplying water only
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 4-24
to the camps of Afghan refugees. The entire area of Upper Sub-division lacks easy access to
drinking water because of high population density and inadequate surface resources.
According to the Public Health Engineering Department (PHED) Sub-Divisional Officer (SDO),
each scheme in Upper Sub Division draws women and girls from a 2-4 mile radius, a long
distance to carry water. An average of 1,026 individuals benefit from each scheme. Thirty three
thousand beneficiaries have access to 32 completed PHED provided potable water schemes in
Upper and Lower Sub-Divisions.
There are three infiltration galleries, and fifteen schemes that carry water from springs. An
infiltration gallery was added in recent years to supply more water to new areas of Warn Pana,
Ibrahamio and Mirako Bala. Most systems do not have pumps and electricity to raise the water
to the supply points but are gravity fed. At present, only four to five schemes are operating
through electrified pumps.
4.2.6 Climate and Air Quality
4.2.6.1 Meteorology
A Pakistan Meteorological Department (PMD) weather station is located at Kohat, near the
project area. Monthly temperature, humidity, and rainfall data recorded at this station is
provided in Table 4.3. The information is based on mean monthly climatic data for the 30-year
period between 1961 and 1990.
4.2.6.2 Climate
Broadly speaking, the climate of the project area can be described as hot and sub-humid.
Various meteorologists have developed classification schemes to describe the local climatic
features of Pakistan. Shamshad (1998) has classified the climate of Pakistan on the basis of
characteristic seasons found in the country. Taking into account topography, proximity to the
sea, rainfall, temperature, and winds, he has defined 11 climatic zones for Pakistan. Under his
scheme, the project area is classified as ‘Subtropical triple season semiarid submontane areas.’
The characteristic feature of this climatic zone is a double rainy season. The region has two types
of land: lowlands and submontane areas. The lowlands receive small amounts of rainfall
between 254-635 mm, and have a steppe landscape. The submontane areas have two types of
climatic varieties: single rainy season areas and double rainy season areas. The single rainy
season areas are of the usual monsoon type, experiencing little precipitation during winter. The
double rainy season areas experience considerable precipitation during winter as well as during
the monsoon.
4.2.6.3 Temperature
The climate of the district is hot from May to September. June is the hottest month. The mean
maximum and minimum temperatures recorded during June are about 40° C and 27°C,
respectively. A pleasant change in the weather is noted from October till February. The winter is
cold and severe. In winter a strong west wind known as the ‘Hangu Breeze’ often blows down
the Miranzai valley towards the project are for weeks. The mean maximum and minimum
temperatures, recorded during the month of January, are about 18° C and 6° C, respectively.
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 4-25
4.2.6.4 Precipitation
The rainfall is received throughout the year. The monsoon rains last from May to October.
August is the rainiest month, with an average of about 111 mm. The winter rain occurs from
November to April, with the most rain falling in March. The average annual rainfall is about 546
mm. Maximum humidity was recorded in the month of August during the summer season and
in December during the winter season.
Table 4.3: Mean Monthly Temperature, Precipitation, and Relative Humidity Recorded at Kohat Station
Month Mean Temperature(°C) Precipitation
(mm) Relative Humidity
(%) Maximum Minimum
January 17.7 5.6 24.7 52.4
February 19.1 7.8 42.1 52.3
March 23.5 12.3 86.1 53.4
April 29.7 17.7 56.3 46.1
May 35.5 22.6 35.5 35.0
June 40.0 26.8 20.3 33.3
July 37.5 26.8 69.6 52.6
August 35.7 25.8 111.4 60.4
September 35.0 23.3 40.3 51.1
October 30.7 18.3 26.1 44.1
November 24.7 12.1 11.0 46.8
December 19.3 6.8 22.7 54.0
Annual 29.1 17.2 545.8 48.4 Source: Normals for the period 1961-1990 Data Processing Center, Pakistan Meteorological Department, Karachi.
4.2.7 Ambient Air Quality
The ambient air quality in the project area is excellent due to minimal sources of air emissions.
The only source of impact on the quality of the ambient air is the rare vehicular traffic on the
roads, which causes some dust emissions whose effect is quite localized. The main pollutants
from vehicle exhaust are lead, particulate matter, carbon monoxide, sulfur dioxide, and nitrogen
oxides. These emissions temporarily affect the air quality in the immediate vicinity of the roads.
4.2.8 Noise Level
There were no permanent sources of noise recorded in the area except a comparatively rare and
random traffic noise.
4.2.9 Minerals
The geological study of Orakzai and Bajaur Agencies was conducted under the scheme
"Investigation and Large scale Mapping in Mineral Bearing Areas" sponsored by the FATA
Development Corporation in October 1976. The study resulted in the discovery of coal, alum,
and phosphate and iron ore. Iron is scattered throughout the Range in fairly sizeable deposits.
The known mineral profile of both agencies is shown in Table 4.4.
Table 4.4: Annually Minerals Extracted from the FATA Region
S. No. Mineral Unit FATA Bajaur Agency Orakzai Agency
1 Barite Tons 10 - -
2 Chromites Tons 66,381 350 -
3 Coal Tons 266,490
141,160
4 Fluorite Tons 892 - -
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 4-26
S. No. Mineral Unit FATA Bajaur Agency Orakzai Agency
5 Limestone Tons 1,461,859 2,686 -
6 Manganese Tons - - -
7 Marble Tons 818,987 30,398 -
8 Mecu Tons 34,935 1 -
9 Quartz Tons 1,760 - -
10 Scrap Marble Tons 3,405 20 -
11 Soapstone Tons 16,600 526 - Source: SBF Mainstreaming FATA, 2009
4.2.10 Physical Cultural Heritage
During survey no site of physical cultural heritage could be seen along the route of the project
road. But in case there is a chance find during excavation for road construction, there are laws
and procedures to handle the find(s).
4.3 Biological Environment
4.3.1 Habitat Types
Based on the geomorphology and floral attributes, the following habitats have been identified in
the project area:
Mountain/hill slopes
Riparian areas
Stream-beds
Stony plains
Agricultural land
4.3.1.1 Mountain/hill Slopes
Most of the lower region is composed of the mountain and hill slopes habitat. Common plant
species found in such habitats are Beri (Zizyphus nummularia), Gandeer (Rhazia sricta),
Shapyanga (Withania coagulanse), Fagonia sp., Sargara (Cymbopogon jwarancusa), Aristida sp.,
and Surmal (Cenchrus ciliaris). The habitat can be characterized into three types:
Slopes composed of Kans grass (Saccharum spontanium), Sargara (Cymbopogon), and
(Chrysopogan sp.) communities.
Hills with a sparse covering of Phulai (Acacia modesta), Gurgura (Monotheca buxifolia),
along with Mesquite (Prosopis juliflora) and Honey Mesquite (Prosopis glandulosa) trees.
Lush green forest dominated by Gurgura (Monotheca buxifolia), Phulai (Acacia
modesta), Spora mollis, Baza (Adhatoda vesica), and Sanatha (Dodonaea viscose).
The overall condition of the vegetation in the communities residing in the vicinity of
mountain/hill slopes is less degraded, and good forage is readily available.
4.3.1.2 Riparian Areas
This habitat is found in lowland plains along the banks of rivers and large streams. The plant
community is dominated by Bulrush (Typha doninanse), Rushes (Juncus sp.), Athel pine (Tamarix
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 4-27
aphylla), Jujube (Ziziphus muritiana), and Weeds (Pteropyrum sp.) It is the most productive
habitat because of moisture availability and good vegetation cover.
4.3.1.3 Streambed
The ‘streambed’ habitat refers to the dry streambeds distributed throughout the areas that are
flooded seasonally. Though low in productivity, the plant community composition is more
diverse than that of riparian habitat. The dominant plant species in this habitat are Kans grass
(Saccharum spontanium), Ber (Zizyphus nummularia), Gandeer (Rhazya stricta), Barayin
(Periploca aphylla), Sanatha (Dadonea viscose), and Phulai (Acacia modesta). The
grazing/browsing pressure in these areas is comparatively high.
4.3.1.4 Stony Plains
This habitat is found in between agricultural lands and extends to the base of mountains and
hills. The area is stony with very sparse vegetation, low vegetation cover, and the lowest species
diversity. The common, dominant species are Ber (Zizyphus nummularia), Saxaul (Haloxylon sp.),
and Karer (Capparis deciduas), along with some grass species, such as Octhocloa compressa,
scutch grass (Cynodan dactylon), and Bluestem (Dicanthium sp.).
4.3.1.5 Agricultural Areas
Approximately 20-30% of the project area is agricultural. The agriculture mainly depends upon
rains, but irrigation facilities such as water channels are available in some areas. The natural
flora has been completely replaced by cultivated species in this area. Along the edge of these
agricultural fields, Kikar (Acacia nilotica), Lachi (Euclyptu camaldanus), Athel pine (Tamarix
aphylla), Peelo (Salvadora oleoides), and Karer (Capparis deciduas) trees, along with calotrope
(Calatropis prorera), Shapyanga (Withania coagulanse), Wild rue (Poganum harmala), Sage
(Salvia sp.), Aster (Parthenium sp.), Dandelion (Traxicum sp.), Black nightshade (Solanum
nigrum), and Yellow-Berried Nightshade (Solanum surratanse). The agricultural areas were not
sampled during this study.
4.3.2 Fauna
In the past, the FATA was known for its rich diversity of wildlife, which was in part attributed to
the relatively sparse population levels and distribution in the area. In recent times, however,
largely as a result of increasing population levels, including a sudden influx of Afghan refugees, a
decline in forest cover was noted, with concomitant decreases in associated wildlife
populations29. The area has some population of wolves and wild cats, the former in the plains,
the latter in the mountainous tracts. Though no accurate estimates about population is available
but fair number of jackals and foxes are also found in the area. There are also sparse Wild pig are
found in the valleys. Table 4.5 presents the animal diversity in the project area.
Snakes are not numerous, and scorpions and most of the reptiles and insects common to the
other regions of Pakistan are found here also. Locusts, though not uncommon visitants, are less
destructive than in the other regions of Pakistan.
29
ADB (2005) Summary Initial Environmental Examination, Federally Administered Tribal Areas Rural Development Project In Pakistan
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 4-28
The mountainous region of Fata still has fair population of wildlife, including some rare species
like leopard, wolf and bird species, which due to non-enforcement of Wildlife Protection Act in
the tribal area are nearing extinction. The area has limited population of pheasants like,
Himalayan Monal (Lophophorus impeyanus), Koklass (Pucrasia macrolopha), and Cheer (Catreus
wallichii). These pheasant species are also either threatened or vulnerable due to habitat
disturbances.
Table 4.5: Fauna of Tribal Areas of Pakistan
No. Common Name Species General
Type National Status
1 Nilgai or Blue Bull Boselaphus tragocamelus
Artiodactyla Endangered
2 Ladakh Urial Ovis vignei vignei Artiodactyla Endangered
3 Bharal or Blue Sheep Pseudois nayaur Artiodactyla Endangered
4 Wild Pig or Indian Wild Boar Sus Scrofa Artiodactyla Least Concern
5 Asiatic Jackal Canis aureus Carnivora Near Threatened
6 Wolf Canis lupus pallipes Carnivora Endangered
7 Jungle Cat Felis chaus Carnivora Least Concern
8 Indian Desert Wild Cat or Asiatic Steppe Wild Cat
Felis silvestris Carnivora Data Deficient
9 India Grey Mongoose or Common India Mongoose
Herpestes edwardsii Carnivora Least Concern
10 Striped Hyaena Hyaena hyaena Carnivora Critically Endangered
11 Smooth-coated Otter or Indian Otter Lutrogale perspicillata Carnivora Near Threatened
12 Yellow throated Marten Martes flavigula Carnivora Data Deficient
13 Panther or Leopard Panthera pardus Carnivora Critically Endangered
14 Asiatic Black Bear or Himalayan Black Bear
Ursus thibetanus thibetanus
Carnivora Vulnerable
15 Marbled Polecat Vormela peregusna Carnivora Least Concern
16 Common Red Fox Vulpes vulpes Carnivora Near Threatened
17 Asian or Eastern Barbastelle Barbastella leucomelas Chiroptera Data Deficient
18 Dark Whiskered Bat Myotis muricola Chiroptera Least Concern
19 Whiskered Bat (extra-limital) Myotis mystacinus Chiroptera Vulnerable
20 Leisler's Noctule or Hairy-armed Bat Nyctalus leisleri Chiroptera Endangered
21 Mountain Noctule Nyctalus montanus Chiroptera Near Threatened
22 Indian Pipistrelle Pipistrellus coromandra Chiroptera Least Concern
23 Himalayan Pipistrelle Pipistrellus javanicus Chiroptera Least Concern
24 Least Pipistrelle Pipistrellus tenuis Chiroptera Least Concern
25 Greater Horseshoe Bat Rhinolophus ferrumequinum
Chiroptera Vulnerable
26 Lesser Horseshoe Bat Rhinolophus hipposideros
Chiroptera Vulnerable
27 Larger Rat-railed Bat or Mouse-tailed Bat
Rhinopoma microphyllum
Chiroptera Least Concern
28 Fulvous Fruit Bat Rousettus leschenaultii Chiroptera Least Concern
29 Common Yellow-bellied Bat or Desert scotophil Bat
CSCotophilus heathii Chiroptera Least Concern
30 Pale Grey Shrew Crocidura pergrisea Insectivora Least Concern
31 Asiatic White-toothed Shrew Crocidura pullata Insectivora Least Concern
32 Asiatic Pygmy Shrew Sorex thibetanus Insectivora Near Threatened
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 4-29
No. Common Name Species General
Type National Status
33 Savi's Pygmy Shrew Suncus etruscus Insectivora Least Concern
34 House Shrew or Musk Shrew Suncus murinus Insectivora Least Concern
35 Indian Hare or Black-naped Hare Lepus nigricollis Lagomorpha Least Concern
36 Indian Pangolin or Scaly Anteater Manis crassicaudata Pholidota Vulnerable
37 Royle's High Mountain Vole Alticola roylei Rodentia Least Concern
38 Field Mouse Apodemus pallipes Rodentia Data Deficient
39 Mouse-like Hamster Calomyscus bailwardi Rodentia Least Concern
40 Migratory Hamster or Grey Hamster Cricetulus migratorius Rodentia Least Concern
41 Northern Palm Squirrel or Five-striped Palm Squirrel
Funambulus pennantii Rodentia Least Concern
42 Small Kashmir Flying Squirrel Hylopetes fimbriatus Rodentia Vulnerable
43 Indian Crested Porcupine Hystrix indica Rodentia Near Threatened
44 Little Indian Field Mouse Mus booduga Rodentia Least Concern
45 House Mouse Mus musculus Rodentia Least Concern
46 Roof Rat or House Rat Rattus rattus Rodentia Least Concern
47 Turkestan Rat Rattus turkestanicus Rodentia Least Concern
48 Indian Gerbil or Antelope Rat Tatera indica Rodentia Least Concern
49 Ardea cinerea Grey Heron Crane/Egret No Data
50 Mesophoyx intermedia Intermediate Egret Crane/Egret No Data
51 Egretta garzetta Little Egret Crane/Egret No Data
52 Grus grus Common Crane Crane/Egret No Data
53 Anthropoides virgo Demoiselle Crane Crane/Egret No Data
54 Melanoperdix niger Black Partridge Pheasant No Data
55 Perdix perdix Grey Partridge Pheasant No Data
56 Alectoris chukar Chukar Partridge Pheasant No Data
57 Ammoperdix griseogularis See-see Partridge Pheasant No Data
58 Lophophorus impeyanus Himalayan Monal Pheasant No Data
59 Pucrasia macrolopha Koklass Pheasant No Data
60 Catreus wallichii Cheer Pheasant No Data
61 Pycnonotus leucogenys Himalayan Bulbul Bird No Data Source: CAMP, IUCN (2003) Status and Red List of Pakistan’s Mammals Iftikhar uz Zamana (2008) Conservation of Pheasants in North West Frontier Province (NWFP), Pakistan.
4.3.3 Flora
The project area is located in the dry subtropical temperate semi-evergreen scrub vegetation
area of Pakistan (Roberts 1991). Scientific literature regarding floral diversity of this area is
limited, Table 4.6 presents the major flora of the area. The detailed list of the fauna found in the
area is attached as annexure.
Table 4.6: Common Flora in FATA
Common Names Botanical Name Habitat
Phulai Acacia modesta Mountain/hill slopes and dry streambeds
Kikar Acacia nilotica Agricultural areas
Baza Adhatoda vesica Mountain and hill slopes habitat
- Aristida sp. Mountain and hill slopes habitat
- Calatropis prorera Agricultural areas
Caper tree, Leafless caper bush, Kira, Karir, Dela, Kreeta, Karer
Capparis decidua Habitat extends from agricultural areas to the base of mountains and hills
Surmal Cenchrus ciliaris Mountain and hill slopes habitat
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 4-30
Common Names Botanical Name Habitat
- Chrysopogan sp. Mountain and hill slopes habitat
Sebestan plum, Clammy cherry, Lasuri, Lasora
Cordia dichotoma A polygamo-dioecious tree.
Sebestan plum, Clammy cherry, Lasora
Cordia myxa A polygamo-dioecious tree.
Sargara Cymbopogon jwarancusa
Mountain and hill slopes habitat
scutch grass Cynodan dactylon Stony Plain habitat between agricultural lands and extends to the base of mountains and hills
Sanatha Dadonea viscose Dry streambeds
Bluestem Dicanthium sp. Stony Plain habitat between agricultural lands and extends to the base of mountains and hills
- Dodonaea viscose Mountain and hill slopes habitat
Lachi Euclyptu camaldanus
Agricultural areas
- Fagonia sp. Mountain and hill slopes habitat
White spurry, Anzirai, Gunghi Grewia tenax Small, depressed shrub, found in and semiarid plains and hills arid.
Saxaul Haloxylon sp. Stony Plain habitat between agricultural lands and extends to the base of mountains and hills
Rushes Juncus sp. Riparian areas, lowland plains along the banks of rivers and large streams
Gurgura Monotheca buxifolia
Small shrub found in hilly area
Dwarf palm, Mazri palm, Patha, Mazri, Mazairay
Nannorrhops ritchiana
Perennial, gregarious, usually small tufted palm, found in sandy hilly areas.
Indian lotus, Kanwal, Behi Nelumbo nucifera Perennial submerged herb.
- Octhocloa compressa
Stony Plain habitat between agricultural lands and extends to the base of mountains and hills
Aster Parthenium sp. Agricultural areas
Weeds Periploca aphylla Dry streambeds
Karer Poganum harmala
Agricultural areas
Honey Mesquite Prosopis glandulosa
Mountain and hill slopes habitat
Mesquite Prosopis juliflora Mountain and hill slopes habitat
Weeds Pteropyrum sp Riparian areas, lowland plains along the banks of rivers and large streams
Gandeer Rhazya stricta Dry streambeds and mountain/hill slopes habitat
Kans grass Saccharum spontanium
Mountain and hill slopes habitat
Tooth brush tree, Jhal, Khabbar, Pilu, Peelo
Salvadora oleoides
Shrub or small tree found in rocky slopes and sandy area.
Tooth brush tree, Jhal, Plaman, Pilu
Salvadora persica Shrub or small tree found in rocky slopes and sandy area.
Sage Salvia sp. Agricultural areas
Black nightshade Solanum nigrum Agricultural areas
Yellow-Berried Nightshade Solanum surratanse
Agricultural areas
- Spora mollis Mountain and hill slopes habitat
Athel pine Tamarix aphylla Riparian areas and agricultural areas, lowland plains along the banks of rivers and large streams
Dandelion Traxicum sp. Agricultural areas
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 4-31
Common Names Botanical Name Habitat
Bulrush Typha doninanse Riparian areas, lowland plains along the banks of rivers and large streams
Shapyanga Withania coagulanse
Habitat extends from mountain/hill slopes to agricultural areas
Indian jujube, Ber, Bera Zizyphus mauritiana
Cultivated and self sown throughout the area in arid and semi-arid area.
Jher, Beri, Karkanra Zizyphus numularia
Shrub or small tree found in arid and semi-arid region usually in hilly area.
Source: H. Ahmad, S. Khan, A. Khan and M. Hamayun (2003) Ethnobotanical Resources of Manikhel Forests, Orakzai Tirah, Pakistan S. K. Marwat, Fazal-ur-Rehman, K. Usman, A. A. Khakwani, S. Ghulam, N. Anwar, M. Sadiq and S. J. Khan (2011) Medico-ethnobotanical studies of edible wild fruit plants species from the flora of north western Pakistan
4.3.4 Protected Areas
There are no protected areas, along the project road, and in the FATA regions as per list of
protected area defined in National Conservation Strategy.
4.3.5 Endangered Species
The project area does not have any endangered, threatened, or vulnerable species. Withania
samnifera and Aerva pseudotomentosa are available but these cannot be regarded as rare,
because they are frequently observed at different locations in the area.
4.3.6 Forest
Of the total 25.0% of the land in the project area is cultivated. Natural forest cover amounts to
approximately 1.0% of the total area (Bajaur has 8.76% reported forest cover and Orakzai has
3.25%). The proposed route for each section of the road has been aligned on the existing tracks,
field surveys and satellite imagery show that none of the proposed alignments will affect the
forest cover in the area and no natural forest is expected to be removed during the construction
of these road sections.
Table 4.7: Land Use and Forest Area in FATA and Project Agencies
Type Unit FATA Bajaur Orakzai
Area Sq. Km 27,220 1,290 1,538
Cultivable Area 1000 hectares 390.17 86.29 19.76
Irrigated Area 1000 hectares 83.24 19.92 2.21
Forest Area 1000 hectares 43.18 11.3 5
Irrigated Area as % of Cultivated % 38.5 26.52 13.55
Forest Area as % of Reported Area, % 1.59 8.76 3.25
Land Use Intensity % 55.14 87.03 82.54 Source: SBF Mainstreaming FATA, 2009
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 4-32
4.4 Social Environment
This section presents a description of the socioeconomic characteristics of the project area, and
where available utilizes national and regional level data for providing a more cogent
understanding of the context. This social baseline analysis is based on:
primary data collected by conducting a systematic settlement survey targeting the
project area in the Bajaur and Orakzai Agencies to supplement the available surveys and
studies; and
Secondary data collated from previously published literature as well as national and
regional data.
The settlement survey was carried out over a period of ten days by two teams comprising a total
of four members. The methodology for the collection of primary data consisted of focus group
discussions and semi-structured interviews in the villages listed below, geared to provide
detailed qualitative social data. The villages included in Table 4.8 are seen as those villages that
will be directly affected by the project activities.
Focus group discussions and semi-structured interviews were chosen as the methodology in
order to, provide detailed information rapidly; to provide information on the many non-
measurable issues (for example, access to natural resources or the structure of social
institutions); and to ensure a more inclusive, participatory approach than what would have been
possible with individual questionnaires.
The Secondary data pertaining to the project area was drawn chiefly from the following sources :
Post-Crisis Needs Assessment (PCNA) KP & FATA, 2010
FATA Sustainable Development Plan (2006-2015)
Shaheed Bhutto Foundation FATA Figures
FATA Multiple Indicator Cluster Survey (MICS FATA), 2009
Rapid Needs Assessment Report of FATA, 2007
Table 4.8: Villages/Settlements in the Project Area
Bajaur Agency Orakzai Agency
Soorbat Kali Dop Sana
Pataselay Largi Tan
Landay Sharo Doghal
Tarry Dargi
Islam Dehrai Shamim Jan Kali
Khayathy Otti Kali
Bandegi Palosia
Kulala Mama Masai, Amber Khel & Hindikali
Brado Sam, Lalpura & Twekali
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 4-33
Although every effort has been made to accurately present the socio-economic situation in the
project area, due to the unavailability of written records for most of the visited settlements,
demographic information is based on figures provided by the local representatives and therefore
may have a minor level of inaccuracy. Similarly, in several sections of the baseline, it is difficult to
describe longer-term trends due to the absence of a detailed social baseline of the project area
prior to the commencement of this ESIA study. Wherever any trends are presented, they have
been extrapolated for the area from statistical data collected by the government or other
secondary sources.
4.4.1 Social Setting
The project area is located in two agencies of the Federally Administered Tribal Areas of
Pakistan, namely the Bajaur Agency and the Orakzai Agency. In terms of ethnicity, clans, tribes
and socio-economic pattern the project area is diverse, but linguistically the area is almost
completely dominated by Pashto. General social pattern of the villages are almost the same with
little variance in the villages that have a mixed population. The social pattern of the villages is
intimately linked with the geography and environment of the area.
Bajaur was declared a Federally Administered Tribal Agency in December 1973. Prior to 1960,
Bajaur almost remained a semi-independent territory and was being treated as an inaccessible
area under the Political jurisdiction of the Political Agent, Malakand. The whole area was divided
among various Khans, i.e. the Khan of Khar, the Khan of Nawagai and the Khan of Pashat etc. In
1960, Bajaur was declared as a subdivision of Malakand Agency and an Assistant Political Agent
was appointed with his headquarter at Munda in the Dir district. The agency is divided into
seven Tehsils, namely Barang, Nawagai, Khar, Mamund, Salarzai, Utmankhel and Chamarkand.
The dominant tribe of Bajaur Agency is the Salarzai branch of the Tarkalanri tribe, which is
further sub-divided into different clans. The ruling family of Ibrahim Khel and Bram Khel (Khan
Khel) belongs to the Salarzai tribe. Most of the land in Khar, Jar, Raghagan, Lossum, Pashat and
Babukara areas still belongs to these Khans.
The Orakzai Agency, which takes its name from the Orakzai tribe that inhabits the area, was
established as an agency in December 1973. The Orakzai Agency is the second smallest agency of
FATA after Bajaur. The whole of the territory of Orakzai is a mountainous tract dissected by
numerous dry water courses. The two major perennial water streams are the Mastura and
Khanki Toi both of which originate in the hills to the West and run to the East. There are two
tribes in the agency, the Orakzai and the Daulatzai. The agency has two main Islamic sects Sunni
and Shia. Lower Orakzai Tehsil is mixture of both sects. The other three Tehsils Upper Tehsil,
Ismailzai Tehsil and Central Tehsil are entirely Sunni.
4.4.2 Population
According to the 1998 Population Census population of FATA was around 3.2 million. Currently
the population of FATA is projected around 3.9 million, with a population density of 141 persons
per square kilometer. The project focuses on the Bajaur and Orakzai agencies having a
respective population of 865,560 and 272,990. The gender distribution of the FATA region is 52%
males and 48% females. In the national population census carried out in 1998, only the male
population was counted, resulting in an unavailability of data on different age groups and
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 4-34
females in the population. For the purpose of this study, this particular data was extrapolated
from the demographics of the Khyber Pakhtunkhwa province of Pakistan.
The primary data collected in the project settlements is quite close to the available population
data for the region, with minor variations in the small settlements. The family size (persons per
household) in Bajaur is 8.3 whereas in the project areas it is about 8.9 and in Orakzai is 10.3 with
the project area data presenting 11.9 persons per household. Table 4.9 presents population and
household details in the project area and the region.
Table 4.9: Population Data for Bajaur and Orakzai
Area/Settlement Number of Households
Population Persons per Household
% Male Population
% Female Population
Bajaur Agency Settlements
Soorbat Kali 60 680 11.33 52.94 47.06
Pataselay 200 1,600 8.00 51.38 48.63
Landay 50 470 9.40 51.91 48.09
Tarry 305 2,400 7.87 49.38 50.63
Islam Dehrai 125 1,150 9.20 54.35 45.65
Khayathy 980 9,600 9.80 52.55 47.45
Bandegi 310 2,250 7.26 50.89 49.11
Kulala 1,200 10,500 8.75 52.86 47.14
Project Area Total 3,230 28,650 8.87 52.27 47.73
Bajaur Agency Total* 104,592 865,560 8.28 51.26 48.74
-
Orakzai Agency Settlements
Dop Sana 110 1,560 14.18 49.36 50.64
Largi Tan 150 2,550 17.00 50.86 49.14
Sharo Doghal 40 510 12.75 53.92 46.08
Dargi 220 2,350 10.68 50.85 49.15
Shamim Jan Kali 30 280 9.33 48.93 51.07
Otti Kali 90 1,300 14.44 49.23 50.77
Palosia 380 4,250 11.18 52.35 47.65
Mama Masai, Amber Khel & Hindikali
295 2,560 8.68 50.86 49.14
Brado Sam, Lalpura & Twekali
170 2,250 13.24 50.53 49.47
Project Area Total 1,485 17,610 11.86 50.98 49.02
Orakzai Agency Total* 26,572 272,986 10.27 50.02 49.98
-
FATA Agency Total** 438,946 3,846,188 8.76 52.01 47.99 * Source: FATA Multiple Indicator Cluster Survey (MICS FATA), 2009 ** Source: Shaheed Bhutto Foundation FATA Figures
The region as a whole has a young population, with children (under 15 years) accounting for
almost 44 % of the population and older persons (65+) accounting for only 2.6 percent of the
population. This trend is reflected in the project area, with approximately half of village
populations falling under 16 years of age. Detailed age distribution in the project area is given in
Table 4.10.
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 4-35
Table 4.10: Age/Gender Distribution in the Project Area
Area/Settlement Total
Population
Children below 15 years (%)
Active population
15–64 years (%)
Aged population 65–above
(%)
Male Population
(%)
Female Population
(%)
Bajaur Agency Settlements
Soorbat Kali 680 44.12 49.26 6.62 50.74 49.26
Pataselay 1,600 51.13 46.69 2.19 50.13 49.88
Landay 470 41.06 50.85 8.09 49.36 50.64
Tarry 2,400 49.79 49.17 1.04 48.96 51.04
Islam Dehrai 1,150 59.13 38.26 2.61 52.61 47.39
Khayathy 9,600 44.27 54.27 1.46 52.60 47.40
Bandegi 2,250 46.67 49.78 3.56 49.33 50.67
Kulala 10,500 48.86 47.43 3.71 52.00 48.00
Project Area Total 28,650 47.53 49.74 2.73 51.58 48.42
Bajaur Agency Total*
865,560 42.00 55.70 2.40 51.26 48.74
-
Orakzai Agency Settlements
Dop Sana 1,560 46.15 48.08 5.77 50.32 49.68
Largi Tan 2,550 51.57 44.00 4.43 49.22 50.78
Sharo Doghal 510 47.06 47.45 5.49 50.39 49.61
Dargi 2,350 51.06 45.53 3.40 48.94 51.06
Shamim Jan Kali 280 56.43 39.64 3.93 48.93 51.07
Otti Kali 1,300 53.46 41.54 5.00 49.23 50.77
Palosia 4,250 49.84 48.52 1.65 51.76 48.24
Mama Masai, Amber Khel & Hindikali
2,560 44.92 50.39 4.69 50.86 49.14
Brado Sam, Lalpura & Twekali
2,250 45.02 49.20 5.78 50.53 49.47
Project Area Total 17,610 48.89 47.10 4.01 50.33 49.67
Orakzai Agency Total*
272,986 44.70 52.90 2.70 50.02 49.98
-
FATA Agency Total**
3,846,188 43.40 54.00 2.60 52.01 47.99
* Source: FATA Multiple Indicator Cluster Survey (MICS FATA), 2009 **Source: Shaheed Bhutto Foundation FATA Figures
4.4.3 Community/Social Structure
Tribes or clans, such as Salarzai, Mamund, Chamarkand, Charmang and Nawagai in Bajaur
Agency and Bosti Khel, Sherakki, Tor Saparis and Zarghun Khels in the Orakzai Agency, define
major identity markers in the FATA region. Within the tribes there are several sub-divisions in
the form of sub-clans and families. Most of the settlements alongside the project area replicate
the social pattern prevalent in the agencies. The population in the project area lives under a
strict and established tribal system. In the tribal and traditional society the females are usually
under reported, especially the names of females are not mentioned by respondents to male
surveyors / enumerators. Also, the tribals are generally reluctant to register the new born
female babies because of the tribal tradition. Even for the overall population, there is no proper
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 4-36
system of keeping records of birth and death rate at district level especially in rural areas. The
tribes/clans according to the survey are presented as Table 4.11 and 4.12.
Table 4.11: Major Tribes/Clans in Bajaur Agency Project Area
Area/Settlement Total
Population Iman Khel
(%) Miangan
(%) Sahibzadagan
(%) Salarzai
(%) Mamund
(%)
Bajaur Agency Settlements
Soorbat Kali 680 50.00 30.00 20.00 0.00 0.00
Pataselay 1,600 70.00 0.00 0.00 30.00 0.00
Landay 470 40.00 0.00 0.00 35.00 25.00
Tarry 2,400 60.00 0.00 0.00 30.00 10.00
Islam Dehrai 1,150 80.00 0.00 0.00 5.00 15.00
Khayathy 9,600 70.00 0.00 0.00 25.00 5.00
Bandegi 2,250 60.00 0.00 0.00 40.00 0.00
Kulala 10,500 70.00 0.00 0.00 20.00 10.00
Project Area Total
28,650 67.81 0.71 0.47 23.81 7.19
Table 4.12: Major Tribes/Clans in Orakzai Agency Project Area
Area/Settlement Total
Population Syed (%)
Abdulaziz Khel (%)
Hwedat Khel (%)
Mani Khel (%)
Saparis (%)
Orakzai Agency Settlements
Dop Sana 1,560 15.00 30.00 55.00 0.00 0.00
Largi Tan 2,550 10.00 0.00 55.00 35.00 0.00
Sharo Doghal 510 0.00 0.00 100.00 0.00 0.00
Dargi 2,350 0.00 0.00 100.00 0.00 0.00
Shamim Jan Kali 280 35.00 0.00 55.00 0.00 10.00
Otti Kali 1,300 0.00 10.00 30.00 0.00 60.00
Palosia 4,250 15.00 0.00 0.00 0.00 85.00
Mama Masai, Amber Khel & Hindikali
2,560 0.00 0.00 0.00 0.00 100.00
Brado Sam, Lalpura & Twekali
2,250 0.00 0.00 0.00 0.00 100.00
Project Area Total 17,610 6.95 3.40 32.17 5.07 52.42
Most of populations in the project live in a close-knit joint family that is rather extended. The
underlying factor for this is mainly poverty, close family marriages, tribal homogeneity and
kinship. As discussed earlier the household size in the project areas ranges from 8 to 11 persons,
with an overall FATA average of 8.8 persons per family.
4.4.4 Poverty Status
In terms of economic activity, the region is generally very poor. Traditionally the local people
managed to survive in this harsh terrain by utilizing the available resources, as meager as they
may be, in a very calculated way maintaining equilibrium with nature. However, with the
increased interface of the region with the outside world, an increase in population that
coincided with decreasing landholding has put strains on the local resources. As a result, in the
project area and the region at large, some people have opted for new professions like mining
and service in the armed forces for alternate source of income, but very limited livelihood base
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 4-37
has thwarted upward mobility of the people. In addition, youth form a bulk of the total
population but a severe lack of facilities for education hinders the efforts of the local youth to
enter into a more diverse job market outside of the Bajaur and Orakzai agencies. There is high
unemployment and nominal initiatives are set in place from the government side for the
economic uplift of the people in project area. As a corollary, poverty is rampant in the villages of
the project area. Main causes for the economic disparity of the region as compared to the rural
areas of KP and Punjab are as follows:
A significant proportion of population is practicing agriculture on highly limited
agricultural land that is mainly rain-fed.
In general due to lack of opportunities and literacy, the rate of unemployment is high.
Absence of major industries and under developed agriculture and livestock sectors do
not form a potential for labor absorption. As a result, the project is expected to have a
healthy effect on the labor and employment market of the project area.
Table 4.13: Income and Landholding in the Project Area
Area/Settlement Total
Households
Per Household Annual Income
(Rs.)
Total Population
Per Capital Annual
Income (Rs.)
Cultivable Land per Household
(kanals)
Bajaur Agency Settlements
Soorbat Kali 60 154,281 680 13,613 33.33
Pataselay 200 91,135 1,600 11,392 15.20
Landay 50 155,407 470 16,533 38.40
Tarry 305 79,854 2,400 10,148 17.05
Islam Dehrai 125 100,785 1,150 10,955 13.44
Khayathy 980 102,684 9,600 10,482 15.35
Bandegi 310 79,417 2,250 10,942 17.55
Kulala 1,200 64,986 10,500 7,427 11.00
Project Area Total 3,230 85,276 28,650 9,614 14.71
-
Orakzai Agency Settlements
Dop Sana 110 95,607 1,560 6,742 13.09
Largi Tan 150 110,827 2,550 6,519 13.87
Sharo Doghal 40 155,894 510 12,227 18.00
Dargi 220 62,623 2,350 5,863 10.18
Shamim Jan Kali 30 113,467 280 12,157 12.00
Otti Kali 90 129,069 1,300 8,936 11.56
Palosia 380 111,414 4,250 9,962 10.95
Mama Masai, Amber Khel & Hindikali
295 88,063 2,560 10,148 9.76
Brado Sam, Lalpura & Twekali
170 132,799 2,250 10,034 14.59
Project Area Total 1,485 103,074 17,610 8,692 11.72
4.4.5 Industries and Livelihoods
Majority of people in the project area are unemployed. More than 80% of population is still
engaged with sustenance agriculture. A small fraction of population is serving in government,
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 4-38
whereas a very small number of persons are engaged in entrepreneurship and employment in
the private sector. Employment and unemployment in the project area is reflected in Table 4.14.
There are no significant industries along the project road. More settled conditions are required
for encouraging more industrial development in the region. Majority of people in the project
area are engaged with agriculture and livestock, but it is mostly for sustenance purpose not for
commercial. The commercial potential of agriculture is stymied by diminishing landholdings as
villages now have more people whereas the available land remains the same. Furthermore,
individual landholdings are getting smaller and smaller due to the practiced custom of land being
divided amongst the children as inheritance upon the death of the father. This has forced people
to opt for other professions such as government and non-government jobs, individual businesses
and working in mainland Pakistan or overseas. Generally, unemployment is very high in the
project area. Even sustenance agriculture cannot provide enough yields for the whole year. As
majority of people in the project area are not widely educated they migrate to nearby areas in
search of odd jobs or any kind of labor. Government services are a cherished source of livelihood
for many. Agricultural farming, micro-level entrepreneurial activities and working on daily wage
basis are also major sources employment in the agency.
Table 4.14: Livelihoods in the Project Area
Sector Area/Settlement
% Engaged in Agriculture, Farming & Livestock Herding
% Employed in Business, Govt., Pvt & Others
Male Female Male Female
Bajaur Agency Settlements
Soorbat Kali 63.64 84.38 25.00 0.00
Pataselay 67.45 75.68 24.51 0.00
Landay 69.26 68.75 27.52 0.00
Tarry 68.21 68.87 22.56 0.00
Islam Dehrai 46.23 85.61 29.81 0.00
Khayathy 87.40 97.71 12.05 0.00
Bandegi 83.41 94.02 15.45 0.00
Kulala 84.60 91.14 8.17 0.00
Project Area Total 81.40 90.10 13.47 0.00
-
Orakzai Agency Settlements
Dop Sana 61.05 82.32 17.44 0.00
Largi Tan 65.09 70.83 16.51 0.00
Sharo Doghal 71.00 72.73 27.50 0.00
Dargi 64.75 65.55 8.33 0.00
Shamim Jan Kali 47.46 78.57 30.51 0.00
Otti Kali 53.00 72.13 17.33 0.00
Palosia 68.49 76.31 17.29 0.00
Mama Masai, Amber Khel & Hindikali
54.56 73.65 15.90 0.00
Brado Sam, Lalpura & Twekali
73.15 78.66 10.90 0.00
Project Area Total 64.22 74.29 15.49 0.00
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 4-39
4.4.6 Education
Though there are schools (nearly all supported by government) in many of the settlements of
the project area, three of the visited settlements in the Orakzai Agency lack any education
facility. The available schools do not adequately address the educational needs of the populace;
particularly for the girls and a major focus area for education should be schools for girls in the
region. The current education scenario is presented in the Table 4.15.
Table 4.15: Education Facilities in the Project Area
Area/Settlement
Primary Schools
Middle Schools High Schools Higher Secondary
Schools
Male Female Male Female Male Female Male Female
Bajaur Agency Settlements
Soorbat Kali 1 2 0 0 0 0 0 0
Pataselay 0 2 1 0 0 0 0 0
Landay 0 1 0 0 0 0 0 0
Tarry 2 1 0 0 0 0 0 0
Islam Dehrai 1 0 0 0 0 0 0 0
Khayathy 3 2 0 0 0 0 0 0
Bandegi 3 2 0 0 0 0 0 0
Kulala 4 2 0 0 0 0 0 0
Project Area Total 14 12 1 0 0 0 0 0
Bajaur Agency Total* 366 165 23 12 22 2 4 1
-
Orakzai Agency Settlements
Dop Sana 1 2 0 0 0 0 0 0
Largi Tan 0 1 0 0 0 0 0 0
Sharo Doghal 0 0 0 1 0 0 0 0
Dargi 1 0 0 1 0 0 0 0
Shamim Jan Kali 0 0 0 0 0 0 0 0
Otti Kali 1 0 0 0 0 0 0 0
Palosia 1 0 0 1 1 0 0 0
Mama Masai, Amber Khel & Hindikali
0 0 0 0 0 0 0 0
Brado Sam, Lalpura & Twekali
0 0 0 0 0 0 0 0
Project Area Total 4 3 0 3 1 0 0 0
Orakzai Agency Total* 226 174 16 10 22 4 2 1
-
FATA Agency Total * 2,628 1,905 287 136 226 32 30 15 * Source: FATA Sustainable Development Plan (2006-2015)
It is evident that the enrollment of girls is a problem that has resulted in an overall female
literacy rate of 3% compared to 29% for the males. Several factors have contributed to the
gender disparity in education. Those factors are related to the special socio-economic conditions
under the tribal setting where males are the main breadwinners. Parents are not investing in
girl’s education on the belief that girls are more productive at home, helping the mothers in
household tasks, collecting fire wood, fetching water, looking after the small brothers and
sisters, livestock grazing etc. Early marriage of girls and the tradition of “purdha” are also major
contributing factors. Table 4.16 provides an overview of the literacy and enrollment in the
region.
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 4-40
Table 4.16: Literacy Rate and Enrollment in the Project Area
Area/Settlement Literacy Ratio (%)
Gross Enrollment up to Primary Level (%)
Male Female Total Male Female Total
Bajaur Agency Settlements
Soorbat Kali - - - 78.57 62.50 70.00
Pataselay - - - 43.90 53.92 48.90
Landay - - - 0.00 96.94 49.22
Tarry - - - 27.50 18.49 23.01
Islam Dehrai - - - 22.22 0.00 11.76
Khayathy - - - 20.71 13.49 17.06
Bandegi - - - 54.72 36.54 45.71
Kulala - - - 44.31 11.24 27.68
Project Area Total - - - 35.22 18.96 27.06
Bajaur Agency Total* 22.32 3.38 13.41 58.77 14.42 36.07
-
Orakzai Agency Settlements
Dop Sana - - - 73.53 55.26 63.89
Largi Tan - - - 0.00 12.12 6.08
Sharo Doghal - - - 0.00 48.00 25.00
Dargi - - - 80.67 0.00 40.00
Shamim Jan Kali - - - 0.00 0.00 0.00
Otti Kali - - - 88.24 0.00 43.17
Palosia - - - 88.95 30.48 59.96
Mama Masai, Amber Khel & Hindikali
- - - 0.00 0.00 0.00
Brado Sam, Lalpura & Twekali - - - 0.00 0.00 0.00
Project Area Total - - - 46.36 15.44 30.78
Orakzai Agency Total* 19.65 1.28 10.63 60.64 30.30 45.04
-
FATA Agency Total* 29.50 3.00 17.40 61.37 29.49 44.83 *Source: Shaheed Bhutto Foundation FATA Figures
4.4.7 Political Parties
There are many political parties in FATA and they try to mobilize political opinion in their favor.
However, tribal affiliation, religion and family kinship are the main factors determining the shape
of political behavior. Important political parties are Jamiat-i-Ulmai–Islam (JUI), Pakistan Muslim
League (PML), Pakistan People’s Party (PPP) and Pakhtoonkhwa Milli Awami Party (PMAP) and
Pakistan Tehreek-e-Insaaf. The role of women in the politics is not significant.
4.4.8 Marriages
In the tribal system of the Bajaur and Orakzai agencies, the society is exceedingly patriarchal.
Marriages are, more often than not, arranged. Due to the practice of consistent segregation of
sexes there is no opportunity for boys or girls to choose their own spouses. The role of women in
decision-making concerning marriage is limited to some influence on selection of the bride for a
male family-member, based on her beauty and aptness in doing household chores. Girls have no
real say in their marriage despite the provision in Islamic Shariat that a woman has a right to
turn down a marriage offer.
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 4-41
4.4.9 Social and Administrative Organization
Majority of the villagers still rely on the traditional tribal system for the resolution of conflicts
and managing the day-to-day affairs in the village. However, there is a limited role of the clergy
in the decision-making process, thereby bringing about a change in the power structure and
relations of the prevalent tribal system. Since most of the people are engaged with agricultural
practices, the tribal system is still relevant to a great extent because the villages were inhabited
under the old pattern of strictly adhered to tribal customs. Every settlement has its own tribal
elder/head or Malik, who is responsible for settling disputes and securing the interest of his
tribe. In the tribal system women do not have any role in the decision-making process. Every
problem of the community is resolved through tribal ‘Jirga’ or the council of tribal elders.
During the survey it was found that people still prefer the tribal Jirga as compared to modern
arbitration methods including the judicial system. The major cause of reliance on the tribal
system is the lack of trust in modern institutions. The Malik system introduced by the British
Govt: was the same in Orakzai and Bajaur Agency as functioning in other agencies of the FATA
region. Traditionally the Maliks have been working as the point of contact between the
administration and the tribe. Maliki is hereditary and devolves on the son and his son so on and
so forth, for which regular benefits and subsidies are sanctioned from time to time. In parallel,
‘Khasadars’ in agencies are another form of appointment within the tribes entrusted with the
protection of strategic roads and other Govt: utilities. They are working under the control of the
‘Political Agent’, and supervise levies ranging in ranks from subedar Major downward up to
sepoy. The Khasadars are appointed by the political Agent. Their recruitment is made in the ratio
of their tribal distribution, which is known as ‘Nikkat’.
Administratively the Political Agent is the overall in charge for the agency administration,
assisted by Assistant Political Agents. In case of Bajaur the agency headquarters is located at
Khar. Administratively, Bajaur Agency comprises of two sub-divisions, namely, Khar sub-division
and Nawagai sub-division under two Assistant Political Agents. Khar sub-division has further
been divided into three Tehsils, namely Khar, Salarzai, and Utmankhel, while Nawagai sub-
division consists of four tehsils, namely Chamarkand, Nawagai, Mamund and Barang. Thus, all
the seven Tehsils in the agency are under the charge of three Political Tehsildars and Political
Naib Tehsildars. In the Orakzai Agency there are two administrative sub-divisions Upper Orakzai
and Lower Orakzai. Each Sub-division consists of two tehsils. The Agency Headquarters is located
at Hangu, which geographically happens to be outside the agency.
Though FATA enjoys representation in the National Assembly of Pakistan, the laws framed by
the National Assembly do not apply in FATA unless so ordered by the President, who is also
empowered to issue regulations for the peace and good government of the tribal areas. Today,
FATA continues to be governed primarily through the Frontier Crimes Regulation (FCR) 1901. The
Governor of the KP administers it in his capacity as an agent to the President of Pakistan, under
the overall supervision of the Ministry of States and Frontier Regions in Islamabad (Khan, 2005).
4.4.10 Religious Beliefs
Almost entire population in the project area of Bajaur and Orakzai Agency are Muslims, in terms
of sect the population in Bajaur project area are 100 percent Sunni of Hanfi school, whereas
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 4-42
entire population of Orakzai project area adhere to Shia Faith. No presence of any other religion
or sect was observed during the survey.
Religious functions are a significant force in the lives of all the people in FATA. Religious leaders
(Mullas) have a hold over a number of aspects of social life and some political parties are
organized along religious lines. Two major festivals observed in the project area are the religious
festivals of ‘Eid-ul-Fitr’ and ‘Eid-ul-Azha’. The people are strongly religious minded and tend to
practice the religious obligations meticulously. They, come what may, offer prayers five times a
day, observe Fasting in the month of Ramadhan and sacrifice animals on Eid-ul-Azha. The
however, do pay Zakat or perform Hajj and Umrah. In addition to Eids the Shia population
Orakzai Agency celebrate religious festivals like Ashura (mainly in the town of Hangu), Yom-e-Ali,
Navroz and Majalis-e-Aza. Most of the cultural festivals and sports are no more celebrated in the
villages of the project area.
4.4.11 Conflict Resolution
There is no major conflict among people on the basis of religion as majority belongs to one sect
in each segment of the project area. Even the relationship between different races, groups,
tribes and families is amicable. The small disputes within the communities are resolved through
the tribal Jirga and arbitration under the supervision of the Maliks.
All conflicts, including civil and criminal cases in FATA are decided under the Frontier Crimes
Regulation 1901 by a Jirga. Residents of the tribal areas may, however, approach the apex courts
(Supreme Court of Pakistan and Peshawar High Court) with a constitutional writ challenging a
decision issued under the 1901 Regulation. During the surveys it was learnt that normally there
are no major conflict within or with adjoined settlements/tribes, but sometimes a dispute
between two individuals, from two tribes, may generate tribal vendetta. Usually in such cases
the Jirga system is considered the only options for resolution of conflicts.
4.4.12 Custom of Carrying Fire Arms
Although the people in the area are inherently peaceful, yet it is customary among the people to
carry arms as a fashion or sign of prestige for tribal elders or notables. Advanced and automatic
weapons like Kalashnikov are preferred. The other reason for displaying arms is illiteracy and
tribal enmity.
Some people consider weapons as ornaments of men. Because of the war in Afghanistan and
influx of Afghan refugees into area, all sorts of weapons are smuggled into the extended project
area and are available at cheap prices.
4.4.13 Role, Position and Status of Women
Status of women is determined by the social pattern that clearly defines the role and
responsibilities of women and men in the different spaces and professions. Majority of the
women are engaged in agricultural activities and household chores. None of the women are
engaged in business or any other service sector job. The area in general is quite conservative,
and there is a clear cut differentiation in the fields where only men or women are allowed to
work.
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 4-43
Women in tribal society for centuries have been victims of patriarchy, male chauvinism, social
discrimination, resource deprivation and denial of basic human rights. Despite constitutional and
legislative provisions, the customary law often prevails making it difficult for women to claim
their legal rights that are supposedly guaranteed. Although Islamic laws of inheritance provide a
share to daughter in father’s property but the local customs do not allow it. However, a person
can bestow gift to his daughter, sister or wife in his lifetime, again treating a woman with no
rights to the property.
In most of the social grouping men hold a monopoly of power in the public arena. In the political
arena, local level chiefs and tribal heads are always men, so are the members of the local council
of elders or Jirga. Religious leaders in authority are all males and men set local codes of value.
This includes denial of basic human rights as well as the inheritance rights to women as
stipulated by Islam.
The economic participation of women is different from that of men. Women participate in both
indoor and outdoor duties that are considered to be a free labor. Women fetch water, collect
fuel wood, look after animals, fetch fodder for cattle, process milk into butter, sour milk and
cheese, and work with wool. They are fully responsible for cooking, cleaning and taking care of
children and other dependent members. Some women are very good at producing handicrafts.
The traditional polygamy keeps them victims of ‘inferiority’ complexes. The family, including the
husband treats the women without children as an outsider.
4.4.14 Migration
All the settlements in the project areas of both Orakzai and Bajaur are tightly knit tribal societies.
There has been no major in and out migration in the villages during last 7 years in the project
area. In the total population of more than 46,000 people, only a combined 25 cases of
households migrating out of the area occurred. These out-migrations took place in both the
Bajaur and Orakzai segments of the project area. The main cause for the leaving the village was
better education for the children and economic opportunities in the urban centers of FATA and
KP (namely to Peshawar and Kohat). In terms of in-migration, many settlements consist of inter-
related families and generally do not allow alien tribes/races to settle in the village. Though the
villagers do tend to migrate seasonally from one location to another but they retain their
ownership in the village.
4.4.15 Housing
Most of the settlements in the project area are small and mid-sized villages with a mix of
concrete/masonry and traditional/mud houses. A typical middle class house in the region has a
guest room, toilet, kitchen, separate bathroom and a courtyard. In newly constructed houses
attached bathroom with flush is an important feature. In rural areas the guest room (called the
hujra) is more spacious than the other rooms and the courtyards are generally very spacious.
Toilets are located at the other end of the courtyard and are usually without any flush system.
Many people of rural area still use fields as open latrines.
The majority of families in the FATA region live in separate houses or part of compounds. Land is
abundant and nonproductive and, therefore, there is no limitation on the occupation of land for
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 4-44
house construction in most areas. Many families construct big compounds with separate houses
for different relatives, mostly for grandsons. On average, 85.8% of households have separate
house/compound, while 11.2% have part of a house or compound.
Figure 4.21: A Typical Dense Settlement in FATA
Figure 4.22: Settlement with Agricultural Land in FATA
There is no tradition of living in apartments and less than one percent of occupants were
observed in flats/apartments in FATA. In urban areas, flats/apartments are becoming popular
due to scarcity of land, with 2.6% of households dwelling in flats/apartments. Many families in
poor communities cannot afford to construct adequate rooms within their house. As a result,
many family members sleep in one room and/ or keep livestock in the same room. This results in
a number of diseases, see Table 4.17 for details.
Table 4.17: Housing Data in the Project Area
Area/Settlement Number of Households
Population Persons per Household
Masonry Houses (%)
Mud/ Traditional Houses (%)
Bajaur Agency Settlements
Soorbat Kali 60 680 11.33 15.00 85.00
Pataselay 200 1,600 8.00 17.50 82.50
Landay 50 470 9.40 10.00 90.00
Tarry 305 2,400 7.87 8.20 91.80
Islam Dehrai 125 1,150 9.20 8.00 92.00
Khayathy 980 9,600 9.80 6.63 93.37
Bandegi 310 2,250 7.26 12.90 87.10
Kulala 1,200 10,500 8.75 12.50 87.50
Project Area Total 3,230 28,650 8.87 10.50 89.50
Bajaur Agency Total* 104,592 865,560 8.28 50.69 49.31
-
Orakzai Agency Settlements
Dop Sana 110 1,560 14.18 13.64 86.36
Largi Tan 150 2,550 17.00 16.67 83.33
Sharo Doghal 40 510 12.75 15.00 85.00
Dargi 220 2,350 10.68 15.91 84.09
Shamim Jan Kali 30 280 9.33 26.67 73.33
Otti Kali 90 1,300 14.44 13.33 86.67
Palosia 380 4,250 11.18 10.53 89.47
Mama Masai, Amber 295 2,560 8.68 8.47 91.53
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 4-45
Area/Settlement Number of Households
Population Persons per Household
Masonry Houses (%)
Mud/ Traditional Houses (%)
Khel & Hindikali
Brado Sam, Lalpura & Twekali
170 2,250 13.24 14.71 85.29
Project Area Total 1,485 17,610 11.86 12.86 87.14
Orakzai Agency Total* 26,572 272,986 10.27 42.80 57.20
-
FATA Agency Total* 438,946 3,846,188 8.76 50.69 49.31 * Source: Rapid Needs Assessment Report of FATA, 2007
4.4.16 Services and Amenities Available in the Area
4.4.16.1 Energy/Power Sources
Where available, electricity is mostly used for lightning, cooking and heating purposes in the
settlements. Electricity is being provided to all the settlements in the project area through the
national grid. Due to the current energy shortfall the Pakistan, FATA is also faced with the energy
crisis. This power shortage forces the villagers to use firewood from adjacent forests and cutting
village trees for heating and cooking purposes. For lighting purposes LPG and kerosene are also
used, but only by the economically stable households. In terms of cost, electricity is the cheapest
power source for the villagers, as the population of FATA does not pay any electricity bills. Forest
wood is also a financial viable alternative for the villages for heating and cooking, as they can get
it free from the village owned forests. But in terms of economic cost an annually average
household consumes about 100 to 150 mounds of wood with an estimated market price of Rs.
400 per mound amounting to Rs. 40,000 to 60,000 per annum. Annually, the project area
consumes about 23,500 metric tons of firewood for household use, most of which is used in
winters for heating and cooking.
4.4.16.2 Telecommunication
In the project area, the network of telecommunication is still lagging behind the national and
regional coverage. In terms of landline telephones and cellular phones, there is a stark contrast
between Bajaur and Orakzai. The project area segment in Bajaur has 100 % mobile coverage,
through private telecom companies, with 12% of the population using cell phones. Whereas in
the Orakzai segment of the project area the mobile coverage is very limited, less than 1 percent
of the population has access to mobile phones. In terms of telephone lines, the project area
segment in Bajaur has no landline connections, whereas the major telecommunication means in
the Orakzai segment is landline telephone with 18.5% of the population having access to the
facility. Table 4.18 provides details regarding the facilities.
4.4.16.3 Radio and Television
Government-owned TV and Radio, Pakistan Television (PTV) and ‘Radio Pakistan’ are available in
parts of the Bajaur and Orakzai agencies. Both TV and radio services are operated from the
Peshawar center. FM wavelength radio services are also available in many parts of the FATA.
Currently no cable networks are available in the areas.
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 4-46
Table 4.18: Services and Amenities Available in the Area
Agency
% Population Access to Facilities
Electricity
Gas Radio TV Telepho
ne Mobile phone
Computer
Internet
Bajaur Project Area Total
100.00 5.30 NA NA 0.00 12.14 NA NA
Bajaur Agency Total*
77.30 2.30 49.20 9.30 10.90 17.20 2.90 1.10
Orakzai Project Area Total
100.00 3.50 NA NA 18.52 0.58 NA NA
Orakzai Agency Total*
68.60 2.50 55.70 14.00 18.30 7.90 1.90 0.50
-
FATA Total* 69.70 2.90 64.10 20.90 18.30 29.60 4.50 1.90
FATA Urban Total*
98.70 15.20 74.80 69.50 45.50 76.10 17.60 8.00
FATA Rural Total*
68.40 2.30 63.60 18.80 17.10 27.60 3.90 1.60
*Source: FATA Multiple Indicator Cluster Survey (MICS FATA), 2009
4.4.17 Transport and Accessibility
FATA has 5399 km of road out of which 3398 km are high type whereas 2001 km are low type,
according to the estimates of 2005. Form the total mentioned above about 674 km long roads
are located in Bajaur and 513 km in Orakzai agency. Construction of roads as part of the
proposed project will not only add more length to the existing road network, but will also aid in
the economic development in the area.
Being situated in a harsh terrain, transport to major towns of the region is quite difficult for the
population of the project area. All the larger villages have their own transport facility, in the
form of pickups and jeeps, with daily services to major towns and urban centers of Kohat, Hangu
and Khar. Compulsory foot walk is a norm at the village level.
Table 4.19: Roads in the FATA Region
Total Roads (Kms) High Type (Kms) Low Type (Kms)
Road per Sq. Km. of Area
Bajaur Agency Total* 673.79 372.05 301.74 0.52
Orakzai Agency Total*
513.32 285.24 228.08 0.33
FATA Total* 5398.72 3398.06 2000.66 0.20 * Source: SBF Mainstreaming FATA, 2009
4.4.18 Health
A major problem in the project area is of health services. For a total population of about 46,200
there are no hospitals. The project area segment located in Bajaur has only 3 basic health units,
2 dispensaries and 1 private clinic for a population of 28,600. In Orakzai the situation is even
worse with just 1 BHU, 1 dispensary and a private clinic for a population of 17,600 people of the
project area. Another significant aspect of the health sector is that many of the facilities are
concentrated in the larger towns that leave the smaller villages without any significant facilities
and trained personal. Additionally the area covered by the project also lack any trained midwives
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 4-47
or health workers, leaving the inhabitants vulnerable and exposed to risk of diseases and
epidemics.
In FATA as a whole, health facilities are totally inadequate in terms of availability and quality.
The state of public social services is even more devastating for women as the lack of
reproductive health facilities endangers the lives of women. However, it has been seen that even
in areas where government has provided infrastructure and staff, the utilization of these
faculties remain low. This is attributable to factors such as a lack of awareness about the
importance of reproductive health care and cultural limitations of female mobility in a tradition
bound area. Often, the rural health centers are located at a distance, necessitating considerable
expense of money or time for a visit making preventive healthcare a luxury which the poor
cannot afford. The coverage of health facilities in the project area is presented as Table 4.20.
Table 4.20: Health Facilities and Coverage in the Project Area
Number of Facilities
Hospital Dispensary R.H.Cs B.H.Us Beds
Bajaur Agency Total* 2 8 2 20 211
Orakzai Agency Total* 3 16 2 25 108
FATA Total* 33 302 8 172 1,654
-
Health Coverage
Pop. Per Bed Doctors Pop. Per Doctor Nurses Pop. Per Nurse
Bajaur Agency Total* 4102 129 6710 22 39343
Orakzai Agency Total* 2527 50 5460 4 68246
FATA Total* 2,325 550 6,993 117 32,873 * Source: SBF Mainstreaming FATA, 2009 & Shaheed Bhutto Foundation FATA Figures
Although the diseases vary from one area to the other and among genders, however, due to lack
of clean drinking water and sanitation facilities, digestive problems, dysentery and respiratory
diseases are very common in the project area. Osteoporosis in women and pneumonia in
children are also quite common pointing to the dietary deficiencies and cold winter
temperatures. Table 4.21 lists the major ailments reported in the project area.
Table 4.21: Major Ailments and Prevalence Reported in the Project Area
Major Ailments Prevalence in Men Prevalence in Women Prevalence in Children
Allergies 6.00 1.41 1.49
Anemia 0.00 8.45 0.00
Blood Pressure 2.00 4.23 0.00
Cancer 4.00 1.41 0.00
Diabetes 6.00 1.41 0.00
Digestive Problems 30.00 14.08 0.00
Dysentery 0.00 0.00 25.37
Heart Diseases 4.00 2.82 0.00
Hepatitis 18.00 7.04 5.97
Kidney Problems 4.00 2.82 0.00
Malaria 6.00 9.86 13.43
Osteoporosis 0.00 22.54 0.00
Pneumonia 0.00 0.00 13.43
Reproductive Diseases 0.00 7.04 0.00
Respiratory Diseases 12.00 12.68 19.40
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 4-48
Major Ailments Prevalence in Men Prevalence in Women Prevalence in Children
Skin Diseases 2.00 2.82 14.93
Tuberculosis 4.00 1.41 0.00
Typhoid 2.00 0.00 5.97
Apart for the common diseases, there are about 129 physical or mentally challenged people in
the project area, the ratio being 3 in every 1000 individuals.
4.4.18.1 Drinking and Domestic Water
Drinking water in FATA is obtained through different sources. Tube wells, hand pumps, wells,
rivers and springs. Tube wells have become the major source of water supply, using plastic pipes.
All the villages in the project area have some source of water for drinking, household use and
irrigation. The population of the project area located in Bajaur depends solely on tube wells for
all the water needs save for some dependence on rain fed agriculture. On the other had the
people in Orakzai area depend on a mix of tube wells, pipelines, water channels and rains fed
streams.
Although not very dominant, but due to lack of proper care drinking water in the project area is
subject to contamination mostly due to sharing with livestock and exposure to dust. This leads to
significant increase in cases of digestive and kidney disorders.
4.4.18.2 Sanitation
The project is located in the rural setting; the overall hygienic conditions and the prevalent
sanitation systems are not satisfactory. In the project area, only 9 % people have covered pit or
flush latrines. Most people in rural areas use open fields for defecation. Women use open
surface latrines within the domestic compound; Younger children are formally allowed to
defecate in the courtyard. The presence of animals within the household compound often add to
the unhealthy living conditions. Sanitation facilities present in the project area are shown in
Table 4.22.
Table 4.22: Sanitation Facilities in the Project Area
Pit latrine
without slab
Flush toilet connected to
pit/septic tank
Flush toilet connected to public
sewerage
Open fields
Total Households
Bajaur Agency Settlements
Soorbat Kali 25.00 15.00 0.00 60.00 60
Pataselay 35.00 15.00 0.00 50.00 200
Landay 35.00 18.00 0.00 47.00 50
Tarry 40.00 10.00 0.00 50.00 305
Islam Dehrai 30.00 10.00 0.00 60.00 125
Khayathy 35.00 5.00 0.00 60.00 980
Bandegi 35.00 12.00 0.00 53.00 310
Kulala 40.00 5.00 0.00 55.00 1,200
Project Area Total 36.95 7.34 0.00 55.71 3,230
Bajaur Agency Total*
44.70 13.60 0.00 41.70 104,592
-
Orakzai Agency Settlements
Dop Sana 5.00 10.00 0.00 85.00 110
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 4-49
Pit latrine
without slab
Flush toilet connected to
pit/septic tank
Flush toilet connected to public
sewerage
Open fields
Total Households
Largi Tan 10.00 5.00 0.00 85.00 150
Sharo Doghal 20.00 5.00 0.00 75.00 40
Dargi 15.00 10.00 0.00 75.00 220
Shamim Jan Kali 10.00 5.00 0.00 85.00 30
Otti Kali 10.00 15.00 0.00 75.00 90
Palosia 35.00 10.00 0.00 55.00 380
Mama Masai, Amber Khel & Hindikali
15.00 10.00 0.00 75.00 295
Brado Sam, Lalpura & Twekali
20.00 10.00 0.00 70.00 170
Project Area Total 19.18 9.56 0.00 71.26 1,485
Orakzai Agency Total*
21.00 8.50 0.80 69.70 26,572
-
FATA Agency Total*
22.60 18.70 1.00 57.70 438,946
* Source: FATA Multiple Indicator Cluster Survey (MICS FATA), 2009
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 5-1
5 Analysis of Alternatives
From the ESIA point of view, the following available alternatives for the FATA ERRP were
considered.
(A) ROAD ALTERNATIVES
1. No project option
2. Project road to follow exactly the existing route with no alteration.
3. Project as proposed in feasibility i.e. double lane with suitable straightening of curves
where necessary.
(B) LOGISTIC SITES
1. Location of Contractor’s facilities e.g. labor campsite, machinery yard and on public land.
2. Location of Contractor’s facilities on private lands.
3. Location of Contractor’s facilities at most appropriate site be it public land or private
land.
(C) LABOR OPTIONS
1. All labor local
2. All labor from outside.
3. An admixture of local and outside labor as per skill required.
An analysis of all above alternatives is as follows:
5.1 Road Alternatives
5.1.1 No Project Option
Analysis
Advantages
If the project is not taken up at all then the MDTF money, efforts and time resource
allocated for the proposed activities will be saved. These resources may become
available for other projects in KP, FATA or Baluchistan that may not address the needs of
the people of Bajaur and Orakzai. No land will be required and no disturbance will be
caused to people through the land acquisition and resettlement processes.
Furthermore, the recurring cost of the maintenance of the new roads along with the
operational cost will be saved. No disturbance will be caused to any physical, biological
and social part of the environment. The status quo will remain and no benefit or
negative impact will be experienced by the communities of the project locations.
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 5-2
Disadvantages
Not taking up the project would mean withholding the development in the severely
affected FATA area and the Bajaur and Orakzai agencies in particular. The proposed
project is of paramount importance in improving the access of the communities residing
within the project area, particularly the remote mountainous communities as well as the
respective agencies as a whole. If the project is not carried out, the opportunity to
improve access to better health, education facilities, access to emergency help and swift
movement outside the area (in case of a required evacuation). Furthermore, this would
also mean restricting the opportunities of the residents of the Bajaur and Orakzai
agencies to improved economic activity and trade enhancement with the rest of the
country. Lastly, the project would provide greater job opportunities to the local people,
both during the construction and operational phases.
Conclusion
For the No-project option, the analysis reveals that the weaknesses and threats far
outweigh the potential strengths and opportunities. Therefore, the “No project option”
is not recommended.
5.1.2 Project Road to Follow Exactly the Existing Route with No Alteration
Analysis
Advantages
No costs will be incurred on the survey and design of new roads proposed as part of the
project. No additional land acquisition would be required and the environmental impact
during the construction and operation of the roads would only be limited to the areas
located on either side of the existing roads / tracks.
Disadvantages
Access to new areas and settlements will not be developed and there will be no
improvement in the existing road routes or in their limitations regarding distance and
velocity. Furthermore, any geotechnical faults that exist with the existing road design,
condition and alignment will continue to exist. Fresh impacts on the environment will be
caused by improvement of the road quality without yielding any advantage.
Conclusion
Construction of new roads on exactly the previous alignment is not a sound engineering
proposal nor does it allow for all the envisaged benefits of the project to be realized.
Therefore, this option cannot be supported.
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 5-3
5.1.3 Project as Proposed in Feasibility with Alterations Where Necessary
Analysis
Advantages
By virtue of a detailed feasibility study (including ESIA), the proposed project is designed
encompassing all the relevant technical, financial, environmental and social
considerations relevant to the project. The project, as a result, addresses the urgent
needs to the communities and is designed to be implemented in the most technically,
financially, environmentally and socially sound way.
All along the proposed project, during construction and after construction there will be
ample job opportunities for local population. Opening up of the area will result in better
education, health and social welfare opportunities. The project area will experience
definite poverty alleviation especially after the sufferings of the people during the
military actions undertaken in the area.
Alterations in sections will be done to render sharp curves gentler, avoid congested
points, negotiate slopes at easier gradients and build stronger road foundation. The
primary objective will be to ensure safety at higher speeds on paved roads.
In the long run, the project is financially viable, socially acceptable, environmentally
manageable, gender-neutral and pro-poverty alleviation.
Conclusion
The opportunity of building new roads and improving some of the existing ones in the
project area is recommended and will prove to be very beneficial for the recipient
communities.
5.2 Logistic Sites
5.2.1 Location of Contractor’s Facilities on Public Land
Analysis
Advantages
The land for setting up the construction camp(s) and the equipment and machinery yard
could be available to the contractor free of cost due to it having no private ownership.
This would reduce the overall contract cost for the project.
The likelihood of friction, disturbances or conflicts with the local communities would be
greatly reduced. With the local communities having no say on the land use, the
contractor would have more freedom and control to manage the activities. Due to the
possibility of supervision of the project proponents, the environmental management
activities ensuring no environmental spillover to the communities.
Disadvantages
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 5-4
There may be limitations to the availability of public land along the RoW of the proposed
roads leading to greater distances between the construction locations and campsites
leading to a slight reduction in the efficiency of the project implementation.
Conclusion
In presence of adequate and encumbrance free state land located within a manageable
distance from the construction site(s), the contractor may be given the option of using it
for setting up the labor camp, machinery yard and work bases. This is an acceptable
option and where applicable is highly recommended.
5.2.2 Siting of Contractor’s Facilities on Private Lands
Analysis
Advantages
The contractor would be free to choose the land and would be able to acquire the most
appropriate location for setting up the required facilities. The contractor would
contribute positively to selected members of the community by providing money against
leasing of land for the duration of the construction resulting in greater ownership of the
project amongst members of the community.
No additional government land will have to be required for the project activities. No
obligations will fall upon the Works and Service Department FATA.
Disadvantages
The contractor will be free to hire comparatively flat agricultural lands and will
temporarily put productive land to non–productive use.
The contractor will include the cost of leasing land in his BOQ for the project costs
included in the bid. This will increase the cost of the bids and subsequently the project
expenditure.
Outside of the direct control of the project proponents, the contractor may indulge in
unplanned environmental social or physical activities which may not be acceptable
within the meanings of the project ESIA.
Conflicts pertaining to land ownership (within the community) and temporary
acquisition of land by the contractor could arise. Also the mobility of women would be
affected more so when the camp sites are located on land that was in the use of the
communities and the possibility of friction with the communities would also increase.
Conclusion
In presence of adequate state land adjacent to or within a manageable distance from
the construction sites acquisition of private land is not advisable. The weakness and
threats of this proposal outweigh strengths and opportunities. The proposal of siting
contractor’s facilities on private lands is therefore not supported. Should the contractor
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 5-5
choose to establish his facilities and labor camp on hired private land then Works and
Services Department FATA bears no responsibility for his costs and commitments.
5.2.3 Siting the Contractor’s Facilities at Appropriate Site, be it Public Land
or Private Land
Analysis
Advantages
The option will create an operationally adjustable opportunity wherein the contractor
will choose the best site. However, the Executive Engineer (XEN) will approve all the
camp and equipment yard sites.
The contractor will not be bound to remain restricted to the sites proposed by the
Works and Services Department XEN and can plan his operations according his
operational convenience and availability of facilities and services.
Where enough state land is not available, and private land is available adjacently, the
contractor can make necessary adjustments without changing the site.
Disadvantages
To the extent that the contractor moves out of state lands, establishment of camps,
yards and facilities close to villages can cause social problems described in the earlier
alternative.
Conclusion
After settling the contractor on public land, this is the second best option. But for
contractors’ activities on privately owned lands the Works and Services Department
holds no responsibility for contractor’s cost and commitments.
5.3 Labor
5.3.1 All Labor Local
Analysis
Advantages
All labor will be local and their employment will fulfill a major social requirement of the
contract. Local economy will benefit and the project will contribute to the poverty
alleviation in the communities of the project area. The project will definitely be highly
socially responsible and will generate unprecedented community ownership and
support. Another big advantage of local labor will be that most of them will come from
and go to their homes daily and there will be very little pressure on labor camps.
Disadvantages
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 5-6
Three types of labor will be required; unskilled, semiskilled and skilled. All types of labor
may not be available locally. So binding contractor to employ all labor locally can put
limitation on contractor and negatively affect the quality of the services offered by the
contractor.
Conclusion
It is not realistic to rely entirely on local labor for all trades. So this option is not
recommended. However, all unskilled labor openings must be given to locals through a
consultative process with the nearby communities ensuring equal opportunities and
reducing the risk of conflicts arising due to unequal opportunities for the communities.
5.3.2 All Labor from Outside
Analysis
Advantages
Labor from outside will be preselected and ergonomically sound. More efficient,
dependable and properly trained manpower will be available for the contractor. The
labor will not be able to erect undue pressure on the contractor or the project. The
outside labor will set a model for untrained labor that may improve. Any spending by
outside labor at local shops and businesses will bring an additional benefit, to local
economy.
Disadvantages
Bringing outside labor will take away the envisaged benefits of employment and
development of employable skills from the locals and will not develop a sense of
ownership for the project amongst the communities. The project objective of
contributing to poverty alleviation, social uplift and capacity building will be defeated
and several social problems including hampering of the mobility of women and
negatively perceived interactions between the locals and outsiders may take place
potentially leading to conflicts with and among the local communities.
Conclusion
In case the labor is brought from outside, the social losses will be much higher than the
economic gains. However, due to limited availability of individuals from the project area
having the required skill and experience may necessitate bringing in a small percentage
of outside manpower at skilled level. But as far as possible the local human resource will
have to be preferred.
5.3.3 An Admixture of Local and Outside Labor as per Skill Required
Analysis
Advantages
Unskilled labor can be locally procured entirely. Preference will be given to local
manpower for semi-skilled labor employment subject to the availability of locals with
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 5-7
the requisite skills and experience. Most of the senior technicians and skilled workers
will have to be brought from outside the project area.
Disadvantages
Because of the presence of the outsiders there are likely to be some social losses.
Income of local communities will also be reduced.
Conclusion
From project implementation point of view, this option presents the best combination of
local and outside labor. This option also presents an opportunity to transfer of skills from
outside technicians to local workers and also contribute positively towards alleviation of
poverty in the project area.
5.4 Summary of Alternatives
i. The no-project option is not recommended.
ii. The option of following exactly the existing alignment may not be the most optimal
option in terms of the benefits that could result from the proposed project.
iii. Project as proposed in feasibility is fully recommended.
iv. Option of locating all Contractor’s facilities on public land is recommended as the best
logistic option.
v. Location of all Contractor’s facilities on privately owned lands is not supportable. Works
and Services Department FATA cannot accept any responsibility for such an option by
the contractor.
vi. Siting of Contractor’s facilities partly on state land and partly on private land is
supported as the second best logistical arrangement, provided that the Works and
Services Department is not held responsible for the cost and commitments of the
contractor pertaining to setting up of facilities on privately owned land.
vii. Option of having all categories of labor from project area is not possible.
viii. Option of bringing all categories of labor from outside is not recommended.
ix. Option of getting 100% local labor from local source, to the extent possible (subject to
availability of requisite skills in the community) semi–skilled labor would be hired from
the community and 100% skilled technicians from open market is the recommended
option.
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 6-1
6 Stakeholder Consultations
6.1 General
This section describes the outcomes of the stakeholder consultation process as part of the ESIA.
This ensures that feedback from communities and other stakeholders directly or indirectly
affected by the project is collected so that it may be used to adjust and improve the project’s
design, planning, implementation and help structure the project that is both environmentally
and socially sound. The consultation process was carried out in accordance with the
requirements of the World Bank and Government of Pakistan on public consultation.
The objectives of this process was:
i. To disseminate information on the project and its expected impacts, long-term as well as
short-term, among primary and secondary stakeholders,
ii. To gather information on relevant issues so that the feedback received could be used to
address these issues at an early stage,
iii. To determine the extent of the negative impacts of different project activities and
suggest appropriate mitigation measures.
6.2 Identification of Stakeholders
Stakeholders are people, groups, institutions, or industrial units that may be affected by, can
significantly influence, or are important to the achievement of the stated purpose of a proposed
intervention. Following are two categories of stakeholders were identified:
Primary Stakeholders: People, groups or institutions affected positively or negatively by
the project
Secondary Stakeholders: People, groups, or institutions that are important
intermediaries in the project delivery process
6.3 Stakeholder Consultation Process
Stakeholder consultation for this project was planned in two stages. The first stage was part of
the ESIA process and documentation, which has already taken place, consisted of meetings with
individuals, groups, relevant organizations and government departments, which are in some way
linked to the project and therefore considered stakeholders. The meetings were conducted to
inform stakeholders about the project and how it may affect their lives/activities, and to record
their concerns, whether real or perceived. Through the use of various tools the study team tried
to involve the stakeholders in active decision-making. The results of this exercise are described
below, where mitigation measures have been developed addressing the pertinent stakeholder
concerns.
The second stage of the stakeholders’ consultation was part of the separate study conducted for
the preparation land acquisition and resettlement framework of the project. The results of this
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 6-2
study and the proposed mitigation measures for potential social impacts will be documented
separately and will be included in the overall framework of the proposed project.
The tribal culture prevalent in the project area does not allow for outsiders to carry out
consultations with the women of the project area. It is also not possible to bring in non-local
females to interview the women of the area and as a result consultations with the women were
not possible. Data within the socioeconomic baseline pertaining to the women of the project
area is based on secondary extrapolated data.
6.4 Primary Stakeholders Consultation
Conducting primary stakeholders’ consultations in the project area was a challenging task mainly
due to volatile law and order situation in the area. Also there were many other constraints
specifically associated with the proposed project area due to local tribal customs. The women of
the area were not allowed for consultations and no women from outside was allowed to
participate in these consultations. However, the process was carried out by holding scoping
sessions with local communities. Table 6.1 provides a summary of the meetings held with
respect to venue, area, name of key respondent and number stakeholder participated.
Table 6.1: Summary of Public Consultations
No. Name of
Settlement District Zone
Nearest Main City/Town
Name of Key Respondent (s)
No of Respondents
1 Soorbat Kali Utman Khel Bajaur Khar Badshahzada Malik 10
2 Pataselay Utman Khel Bajaur Khar Gaous-ur-Rehman 7
3 Landay Utman Khel Bajaur Khar Dilawar Khan 5
4 Tarry Utman Khel Bajaur Khar Muhammad Anjum 9
5 Islam Dehrai Utman Khel Bajaur Khar Bacha Zada 6
6 Khayathy Utman Khel Bajaur Khar Gul Khan-ud-Din 10
7 Bandegi Utman Khel Bajaur Khar Gafar Malik 4
8 Kulala Utman Khel Bajaur Khar Fida Muhammad 8
9 Dop Sana Kalai Orakzai Kuraz Syed Abdul Hassan 8
10 Largi Tan Kalai Orakzai Kuraz Syed Ali Shah 10
11 Sharo Doghal Lower
Orakzai Orakzai Dargi Malik Kishwar Ali 9
12 Dargi Lower
Orakzai Orakzai Dargi Ahsraf Ali 6
13 Shamim Jan Kali Lower
Orakzai Orakzai Dargi Syed Shamim Jan 5
14 Otti Kali Lower
Orakzai Orakzai Palosia Ali Musa 5
15 Palosia Lower
Orakzai Orakzai Palosia Malik Yaqoob Ali 7
16 Mama Masai, Amber Khel
Lower Orakzai
Orakzai Palosia Ali Noor 8
17 Brado Sam, Lalpura
Lower Orakzai
Orakzai Palosia Ishrat Hussain,
Qurban Ali, Shah Hussain
10
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 6-3
6.4.1 Topics for Discussion
Given below is a list of the topics that were covered during the meetings.
Employment
Public safety
Dust
Noise
Community development
Traffic
Non-local workforce
Cultural and gender related issues
6.4.2 Outcomes of Consultations
Concerns raised by stakeholders regarding the environmental implications of proposed project
during construction and operations:
The alignment of route and associated structures should be in consultation with local
communities and elders.
Existing traffic on the road shall be affected.
Noise and air pollution associated with trucking causing disturbance to residents along
the road.
Livestock safety during construction or use of roads.
New roads disturbing rain-fed agricultural production systems, increasing water
shortages may result in increased poverty.
Project related traffic causing congestion
Road safety measures required, such as speed breakers and restrictions, so speed limits
are observed and accidents avoided
Public safety for people crossing the road, particularly the elderly, women and children
Heavy traffic destroying road
Sanitation awareness in camping facilities
Privacy related matters and cultural sensitivities
Improve general standards of construction.
Blasting should not be carried out settlements.
The business of the people should not be affected due to project activities.
Protection walls should be constructed where needed.
Provide streams outlets to help drain away runoff from the highway into the river.
Plant trees along the highway that could be entrusted to the care of local communities.
Avoid relocating/dismantling mosques and other permanent structures.
Proper traffic management plan should be provided during construction activities.
Job opportunities should be provided to the locals during construction activities.
Safety of local residents along the road should be ensured particularly due to land sliding
and stones rolling.
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 6-4
6.5 Secondary Stakeholder Consultations
Secondary stakeholder consultations were more formal as they involved a non-governmental
organization and government personnel who were consulted. They were briefed on the ESIA
process, the project design, and the potential negative and positive impact of the project on the
area’s environment and communities. Community development needs and programs were also
discussed. It was important not to raise community expectations unnecessarily or unrealistically
during the stakeholder consultation meetings in order to avoid undue conflict with tribal people
or government administration. The issues recorded in the consultation process were examined
and validated, and are addressed in the ESIA report.
The other departments of government of FATA and political administration were consulted
during project planning and their concerns were already included in the project design and
management.
6.5.1 Consultation with NGOs
During the field surveys it was found that only one non-governmental organization named Tribal
Development Network (TDN) that was involved in the project area. TDN is a Peshawar based
organization.
6.5.1.1 Tribal Development Network
The TDN operates in all seven agencies and six frontier regions. There are 62 local community
based organizations and village organizations networked under this umbrella. A formal meeting
with its members and coordinator was held to carry out this consultation process. Following
concerns were identified during this meeting;
The security matters are very sensitive in the project area. Therefore all security
arrangements for the execution of this project should be finalized after involvement and
inputs from local elders and tribal representatives.
Where possible all contracts and subcontracts should be provided to local contractors.
The contractors from the outside the project area should be involved only if no qualified
locals are available.
All contractors and subcontractors should be advised to hire local people for all unskilled
jobs.
If religious structures are to be affected as a result of construction work, then religious
leaders and tribal elders should be informed and taken into confidence.
A prior consent and approval shall be obtained from the owners if a private structure
needs to be removed or damaged. An agreement with private owners should be
initiated through local Maliks.
6.5.2 Consultation with EPA Khyber Pakhtunkhwa (KP)
Director EPA KP was consulted for the feedback on the project. He informed that a new
notification has recently been issues by Federal Government for the extension of Pakistan
Environmental Protection Act to the Federally Administrated Tribal Areas and Provincially
Administrated Tribal Areas. After this notification the jurisdiction of KP-EPA in not applicable to
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 6-5
project area therefore he said that he cannot represent the EPA for feedback on the current
project. However as an environmentalist and a citizen of Pakistan he recommended following
areas to be considered during project design as well as management;
Project foot print should be minimized to the extent possible.
Routes of the proposed roads should be aligned in a way to minimize the clearance of
natural vegetation. Cutting of natural forest should be avoided.
Offsetting of the routes to avoid cultural sensitivities should be considered.
Awareness on environmental sensitivities should be created among the project
personnel through trainings and workshops.
The tribal norms and other privacy matters should be understood and the awareness of
such issues should be communicated all personnel onboard.
6.5.3 Consultation with Pak- EPA
The Pakistan EPA was contacted to know the level of its involvement in regulating the
environmental standards in the Federally Administrated Tribal Areas. It was learned that after
the implementation of 18th Amendment in the Constitution of Pakistan and the subsequent
notification for the extension of jurisdiction of Pakistan Environmental Protection Act 1997 to
these tribal areas, the role of Pak-EPA is not applicable to the project area. Therefore no specific
concerns were raised.
6.6 Land Acquisition and Resettlement–Related Concerns
Concerns related to land acquisition, both temporary and permanent, and the resettlements
were not recorded because a separate consultation in the second stage is being conducted
specifically to address these issues.
6.7 Addressing Stakeholders Concerns
The most of the concerns raised by stakeholders have been incorporated into the project’s
environmental and social assessment and ESMPs. In addition a Grievance Redress
Mechanism/Complaint Handling Mechanism will be developed at the implementation level by
forming Grievance Redress Committee which will receive and resolve complaints of the project
affected persons and other stakeholders of the project area.
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 7-1
7 Environmental Impact Assessment and
Mitigation Measures
This section describes the environmental impacts that could occur as a result of the project
components. The impacts have been identified based on consideration of the information
presented in Chapters 1, 2, 4 and 5.
A summary of significant impacts evaluated in this chapter is given in Table 7.1, grouped into the
project components and impact groups.
Table 7.1: Summary of Evaluated Significant Environmental Impacts
Aspect Impact
Land and landscape transformation
Impact of taking material from the borrow site
Availability of water and change of drainage patterns
Activities for construction and improvement of road changing surface and sub-surface drainage affecting other water users. Activities for construction and improvement of road resulting in sediment mobilization and settlement in ephemeral streams and low-lying areas crossed by the route. Access to water for the community can be changed due to sharing of water resources for project needs.
Releases to air Activities for widening and improvement of road generating dust, including fine particulates, causing nuisance and health effects for nearby communities and commercial areas. Gaseous emissions from vehicles and construction machinery causing health effects for nearby communities. Gaseous emissions from vehicles during operational phase causing health effects for nearby communities.
Noise and vibrations Noise and blasting associated with construction disturbing local communities and wildlife. Project equipment and vehicles used in project resulting in unacceptable increases in noise and vibration levels in local communities. Vehicles movements during operational phase resulting in unacceptable increases in noise and vibration levels in local communities.
Ecology and biodiversity disturbance
Activities for construction and improvement of road resulting in ecological disturbance. Vehicle traffic resulting in animal disturbance both during construction and operational phases.
Contaminations of soil and water resource
Soil contamination from diesel and other spills from construction machinery. Release of construction water to any river structure such as bridge/culvert
Disturbances to the community Activities for construction and improvement of proposed road sections disturbing land used by local communities. Activities for construction and improvement of road disrupting community transport routes.
Monitoring and Evaluation as per operational manual and monitoring plan
M & E is required to ensure the implementation of proposed mitigation measures to avoid or minimized potential impacts during operational phases
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 7-2
7.1 Potential Impact Sources
This section covers impacts associated with the following project activities:
Construction activities
Storage of construction material,
Use of local resources,
Construction and operations of camps and project auxiliary facilities
Operational phases of the roads.
Issues raised by stakeholders regarding the environmental implications of proposed project
during construction and operations:
The alignment of route and associated structures should be in consultation with local
communities and elders.
Existing traffic on the road shall be affected.
Noise and air pollution associated with trucking causing disturbance to residents along
the road.
Livestock safety during construction and use of roads.
New roads disturbing rain-fed agricultural production systems, increasing water
shortages may result in increased poverty.
Project related traffic causing congestion
Road safety measures required, such as speed breakers and restrictions, so speed limits
are observed and accidents avoided
Public safety for people crossing the road, particularly the elderly, women and children
Heavy traffic destroying road
Sanitation awareness in camping facilities
Privacy related matters and cultural sensitivities
Environmental and social impacts attributable to the project can broadly be classified into those
taking place during construction and those occurring during the operational phase. Some of
these impacts can be anticipated and avoided through appropriate adjustments / provisions in
the project design. Some can be mitigated by careful implementation of the project while some
other can be adjusted with by appropriately following the operational manual and an effective
collaboration with communities.
Construction related impacts are heavily dependent on:
The contractor’s work practices, especially those related to storage of construction
materials and cleanliness of work site;
Cooperation between local communities and local authorities and the contractor in
terms of observance of Social Framework Agreement (SFA) and use of public space and
utilities;
Project management’s enforcement of correct construction practices and standards;
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 7-3
The incorporation of mitigation measures identified the ESIA into the tender documents
and specifications, in bid and Contracts documents and provision of linkage between
ESMP and contractors payments.
An effective collaboration with local communities in evolving a workable Social
Framework Agreement (SFA).
The quality of Monitoring and Reporting of EMP implementation.
Operational impacts of the proposed project are associated with the movement of vehicular
traffic on it and allied activities. These include air and noise pollution, safety hazards and other
similar impacts.
For this Project, potential impacts are reviewed under construction and operational phases. The
environment has been studied under the following sub–heads:
Physical Environment
o Land Resource
o Water Resource
o Air Quality
o Noise Level
Biological Environment
o Flora
o Fauna
o Fish
o Endangered Species
Cultural and Historical Sites
Socio–economic Environment
Table 7.2 provides a checklist of potential impacts likely to be associated with the construction
phase of the proposed project. In general these areas are divided into groups based on general
environmental aspects that are effected or likely to be affected from the modification in the flow
of traffic. The set of impacts based upon physical, biological, cultural and social aspects have
been classified as under construction and operational phases. Each sub–factor has been marked
as curable, reversible or irreversible. Each sub–factor so assessed has been shortly discussed and
explained in the part of the chapter 7 following the Assessment Table 7.2.
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 7-4
Table 7.2: Evaluation of Environmental and Social Impacts
Aspects Impacts Assessed
Assessment
Slight Moderate Significant
1 2 3 1 2 3 1 2 3
1. Land and landscape transformation
1.1.1 Site for disposal of waste construction material
1.1.2 Land slide, unstable soil or similar unforeseen conditions
1.1.3 Location of labor camps, material dumps, equipment yard and approach road.
1.1.4 Any natural disasters such as heavy rains, floods and earthquakes
1.1.5 Soil contamination from diesel and other spills from construction machinery
1.1.6 Damage/blockage of Drain, paths, roads, and cross drainage by moving machinery.
1.1.7 Scouring of Earthen embankment or concrete work edge
1.1.8 Release of construction water on unstable slope or any public/private property
1.1.9 Release of construction water to any river structure such as bridge/culvert.
1.1.10 Any discharge, spill or dumping on any building or house on riverbank.
1. Avoidable through design (Avoidance): Curable 2. Mitigation through contractor’s obligation or by communities through Social Framework
Agreement (SFA) (Curative): reversible 3. Non–reversible, Permanent change (to be adopted): irreversible
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 7-5
Aspects Impacts Assessed
Assessment
Slight Moderate Significant
1 2 3 1 2 3 1 2 3
1.1.11 Impact of taking borrow martial from earth borrow site.
1.1.12 Impact on paths or road used for transport of construction material.
1.1.13 Impact of stone quarrying.
1.1.14 Any blasting during Construction
1.1.15 Activities for construction and improvement of proposed road sections disturbing land used by local communities.
2.Water Resources
1.2.1 Sourcing of construction water and potable water for camps.
1.2.2 Impact of surface water.
1.2.3 Impact of ground water.
1.2.4 Impact of drinking water.
1.2.5 Diesel and other fluids spilling over to river water form machinery.
1.2.6 Damages from floods of river or streams.
1.2.7 Obstruction of flow of water in the river or any stream.
1.2.8 Effect on surface flow conditions in rains.
3.Air Quality and Noise Pollution.
1.3.1 Dust, smoke and other pollutants from construction Machinery including asphalt and concrete batching plant.
1.3.2 Dust of other pollutants from stored material and spoil keeps.
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 7-6
Aspects Impacts Assessed
Assessment
Slight Moderate Significant
1 2 3 1 2 3 1 2 3
1.3.3 Smoke from burning of waste material or burning firewood.
1.3.4 Noise from use of old or outdate machinery.
1.3.5 Noise due to any blasting.
1.3.6 Soil compaction due to labor camps and machinery yards.
4. Biological Resources
1.4.1 Damage to biological resources
1.4.2 Damage to Fisheries
1.4.3 Impact on (adjacent) open land
1.4.4 Impact on any migratory birds.
1.4.5 Impact on endangered spices.
5.Socio–Economic Cultural and Archeological Issues.
1.5.1 Existing services education, health, electricity, water supply communication.
1.5.2 Local ethnicity, Tribal Tensions, communal rivalries
1.5.3 Impact on area under crops
1.5.4 Land ownership / Land tenure system
1.5.5 Access to construction material.
1.5.6 Adverse effect on cultural and archaeological heritage (if any).
1.5.7 Graveyards or burials.
1.5.8 Public safety at construction site.
1.5.9 Health and safety of labor and employees on construction site.
1.5.10 Resettlement of Affectee land inhabitants of houses in RoW.
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 7-7
Aspects Impacts Assessed
Assessment
Slight Moderate Significant
1 2 3 1 2 3 1 2 3
1.5.11 Loss of cultural ties and family lands due to involuntary shifting of population
1.5.12 Loss of livelihood due to loss of land and ancestral villages.
1.5.13 Loss of local technique and knowledge due to shifting of population
1.5.14 Employment
1.5.15 Women status: Exposure to employment and education opportunities.
1.5.16 Hurdle in cultural Reunion.
1.5.17 Hurdle in accessing market opportunities for agricultural produce.
1.15.18 Reduction in recreation opportunities.
7.2 Explanation of the Impact Assessment
Table 7.2 above provide a schematic presentation of the degree, significance and mitigation of
various environmental and social factors at construction and operational phases. This section
provides a brief explanation of these factors, also suggesting a line of action towards mitigation
measures for the adverse impacts.
7.2.1 Soil and Landscape
Potential Impact
Cutting and filling operations during construction may have a geophysical impact
leading to:
i. Physical Scarring of landscape
ii. Increased risk of land slippage
iii. Accelerated soil erosion
iv. Blockage of natural drainage.
These are discussed in more detail below.
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 7-8
Evaluation of Impact
Physical Scarring
Physical Scarring occurs when changes in the physical appearance of the land affect
the aesthetic quality of the landscape. Physical changes to the landscape proposed by
the project include the construction of road, and construction of camps and auxiliary
facilities.
Land Slippage and Soil Erosion
The extent of potential land slippage depends on the following factors:
i. Type of soil (homogeneity, cohesiveness, compactness)
ii. Water content of the soil (depends on rainfall, drainage, vegetation, evaporation
rate, etc.)
iii. Topography (slope gradient)
iv. Vegetation cover
v. Exposed rocks.
If any of these factors change significantly, the risk of land slippage or soil erosion will
accelerate. In the context of the proposed project, the most important factor is
topography. Although the road widening involves some vegetation clearance and
change in soil characteristics, the subsequent compaction will significantly reduce any
risk of land slippage. The risk of land slippages near the stream banks will be reduced
by ensuring thorough maintenance of a gentle slope and by applying water.
Monitoring during construction will further minimize the risk.
Blockage of Irrigation systems and Natural Drainage
The routes may also cross many streams and channels. These channels and streams
may be blocked and the catchment of the downstream may be disturbed during
construction phase.
Mitigation Measures
To minimize the impact of the project on the geophysical environment, a number of
measures have been included in the design that will need to be taken into account
when constructing the project facilities. A second class of measures is related to the
day-to-day management of the project during construction. Following specific
measures are required to minimize potential impacts:
i. Unnecessary widening beyond the proposed design of the road shall be
avoided at straight portions and on bends.
ii. The alignment of the widening will be selected so as to minimize the clearing
of vegetation; and minimized trees cutting.
iii. Steep cut-and-fill will be avoided, and a gentle side slope maintained where
possible. Retaining walls will be constructed where necessary.
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 7-9
iv. The natural drainage pattern will not be disturbed, and culverts will be
constructed where required.
v. Surplus soil and cleared vegetation will be disposed of so as to avoid
disturbing the natural drainage.
vi. The movement of construction equipment and vehicles will be restricted to
work areas.
vii. The one clear passage for transport will continue to be maintained during
the project, and measures such as spraying water implemented to reduce
dust emission and erosion.
viii. Safe driving practices must be encouraged to minimize soil erosion. A speed
limit of 40 kmph will be observed and monitored in the project area, and off-
road driving strictly prohibited.
ix. Environmental monitoring will involve checks for any signs of soil erosion so
that remedial actions, such as applying water and compaction, can be
implemented.
x. The state of the work corridor will be monitored during project to prevent
any spillover outside the corridor.
xi. All sections of the road close to or on steep slopes will be closely monitored
for any signs of soil erosion or land slippage.
xii. The Executive Engineer (XEN) of the Works and Service Department (FATA)
will allow local readjustments in foundation treatment or any other small
changes to the contractor.
7.2.2 Location of Labor Camps, Material Depots, Equipment Yards and
Approach Roads
Potential Impact
Location of camps near sensitive receptors like water resources, private lands without
prior consent of landowners and dumping and storage of construction material and
equipment in private lands may cause adverse impacts.
Evaluation of Impact
Location of labor camps material depot, equipment yard and approach roads will not
cause any serious problem if selected in consultation with local communities and
landowners. So this is a matter of slight significance and can easily be mitigated.
Mitigation
i. The contractor will, in consultation with XEN, select the location of all these
facilities after a rapid assessment through the Screening checklist (Annexure 3).
ii. The camp/other site facilities will be established on a flat land without much
natural vegetation, at least 500 m away from the communities.
iii. Satellite imagery can also be used to select the suitable sites, to record the pre-
construction conditions, and to monitor the condition of these sites during and
after the construction phase.
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 7-10
7.2.3 Oil Spills from Construction Machinery
Potential Impact
Any leakage or spillage of diesel, oil or any other chemical will contaminate the soil
which may in turn impact the water sources, nearby community and/or productive
land.
Evaluation of Impact
The contamination of soil and water resources may affect the communities and
biodiversity of the area. Categories of spillages and requirements are discussed as
under;
Minor Spill / Leakage: Soil contaminated by minor spills / leakages (defined as leaks
from vehicles, machinery, equipment or storage containers such that the area and
depth of soil contaminated is less than 10 sq. ft. and 3 inches respectively) is to be
scraped and burnt in a burn pit, away from population.
Moderate Spills are defined as spills of volume less than or equal to 200 liters is to be
contained and controlled using shovels, sands and native soil. These equipment and
materials are to be made available at campsites during the operation. The
contaminated soil is to be excavated and stored in a burn area lined with an
impermeable base. Depending on the volume, the contaminated soil is either disposed
off by burning in the burn pit or by specialized treatment such as bioremediation.
Major Spills (defined as spills of volume much greater than 200 liters) requires
initiation of Emergency Response Procedures and Oil Spill Contingency Plan. These
spills are to be handled and controlled according to the plan and require special
treatment such as bioremediation.
Mitigation
Following measures shall be implemented to avoid such events;
i. Contractor will apply strict rules on his workers and labor to ensure that no spill
or leakages are caused. All fuels, oils and bitumen will be stored appropriately,
with concrete padding and bunding for containment in case of leakage.
ii. If the spills or leakages do take place, it must be followed by the treatment
prescribed below as per the degree of spill or leakages.
iii. The contractor will employ the general criteria for oil and leakage at
construction sites, as per standards set forth by “Guidelines for Oil Spill Waste
Minimization and Management” issued by International Petroleum Industry
Environmental Conservation Associate which are as follows: (Source: IPIECA
Report Series, Volume-12, “Guidelines for Oil Spill Waste Minimization and
Management”)
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 7-11
7.2.4 Earthen Embankments or Concrete Work, Edge Scouring
Evaluation of Impact
Poor design and inappropriate construction procedures can potentially damage the
embankments, concrete works or road edges. The impact is moderately significant but
can easily be mitigated.
Mitigation
i. Edge scouring of earthen embankments or concrete work must first be dealt at
design stage. Wherever such a situation is anticipated, aprons should be
provided to secure edges and specifications must be kept of high standards.
ii. During the construction phase this aspect should be addressed through
appropriate construction methodology and employing appropriate techniques
such as protection walls and rip rap.
iii. Contractor will repair all damages to the earthen embankments, concrete works,
or pavement edges caused by the construction works.
iv. During the operation phase appropriate measures need to be incorporated in
the Operational Manual.
7.2.5 Impact of Borrowing Material from Earth Borrow Sites and Stone
Quarrying
Evaluation of Impact
A large quantity of earth will be removed from borrow pits located within the state
land on either side of the road. This can potentially cause slope instability, loss of
soil/land productivity, uneven terrain, and altered drainage.
Mitigation
i. The topsoil up to 30 cm shall be removed and stored prior to excavation of fill
material. After completion of borrowing the area would be leveled and the top
soil would be restored to ensure no loss in productivity of land.
ii. Borrow sites would not be deeper than 3 ft at any location to avoid alteration in
drainage pattern and reduce the risk of soil erosion
iii. The borrow areas will be selected after obtaining approval from the RE.
iv. The contractor will ensure that the borrowing does not cause slope instability,
loss of soil/land productivity, uneven terrain, and altered drainage.
v. Wherever possible/necessary, these places will be leveled and planted with
trees using appropriate planting technology/methodology.
7.2.6 Water Resources
The source of the project’s water will be mainly from the nearby rivers and small
tributaries and for the contractor’s camps can also be supplied by digging wells. This
section evaluates the potential environmental issues involved in using the area’s
surface and groundwater resources to meet project needs.
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 7-12
Potential Issues
The potential environmental issues associated with the use of the area’s surface and
groundwater resources for the purposes of the project are as follows:
i. Long-term impact—Groundwater extraction over and above the sustainable
yield will reduce the volume of groundwater available
ii. Water rights—the local communities’ rights over water shall be recognized and
adequately compensated.
Evaluation of Impact
Long-Term Availability of Water
There are seasonal rain fed streams and rivers in the project area. Therefore water if
extracted from river will have no short or long term environmental issues.
Sustainability is broadly defined as a state in which utility (or consumption) remains
non-declining through time. There are two forms of sustainability: ‘weak sustainability’
implies that the value of total capital stock should not decline, i.e., individual
components of the aggregate may decline in value as long as other components are
increased in value (normally through investment) sufficiently to leave the aggregate
value unchanged. ‘Strong’ sustainability implies that the value of the remaining stock
of natural capital should not decrease.
In terms of the project’s water requirements, attempts to ensure ‘strong’
sustainability would require that water not be extracted beyond the sustainable yield
limit, defined as that volume of groundwater if used that can be extracted annually
from a groundwater basin without reducing the total size of the aquifer. On the other
hand, maintaining ‘weak’ sustainability would allow a decline in overall water
resources due to project activity as long as the total capital stock of the community did
not fall. Water for the project will be used on the basis of the strong sustainability
principle.
Water Rights
There is a third, but potentially more fundamental issue related to water rights. The
community residing in the area as well as the wildlife depends on the availability of
surface water. The community uses this water for drinking, for domestic purposes,
raising farm animals, and farming. The wildlife also needs drinking water, as does the
vegetation on which they graze. The water is a scarce resource in the project area,
therefore it should be considered that locals have rights to allow or not allow the use
for the project. Limited sources shall be avoided where possible.
Mitigation Measures
Based on the discussion above, the following measures are proposed:
i. The community will be compensated for the water extracted from the area’s
water resources.
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 7-13
ii. Water will be extracted only from a major source or main stream.
iii. Given that water is to be extracted from a ground water aquifer whose recharge
rate, (like the actual volume of water available or its rate of depletion) is not
known, the extraction will be monitored to ensure that it does not lead to
irreversible environmental damage.
iv. The depth of the aquifer water table will be monitored.
7.2.7 Contamination of Soil and Water
Potential Issues
Effluents released as a result of the project activities, if not contained properly, may
contaminate the soil and water. Water quality is likely to deteriorate if pollutants or
contaminated soil mix with surface runoff during the rains and are carried downhill to
water bodies. If allowed to leach into the ground, the contaminants may also pollute
groundwater. Potential sources of pollution in such cases include:
i. domestic waste (sanitary and kitchen discharge)
ii. oil and grease
iii. chemicals
Evaluation of Impact
There is a causal link between effluent discharge and health, the impact of which is
analyzed based on:
i. The nature of pollutants (oil and grease, chemicals, organic substances, etc.)
ii. Discharge rate and duration
iii. Discharge conditions
iv. Characteristics of surface drainage and receiving water body e.g. water quality,
flow rate etc.
v. Location of receptors (communities) with respect to the discharge point
vi. Communities’ exposure to pollutants (concentration of pollutants in water)
vii. Current and potential uses of water in the community
viii. Health risks due to pollutants.
Mitigation Measures
Mitigation measures to reduce the impact of waste effluents produced during project
activities are listed below.
i. The camps will be located as to avoid proximity drinking water sources,
maintaining a minimum distance of 500 m from such natural resources.
ii. No contaminated effluents will be released into the environment without having
been treated.
iii. Sewage and other waste effluents will be handled so as to avoid contaminating
surface and groundwater.
iv. Water from washing areas and kitchen will be released into sumps.
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 7-14
v. An appropriately designed septic tank will be used to treat sewage, and outlets
will release treated effluents into sumps. The integrity of the entire system will
be maintained and monitored.
vi. Septic tanks and sumps will be built at a safe distance from any water hole,
stream or dry streambed, so as to prevent the entry of surface water, and the
bottom of the sump will be kept above groundwater level.
vii. Sumps will be located in a position such that they are:
a. Fixed in absorbent soil
b. Down-slope and away from the camp (and downwind, if practical)
c. Downstream from the camp water source and above the high-water mark of
any nearby water body (if any).
viii. When abandoning sumps, an extra cap of soil will be placed over them to allow
compaction.
ix. Solid waste (including food waste) will be segregated and disposed of as follows:
x. Materials suitable for recycling will be stored separately and sold to approved
recycling contractors
xi. Combustible waste, Non-combustible, non-recyclable rubbish will be sent to a
landfill
xii. Solid residue from the septic tanks will be transported to municipal sewage
treatment drains.
xiii. Vehicle and equipment maintenance, including washing, will be allowed only in
designated areas underlain with concrete slabs and a system to catch runoff.
xiv. Fuels, oils, and other hazardous substances will be handled and stored according
to standard safety practices.
xv. Fuel tanks will be appropriately marked by content, and along with oils, and
chemicals will be stored in dyked areas lined with an impervious base.
xvi. Precautions, such as drip pans, will be used to avoid any spills that may occur
during fuel and oil transfer operations.
xvii. Fuels, oil, and chemical storage facilities will be checked daily for any signs of
leakage.
xviii. Precautionary materials, including shovels, plastic bags and absorbent materials
will be kept available near fuel and oil storage areas.
7.2.8 Releases to Air
Potential Issues
Emissions generated during the project are likely to include:
i. Dust emissions from vehicular traffic,
ii. Dust emissions from earthworks along the road,
iii. Exhaust fumes from vehicles and construction machinery,
iv. Emissions from asphalt plants
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 7-15
Evaluation of Impact
Dust emissions caused by vehicular traffic on unpaved roads are an important
concern, primarily when such traffic passes near community settlements. It is not
uncommon to see a huge cloud of dust following vehicles traveling on unpaved roads.
Where these roads are paved, the problem is usually not as serious. The exception is
when two vehicles coming from opposite directions cross on a single-lane paved road
two to three meters wide. In such situations, usually one or both the vehicles are
partially forced off the paved surface, producing dust emissions since the road
shoulder is generally unpaved. Dust emissions cause the amount of particulate matter
in the air to increase, and thus become a health concern. Crops may be damaged
when dust settles on them although the significance of such damage varies from crop
to crop. Dust clouds also reduce road visibility, creating a traffic hazard.
Emissions produced by vehicles and equipment will be similar to those produced by
diesel generators in terms of the resulting pollutants (SO2, NOx, PM, etc.). However,
the extent to which they are produced will be considerably lower, since much smaller
diesel engines are used in vehicles and construction machinery.
Smoke emission from asphalt plants is an important aspect. The location of such plants
and proximity to the receptors is a matter of concern. Such plants are generally kept
away from sensitive receptors.
Mitigation Measures
None of the potential effects are expected to exceed acceptable limits. The mitigation
measures given below will further reduce their impact, and ensure that they remain
within acceptable limits.
i. All equipment, generators and vehicles used during the project will be properly
tuned and maintained in good working condition in order to minimize exhaust
emissions.
ii. Imposing speed limits and encouraging more efficient journey management will
reduce the dust emissions produced by vehicular traffic. Water will be sprinkled
where necessary to contain dust emissions.
iii. Dust emissions at the construction sites will be minimized using good
housekeeping and management practices.
iv. The asphalt plant will not be operated without properly functioning dust control
system such as wet scrubber.
7.2.9 Noise and Vibrations
Potential Issues
Potential sources of noise and vibrations include:
i. Equipment and vehicular noise,
ii. Noise from materials handling,
iii. Blasting noise and vibrations,
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 7-16
iv. Transport related noise and vibrations.
Mitigation Measures
Following the good practice management measures:
i. Equipment in good working conditions shall be used and regularly maintained.
ii. Horns shall be avoided near sensitive receptors like schools, mosques etc.
iii. Special care shall be exercised during loading and unloading of materials to
minimize vibration and noise near receptors.
iv. Plan for blasting times to be outside of hours when people are most disturbed
by noise (such as prayer and night times).
v. Develop and implement standard operating procedures, blasting rules and a
safety management plan that:
a. delineates the danger zone associated with each blast of at least 500m and
clear people and animals from this zone before, during and after (30
minutes) each blast;
b. provides an audible warning at least three minutes before blast is fired; and
c. Informs local communities of blasting timetable in advance and provide
adequate notices of blasts are required outside of the planned schedule.
vi. The use of blasting will be kept to an absolute minimum.
vii. Basting near the communities will be avoided to the extent possible.
viii. A detailed protocol for management and monitoring of blasting operation will
be established.
ix. The intended target of the blasting will be marked prior to its start.
x. If any significant damage to the ground is observed, the blasting parameters will
be modified or the blasting will be re-planned.
xi. Standard safety procedures for handling explosives will be used to protect the
staff, the community, and the environment.
7.2.10 Ecology and Biodiversity Disturbance
Potential Issues
Aspects affecting ecology and biodiversity along the corridors:
i. Temporary or permanent surface disturbance during construction
ii. Vehicle travel
iii. Equipment noise
iv. Blasting noise and vibrations during cut and fill construction activities
v. Transport related noise and vibrations
vi. Illumination of Project infrastructure
vii. Fugitive dust from road transportation
viii. Change in chemical characteristics of water bodies as a result of spills
ix. Temporary construction camps, accommodation and waste disposal facilities
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 7-17
Evaluation of Impact
Construction of road will lead to direct and indirect ecological disturbance. Direct
ecological disturbance as a result of land take will include habitat loss and habitat
fragmentation from removal of vegetation and burrows, and presence of barriers to
movement such as embankments, camps and lay down areas. This will result in a
temporary loss of food, shelter and range for small mammals. Accidental death of
individuals may also occur although mobile species such as reptiles and small
mammals are expected to move away from the area due to the noise of the machines
prior to surface disturbance. The impacts of habitat loss will be further exacerbated by
indirect ecological disturbance during construction, which will include increased noise,
blasting, vibrations, light, dust and increased access for hunting.
The direct impacts discussed above will be largely temporary and reversible. Following
construction, the restoring habitat and removing barriers to movement reverse all
impacts.
The project activities may potentially cause some disturbances for the wildlife of the
area, however, this impact is not significant. The area has already underwent
modification because of human settlements, building of the road, and associated
vehicular traffic, therefore most of the wild fauna species would have already left the
area
Mitigation Measures
i. No clearance of vegetation or killing/hunting/trapping of wild animal will be
allowed.
ii. Compensation will be paid for any tree cutting on the private land.
iii. Compensatory tree plantation will be carried out for Forest Department owned
trees and for each tree removed, five saplings will be planted.
iv. The Project will ensure appropriate care and monitoring of this plantation.
v. Camps and other temporary facilities will be established in a manner that
minimizes loss of natural vegetation including trees.
vi. Borrow material will be obtained without causing any damage to the natural
vegetation.
7.2.11 Acquisition of Private Assets and Compensation
A separate study Resettlement Action Plan (RAP) has been carried out to address the
issues related to acquisition of private assets and compensation. The same study is
submitted separately.
7.2.12 Increased Risk of Accidents Caused by Partial Closure of Road during
Construction
Current traffic on the road being constructed or improved in the proposed project is
not very high, however, the traffic flow is likely to be affected during construction
activities. Some of the roads in the project function as the vital link for the settlements
for daily supplies and trade activities. At sections passing through populated areas,
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 7-18
there will be limited scope for providing diversion tracks for the mobility of local and
thorough traffic. During the project implementation phase the traffic volume will
increase, there may be safety hazards for the locals residing along the edge of the road
as well as vehicular traffic.
Mitigation
Proper site-specific measures will be carried out in consultation with supervisory
consultants to ensure the safety of population residing along and around the project
corridor. A detailed Traffic Management Plan (TMP) will be prepared and
implemented by the contractor with the approval of the Works and Service
Department (FATA), XEN.
Necessary measures will be taken to ensure the safety of traffic during construction,
including barricades (including signs, pavement markings, flags, and lights) erected as
required by the Works and Services Department (FATA) and set up as per local
regulations.
The construction work will be managed such that part of the carriageway at a time is
upgraded leaving the other part available to serve one-way traffic. Construction work
will be carried out in small stretches instead of a long stretch.
During operation stage Works and Services Department (FATA) will make
arrangements with some organization/contractor for proper maintenance and
operation of the road. Periodic inspections will be made by contracted firm
particularly in monsoon season to identify the landslide areas and their remedial
measures. In case of any land slide contracted firm will clear the road within minimum
time. For this purpose the firm should be fully equipped and there should be
contingency plan in case of any emergency/natural disaster.
7.2.13 Safety and Health Hazards
Occurrence of accidents/incidents during the construction activities, particularly from
excavation activities is generally common. The workers and general public residing
along the project corridor or near the work sites will particularly be at risk. In addition,
contractor staff while on work may get injuries.
Mitigation
The contractor will comply with the safety precautions for construction workers as per
International Labor Organization (ILO) Convention No. 62, as far as applicable to the
project contract. The construction workers will be trained in construction safety
procedures, social awareness, equipping all construction workers with safety boots,
helmets, gloves, and protective masks, and monitoring their proper and sustained
usage. Contractor will ensure the provision of medicines, first aid kits, vehicle, etc. at
the campsite.
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 7-19
7.2.14 Restricted Mobility of Local Population
During the construction phase the general mobility of the local residents and their
livestock in and around the project area is likely to be hindered. Likewise access to the
natural resource may be affected. This particularly implies to the women folk and
children, especially in the context of FATA where women observe proper veil and do
not interact with non-locals. Construction activities, particularly excavation and
movement of haul truck and machinery may disrupt the existing tracks leading from
the main road to settlements. This will limit the accessibility of the local population to
the main road.
Mitigation
The contractor will ensure that the mobility of the local communities and their
livestock is not hindered by the construction activities. The contractor will provide
crossing points at the road at appropriate places to facilitate the people for going
across the road for their daily works and having free access to the natural resources.
Generally the contractor will avoid using the village tracks for hauling the construction
material. However, if it is unavoidable, the existing ones will be widened, overlaid with
shingle or surface treated to accommodate local as well as contractors traffic under
the approval of the Project Engineer.
The contractor will always consider the local sensitivities while performing the project
activities. All the personnel engaged would also be properly briefed about the local
norms and ethics prior to commencement of work.
7.2.15 Gender Issues
Findings of the socioeconomic survey reveal that the privacy of women is a major
cause of concern for the communities of the project area. Due to the project activities
local women many not be able to perform their daily outdoor chores. Women in the
project are participate in other outdoor activities such as livestock rearing, bringing of
potable water, collection of fire wood etc. that may also be affected by the project
activities.
The induction of outside labor may create social and gender issues due to the labor
force being unaware of local customs and norms. It may also cause hindrance to the
mobility of local women for working in the field, herding livestock, picking fuel wood,
etc.
Mitigation
The Contractor will select the specific timings for the construction activities
particularly near the settlements, so as to cause least disturbance to the local
population particularly women.
The Contractor will carry out the construction activities in such a way that the open
defecation timings by the local community particularly women, should not be
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 7-20
affected. The normal defecation timings are early in the morning and at late in the
evening. So, the Contractor will have to take care of these timings.
Contractor will take due care of the local community and observe sanctity of local
customs and traditions by his staff. Contractor will warn the staff strictly not to involve
in any unethical activities and to obey the local norms and cultural restrictions
particularly with reference to women.
During construction activities, if privacy of the nearby households is affected, the
Contractor will inform the house owner to make some arrangements. Similarly,
Contractor will take care as much as possible that the construction activities should
not affect the privacy particularly with reference to women.
7.2.16 Social Conflicts and Employment of Locals on the Project
The areas of Bajaur and Orakzai, where the project is proposed, present very distinct
local settings. Both the locations have an over-whelming majority of one sectarian
group. In such a situation, presence of outside construction workers may cause some
degree of social disruption and even active disputes with the local community as a
result of differences of religious opinions and culture. This particularly relates to the
non-local work force adhering to a different religious sect that many result in
escalation of sectarian issues. This coupled with decline of economic activities and the
disruption of the privacy of women folk working in the fields or even in the yards of
their houses, should the house be lying at a lower elevation than the working sites.
Likewise the risk of theft of the community assets by the Contractor workers and vice
versa may occur.
Mitigation
Good relations with the local communities will be promoted by encouraging
Contractors to provide opportunities for skilled and unskilled employment to the
locals, as well as on-the-job training in construction for young people.
Sectarian sensitivities should be given due consideration in engaging labor for the
project. Where possible local labor should be engaged for the project, this will not only
provide economic opportunities for the locals but will help the contractor in gaining
local trust and security.
7.2.17 Rise in the Prices of Essential Commodities
Due to induction of outside labor for project works, the demand for basic items will
increase thereby causing an increase in the prices of essential commodities.
Additionally, the road improvement activities during the construction phase may
disrupt the normal flow of trade and supply of essential goods.
Mitigation
In terms of labor induction the project will exert no significant impacts on the prices of
essential commodities. To avoid risk of such price hikes, majority of the unskilled and
semi-skilled labor will be recruited from the local areas. As such there will be no
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 7-21
extraordinary increase in the demand for essential or other commodities. The
contractor should normally procure the field camps supplies from the main markets of
Kohat, Khar, Peshawar or any nearby commercially active city.
7.2.18 Use of Local Water Supplies and Other Common Resources
Many of the settlements in Bajaur and Orakzai depend on village tube wells for their
daily water requirements. The campsites will also be depending on these local water
resources to meet personal use and construction requirements. This will put strain on
the limited supply of water, putting the construction workers in competition with the
locals for the resource. Local water may be affected due to implementation of project
both in quantity as well as quality.
The project campsites may also use other local resources like fire wood, game and
public resources. This again will affect the availability of these resources to the locals,
as already these areas have very limited resources. Locals have devised a finely
balanced way of life in these harsh conditions and any external influence threatens to
disturb this balance.
Mitigation
The contractor will explore the alternative water resource so that the existing
community water resources are not impacted. No existing water source under the use
of community will be exploited by the Contractor for campsite facilities as well as
construction purposes.
Availability of water for campsite facilities and construction purposes will be ensured
by the Contractor prior to start of construction activities. As per local customs and
government regulations, the contractor will seek approval from the local community
and government for exploitation of the water resources.
The Contractor will be required to maintain close liaison with local communities to
ensure that any potential conflicts related to common resource utilization for project
purposes are resolved quickly.
The contractor will prepare guidelines for the workers for minimizing the wastage of
water during construction activities and at campsites.
7.2.19 Adverse Effects on Archaeological Sites
No known archeological sites exist along the project corridor or its close vicinity.
Mitigation
The Contractor will be required to instruct the construction crew(s) and site
supervisors in archaeological / cultural / historical site and artifact recognition,
conservation procedures, and temporary site protection.
In case of a chance find during excavation, the Contractor must halt work at the site
immediately, inform the XEN and notify the Department of Archaeology and Museums
through the Works and Services Department.
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 7-22
7.2.20 Graveyards
Graveyards and burial sites are very sensitive for the local communities. The shifting of
graves falling in the RoW may cause social disruption leading to possible conflicts,
ultimately affecting the project works. However, in the proposed project, no graves or
burial site would be affected.
Mitigation
Though the proposed project poses no destruction and disturbance to graveyards,
however, if such a requirement were to arise, a detailed consultation with the local
communities would be carried out. After the agreement and approval of the local
community the affected graves would be shifted to some other site. For this, a proper
shifting allowance would be provided.
7.2.21 Spread of Communicable Diseases amongst the Project Labor and
Adjoining Population
The presence of a large number of construction workers and other associated
personnel may lead to the spread of communicable diseases such as HIV/AIDS and
hepatitis.
Mitigation
The Contractor should excise due diligence in avoidance and control of such mishaps.
Contractor will arrange awareness programs for the communicable diseases in the
field camps on regular basis by a qualified expert/doctor. Contractor will provide
recreational facilities such as playing volleyball of football after work hours. Similarly,
he will provide indoor recreation in terms of radio and TV at the eating-place. The
Contractor will ensure regular medical check–up of the camp staff from a qualified
doctor on fortnightly basis. If any person found affected with any of the transmittal
diseases will be immediately shifted from the camp to the hospital for detailed check–
up and treatment. The cost will be borne by the Contractor. Contractor will restrict his
permanent staff to mix with the locals to avoid any social and health problems.
7.2.22 Recreational Facilities for Public
The construction activities may damage any nearby parks or recreation areas used by
the local population or the tourists.
Mitigation
Currently there are no such damages envisaged however the Contractor will ensure
the restoration and rehabilitation of construction and campsites on completion of the
project. Works and Service Department (FATA) will develop parks, particularly for
children and ladies, at appropriate sites along the road to provide them better
recreational opportunities. This will also attract the outside tourists as well, thus
increasing the incomes of the local people through increased socio–economic
activities. The Works and Service Department (FATA) would carry out tree plantation
along the road.
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 7-23
7.2.23 Operational and Management Phase
At operational phase the Project Manager will develop a comprehensive operational
and Management Manual of the roads and an effective monitoring plan. Mistakes at
operational level or handling of operations by untrained staff can prove very risky and
costly. Important points to be attended at operational stage are as follows:
i. Strict application of prescribed M&E plan
ii. Continuous evaluation of design efficiencies
iii. Understanding and training of Operational and Maintenance Manual
iv. Regular maintenance of engineering works (mechanical as well as civil).
v. Continued Public consultation and feed back
vi. Continued attention towards Gender issues and women consultation
vii. Refresher Training Courses for operational and maintenance staff
7.2.24 Socioeconomic Impacts on the Overall Project Area
In ultimate analysis the impacts of project on social and economic activities in the
Project area will be mostly positive. The economic analysis shows very high economic
benefits compared to the cost. Salient economic benefits of the project are:
i. Many of the settlements in the project area lack proper health facilities. In case
of malignant diseases the locals generally head to nearby towns and cities for
medical help. Improved roads as a result of the proposed project will ease
access to medical help for the communities of the project area.
ii. The improved mobility of human and material resource leads to a better
economy. The construction of roads in the area will not only provide markets to
material resources, but will also give the local population access to job markets.
iii. Boosting of trade through ensured and enhanced capacity to take additional
traffic.
iv. Increased economic activity with improved transport will ensure easy marketing
of agriculture and livestock produce.
v. With improved economy, there will be further improvement in services in the
area and opportunities for employment, education, healthcare, especially for
women and children, will improve.
vi. Possible stimulus to other diversified economic development, such as Tourism
development programmers, will be generated
vii. Employment during construction phase will employ and train a large number of
unemployed youth. They will receive a life time benefit through skill training,
capacity building and poverty alleviation. A large number of semi and unskilled
workers in the project area will be hired.
viii. Greater awareness about Health care and infectious diseases amongst the labor
and the close by community will be created.
ix. As populations grow, the limited village lands and resources cannot sustain the
local community. To sustain the future communities, villages and settlements
needs to expand, this is only possible through transportation networks.
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 7-24
x. At micro-level the better roads lead to active communities, which in term
enhance economic activities. This not only improves the quality of life but also
brings down the cost of living by making essential commodities available at
cheaper rates. This combined with higher incidence of employments will bring
the poverty line and crime rate much lower.
xi. Areas of Bajaur and Orakzai where the project is proposed have many untapped
natural resources like marble and minerals etc. Being inaccessible the locals and
outside investors cannot benefit from these resources. Improved roads will no
doubt open up venue for investment and business that could potentially result
in accelerated development and the area and significant economic benefit for
the communities..
xii. FATA, due to its mountainous terrain and other socio-political factors has been
facing unrest and violence. A prime cause for this situation is its remote location
and minimum interaction with outside world, construction of roads will not only
create economic opportunities, but will also expose the people to modernity
and if required would provide fast and efficient evacuation routes.
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 8-1
8 Environmental and Social Management Plan
(Phase I)
8.1 General
This chapter contains the Environmental and Social Management Plan (ESMP) for phase I of the
proposed project. Phase I of the project as described in Section 3 of the ESIA report consists of
one road in Bajaur and four roads in Orakzai, with the stretch of road in Bajaur being 20 km long
whereas the four stretches of road in Orakzai being 2, 2, 2 and 3 km respectively.
This ESMP encompasses the following components:
Potential Environmental and Social Impacts (summary)
Monitoring Program
Institutional Agreements
Comprehensive Mitigation Plans
Most of the mitigation activities proposed in ESMP will be included under provisions in the
construction contract, engineering supervision contract and necessary agreement with the
communities.
8.2 Mitigation through Avoidance of Adverse Impacts by
Suitable Design
Negative impacts to the natural and socioeconomic environment can take place due to improper
design and management of the project. Most negative factors can be avoided (eliminated)
through the use of proper and environmentally sound technical design.
Lessons can be learnt from the construction and operation of other roads and highways built in
the country, particularly in the FATA region. A number of inherent shortcomings and defects can
be avoided by following good design principles and practices used by successful models for
development of rural road infrastructure. Record of such models is available within the Works
and Services Department and it would be made compulsory for all project implementation and
management entities to follow such a model (selected by the department) for their respective
activities.
8.3 Tender and Construction Phase
8.3.1 Impact Reduction Measures
There are specific measures required of the contractor to reduce the potential impacts of
physical works and also the proposal for monitoring contractor’s compliance / performance
during construction phase.
The contract document will contain requirements for:
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 8-2
Preparation and implementation of a health, safety and environment (HSE) Plan,
addressing occupational health, safety, and environmental aspects.
Preparation of traffic management plan, addressing movement of vehicles for
material/construction manpower transportation, full/partial road closure during road
construction, warning signs, and other necessary measures.
Preparation and maintenance of documentation record of any road accidents or site
accidents. Provision of insurance coverage to the construction workers.
Proper management of construction waste and preparation of waste management plan
Control measures for waste fuel
Reduction of oil / lubricants, spill or leakage, noise and dust level
Rehabilitation of areas used for construction detours and sites used to temporarily store
construction materials.
Use and proper maintenance of equipment with appropriate noise and smoke
abatement
Restoration of borrow areas or stone quarry areas.
Other requirements as obligation of the contractor, emanating from the Mitigation Plan
and the ESMP.
Specific provision will also include mandating the use of formal health including
protection against communicable diseases, safety and group insurance measures to
minimize accidents and avoid fatalities during the construction process.
Advisory element to address a number of other issues will also be included in the
contract. These will include Implementation of ESMP and its monitoring through the
Environmental Mitigation and Monitoring Plan (EMMP).
8.3.1.1 Road Closures
If a road would have to be closed for a particular duration of time, it must be done with the
permission of the Works and Services Department and in consultation with the communities in
the vicinity. Furthermore, to the extent possible alternate route(s) are to be provided through
diversions, adequate signage and traffic management plan.
8.3.1.2 Cultural and Historical Resources
Local communities will be requested to identify all known sites of cultural and historical
significance in the project area that may be affected by the project, prior to the commencement
of the construction activities to ensure adequate measures for their protection by the contractor
during construction phase.
8.3.1.3 Archaeological Field Support
The Works and Services Department will request the Archaeological Department to make
available (where required) a qualified archaeologist to conduct field investigations when
important search work and new material sites are opened. No such site is yet in view but just in
case it does; the services of archeologist would be available.
8.3.1.4 Graveyard and Burials
If unrecorded graveyards and / or burials are found during the course of construction activities,
the supervisions agency will contact and work with local communities within the immediate
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 8-3
project area to allow for possible identification of the remains and where required, properly
undertake relocation and burial.
8.3.1.5 Local Employment
The contractor is advised to hire all unskilled labor from the local communities. Furthermore,
where individuals with the required skills and experience are available from the local
communities they should be preferred for jobs. It is unlikely, due to the existing level of
education and technical capacity of the local communities, that the contractor would be able to
find any skilled workforce within the project area and so may hire it from elsewhere. There is no
legal obligation to hire local labor but it is desirable that maximum employment benefits are
made available to local communities.
8.3.1.6 Resources use Agreement–Construction Materials
Earth is available in the state-owned lands on either side of the road. It has been estimated that
the entire quantity of the earth required for the construction of the proposed road
infrastructure will be available from the proposed borrow sites. The stream-bed sand is fit for
use in rough construction. Stones may be available from local or nearby quarries. Yet there may
be a need for additional agreement with public to obtain certain materials. In that case
agricultural land would be given the lowest priority in the procurement of fill material.
Whenever the borrow pits are dug, considerable care should be taken in their location. The site
may invariably be rehabilitated after use. Ideal situation would be that site is made good to a
condition almost similar to that prior to the project. It will be helpful if photographs of pre–
project condition are used for the purpose of comparison.
8.3.1.7 Resources Use Agreements - Water
The contractor will be required to provide details of water demands and indicate source of
water prior to the start of construction. Disposal plan for wastewater without polluting the
fertile soil, clean river water or ambient air, will be produced by the contractor for approval of
Executive Engineer and the Project Manager (PM) assisted by an Environmental Consultant.
8.3.2 Pre–Tender Conference
To ensure full understanding of above clauses by prospective contractors, all prequalified
contractors will attend a pre–tender conference, where they will be briefed on their
responsibilities with regard to environmental, social, health and safety issues. These briefings
will review specific provisions of the construction tender documents and contracts.
8.3.3 Pre-Construction Coordination Meeting
Once the contract is awarded the contractor will be required to regularly attend coordination
meeting(s) with project authorities and the local communities. At these meetings, the Project
Manager (PM) and the Executive Engineer (XEN) will further explain the Terms and Conditions of
the Contract, especially those narrated above, if possible.
8.4 Operational Phase - Management of Operational Impact
The Project will also address future maintenance impacts. These will be implemented through
specially requested financial support from Works and Services Department (FATA) and the Multi
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 8-4
Donor Trust Fund (MTDF) as recurring budget to avoid any deterioration in the functioning of
the newly constructed and rehabilitated roads. Maintenance agency / contractor will be
required to follow procedures similar to those for the construction contractor concerning proper
disposal of construction waste, control measures, for waste fuel, oil and lubricants and adoption
of health and safety measures for personnel.
8.5 Management of Social Impacts
To assess, address and manage the social aspects of the project, a social assessment has been
included in this ESIA during which social impacts and their mitigation have been identified in
detail. In addition, social impacts will be managed through the Social Framework Agreement
(SFA), which will be made available with the XEN as representative of the Works and Services
Department, Construction Supervision Consultants (CSC) the contractor and the communities
residing within the project area.
The SFA will be drafted and signed when the project is finally approved and the implementation
commences. A draft illustrative agreement has been provided which may be updated, if
necessary.
8.6 Environmental Mitigation and Monitoring Plan (EMMP)
The environmental mitigation and monitoring plan (EMMP) is a very important component of
the ESMP. The implementation of the ESMP will be the contractual obligation of the contractor.
For that the contracted will engage a full time technical staff capable of a carrying out the
prescriptions of the ESMP as contractual obligations under the contract document. The
engineering consultants will have on their team a full time professional level environmental
expert to provide an overall professional cover to the environmental monitoring process and the
procedures and develop required reports and point out any gaps in the implementation of the
mitigation measures or enforcement of the prescriptions of the ESMP. In Works and Services
Department there is an Environmentalist, who will be responsible for the monitoring and
evaluation (M&E) of environmental and social mitigation measures at the detailed design,
bidding, construction and implementation stages. The results of the M&E activities will be
included in the reports prepared for the project manager and XEN of the Works and Services
Department.
The monitoring program will comprise site inspection designed to determine contractor’s
compliance or otherwise with ESMP and applicable regulations and statutes.
A monitoring program designed providing ex-ante and ex-post quality assessments of the
environmental parameters of the project are not proposed. It is however to be noted that:
Project impacts will be identified by site inspections and in discussion with site in
charge(s), XEN and local communications
The project is a localized activity and changes in the environment are likely to be
minimum.
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 8-5
Except for some unanticipated factors, originating from offsite facilities, the project is
not likely to cause significant discomfort/disturbance to communities. For offsite
facilities, if needed, inspections (and response to complaints, if any) will indicate
whether any further action needs to be taken or not.
The proposed site inspections by the consultants’ environmentalist and the Works and Services
Department will be carried out on regular basis as per their own time schedules, but not
necessarily as minimum level of M&E activities by each monitoring agency. The program
outlined in Table 8.1 below should be observed.
Table 8.1: Minimum Monitoring Plan
Project Phase Proposed Minimum Inspections
Pre-Construction
One visit to main project site
One visit each to proposed Borrow site, Camp site, Material Depot site, Proposed machinery yard and other proposed sites.
One visit to each community
One visit to proposed water sources
Construction
Visits to main project site at 20%, 50%, 75% and 100% completion stage.
One visit to other project sites every quarter.
Two visits per quarter in response to complaints
Post Construction
One visit to each construction site (part) site during construction.
Two visits to each component site 12–18 months after the completion of the highway
Two visits per quarter on response to any complaints
It is also anticipated that additional inspection will be required in response to any complaints by
local communities. So another two visits per quarter may be budgeted for M&E personnel. All
officers concerned with M&E will prepare their own M&E Implementation Plans for information
of all concerned. All M&E personnel will be given optimal mobility and flexibility to implement
their M&E implementation plans.
8.7 Visits / Inspection Authorization
For the inspection process to function, access to the project and other related sites must be
guaranteed by Works and Services Department. Accordingly, the contract documents and
operating documents will incorporate a phrase with similar intent to that outlined below:
Any officer authorized in writing by the Works and Services Department or
Environmental Protection Agency (EPA), may at any time enter any premises whether
prescribed or otherwise, and may:
o Examine and inspect materials, machinery, control equipment and monitoring
equipment. Take samples of any pollutants that are emitted, discharged or
deposited, or are likely to be or are of a class or kind that are usually emitted,
discharged or deposited from such premises.
o Examine any books, records or documents relating to the performance or use of
such equipment, control equipment, monitoring equipment or relating to the
emission, discharge or deposit from such premises.
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 8-6
o Photograph such premises as he/she considers necessary or make copies of any
book, records or documents seen in the course of such examination.
8.8 ESMP Implementation Arrangements
8.8.1 Institutional Arrangements
The overall responsibility of ESMP implementation will rest with the Chief Engineer of the Works
and Services Department, FATA. A Project Management Unit (PMU) will be established headed
by the Project Director (FATA ERRP). The PMU will ensure the implementation of ESMP through
Field Implementation Units (FIU) which will be established within each of the agency (district)
offices of W&SD in Bajaur and Orakzai Agencies. PIUs will be headed by the respective Executive
Engineer (XEN) and supported by Sub Divisional Officer (SDO) and Deputy Director Environment
(DDE).
A professional consulting firm will be responsible for Contract Administration & Construction
Supervision. The firm will be fully empowered as the ‘Construction Supervision Consultant’ (CSC).
The CSC will have a full time field based environmental specialist to ensure the implementation
of ESMP. The environmental specialist of CSC will also develop training modules and conduct
environmental trainings for the contractor’s staff.
The contractor will be responsible for the implementation of ESMP. A full time field based
environmental expert will be hired whose responsibility will be to monitor and report all the
ESMP implementation related activities on a regular basis.
An independent external monitor will be hired to monitor and provide external monitoring
reports of the ESMP implementation. The figure below illustrates the institutional set-up for the
ESMP and EMMP.
The organogram below gives the overall implementation arrangements for the project.
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 8-7
Figure 8.1: Organogram for Implementation of ESMP
8.8.2 Management Responsibility
The following entities constitute the project organization. Their specific roles and responsibilities
for environmental management during the construction phase of the project are explained in
the subsequent paragraphs.
(i) The Implementation
Agency (IA)
Works and Services Department, FATA through the Project
Management Unit (PMU) will be responsible for the
implementation of ESMP. Main responsibilities of the IA will be to:
i. Monitor the ESMP implementation.
ii. Review monthly, quarterly and annual progress reports
from contractor, CSC and IEM as vetted by the project
consultants.
iii. Facilitate coordination with the XEN.
iv. Submitting monthly and quarterly progress and monitoring
reports to the Client.
v. Hiring of external monitor as per the guidelines and
approval of the client to monitor the implementation of
the ESMP.
vi. Provide financing to cover all expenses for the tasks
included in the project budget.
WS&D (FATA), Project Management Unit
Field Implementation Units Executive Engineer (XEN)
Sub Divisional Officer (SDO)
Supervision Consultant Environmental Specialist
Independent Environment Monitor
Deputy Director Environment (DDE)
Contractor
Contractor’s Environmentalist
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 8-8
(ii) Construction Supervision
Consultant
Construction Supervision consultant (CSC) will be responsible for
the supervision of contractor for the implementation of civil works
as well as ESMP. Full time field based environmental and social
expert will be employed to ensure the implementation of ESMP.
The CSC will also be responsible to design and impart
environmental and social trainings for the contractor’s staff.
(iii) Contractor The engineering procurement and construction (EPC) company
contracted by the implementation agency to carry out the
construction of the proposed roads. Implementation of the ESMP
will be the responsibility of the contractor for which well-qualified
environmental engineer and a full time field based environmental
expert will be employed.
All mitigation measures for adverse impacts proposed in the ESMP
will be duly and timely implemented in letter and spirit. For this
purpose, daily, monthly and annual checklists will be formulated
and maintained.
(iv) General Assistance to all
above agencies in their
respective tasks
Works and Services Department, Executive Engineer (XEN) of the
Project will facilitate communications, logistics and data collection
as and when required. . For all M&E activities in the field the XEN
will act as the focal person.
(v) External Monitoring An Independent Environmental Monitor (IEM) will be engaged by
the Works and Services Department to periodically monitor the
implementation of ESMP. The IEM will monitor the compliance
status develop external monitoring reports on a quarterly basis.
8.8.3 Summary of Finances for Various Agencies
As provided above in different paragraphs, following is the summary of Finances for various tiers
of ESMP implementation:
Agency Financial Agreement
Contractor’s technical staff for ESMP implementation and allied logistics.
Cost provided in BOQ as per PC–1.
Consultants environmental expert, the support staff and allied logistics.
Included as consultants fees in the consultants costs as per PC–1.
Environmental officer(s) of the Works and Services Department consisting of Deputy Director Environment and Deputy Director Sociology, support staff and allied logistics.
Included in the Works and Services Department Budget estimate as per PC–1.
Executive engineer Included in Works and Services Department Budget as per PC–1.
Donor external monitoring mission Included in donor procurement costs.
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 8-9
8.8.4 Reporting and Supervision
The environmental expert of the CSC will receive information from contractor’s environmentalist
in the form of periodical reports as well as inspection notes based upon his monitoring and
inspection at the project site. This information will make a basis for the environment section /
unit of the Works and Services Department for their further reporting. All reports will be location
and activity specific. The reports will especially identify areas of contractor’s non–compliance
with the ESMP and provide guiding remarks on actions to be taken. The significance of the non–
compliance will also be noted.
The Works and Services Department will prepare and submit periodical reports to the Bank on
quarterly basis. Copies of these reports will also be sent to the Project Manager as well as the
Project Director for their information and necessary action. The non-compliance by contractor
will be linked with the system of payment of bills by classifying the non-compliances as minor,
moderate or major depending upon the period over which the non-compliance is continued.
Within one month the non-compliance is minor, after two months it is moderate and after three
months it becomes major.
The Environmental Expert, in his routine reports, will include a summary status of activities
relating to the ESMP. As and when necessary, supplemental reports with greater detail than the
routine reports should also be prepared. These reports will reinforce the information for the
environmental staff of the Works and Services Department who may use it for sending
additional reports to the Bank.
Works and Services Department will also engage Independent Environmental Monitor (IEM) to
periodically verify the effective implementation of the ESMP, IEM will submitreports to the
Works and Services Department on regular basis.
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 8-10
8.9 Mitigation Plans
Table 8.2: Environmental Impacts during Construction Phase
Impact
Mitigation Responsibility
Mitigation Measure Contract and Social
Framework Agreement (SFA) Clauses
Implementation Supervision Monitoring
1. Soil and Landscape
1.1 Physical Scarring of landscape
Unnecessary widening beyond the proposed design of the road shall be avoided at straight portions and on bends. The movement of construction equipment and vehicles will be restricted to work areas. Safe driving practices must be encouraged to minimize soil erosion. A speed limit of 40 kmph will be observed and monitored in the project area, and off-road driving strictly prohibited. The alignment of the widening will be selected so as to minimize the clearing of vegetation and minimized trees cutting. Steep cut-and-fill will be avoided, and a gentle side slope maintained where possible. Retaining walls will be constructed where necessary.
Contractor’s obligation as defined in the Tender and Contract Documents
Contractor in Collaboration with XEN
Environmentalist of CSC
(i) DDE of Works and Services Department (ii) Independent Environmental Monitor (IEM)
1.2 Increased risk of land slippage and accelerated soil erosion
The one clear passage for transport will continue to be maintained during the project, and measures such as spraying water implemented to reduce dust emission and erosion. All sections of the road close to or on steep slopes will be closely monitored for any signs of soil erosion or land slippage. Environmental monitoring will involve checks for any signs of soil erosion so that remedial actions, such as applying water and compaction, can be implemented. The state of the work corridor will be monitored during project to prevent any spillover outside the corridor. The Executive Engineer (XEN) of the Works and Service
Contractor’s obligation as defined in contract and the Tender document
Contractor and XEN CSC (i) DDE (ii) IEM
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 8-11
Impact
Mitigation Responsibility
Mitigation Measure Contract and Social
Framework Agreement (SFA) Clauses
Implementation Supervision Monitoring
Department (FATA) will allow local readjustments in foundation treatment or any other small changes to the contractor.
1.3 Blockage of natural drainage.
The natural drainage pattern will not be disturbed, and culverts will be constructed where required. Surplus soil and cleared vegetation will be disposed of so as to avoid disturbing the natural drainage.
Contactor’s obligation defined in the Tender and contract data and SFA with community
Contractor and XEN CSC (i) DDE (ii) IEM
2. Location of Labor Camps, Material Depots, Equipment Yards and Approach Roads
2.1 Location of camps near sensitive receptors like water resources, private lands without prior consent of landowners and dumping and storage of construction material equipment in private lands may cause adverse impacts to the environment within the vicinity of the facilities
The contractor will, in consultation with XEN, select the location of all these facilities within a prior approved land. The camp/other site facilities will be established on a flat land without much natural vegetation, at least 500 m away from the communities. Satellite imagery can also be used to select the suitable sites, to record the pre-construction conditions, and to monitor the condition of these sites during and after the construction phase.
Contract Documents and Contractor’s obligations
Contractor and XEN CSC (i) DDE (ii) IEM
3. Oil Spills from Construction Machinery
3.1 Any leakage or spillage of diesel, oil or any other chemical will contaminate the soil which may in turn impact the water
Contractor will apply strict rules on his workers and labor to ensure that no spill or leakages are caused. All fuels, oils and bitumen will be stored appropriately, with concrete padding and bunding for containment in case of leakage. If the spills or leakages do take place, it must be
Contract Documents and Contractor’s obligations
Contractor and XEN CSC (i) DDE (ii) IEM
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 8-12
Impact
Mitigation Responsibility
Mitigation Measure Contract and Social
Framework Agreement (SFA) Clauses
Implementation Supervision Monitoring
sources, nearby community and/or productive land
followed by the treatment prescribed below as per the degree of spill or leakages. The contractor will employ the general criteria for oil and leakage at construction sites, as per standards set forth by “Guidelines for Oil Spill Waste Minimization and Management” issued by International Petroleum Industry Environmental Conservation Associate which are as follows: (Source: IPIECA Report Series, Volume-12, “Guidelines for Oil Spill Waste Minimization and Management”)
4. Earthen Embankments or Concrete Work, Edge Scouring
4.1 Poor design and inappropriate construction procedures can potentially damage the embankments, concrete works or road edges. The impact is moderately significant but can easily be mitigated
Edge Scouring of earthen embankments or concrete work must first be dealt at design stage. Wherever such a situation is anticipated, aprons should be provided to secure edges and specifications must be kept of high standards. During the construction phase this aspect should be addressed through appropriate construction methodology and employing appropriate techniques such as protection walls and rip rap. Contractor will repair all damages to the earthen embankments, concrete works, or pavement edges caused by the construction works. During the operation phase appropriate measures need to be incorporated in the Operational Manual.
Contractor’s obligation defined in the Tender and contract documents
Contractor and XEN CSC (i) DDE (ii) IEM
5. Impact of Borrowing Material from Earth Borrow Sites and Stone Quarrying
5.1 A large quantity of earth will be
The topsoil up to 30 cm shall be removed and stored prior to excavation of fill material. After completion of
Contactor’s obligation defined in the Tender and
Contractor and XEN CSC (i) DDE (ii) IEM
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 8-13
Impact
Mitigation Responsibility
Mitigation Measure Contract and Social
Framework Agreement (SFA) Clauses
Implementation Supervision Monitoring
removed from borrow pits located within the state land on either side of the road. This can potentially cause slope instability, loss of soil/land productivity, uneven terrain, and altered drainage.
borrowing the area would be leveled and the top soil would be restored to ensure no loss in productivity of land Borrow sites would not be deeper than 3 ft at any location to avoid alteration in drainage pattern and reduce the risk of soil erosion The borrow areas will be selected after obtaining approval from the XEN. The contractor will ensure that the borrowing does not cause slope instability, loss of soil/land productivity, uneven terrain, and altered drainage. Wherever possible/necessary, these places will be leveled and planted with trees using appropriate planting technology/methodology.
contract data and SFA with community.
6. Water Resources
6.1 Groundwater extraction over and above the sustainable yield will reduce the volume of groundwater available
Water will not be extracted beyond the sustainable yield limit, defined as that volume of groundwater if used that can be extracted annually from a groundwater basin without reducing the total size of the aquifer. Given that water is to be extracted from a ground water aquifer whose recharge rate, (like the actual volume of water available or its rate of depletion) is not known, the extraction will be monitored to ensure that it does not lead to irreversible environmental damage. The depth of the aquifer water table will be monitored
Contactor’s obligation defined in the Tender and contract data and SFA with community.
Contractor and XEN CSC (i) DDE (ii) IEM
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 8-14
Impact
Mitigation Responsibility
Mitigation Measure Contract and Social
Framework Agreement (SFA) Clauses
Implementation Supervision Monitoring
6.2 The local communities’ rights over water shall be recognized and adequately compensated
Water will be extracted only from a major source a main stream. The community will be compensated for the water extracted from the area’s water resources in recognition of their rights
Contactor’s obligation defined in the Tender and contract data and SFA with community.
Contractor and XEN CSC (i) DDE (ii) IEM
7. Contamination of Soil and Water
7.1 Effluents released as a result of the project activities, if not contained properly, may contaminate the soil and water
No contaminated effluents will be released into the environment without having been treated. When abandoning sumps, an extra cap of soil will be placed over them to allow compaction. Fuels, oils, and other hazardous substances will be handled and stored according to standard safety practices. Fuels, oil, and chemical storage facilities will be checked daily for any signs of leakage.
Contractor’s obligation defined in the Tender and contract documents
Contractor and XEN CSC (i) DDE (ii) IEM
7.2 Water quality is likely to deteriorate if pollutants or contaminated soil mix with surface runoff during the rains and are carried downhill to water bodies
The camps will be located as to avoid proximity drinking water sources, maintaining a minimum distance of 500 m from such natural resources. Sumps will be located in a position such that they are: Fixed in absorbent soil Down-sloped and away from the camp (and downwind, if practical) Downstream from the camp water source and above the high-water mark of any nearby water body (if any). Vehicle and equipment maintenance, including washing, will be allowed only in designated areas underlain with concrete slabs and a system to catch runoff. Solid waste (including food waste) will be segregated and disposed of as follows: Materials suitable for recycling will be stored separately
Contractor’s obligation defined in the Tender and contract documents
Contractor and XEN CSC (i) DDE (ii) IEM
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 8-15
Impact
Mitigation Responsibility
Mitigation Measure Contract and Social
Framework Agreement (SFA) Clauses
Implementation Supervision Monitoring
and sold to approved recycling contractors Combustible waste, Non-combustible, non-recyclable rubbish will be sent to a landfill Solid residue from the septic tanks will be transported to municipal sewage treatment drains. Precautions, such as drip pans, will be used to avoid any spills that may occur during fuel and oil transfer operations. Precautionary materials, including shovels, plastic bags and absorbent materials will be kept available near fuel and oil storage areas.
7.3 If allowed to leach into the ground, the contaminants may also pollute groundwater.
Sewage and other waste effluents will be handled so as to avoid contaminating surface and groundwater. Water from washing areas and kitchen will be released into sumps. An appropriately designed septic tank will be used to treat sewage, and outlets will release treated effluents into sumps. The integrity of the entire system will be maintained and monitored. Septic tanks and sumps will be built at a safe distance from any water hole, stream or dry streambed, so as to prevent the entry of surface water, and the bottom of the sump will be kept above groundwater level. Fuel tanks will be appropriately marked by content, and along with oils, and chemicals will be stored in dyked areas lined with an impervious base.
Contractor’s obligation defined in the Tender and contract documents
Contractor and XEN CSC (i) DDE (ii) IEM
8. Releases into the Air
8.1 Dust emissions from vehicular traffic
Imposing speed limits and encouraging more efficient journey management will reduce the dust emissions produced by vehicular traffic. Water will be sprinkled where necessary to contain dust emissions.
Contactor’s obligation defined in the Tender and contract data and SFA with community.
Contractor and XEN CSC (i) DDE (ii) IEM
8.2 Dust emissions Dust emissions at the construction sites will be Contactor’s obligation Contractor and XEN CSC (i) DDE
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 8-16
Impact
Mitigation Responsibility
Mitigation Measure Contract and Social
Framework Agreement (SFA) Clauses
Implementation Supervision Monitoring
from earthworks along the road
minimized using good housekeeping and management practices.
defined in the Tender and contract data and SFA with community.
(ii) IEM
8.3Exhaust fumes from vehicles and construction machinery,
All equipment, generators and vehicles used during the project will be properly tuned and maintained in good working condition in order to minimize exhaust emissions
Contactor’s obligation defined in the Tender and contract data and SFA with community.
Contractor and XEN CSC (i) DDE (ii) IEM
8.4 Emissions from asphalt plants
The asphalt plant will not be operated without properly functioning dust control system such as wet Scrubber.
Contractor’s obligation defined in the Tender and contract documents
Contractor and XEN CSC (i) DDE (ii) IEM
9. Noise and Vibrations
9.1 Equipment and vehicular noise
Equipment and vehicles will be maintained on regular basis
Contactor’s obligation defined in the Tender and contract data and SFA with community.
Contractor and XEN CSC (i) DDE (ii) IEM
9.2 Blasting noise and vibrations
Plan for blasting times to be outside of hours when people are most disturbed by noise (such as prayer and night times). Develop and implement standard operating procedures, blasting rules and a safety management plan that: delineates the danger zone associated with each blast of at least 500m and clear people and animals from this zone before, during and after (30 minutes) each blast; provides an audible warning at least three minutes before blast is fired; and Informs local communities of blasting timetable in advance and provide adequate notices of blasts are required outside of the planned schedule The use of blasting will be kept to an absolute minimum. Rock basting near the communities will be avoided to
Contactor’s obligation defined in the Tender and contract data and SFA with community.
Contractor and XEN CSC (i) DDE (ii) IEM
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 8-17
Impact
Mitigation Responsibility
Mitigation Measure Contract and Social
Framework Agreement (SFA) Clauses
Implementation Supervision Monitoring
the extent possible. A detailed protocol for management and monitoring of blasting operation will be established. The intended target of the blasting will be marked prior to its start. If any significant damage to the ground is observed, the blasting parameters will be modified or the blasting will be re-planned. Standard safety procedures for handling explosives will be used to protect the staff, the community, and the environment
10. Ecology and Biodiversity Disturbance
10.1Temporary or permanent surface vegetation clearance during construction
No clearance of vegetation or killing/hunting/trapping of wild animal will be allowed. Compensation will be paid for any tree cutting on the private land. C compensatory tree plantation will be carried out for Forest Department owned trees and for each tree removed, five saplings will be planted. The Project will ensure appropriate care and monitoring of this plantation. Camps and other temporary facilities will be established in a manner that minimizes loss of natural vegetation including trees. Borrow material will be obtained without causing any damage to the natural vegetation.
Contactor’s obligation defined in the Tender and contract data and SFA with community.
Contractor and XEN CSC (i) DDE (ii) IEM
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 8-18
Table 8.3: Social Impacts
Social Risk Mitigation Responsibility Construction Stage
1. Land Acquired on Temporary and Permanent Basis
A separate study Resettlement Action Plan (RAP) has been carried out to address the issues related to acquisition of private assets and compensation. The same study shall be submitted separately.
2. Increased risk of accidents caused by partial closure of road during construction
During construction activities, traffic flow will be disturbed. At sections passing through populated areas, there will be limited scope for providing diversion tracks for the mobility of local and thorough traffic that will increase the risk of accidents.
Proper site-specific measures will be carried out in consultation with supervisory consultants to ensure the safety of population residing along and around the project corridor. A detailed Traffic Management Plan (TMP) will be prepared and implemented by the contractor with the approval of the Works and Service Department (FATA), XEN
Contractor / XEN Construction
Necessary measures will be taken to ensure the safety of traffic during construction, including barricades (including signs, pavement markings, flags, and lights) erected as required by the Works and Services Department (FATA) and set up as per local regulations.
Contractor / XEN Construction
The construction work will be managed such that part of the carriageway at a time is upgraded leaving the other part available to serve one-way traffic. Construction work will be carried out in small stretches instead of a long stretch.
Contractor / XEN Construction
As a result of road improvement the traffic volume will increase during operation stage, there may be safety hazards for the locals residing along the edge of the road as well as vehicular traffic.
During operation stage Works and Services Department (FATA) will make arrangements with some organization/contractor for proper maintenance and operation of the road. Periodic inspections will be made by contracted firm particularly in monsoon season to identify the landslide areas and their remedial measures. In case of any land slide contracted firm will clear the road within minimum time. For this purpose the firm should be fully equipped and there should be contingency plan in case of any emergency/natural disaster.
Works and Services Department
Operation
3. Health and Safety Hazards
Occurrence of The contractor will comply with the safety precautions for Contractor / XEN Construction
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 8-19
Social Risk Mitigation Responsibility Construction Stage
accidents/incidents during the construction activities, particularly from excavation activities is generally common. The workers and general public residing along the project corridor or near the work sites will particularly be at risk. In addition, contractor staff while on work may get injuries.
construction workers as per International Labor Organization (ILO) Convention No. 62, as far as applicable to the project contract. The construction workers will be trained in construction safety procedures, social awareness, equipping all construction workers with safety boots, helmets, gloves, and protective masks, and monitoring their proper and sustained usage. Contractor will ensure the provision of medicines, first aid kits, vehicle, etc. at the campsite.
4. Gender Issues
Findings of the socioeconomic survey reveal that the privacy of women is a major cause of concern for the communities of the project area. Due to the project activities local women many not be able to perform their daily outdoor chores. Women in the project are participate in other outdoor activities such as livestock rearing, bringing of potable water, collection of fire wood etc. that may also be affected by the project activities.
The Contractor will select the specific timings for the construction activities particularly near the settlements, so as to cause least disturbance to the local population particularly women.
Contractor / XEN Construction
The Contractor will carry out the construction activities in such a way that the open defecation timings by the local community particularly women, should not be affected. The normal defecation timings are early in the morning and at late in the evening. So, the Contractor will have to take care of these timings.
Contractor / XEN Construction
Findings of the socioeconomic survey reveal that the privacy of women is a major cause of concern for the communities of the project area. Due to the project activities local women many not be able to perform their daily outdoor chores. Women in the project are
Contractor will take due care of the local community and observe sanctity of local customs and traditions by his staff. Contractor will warn the staff strictly not to involve in any unethical activities and to obey the local norms and cultural restrictions particularly with reference to women.
Contractor / XEN Construction
During construction activities, if privacy of the nearby households is affected, the Contractor will inform the house owner to make some arrangements. Similarly, Contractor will take care as much as possible that the construction activities should not affect the
Contractor / XEN Construction
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 8-20
Social Risk Mitigation Responsibility Construction Stage
participate in other outdoor activities such as livestock rearing, bringing of potable water, collection of fire wood etc. that may also be affected by the project activities.
privacy particularly with reference to women.
5. Social Conflicts and Employment of Locals on the Project
Both the locations have an over-whelming majority of one sectarian group. In such a situation, presence of outside construction workers may cause some degree of social disruption and even active disputes with the local community as a result of differences of religious opinions and culture. This particularly relates to the non-local work force adhering to a different sect that many result in escalation of sectarian issues. This coupled with decline of economic activities and the disruption of the privacy of women folk working in the fields or even in the yards of their houses, should the house be lying at a lower elevation than the working sites. Likewise the risk of theft of the community assets by the Contractor workers and vice versa may occur.
Good relations with the local communities will be promoted by encouraging Contractors to provide opportunities for skilled and unskilled employment to the locals, as well as on-the-job training in construction for young people. Sectarian sensitivities should be given due consideration in engaging labor for the project. Where possible local labor should be engaged for the project, this will not only provide economic opportunities for the locals but will help the contractor in gaining local trust and security.
Contractor / XEN Construction
6. Rise in the Prices of Essential Commodities
Due to induction of outside labour for project works, the
The project will exert no negative impacts on the prices of essential In terms of labor induction the project will exert no
Contractor Construction
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 8-21
Social Risk Mitigation Responsibility Construction Stage
demand for basic items will increase thereby causing an increase in the prices of essential commodities
significant impacts on the prices of essential commodities. To avoid risk of such price hikes, majority of the unskilled and semi-skilled labor will be recruited from the local areas. As such there will be no extraordinary increase in the demand for essential or other commodities. The contractor should normally procure the field camps supplies from the main markets of Kohat, Khar, Peshawar or any nearly by commercially active city.
7. Use of Local Water Supplies and Other Common Resources
The campsites will also be depending on local water supplies to meet personal use and construction requirements. This will put strain on the limited supply of water, putting the construction workers in competition with the locals for the resource. Local water may be affected due to implementation of project both in quantity as well as quality.
The contractor will explore the alternative water resource so that the existing community water resources are not impacted. The Contractor for campsite facilities as well as construction purposes will exploit no existing water source under the use of community.
Contractor Construction
The project campsites may also use other local resources like fire wood, game and public resources. This again will affect the availability of these resources to the locals, as already these areas have very limited resources. Locals have devised a finely balanced way of life in these harsh conditions and any external influence threatens to disturb this balance.
The Contractor prior to start of construction activities will ensure availability of water for campsite facilities and construction purposes. As per local customs and government regulations, the contractor will seek approval from the local community and government for exploitation of the water resources.
Contractor / XEN / Local Govt.
The Contractor will be required to maintain close liaison with local communities to ensure that any potential conflicts related to common resource utilization for project purposes are resolved quickly.
Contractor
The contractor will prepare guidelines for the workers for minimizing the wastage of water during construction activities and at campsites.
Contractor
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 8-22
Social Risk Mitigation Responsibility Construction Stage
The presence of a large number of construction workers and other associated personnel may lead to the spread of communicable diseases such as hepatitis.
The Contractor should excise due diligence in avoidance and control of such mishaps. Contractor will arrange awareness programs for the communicable diseases in the field camps on regular basis by a qualified expert/doctor. Contractor will provide recreational facilities such as playing volleyball of football after the work hours. Similarly, he will provide indoor recreation in terms of radio and TV at the eating-place. The Contractor will ensure regular medical check–up of the camp staff from a qualified doctor on fortnightly basis. If any person found affected with any of the transmittal diseases will be immediately shifted from the camp to the hospital for detailed check–up and treatment. The cost will be borne by the Contractor. Contractor will restrict his permanent staff to mix with the locals to avoid any social and health problems.
Contractor Post -Construction
The construction activities may damage any nearby parks or recreation areas used by the local population or the tourists.
The Contractor will ensure the restoration and rehabilitation of construction and campsites on completion of the project. Works and Service Department (FATA) will develop parks, particularly for children and ladies, at appropriate sites along the road to provide them better recreational opportunities. This will also attract the outside tourists as well, thus increasing the incomes of the local people through increased socio–economic activities. The Works and Service Department (FATA) would carry out tree plantation along the road.
8. Restricted Mobility
During the construction phase the general mobility of the local residents and their livestock in and around the project area is likely to be hindered. Likewise access to the natural resource may be affected. This
The contractor will ensure that the mobility of the local communities and their livestock is not hindered by the construction activities. The contractor will provide crossing points at the road at appropriate places to facilitate the people for going across the road for their daily works and having free access to the natural resources.
Contractor / XEN Construction
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 8-23
Social Risk Mitigation Responsibility Construction Stage
particularly implies to the women folk and children, especially in the context of FATA where women observe proper veil and do not interact with non-locals. Construction activities, particularly excavation and movement of haul truck and machinery may disrupt the existing tracks leading from the main road to settlements. This will limit the accessibility of the local population to the main road.
Generally the contractor will avoid using the village tracks for hauling the construction material. However, if it is unavoidable, the existing ones will be widened, overlaid with shingle or surface treated to accommodate local as well as contractors traffic under the approval of the Project Engineer.
9. Adverse Effects on Graveyards and Archaeological Sites (if any)
The shifting of graves falling in the RoW may cause social disruption leading to possible conflicts, ultimately affecting the project works
A detailed consultation with the local communities would be carried out. After the agreement and approval of the local community the affected graves would be shifted to some other site. For this, a proper shifting allowance would be provided. The Contractor will be required to instruct the construction crew(s) and site supervisors in archaeological / cultural / historical site and artifact recognition, conservation procedures, and temporary site protection. In case of a chance find during excavation, the Contractor must halt work at the site immediately, inform the XEN and notify the Department of Archaeology and Museums through the Works and Services Department.
Contractor / XEN Contractor / XEN / Archaeological Department
Construction Construction
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 8-24
Table 8.4: Operational Phase
1. Strict application of prescribed Monitoring & Engineering plan
Works and Services Department Staff
Works done through contractor to according to strict specification and in commutation with communities
XEN In charge of the road
Officer(s), authorized by Works and Services Department
2. Continuous evaluation of design efficiencies
Works and Services Department Staff
Works done through contractor to according strict specification and in communication with communities
XEN In charge of the road
Works and Services Department or whosever is i/c of the road
3. Understanding and training of operational manual
Works and Services Department Staff
Works done through contractor to according to strict specification and in communication with communities
XEN In charge of the road
Works and Services Department or whosever is i/c of the road
4. Environmental Annual Audit
Works and Services Department Staff
Works done through maintenance contractor to according to strict specification and in communication with communities
XEN In charge of the road
Works and Services Department or whosever is i/c of the road
5. Regular Maintenance of engineering works
Works and Services Department Staff
Works done through maintenance contractor to according to strict specification and in communication with communities
XEN In charge of the road with the assistance of contractor
Works and Services Department or whosever is i/c of the road
6. Continued Public Consultant
Works and Services Department Staff
Works done through contractor to according to strict specification and in communication with communities
XEN In charge of the road
Works and Services Department or whosever is I/c of the road
7. Continued Gender issues and women Consultants
Works and Services Department Staff
Works done through contractor to according to strict specification and in communication with communities. To have gender-neutral policy
XEN In charge of the road with the assistance of contractor
Works and Services Department or whosever takes over the management and maintenance of the road
8. Refresher courses for the operational staff
Works and Services Department Staff
Works done through contractor to according to strict specification and in communication with communities.
XEN In charge of the road with the assistance of contractor
Works and Services Department or whoever takes the management and maintenance of the road
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 8-25
8.10 Environmental Monitoring
8.10.1 Compliance Monitoring
The environmental monitoring will be carried out with the help of checklists prepared on the
basis of the mitigation plans provided in Tables 8.2 and 8.3. These checklists will be filled by the
contractor’s environment specialist on a regular basis, and provided to the CSC. All non-
compliances recorded in the filled checklists will be followed up for remediation. The summary
of filled checklists, non-compliances and remedial actions will be included in the progress
reports.
8.10.2 Effects Monitoring
Works and Services Department will engage a competent consultant to conduct effects
monitoring on a periodic basis. The effects monitoring plan is provided in the Table 8.5. The
overall objective of the effects monitoring is to ensure that the key environmental parameters in
the project area remain within the acceptable limits specified by the National Environmental
Quality Standards (NEQS) (and other relevant benchmarks) throughout the project execution.
For this purpose, the Independent Environmental Monitor (IEM) will carry out the periodic
sampling, monitoring, and analysis of the key environmental parameters specified in the ESMP
and provide their results to the Works and Services Department.
8.10.3 Third Party Monitoring
Works and Services Department will engage a suitable consultant to carry out environmental
audit of the project on a bi-annual basis. During these audits, the ESMP compliance and its
effectiveness will be assessed. This monitoring will help identify weaknesses in the ESMP
implementation and also recommend the corrective measures.
8.10.4 Checklists for Environmental Monitoring
For the purpose of conducting environmental monitoring, the following checklists will be
prepared and used at the site:
i. Campsite Checklist
a. Location of labor camps, material dumps, equipment yards and approach roads
b. Pollution from diesel and other oil spills from machinery
c. Smoke from burning of waste material or burning firewood
d. Soil Compaction due to Labor Camps and machinery yards.
e. Infection diseases in Labor employees and nearby public.
f. Water sources used and its impact on community water sources
ii. Borrow Area and Quarries Checklist (for each site)
a. Impact of taking borrow material from earth borrow site.
b. Access to other construction materials.
iii. Waste Material Disposal
a. Site for disposal of waste construction material
b. Material and construction waste management after completion of road
construction
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 8-26
c. Diesel and other fluids spilling over to the construction site machinery.
iv. Construction Site Checklist
a. Adjustments with unstable locations appearing during construction.
b. Limitations of construction sites resolved appropriately.
c. Earthen embankment or concrete work edge Scouring.
d. Discharge to unstable slopes or leakages on construction.
e. Any damage / discharge diversion of water to any spur/bund avoided.
f. Any discharge spill or dumping on any building or house on any surface water
body
g. Effect on surface flow conditions in case of rain.
h. Dust smoke and other polluting impacts from construction machinery.
i. Dust or other pollutants from stored material / spoil heaps.
j. Noise from use of old or outdated machinery.
k. Noise due to blasting in hilly tract
l. Public safety at construction site.
m. Health and safety of labor and employees at construction site.
v. Water Extraction Point Checklist
a. Impacts on source of construction water.
b. Impacts on sources of surface water.
c. Impacts on sources of groundwater.
d. Impacts on sources of drinking water.
vi. Road Checklist
a. Drains, paths roads crossed by moving machinery and the damage suitably
repaired.
b. Impacts on roads used for transport of construction material.
c. Impact of stone quarrying.
vii. Operational Checklist
a. Strict application of prescribed M&E plan.
b. Continuous evaluation of design efficiency.
c. Understanding and training of operational manual.
d. Annual environmental audit.
e. Regular maintenance.
f. Staff welfare.
g. Continued public consultation.
h. Continued mitigation of gender issues and women consultation.
i. Refresher courses for operational staff.
j. Staff and labor colony reconstruction.
k. Construction of some additional / support structures.
viii. Biological Checklist
a. Damage to Flora.
b. Damage to Fauna.
c. Damage to Fisheries (where applicable)
d. Impact on adjacent open lands.
e. Impact on Endangered species.
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 8-27
ix. Sociological Checklist
a. Impact on existing services, education, health, electricity, water supply,
communication.
b. Impact on local ethnicity, tribal tension, community rivalries and canal water
disputes.
c. Impact on land ownership.
d. Adverse effect on cultural and archaeological heritage.
e. Chance find during construction.
f. Graveyards or burials.
g. Employment.
h. Women status, exposure to employment and education opportunities
i. Cultural reunion through better communication.
j. Market opportunities.
k. Recreation opportunities and Tourism.
x. General Check List
a. Is ESIA complete
b. Is ESIA, IEE, training complete
c. Is HSE management complete
This monitoring plan will cover the entire project implementation period, which will be 24
months.
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 8-28
Table 8.5: Effects Monitoring Plan
Project Stage Parameters Details Applicable Standard
Location Frequency Duration
Air Quality
Pre-construction PM10, SO2, NOX, CO
15 m downwind from the edge of the pavement and asphalt plant location
NEQS for Ambient Air Quality; WHO
Three locations along the road, and near the asphalt plant site
Once; prior to construction commencement
Continuous 24 hours
Construction
PM10, SO2, NOX, CO, HC
40 m downwind from Hot Mix Plant and Asphalt Plant
NEQS for Ambient Air Quality; WHO
Three locations along the road, and near the asphalt plant
Once in 4 months Continuous 24 hours
PM10, SO2, NOX, CO, HC
15 m from pavement NEQS for Ambient Air Quality; WHO
Stretch of highway where work is in progress
Once in 4 months Continuous 24 hours
Water Quality
Pre-construction Pb, BOD5, total coliforms, fecal coliforms, TDS
Community water sources NEQS for Drinking Water; WHO
5 locations near the CoI-2 (RoW, campsite, asphalt plant site)
Once about a fortnight before contractor mobilization
-
Construction
Common ions, Pb, BOD5, total coliforms, fecal coliforms, TDS
Community water sources NEQS for Drinking Water; WHO
5 locations near CoI-2 (number of locations to be determined according to requirement)
Once in 4 months -
Common ions, TSS, TDS, Turbidity
River water near the CoI-2 NEQS/other relevant standards
5 locations near CoI-2 (number of locations to be determined according to requirement)
Once in 4 months -
32 parameters per the NEQS
Waste effluents from camps, asphalt plant and offices
NEQS camps, asphalt plant and offices Once in 4 months -
Noise
Pre-construction Noise level on dB(A) Scale
15 m from edge of pavement /site for other facilities
NEQS standards for Ambient Noise; WHO
Three locations along stretch of highway where work is in progress; near asphalt plant site; near camp site
Once about a fortnight before contractor mobilization
24 hours
Construction Noise level on 7 m from equipment / NEQS; WHO At equipment yard, asphalt plant and Once in 4 months 24 hours
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 8-29
Project Stage Parameters Details Applicable Standard
Location Frequency Duration
dB(A) Scale machinery construction site
Noise level on dB(A) Scale
15 m from edge of pavement /other facilities
NEQS standards for Ambient Noise; WHO
Three locations along stretch of highway where work is in progress; near asphalt plant site; near camp site
Once in 4 months 24 hours
Soil
Construction Oil and grease Relevant international standards
Three locations in equipment yard and other locations specified by CSC
Once in 4 months -
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 8-30
8.11 Environmental and Social Trainings
The capacity building and awareness raising of the project staff for the environmental and social
aspects is critically important to ensure effective implementation of the ESMP and its various
elements particularly the EMMP. The supervision consultants (CSC) and the contractor will be
responsible to impart these trainings. The indicative training plan is presented in Table 8.6,
which will be finalized by the CSC.
Table 8.6: Environmental and Social Trainings
Contents Participants Responsibility
General environmental and socioeconomic awareness; Environmental and social sensitivity of the project area; Key findings of the ESIA; Mitigation measures; EMMP; Social and cultural values of the area.
Selected project management staff
CSC
General environmental and socioeconomic awareness; Environmental and social sensitivity of the project area; Mitigation measures; Community issues; Safety issues; Awareness of transmissible diseases Social and cultural values.
All site personnel CSC and Contractor’s Environment Specialist
EMMP; Safety issues; Waste disposal
Construction crew Contractor’s Environment Specialist
Road safety; Defensive driving; Waste disposal; Cultural values and social sensitivity.
Drivers Contractor’s Environment Specialist
Camp operation; Waste disposal; Natural resource conservation; Safety Housekeeping.
Camp staff Contractor’s Environment Specialist
Restoration requirements; Waste disposal
Restoration teams CSC and Contractor’s Environment Specialist
8.12 Environmental and Social Management Budget
The environmental and social management cost includes tree plantation program and health
and safety measures. The environmental monitoring cost has been worked out on the basis of
Effects Monitoring Plan is given in Table 8.5 As the project is scheduled for completion in two
years, therefore, environmental monitoring cost has been worked out for two years. The staff
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 8-31
responsible for operation of the project road will be trained to implement environmental
safeguard in post construction period and respective cost has been worked out. The total
environmental and social management cost including the resettlement cost is estimated to be
about Rs. 7.917 Million.
Table 8.7: Cost Estimates for Environmental Management
Environmental Component Quantity Amount Pak Rs.
Details/Basis
i. Tree Plantation
660 790,000 Cost includes plantation and maintenance up to three years
ii. Health & Safety Measures L.S. 350,000 Lump sum
iii. Miscellaneous Cost L.S. 160,000 Lump sum
iv. Air Quality Monitoring 50 1,500,000 50 samples @ Rs. 30,000/sample
v. Water Quality Monitoring 80 1,200,000 80 samples @ Rs. 15,000/sample
vi. Noise Level Monitoring 65 325,000 65 samples @ Rs. 5,000/sample
vii. Soil Tests 30 1,940,000
Training 1,650,000 Lump sum
External Monitoring 4,100,000
Total Environmental and Social Management Cost 7,917,000
8.13 Recommendations
8.13.1 Avoidance
Based upon the lessons learnt from the past experience regarding rural roads the Works and
Services Department designers or their design consultants will avoid any model that may
become environmental or social hazard at any stage.
8.13.2 Contractor’s Obligations
The following conditions should be included, in addition to general conditions provided for
environmental and socioeconomic impact mitigation in the tender document(s):
Clause regarding disposal of waste construction material
The Contractor will in consultation with and with the approval of the project XEN and the
recommendation of the environmental experts, select a site for disposal of waste construction
material. Contravention to this clause may tantamount to non–compliance to the contract and
the contractor will be responsible for removing the non-approved material dumped at his own
expense and pay a fine for the negligence.
Clause regarding adjustment with unstable locations appearing during construction especially
the foundation
In case an unstable location appears during construction, especially the foundation, of the road,
contractor will immediately inform the XEN providing full technical details about the problem.
The XEN will inspect the site; preferably the same day the report is received and will, if
necessary, agree to make modifications and changes in the design to stabilize the situation such
as change in the depth of foundation. Contractor will not make any changes in the specification
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 8-32
without express approval of the XEN. Contravention to this provision will mean unauthorized
construction carried out for which XEN may issue dismantling orders.
Clause regarding Location of Labor Camps, Material Dumps / Depots, Equipment and
Machinery Yards, approach roads and routes
State land is available for location of labor camps, material depots, equipment and machinery
yard, link road / diversion or any other facility(s) related to the proposed project. The Contractor
will choose particular sites within the overall campus indicated in consultation with XEN. These
activities will not be allowed outside the state land, located on either side of highway. If the
Contractor chooses to locate his facilities on a private land, he will himself be responsible for any
compensation, resettlement or rehabilitation process and related costs and XEN or Works and
Services Department will not be involved in acquiring or using the land in making any payments
for doing so.
Clause regarding Rehabilitation of Construction and extraction sites
The Contractor will carry out construction work exactly on the same site and according to the
same design as provided in the tender documents. Also the campsite, material depot, machinery
and equipment yard, link roads, borrow areas will, after the completion of construction, be
restored and rehabilitated and brought to at least the same condition, in which these were
handed over to the contractor. A set of photographic and video record will be made of the sites
prior to construction to ensure proper restoration and rehabilitation. Final payments and the
release of securities deposited will be subject to compliance with this clause.
Clause regarding drainage, paths, roads, Linear Fixtures crossed / damaged by Machinery
moving to and from the construction sites
During the construction, if the contractor’s vehicles moving to and from the construction site(s)
causing any damage or disruption of services pertaining to drainage systems, paths, roads linear
fixtures e.g., transmission lines and fences, the contractor, will get the damage repaired and
services restored within 24 hours of the damage, failing which the XEN will get an assessment of
the damage and losses and debit that amount to the contractors account and the next payment
will be made to the contractor after deducting the debited amount.
Clause regarding earthen embankments or Concrete Work vicinity Scouring
All such spots where there is a possibility of Scouring of earthen embankments or concrete work
as mentioned in the tender and the subsequent construction contract, the contractor will
protect the embankments by erecting protection walls and stone rip–rap work, failing which the
payment of the contractor will be withheld.
Clause regarding discharge spill or dumping on any building, House, graveyard, archaeological
site (established or newly found), unstable slopes, un-compacted embankment or leaking into
construction area
The contractor will be contractually bound to not to allow or cause discharge spill or dumping on
any building, house, graveyard, archaeological site (established or newly found), unstable slopes,
un-compacted embankment or leakage into the construction area. Any such failure will be duly
noted by the XEN during site inspections and the contractor will immediately remedy the
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 8-33
situation failing which the payment of the contractor will be withheld and the damage so caused
will be debited to contractor’s account under the contractual provisions.
Clause regarding diesel and other fluids spilling over to stream water or open areas from
construction machinery
The contractor will ensure that his construction machinery is always in an excellent working
order and no spilling of diesel or any other fluids into the water stream or open areas, is caused
by the contractor’s machinery. For any such spill the contractor will pay the environmental
compensation to be assessed by XEN in consultation with Pak–EPA and the said amount will be
debited towards the payment of the contractor.
Clause regarding providing proper diversion of water
The contractor will, in consultation with the XEN provide proper diversion to water flowing cross
stream, and by collaboration with local communities as per the Social Framework Agreement
and preparing them for any such diversions or closures. Losses caused to construction work due
to poor or mismanaged stream flow diversion will be considered as negligence on the part of
contractor any damages or losses caused due to this negligence will be borne by the contractor.
Clause regarding control on air quality by not allowing machinery to cause dust, smoke or
noise pollution
The contractor will not cause deterioration of air quality by using old or ill maintained machinery
that cause excessive dust emissions, smoke or noise pollution. The contractor will follow strict
standards of maintenance of machinery, provide qualified and trained drivers and operations for
the vehicles. The contractor will also sprinkle water on dirt roads to be used as link roads, and
sites where the earth is to be dumped to suppress dust emissions. Furthermore, the contractor
will provide protective masks to his work force. Failure to do so will be taken as serious
contravention of the contract and will cause the payment to be deferred till the correction of the
situation.
Clause regarding control on dust or other pollutants from Stored materials, material depots or
spoil heaps
The Contractor will:
locate his material depots and spoil dump as far away from the villages / community
“Hujras” as possible.
keep all such materials covered for effective control of the fugitive dust.
Failing to do so the contractor will bear the cost which may have to be incurred on remedial
actions or compensation to be paid to the local community member(s).
Clause regarding use of outdated machinery
The Contractor will obtain a certificate from the Vehicle Examiner working under the XEN but
paid by the contractor, that all the machinery employed is either new or in first class working
condition so as not to cause smoke or oil leakages. XEN will not allow the use of any outdated
machinery.
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 8-34
Clause to Protect the Biological Resources
The Contract will ensure that:
i. Unnecessary and out of bound activities/movements are not conducted outside the
campus allotted for setting–up the labor camp, material depots and machinery yard.
ii. No firearms are carried by any of the employees or labor except for any security officers
/ guards.
iii. All Forest, Wildlife and Fisheries Laws are fully respected and abided by both the
contractor and the work force.
iv. The Biodiversity is respected and protected along with its terrestrial, aquatic and aerial
habitats.
v. Necessary signboards are displayed to remind the labor force, visitors and members of
public about their obligations towards the biological resources of the project area.
vi. Inspections by Wildlife, Forest and Fisheries Officers are facilitated in camps to facilitate
a proper implementation of relevant Laws.
vii. Communities are made aware and are involved in proper protection of the biological
resources within and around the project site(s).
viii. Any contravention to any of the above sub–clauses will be considered as breach of
contract and could lead to disqualification of the contractor.
Clause regarding respect for Socio–economic and Cultural Values and physical cultural
The Contractor will be bound to:
i. Ensure that no damage or disruption is caused to the social infrastructure or public
services being provided to the people e.g., education, health, electricity supply, drinking
water supply facilities for public gathering or religious congregations.
ii. Ensure the Contractor or his employees remain aloof of the local tribal tensions
especially the strife’s over distribution of canal water.
iii. Ensure that existing ownership of land around the project is respected.
iv. Ensure that if some construction material has to be procured from or through a member
of the local community, it must be carried out under the provisions of the Social
Framework Agreement with the local communities.
v. Ensure that no damage or adverse effect is caused to archaeological (present or chance
find) sites, graveyards and burial places.
Clause regarding Public Safety, Health and Safety at Construct Site, including measures against
HIV/AID and Life insurance.
The Contractor will:
i. put up temporary but prominent sign boards warning people against likely hazards
which can be caused due to certain activities. (Also to be reflected in SFA).
ii. arrange to run a proper campaign in the labor camp, to make people aware of the
causes, mode of transmission and consequences of HIV/AIDS and other infectious
diseases particularly Hepatitis and Cholera.
iii. upgrade the nearest existing BHU(s) for the benefit of the labor as well as the
surrounding villages.
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 8-35
iv. ensure proper cleanliness and hygienic conditions at labor camps by ensure a clean
mess, proper drainage and suitable disposal of solid waste. Inoculation against Cholera
and Hepatitis will be arranged at intervals as recommended by the Health Department.
v. keep all the camps, offices, material depots, machinery yards and work sites open for
the inspection of health and safety measures and related documents.
vi. provide proper safety gear such as overalls, helmets, field boots and earplugs to all the
workers as a precaution against any mishap, interlink various parts of the construction
complex with local wireless telephones for quick reporting of any accident / mishap and
also provide standby vehicles for transportation in case of a serious injury.
vii. Provide a comprehensive group insurance cover to the workers and labor working on
site or in the camp, against accidents, mishaps or loss of life on duty.
Clause regarding employment of Locals in the Construction work
The Contractor as an obligation of the Contract will employ, subject to availability and work
ability, maximum number of local labor for construction work.
Note: The aforementioned clauses have been suggested purely from a technical point of view.
These may be vetted by a qualified legal professional / officer before incorporating them into
the tender or contract document(s).
8.13.3 Social Frame Work Agreement (SFA)
A social Frame Work Agreement (SFA) will be signed through mutual open consent between the
local village leaders project contractor and the XEN of the Project. At least two confirmed
leaders / elders will be chosen from each of the villages situated adjacent to the area where
construction activity is going to be witnessed. These leaders / elders will constitute a villagers
committee and they will choose a Chairman from among themselves. The SFA will be signed by
the XEN, the Contractor and by the Chairman of villager’s committee from the village’s side. SFA
will be drafted on the lines of legal agreements signed amongst three parties and should
preferably be on a stamped paper to be provided by the XEN at the project cost. All the
mitigation measures where reference to SFA has been made in the ESMP, will be included in the
SFA. The Works and Services Department obligations through XEN, village’s social obligations
and Contractor’s obligations will be listed separately. Copies of SFA will be kept by XEN, the
villagers chairman and the Contractor. The SFA will be considered as a natural follow up of the
public consultation and public hearing and an indication that Works and Services Department
and the local people are mutually facilitating the construction of new the proposed road
infrastructure.
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 8-36
8.13.4 Social Frame Work Agreement
1. This is a sample Social Frame Work Agreement between Executive Engineer (XEN) and
the villagers committee of the project Area.
Village Name
(Two of each village) Father’s Name
1. 1
2
2. 1
2
3. 1
2
4. 1
2
5. 1
2
6. 1
2
7. 1
2
8. 1
2
9. 1
2
10. 1
2
2. We the committee of village leader / elders of the project area have agreed unanimously
to nominate ________________________________S/O ______________________ as
our chairman and authorize him to enter into an SFA with the project XEN on our behalf
and on his own behalf. We understand and pledge that this SFA will be a binding
between us and the XEN throughout the duration of the construction work as well as the
operational phase.
SR. No. Name Signatures / LTI
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 8-37
3. By mutual consent it is agreed the Works and Services Department, their consultants
and contractors:
a. Will not occupy any agricultural land or acquire any other land during the construction
of this project.
b. Will not cause any damage or reduction in the water supply in the stream flowing in the
area through any of actions to the projects.
c. Will not cause any disturbance to Forest Wildlife, any public archeological heritage or a
place of worship.
d. Will not interfere in the social political or tribal balance of the area.
e. Will / wherever possible, facilitate better services and supplies to the area e.g. schooling,
health, awareness on epidemic diseases, electricity and road/rail communication.
f. (More commitments can be added if required)
Also, by mutual consent it is agreed that all the villagers residing in the area located within 2 km
on either side of the roads proposed in the project (names of villages listed in para I above,
collectively and severally:
a. Will not interfere in the location of labor camps, material depots, equipment yards and
all the approach roads to be used during project construction phase, all of which will be
located on the state land.
b. Will not interfere if the Works and Services Department decides to shift the construction
to a more suitable site as long as the activity remains on state land.
c. Will not receive any discharge of water slurry or oil spills to any graveyard or
archaeological site.
d. Will not cause any damage to wildlife, or fisheries forest resources of the area. No
villagers will be involved in killing, poaching or hunting of animals.
e. Will not allow reduction or official interference in our existing services and facilities e.g.
education, health, electricity, drinking water supply, religious and social congregations.
f. Will not allow any interference in our tribal, commercial or social norms, and we
understand that no land acquisition is involved under the project.
g. Agree that in case the contractor wishes to obtain some material from the private lands
or wishes to make use of any piece of land outside the state land that would invoke a
new bi-lateral agreement between the villager(s) and the contractor and the Works and
Services Department (FATA) will not be involved in that in any way.
h. Agree to respect and observe the cautions on the sign boards displayed by project
authorities and will not remove or cause to be removed any signboards or installations
authorized by the XEN.
Note: Add more conditions if required as per the prevailing circumstances.
This SFA has been signed this _____________day of _________, at _________
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 8-38
Signatures Signatures Executive Engineer Chairman Villager’s Committee (Name and address) (Name and Address)
Signatures Signatures Local XEN Contractor (Name and address) (Name and Address) Counter singed
Signature Project Director, Works and Services Department (Name and address)
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 8-39
8.13.5 Operational Manual
For post construction phase of the project, it is recommended, that a broad based team of
experts is assigned the development of a comprehensive operation manual for the proposed
roads. The manual should also include a provision for continuous training of the staff that have
to be assigned operational or maintenance duties. An effective monitoring and evaluation (M&E)
system should make an integral part of the operation manual by way of providing a check list for
every operational and maintenance stage. As stated in the ESMP, the following points must be
part of the operation manual:
a. Strict application of the prescribed M&E plan.
b. Continuous evaluation of design efficiency.
c. Training sessions for understanding and operating the manual.
d. Annual audit of environment (comparison of what is happening vis-à-vis set standards)
to be conducted by an independent party.
e. Regular maintenance.
f. Staff welfare.
g. Continuous public consultation and Public Relations (PR).
h. Continue address of gender issues and women consultation.
Refresher courses for the operational staff are recommended.
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 9-1
9 Environmental Management Plan (Phase II)
9.1 General
This chapter contains the Environmental and Social Management Plan (ESMP) for phase II of the
proposed project. Phase II of the project consists of six stretches of road in the Bajaur agency
totaling 35.5 km, whereas the total length of the four stretches of road in the Orakzai agency is
11 km. The exact alignment of these roads is not known at this stage, therefore it was not
possible to collect site specific environmental and social data for these stretches of road.
Since both the phases have roads in both the Orakzai and Bajaur agencies, are of the same width
/ type and are located in the same areas (within the respective agency), the associated potential
issues, their proposed mitigation and subsequent monitoring requirements would be very
similar. Similarly, the overall framework of the ESMP presented in Section 8 for phase I of the
proposed project would also apply to phase II, just as the SFA, construction contracts and the
engineering supervision (consultancy) contracts, etc. and their requirements for phase II of the
proposed project would be identical to that of phase I.
This ESMP encompasses the following components:
Potential Environmental and Social Impacts (summary)
Monitoring Program
Institutional Agreements
Comprehensive Mitigation Plans
Most of the mitigation activities proposed in ESMP will be included under provisions in the
construction contract, engineering supervision contract and necessary agreement with the
communities.
9.2 Mitigation through Avoidance of Adverse Impacts by
Suitable Design
Negative impacts to the natural and socioeconomic environment can take place due to improper
design and management of the project. Most negative factors can be avoided (eliminated)
through the use of proper and environmentally sound technical design.
Lessons can be learnt from the construction and operation of other roads and highways built in
the country, particularly in the FATA region. A number of inherent shortcomings and defects can
be avoided by following good design principles and practices used by successful models for
development of rural road infrastructure. Record of such models is available within the Works
and Services Department and it would be made compulsory for all project implementation and
management entities to follow such a model (selected by the department) for their respective
activities.
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 9-2
9.3 Tender and Construction Phase
9.3.1 Impact Reduction Measures
There are specific measures required of the contractor to reduce the potential impacts of
physical works and also the proposal for monitoring contractor’s compliance / performance
during construction phase.
The contract document will contain requirements for:
Preparation and implementation of a health, safety and environment (HSE) Plan,
addressing occupational health, safety, and environmental aspects.
Preparation of traffic management plan, addressing movement of vehicles for
material/construction manpower transportation, full/partial road closure during road
construction, warning signs, and other necessary measures.
Preparation and maintenance of documentation record of any road accidents or site
accidents. Provision of insurance coverage to the construction workers.
Proper management of construction waste and preparation of waste management plan
Control measures for waste fuel
Reduction of oil / lubricants, spill or leakage, noise and dust level
Rehabilitation of areas used for construction detours and sites used to temporarily store
construction materials.
Use and proper maintenance of equipment with appropriate noise and smoke
abatement
Restoration of borrow areas or stone quarry areas.
Other requirements as obligation of the contractor, emanating from the Mitigation Plan
and the ESMP.
Specific provision will also include mandating the use of formal health including
protection against communicable diseases, safety and group insurance measures to
minimize accidents and avoid fatalities during the construction process.
Advisory element to address a number of other issues will also be included in the
contract. These will include Implementation of ESMP and its monitoring through the
Environmental Mitigation and Monitoring Plan (EMMP).
9.3.1.1 Road Closures
If a road would have to be closed for a particular amount of time, it must be done with the
permission of the Works and Services Department and in consultation with the communities in
the vicinity. Furthermore, to the extent possible alternate route(s) are to be provided through
diversions, adequate signage and traffic management plan.
9.3.1.2 Cultural and Historical Resources
Local communities will be requested to identify all known sites of cultural and historical
significance in the project area that may be affected by the project, prior to the commencement
of the construction activities to ensure adequate measures for their protection by the contractor
during construction phase.
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 9-3
9.3.1.3 Archaeological Field Support
The Works and Services Department request the Archaeological Department to make available
(where required) a qualified archaeologist to conduct field investigations when important search
work and new material sites are opened. No such site is yet in view but just in case it does; the
services of archeologist would be available.
9.3.1.4 Graveyard and Burials
If unrecorded graveyards and / or burials are found during the course of construction activities,
the supervisions agency will contact and work with local communities within the immediate
project area to allow for possible identification of the remains and where required, properly
undertake relocation and burial.
9.3.1.5 Local Employment
The contractor is advised to hire all unskilled labor from the local communities. Furthermore,
where individuals with the required skills and experience are available from the local
communities they should be preferred for semi-skilled jobs. It is unlikely, due to the existing
level of education and technical capacity of the local communities, that the contractor would be
able to find any skilled workforce within the project area and so may hire it from elsewhere.
There is no legal obligation to hire local labor but it is desirable that maximum employment
benefits are made available to local communities.
9.3.1.6 Resources use Agreement–Construction Materials
Earth is available in the state-owned lands on either side of the road. It has been estimated that
the entire quantity of the earth required for the construction of the proposed road
infrastructure will be available from the proposed borrow sites. The stream-bed sand is fit for
use in rough construction. Stones may be available from local or nearby quarries. Yet there may
be a need for additional agreement with public to obtain certain materials. In that case
agricultural land would be given the lowest priority in the procurement of fill material.
Whenever the borrow pits are dug, considerable care should be taken in their location. The site
may invariably be rehabilitated after use. Ideal situation would be that site is made good to a
condition almost similar to that prior to the project. It will be helpful if photographs of pre–
project condition are used for the purpose of comparison.
9.3.1.7 Resources Use Agreements - Water
The contractor will be required to provide details of water demands and indicate source of
water prior to the start of construction. Disposal plan for wastewater without polluting the
fertile soil, clean river water or ambient air, will be produced by the contractor for approval of
Executive Engineer and the Project Manager (PM) assisted by an Environmental Consultant.
9.3.2 Pre-Tender Conference
To ensure full understanding of above clauses by prospective contractors, all prequalified
contractors will attend a pre–tender conference, where they will be briefed on their
responsibilities with regard to environmental, social, health and safety issues. These briefings
will review specific provisions of the construction tender documents and contracts.
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 9-4
9.3.3 Pre-Construction Coordination Meeting
Once the contract is awarded the contractor will be required to regularly attend coordination
meeting(s) with project authorities and the local communities. At these meetings, the Project
Manager (PM) and the Executive Engineer (XEN) will further explain the Terms and Conditions of
the Contract, especially those narrated above, if possible.
9.4 Operational Phase – Management of Operational Impact
The Project will also address future maintenance impacts. These will be implemented through
specially requested financial support from Works and Services Department (FATA) and the Multi
Donor Trust Fund (MTDF) as recurring budget to avoid any deterioration in the functioning of
the newly constructed and rehabilitated roads. Maintenance agency / contractor will be
required to follow procedures similar to those for the construction contractor concerning proper
disposal of construction waste, control measures, for waste fuel, oil and lubricants and adoption
of health and safety measures for personnel.
9.5 Management of Social Impacts
To assess, address and manage the social aspects of the project, a social assessment has been
included in this ESIA during which social impacts and their mitigation have been identified in
detail. In addition, social impacts will be managed through the Social Framework Agreement
(SFA), which will be made available with the XEN as representative of the Works and Services
Department, construction Supervision Consultants (CSC) the contractor and the communities
residing within the project area.
The SFA will be drafted and signed when the project is finally approved and the implementation
commences. A draft illustrative agreement has been provided which may be updated, if
necessary.
9.6 Environmental Mitigation and Monitoring Plan (EMMP)
The environmental mitigation and monitoring plan (EMMP) is a very important component of
the ESMP. The implementation of the ESMP will be the contractual obligation of the contractor.
For that the contracted will engage a full time technical staff capable of a carrying out the
prescriptions of the ESMP as contractual obligations under the contract document. The
engineering consultants will have on their team a full time professional level environmental
expert to provide an overall professional cover to the environmental monitoring process and the
procedures and develop required reports and point out any gaps in the implementation of the
mitigation measures or enforcement of the prescriptions of the ESMP. In Works and Services
Department there is an Environmentalist, who will be responsible for the monitoring and
evaluation (M&E) of environmental and social mitigation measures at the detailed design,
bidding, construction and implementation stages. The results of the M&E activities will be
included in the reports prepared for the project manager and XEN of the Works and Services
Department.
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 9-5
The monitoring program will comprise site inspection designed to determine contractor’s
compliance or otherwise with ESMP and applicable regulations and statutes.
A monitoring program designed providing ex-ante and ex-post quality assessments of the
environmental parameters of the project are not proposed. It is however to be noted that:
Project impacts will be identified by site inspections and in discussion with site in
charge(s), XEN and local communications
The project is a localized activity and changes in the environment are likely to be
minimum.
Except for some unanticipated factors, originating from offsite facilities, the project is
not likely to cause significant discomfort/disturbance to communities. For offsite
facilities, if needed, inspections (and response to complaints, if any) will indicate
whether any further action needs to be taken or not.
The proposed site inspections by the consultants’ environmentalist and the Works and Services
Department will be carried out on regular basis as per their own time schedules, but not
necessarily as minimum level of M&E activities by each monitoring agency. The program
outlined in Table 9.1 below should be observed.
Table 9.1: Minimum Monitoring Plan
Project Phase Proposed Minimum Inspections
Pre-Construction
One visit to main project site
One visit each to proposed Borrow site, Camp site, Material Depot site, Proposed machinery yard and other proposed sites.
One visit to each community
One visit to proposed water sources
Construction Visits to main project site at 20%, 50%, 75% and 100% completion stage.
One visit to other project sites every quarter.
Two visits per quarter in response to complaints
Post Construction
One visit to each construction site (part) site during construction.
Two visits to each component site 12–18 months after the completion of the highway
Two visits per quarter on response to any complaints
It is also anticipated that additional inspection will be required in response to any complaints by
local communities. So another two visits per quarter may be budgeted for M&E personnel. All
officers concerned with M&E will prepare their own M&E Implementation Plans for information
of all concerned. All M&E personnel will be given optimal mobility and flexibility to implement
their M&E implementation plans.
9.7 Visits / Inspection Authorization
For the inspection process to function, access to the project and other related sites must be
guaranteed by Works and Services Department. Accordingly, the contract documents and
operating documents will incorporate a phrase with similar intent to that outlined below:
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 9-6
Any officer authorized in writing by the Works and Services Department or
Environmental Protection Agency (EPA), may at any time enter any premises whether
prescribed or otherwise, and may:
o Examine and inspect materials, machinery, control equipment and monitoring
equipment. Take samples of any pollutants that are emitted, discharged or
deposited, or are likely to be or are of a class or kind that are usually emitted,
discharged or deposited from such premises.
o Examine any books, records or documents relating to the performance or use of
such equipment, control equipment, monitoring equipment or relating to the
emission, discharge or deposit from such premises.
o Photograph such premises as he/she considers necessary or make copies of any
book, records or documents seen in the course of such examination.
9.8 ESMP Implementation Arrangements
9.8.1 Institutional Arrangements
The overall responsibility of ESMP implementation will rest with the Chief Engineer of the Works
and Services Department, FATA. A Project Management Unit (PMU) will be established headed
by the Project Director (FATA ERRP). The PMU will ensure the implementation of ESMP through
Field Implementation Units (FIU) which will be established within each of the agency (district)
offices of at W&SD in Bajaur and Orakzai Agencies. PIUs will be headed by the respective
Executive Engineer (XEN) and supported by Sub Divisional Officer (SDO) and Deputy Director
Environment (DDE).
A professional consulting firm will be responsible for Contract Administration & Construction
Supervision. The firm will be fully empowered as the ‘Construction Supervision Consultant’ (CSC).
The CSC will have a full time field based environmental specialist to ensure the implementation
of ESMP. The environmental specialist of CSC will also develop training modules and conduct
environmental trainings for the contractor’s staff.
The contractor will be responsible for the implementation of ESMP. A full time field based
environmental expert will be hired whose responsibility will be to monitor and report all the
ESMP implementation related activities on a regular basis.
An independent external monitor will be hired to monitor and provide external monitoring
reports of the ESMP implementation. The figure below illustrates the institutional set-up for the
ESMP and EMMP.
The organogram below gives the overall implementation arrangements for the project.
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 9-7
Figure 9.1: Organogram for Implementation of ESMP
9.8.2 Management responsibility
The following entities constitute the project organization. Their specific roles and responsibilities
for environmental management during the construction phase of the project are explained in
the subsequent paragraphs.
(i) The Implementation
Agency (IA)
Works and Services Department, FATA through the Project
Management Unit (PMU) will be responsible for the
implementation of ESMP. Main responsibilities of the IA will be to:
vii. Monitor the ESMP implementation.
viii. Review monthly, quarterly and annual progress reports
from contractor, CSC and IEM as vetted by the project
consultants.
ix. Facilitate coordination with the XEN.
x. Submitting monthly and quarterly progress and monitoring
reports to the Client.
xi. Hiring of external monitor as per the guidelines and
approval of the client to monitor the implementation of
the ESMP.
i. Provide financing to cover all expenses for the tasks
included in the project budget.
WS&D (FATA), Project Management Unit
Field Implementation Units Executive Engineer (XEN)
Sub Divisional Officer (SDO)
Supervision Consultant Environmental Specialist
Independent Environment Monitor
Deputy Director Environment (DDE)
Contractor
Contractor’s Environmentalist
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 9-8
(ii) Construction Supervision
Consultant
Construction Supervision consultant (CSC) will be responsible for
the supervision of contractor for the implementation of civil works
as well as ESMP. Full time field based environmental and social
expert will be employed to ensure the implementation of ESMP.
The CSC will also be responsible to design and impart
environmental and social trainings for the contractor’s staff.
(iii) Contractor The engineering procurement and construction (EPC) company
contracted by the implementation agency to carry out the
construction of the proposed roads. Implementation of the ESMP
will also be the responsibility of the contractor for which well-
qualified environmental engineer and a full time field based
environmental expert will be employed.
All mitigation measures for adverse impacts proposed in the ESMP
will be duly and timely implemented in letter and spirit. For this
purpose, daily, monthly and annual checklists will be formulated
and maintained.
(iv) General Assistance to all
above agencies in their
respective tasks
Works and Services Department, Executive Engineer (XEN) of the
Project will facilitate communications, logistics and data collection
as and when required. . For all M&E activities in the field the XEN
will act as the focal person.
(v) External Monitoring An Independent Environmental Monitor (IEM) will be engaged by
the Works and Services Department to periodically monitor the
implementation of ESMP. The IEM will monitor the compliance
status develop external monitoring reports on a quarterly basis.
9.8.3 Summary of Finances for Various Agencies
As provided above in different paragraphs, following is the summary of Finances for various tiers
of ESMP implementation:
Agency Financial Agreement
Contractor’s technical staff for ESMP implementation and allied logistics.
Cost provided in BOQ as per PC–1.
Consultants environmental expert, the support staff and allied logistics.
Included as consultants fees in the consultants costs as per PC–1.
Environmental officer(s) of the Works and Services Department consisting of Deputy Director Environment and Deputy Director Sociology, support staff and allied logistics.
Included in the Works and Services Department Budget estimate as per PC–1.
Executive engineer Included in Works and Services Department Budget as per PC–1.
Donor external monitoring mission Included in donor procurement costs.
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 9-9
9.8.4 Reporting Supervision
The environmental expert of the CSC will receive information from contractor’s environmentalist
in the form of periodical reports as well as inspection notes based upon his monitoring and
inspection at the project site. This information will make a basis for the environment section /
unit of the Works and Services Department for their further reporting. All reports will be location
and activity specific. The reports will especially identify areas of contractor’s non–compliance
with the ESMP and provide guiding remarks on actions to be taken. The significance of the non–
compliance will also be noted.
The Works and Services Department will prepare and submit periodical reports to the Bank on
quarterly basis. Copies of these reports will also be sent to the Project Manager as well as the
Project Director for their information and necessary action. The non-compliance by contractor
will be linked with the system of payment of bills by classifying the non-compliances as minor,
moderate or major depending upon the period over which the non-compliance is continued.
Within one month the non-compliance is minor, after two months it is moderate and after three
months it becomes major.
The Environmental Expert, in his routine reports, will include a summary status of activities
relating to the ESMP. As and when necessary, supplemental reports with greater detail than the
routine reports should also be prepared. These reports will reinforce the information for the
environmental staff of the Works and Services Department who may use it for sending
additional reports to the Bank.
Works and Services Department will also engage Independent Environmental Monitor (IEM) to
periodically verify the effective implementation of the ESMP. IEM will submit reports to the
Works and Services Department on regular basis.
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 9-10
9.9 Mitigation Plans
Table 9.2: Environmental Impacts during Construction Phase
Impact
Mitigation Responsibility
Mitigation Measure Contract and Social
Framework Agreement (SFA) Clauses
Implementation Supervision Monitoring
1. Soil and Landscape
1.1 Physical Scarring of landscape
Unnecessary widening beyond the proposed design of the road shall be avoided at straight portions and on bends. The movement of construction equipment and vehicles will be restricted to work areas. Safe driving practices must be encouraged to minimize soil erosion. A speed limit of 40 kmph will be observed and monitored in the project area, and off-road driving strictly prohibited. The alignment of the widening will be selected so as to minimize the clearing of vegetation and minimized trees cutting. Steep cut-and-fill will be avoided, and a gentle side slope maintained where possible. Retaining walls will be constructed where necessary.
Contractor’s obligation as defined in the Tender and Contract Documents
Contractor in Collaboration with XEN
Environmentalist of CSC
(i) DDE of Works and Services Department (ii) Independent Environmental Monitor (IEM)
1.2 Increased risk of land slippage and accelerated soil erosion
The one clear passage for transport will continue to be maintained during the project, and measures such as spraying water implemented to reduce dust emission and erosion. All sections of the road close to or on steep slopes will be closely monitored for any signs of soil erosion or land slippage. Environmental monitoring will involve checks for any signs of soil erosion so that remedial actions, such as applying water and compaction, can be implemented. The state of the work corridor will be monitored during project to prevent any spillover outside the corridor. The Executive Engineer (XEN) of the Works and Service
Contractor’s obligation as defined in contract and the Tender document
Contractor and XEN CSC (i) DDE (ii) IEM
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 9-11
Impact
Mitigation Responsibility
Mitigation Measure Contract and Social
Framework Agreement (SFA) Clauses
Implementation Supervision Monitoring
Department (FATA) will allow local readjustments in foundation treatment or any other small changes to the contractor.
1.3 Blockage of natural drainage.
The natural drainage pattern will not be disturbed, and culverts will be constructed where required. Surplus soil and cleared vegetation will be disposed of so as to avoid disturbing the natural drainage.
Contactor’s obligation defined in the Tender and contract data and SFA with community
Contractor and XEN CSC (i) DDE (ii) IEM
2. Location of Labor Camps, Material Depots, Equipment Yards and Approach Roads
2.1 Location of camps near sensitive receptors like water resources, private lands without prior consent of landowners and dumping and storage of construction material equipment in private lands may cause adverse impacts to the environment within the vicinity of the facilities
The contractor will, in consultation with XEN, select the location of all these facilities within a prior approved land. The camp/other site facilities will be established on a flat land without much natural vegetation, at least 500 m away from the communities. Satellite imagery can also be used to select the suitable sites, to record the pre-construction conditions, and to monitor the condition of these sites during and after the construction phase.
Contract Documents and Contractor’s obligations
Contractor and XEN CSC (i) DDE (ii) IEM
3. Oil Spills from Construction Machinery
3.1 Any leakage or spillage of diesel, oil or any other chemical will contaminate the soil which may in turn impact the water
Contractor will apply strict rules on his workers and labor to ensure that no spill or leakages are caused. All fuels, oils and bitumen will be stored appropriately, with concrete padding and bunding for containment in case of leakage. If the spills or leakages do take place, it must be
Contract Documents and Contractor’s obligations
Contractor and XEN CSC (i) DDE (ii) IEM
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 9-12
Impact
Mitigation Responsibility
Mitigation Measure Contract and Social
Framework Agreement (SFA) Clauses
Implementation Supervision Monitoring
sources, nearby community and/or productive land
followed by the treatment prescribed below as per the degree of spill or leakages. The contractor will employ the general criteria for oil and leakage at construction sites, as per standards set forth by “Guidelines for Oil Spill Waste Minimization and Management” issued by International Petroleum Industry Environmental Conservation Associate which are as follows: (Source: IPIECA Report Series, Volume-12, “Guidelines for Oil Spill Waste Minimization and Management”)
4. Earthen Embankments or Concrete Work, Edge Scouring
4.1 Poor design and inappropriate construction procedures can potentially damage the embankments, concrete works or road edges. The impact is moderately significant but can easily be mitigated
Edge Scouring of earthen embankments or concrete work must first be dealt at design stage. Wherever such a situation is anticipated, aprons should be provided to secure edges and specifications must be kept of high standards. During the construction phase this aspect should be addressed through appropriate construction methodology and employing appropriate techniques such as protection walls and rip rap. Contractor will repair all damages to the earthen embankments, concrete works, or pavement edges caused by the construction works. During the operation phase appropriate measures need to be incorporated in the Operational Manual.
Contractor’s obligation defined in the Tender and contract documents
Contractor and XEN CSC (i) DDE (ii) IEM
5. Impact of Borrowing Material from Earth Borrow Sites and Stone Quarrying
5.1 A large quantity of earth will be
The topsoil up to 30 cm shall be removed and stored prior to excavation of fill material. After completion of
Contactor’s obligation defined in the Tender and
Contractor and XEN CSC (i) DDE (ii) IEM
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 9-13
Impact
Mitigation Responsibility
Mitigation Measure Contract and Social
Framework Agreement (SFA) Clauses
Implementation Supervision Monitoring
removed from borrow pits located within the state land on either side of the road. This can potentially cause slope instability, loss of soil/land productivity, uneven terrain, and altered drainage.
borrowing the area would be leveled and the top soil would be restored to ensure no loss in productivity of land Borrow sites would not be deeper than 3 ft at any location to avoid alteration in drainage pattern and reduce the risk of soil erosion The borrow areas will be selected after obtaining approval from the XEN. The contractor will ensure that the borrowing does not cause slope instability, loss of soil/land productivity, uneven terrain, and altered drainage. Wherever possible/necessary, these places will be leveled and planted with trees using appropriate planting technology/methodology.
contract data and SFA with community.
6. Water Resources
6.1 Groundwater extraction over and above the sustainable yield will reduce the volume of groundwater available
Water will not be extracted beyond the sustainable yield limit, defined as that volume of groundwater if used that can be extracted annually from a groundwater basin without reducing the total size of the aquifer. Given that water is to be extracted from a ground water aquifer whose recharge rate, (like the actual volume of water available or its rate of depletion) is not known, the extraction will be monitored to ensure that it does not lead to irreversible environmental damage. The depth of the aquifer water table will be monitored
Contactor’s obligation defined in the Tender and contract data and SFA with community.
Contractor and XEN CSC (i) DDE (ii) IEM
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 9-14
Impact
Mitigation Responsibility
Mitigation Measure Contract and Social
Framework Agreement (SFA) Clauses
Implementation Supervision Monitoring
6.2 The local communities’ rights over water shall be recognized and adequately compensated
Water will be extracted only from a major source a main stream. The community will be compensated for the water extracted from the area’s water resources in recognition of their rights
Contactor’s obligation defined in the Tender and contract data and SFA with community.
Contractor and XEN CSC (i) DDE (ii) IEM
7. Contamination of Soil and Water
7.1 Effluents released as a result of the project activities, if not contained properly, may contaminate the soil and water
No contaminated effluents will be released into the environment without having been treated. When abandoning sumps, an extra cap of soil will be placed over them to allow compaction. Fuels, oils, and other hazardous substances will be handled and stored according to standard safety practices. Fuels, oil, and chemical storage facilities will be checked daily for any signs of leakage.
Contractor’s obligation defined in the Tender and contract documents
Contractor and XEN CSC (i) DDE (ii) IEM
7.2 Water quality is likely to deteriorate if pollutants or contaminated soil mix with surface runoff during the rains and are carried downhill to water bodies
The camps will be located as to avoid proximity drinking water sources, maintaining a minimum distance of 500 m from such natural resources. Sumps will be located in a position such that they are: Fixed in absorbent soil Down-sloped and away from the camp (and downwind, if practical) Downstream from the camp water source and above the high-water mark of any nearby water body (if any). Vehicle and equipment maintenance, including washing, will be allowed only in designated areas underlain with concrete slabs and a system to catch runoff. Solid waste (including food waste) will be segregated and disposed of as follows: Materials suitable for recycling will be stored separately
Contractor’s obligation defined in the Tender and contract documents
Contractor and XEN CSC (i) DDE (ii) IEM
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 9-15
Impact
Mitigation Responsibility
Mitigation Measure Contract and Social
Framework Agreement (SFA) Clauses
Implementation Supervision Monitoring
and sold to approved recycling contractors Combustible waste, Non-combustible, non-recyclable rubbish will be sent to a landfill Solid residue from the septic tanks will be transported to municipal sewage treatment drains. Precautions, such as drip pans, will be used to avoid any spills that may occur during fuel and oil transfer operations. Precautionary materials, including shovels, plastic bags and absorbent materials will be kept available near fuel and oil storage areas.
7.3 If allowed to leach into the ground, the contaminants may also pollute groundwater.
Sewage and other waste effluents will be handled so as to avoid contaminating surface and groundwater. Water from washing areas and kitchen will be released into sumps. An appropriately designed septic tank will be used to treat sewage, and outlets will release treated effluents into sumps. The integrity of the entire system will be maintained and monitored. Septic tanks and sumps will be built at a safe distance from any water hole, stream or dry streambed, so as to prevent the entry of surface water, and the bottom of the sump will be kept above groundwater level. Fuel tanks will be appropriately marked by content, and along with oils, and chemicals will be stored in dyked areas lined with an impervious base.
Contractor’s obligation defined in the Tender and contract documents
Contractor and XEN CSC (i) DDE (ii) IEM
8. Releases into the Air
8.1 Dust emissions from vehicular traffic
Imposing speed limits and encouraging more efficient journey management will reduce the dust emissions produced by vehicular traffic. Water will be sprinkled where necessary to contain dust emissions.
Contactor’s obligation defined in the Tender and contract data and SFA with community.
Contractor and XEN CSC (i) DDE (ii) IEM
8.2 Dust emissions Dust emissions at the construction sites will be Contactor’s obligation Contractor and XEN CSC (i) DDE
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 9-16
Impact
Mitigation Responsibility
Mitigation Measure Contract and Social
Framework Agreement (SFA) Clauses
Implementation Supervision Monitoring
from earthworks along the road
minimized using good housekeeping and management practices.
defined in the Tender and contract data and SFA with community.
(ii) IEM
8.3Exhaust fumes from vehicles and construction machinery,
All equipment, generators and vehicles used during the project will be properly tuned and maintained in good working condition in order to minimize exhaust emissions
Contactor’s obligation defined in the Tender and contract data and SFA with community.
Contractor and XEN CSC (i) DDE (ii) IEM
8.4 Emissions from asphalt plants
The asphalt plant will not be operated without properly functioning dust control system such as wet scrubber.
Contractor’s obligation defined in the Tender and contract documents
Contractor and XEN CSC (i) DDE (ii) IEM
9. Noise and Vibrations
9.1 Equipment and vehicular noise
Equipment and vehicles will be maintained on regular basis
Contactor’s obligation defined in the Tender and contract data and SFA with community.
Contractor and XEN CSC (i) DDE (ii) IEM
9.2 Blasting noise and vibrations
Plan for blasting times to be outside of hours when people are most disturbed by noise (such as prayer and night times). Develop and implement standard operating procedures, blasting rules and a safety management plan that: delineates the danger zone associated with each blast of at least 500m and clear people and animals from this zone before, during and after (30 minutes) each blast; provides an audible warning at least three minutes before blast is fired; and Informs local communities of blasting timetable in advance and provide adequate notices of blasts are required outside of the planned Schedule The use of blasting will be kept to an absolute minimum. Rock basting near the communities will be avoided to
Contactor’s obligation defined in the Tender and contract data and SFA with community.
Contractor and XEN CSC (i) DDE (ii) IEM
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 9-17
Impact
Mitigation Responsibility
Mitigation Measure Contract and Social
Framework Agreement (SFA) Clauses
Implementation Supervision Monitoring
the extent possible. A detailed protocol for management and monitoring of blasting operation will be established. The intended target of the blasting will be marked prior to its start. If any significant damage to the ground is observed, the blasting parameters will be modified or the blasting will be re-planned. Standard safety procedures for handling explosives will be used to protect the staff, the community, and the environment
10. Ecology and Biodiversity Disturbance
10.1Temporary or permanent surface vegetation clearance during construction
No clearance of vegetation or killing/hunting/trapping of wild animal will be allowed. Compensation will be paid for any tree cutting on the private land. C compensatory tree plantation will be carried out for Forest Department owned trees and for each tree removed, five saplings will be planted. The Project will ensure appropriate care and monitoring of this plantation. Camps and other temporary facilities will be established in a manner that minimizes loss of natural vegetation including trees. Borrow material will be obtained without causing any damage to the natural vegetation.
Contactor’s obligation defined in the Tender and contract data and SFA with community.
Contractor and XEN CSC (i) DDE (ii) IEM
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 9-18
Table 9.3: Social Impacts
Social Risk Mitigation Responsibility Construction Stage
1. Land Acquired on Temporary and Permanent Basis
A separate study Resettlement Action Plan (RAP) has been carried out to address the issues related to acquisition of private assets and compensation. The same study shall be submitted separately.
2. Increased risk of accidents caused by partial closure of road during construction
During construction activities, traffic flow will be disturbed. At sections passing through populated areas, there will be limited Scope for providing diversion tracks for the mobility of local and thorough traffic that will increase the risk of accidents.
Proper site-specific measures will be carried out in consultation with supervisory consultants to ensure the safety of population residing along and around the project corridor. A detailed Traffic Management Plan (TMP) will be prepared and implemented by the contractor with the approval of the Works and Service Department (FATA), XEN
Contractor / XEN Construction
Necessary measures will be taken to ensure the safety of traffic during construction, including barricades (including signs, pavement markings, flags, and lights) erected as required by the Works and Services Department (FATA) and set up as per local regulations.
Contractor / XEN Construction
The construction work will be managed such that part of the carriageway at a time is upgraded leaving the other part available to serve one-way traffic. Construction work will be carried out in small stretches instead of a long stretch.
Contractor / XEN Construction
As a result of road improvement the traffic volume will increase during operation stage, there may be safety hazards for the locals residing along the edge of the road as well as vehicular traffic.
During operation stage Works and Services Department (FATA) will make arrangements with some organization/contractor for proper maintenance and operation of the road. Periodic inspections will be made by contracted firm particularly in monsoon season to identify the landslide areas and their remedial measures. In case of any land slide contracted firm will clear the road within minimum time. For this purpose the firm should be fully equipped and there should be contingency plan in case of any emergency/natural disaster.
Works and Services Department
Operation
3. Health and Safety Hazards
Occurrence of The contractor will comply with the safety precautions for Contractor / XEN Construction
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 9-19
Social Risk Mitigation Responsibility Construction Stage
accidents/incidents during the construction activities, particularly from excavation activities is generally common. The workers and general public residing along the project corridor or near the work sites will particularly be at risk. In addition, contractor staff while on work may get injuries.
construction workers as per International Labor Organization (ILO) Convention No. 62, as far as applicable to the project contract. The construction workers will be trained in construction safety procedures, social awareness, equipping all construction workers with safety boots, helmets, gloves, and protective masks, and monitoring their proper and sustained usage. Contractor will ensure the provision of medicines, first aid kits, vehicle, etc. at the campsite.
4. Gender Issues
Findings of the socioeconomic survey reveal that the privacy of women is a major cause of concern for the communities of the project area. Due to the project activities local women many not be able to perform their daily outdoor chores. Women in the project are participate in other outdoor activities such as livestock rearing, bringing of potable water, collection of fire wood etc. that may also be affected by the project activities.
The Contractor will select the specific timings for the construction activities particularly near the settlements, so as to cause least disturbance to the local population particularly women.
Contractor / XEN Construction
The Contractor will carry out the construction activities in such a way that the open defecation timings by the local community particularly women, should not be affected. The normal defecation timings are early in the morning and at late in the evening. So, the Contractor will have to take care of these timings.
Contractor / XEN Construction
Findings of the socioeconomic survey reveal that the privacy of women is a major cause of concern for the communities of the project area. Due to the project activities local women many not be able to perform their daily outdoor chores. Women in the project are
Contractor will take due care of the local community and observe sanctity of local customs and traditions by his staff. Contractor will warn the staff strictly not to involve in any unethical activities and to obey the local norms and cultural restrictions particularly with reference to women.
Contractor / XEN Construction
During construction activities, if privacy of the nearby households is affected, the Contractor will inform the house owner to make some arrangements. Similarly, Contractor will take care as much as possible that the construction activities should not affect the
Contractor / XEN Construction
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 9-20
Social Risk Mitigation Responsibility Construction Stage
participate in other outdoor activities such as livestock rearing, bringing of potable water, collection of fire wood etc. that may also be affected by the project activities.
privacy particularly with reference to women.
5. Social Conflicts and Employment of Locals on the Project
Both the locations have an over-whelming majority of one sectarian group. In such a situation, presence of outside construction workers may cause some degree of social disruption and even active disputes with the local community as a result of differences of religious opinions and culture. This particularly relates to the non-local work force adhering to a different sect that many result in escalation of sectarian issues. This coupled with decline of economic activities and the disruption of the privacy of women folk working in the fields or even in the yards of their houses, should the house be lying at a lower elevation than the working sites. Likewise the risk of theft of the community assets by the Contractor workers and vice versa may occur.
Good relations with the local communities will be promoted by encouraging Contractors to provide opportunities for skilled and unskilled employment to the locals, as well as on-the-job training in construction for young people. Sectarian sensitivities should be given due consideration in engaging labor for the project. Where possible local labor should be engaged for the project, this will not only provide economic opportunities for the locals but will help the contractor in gaining local trust and security.
Contractor / XEN Construction
6. Rise in the Prices of Essential Commodities
Due to induction of outside labour for project works, the
The project will exert no negative impacts on the prices of essential In terms of labor induction the project will exert no
Contractor Construction
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 9-21
Social Risk Mitigation Responsibility Construction Stage
demand for basic items will increase thereby causing an increase in the prices of essential commodities
significant impacts on the prices of essential commodities. To avoid risk of such price hikes, majority of the unskilled and semi-skilled labor will be recruited from the local areas. As such there will be no extraordinary increase in the demand for essential or other commodities. The contractor should normally procure the field camps supplies from the main markets of Kohat, Khar, Peshawar or any nearly by commercially active city.
7. Use of Local Water Supplies and Other Common Resources
The campsites will also be depending on local water supplies to meet personal use and construction requirements. This will put strain on the limited supply of water, putting the construction workers in competition with the locals for the resource. Local water may be affected due to implementation of project both in quantity as well as quality.
The contractor will explore the alternative water resource so that the existing community water resources are not impacted. The Contractor for campsite facilities as well as construction purposes will exploit no existing water source under the use of community.
Contractor Construction
The project campsites may also use other local resources like fire wood, game and public resources. This again will affect the availability of these resources to the locals, as already these areas have very limited resources. Locals have devised a finely balanced way of life in these harsh conditions and any external influence threatens to disturb this balance.
The Contractor prior to start of construction activities will ensure availability of water for campsite facilities and construction purposes. As per local customs and government regulations, the contractor will seek approval from the local community and government for exploitation of the water resources.
Contractor / XEN / Local Govt.
The Contractor will be required to maintain close liaison with local communities to ensure that any potential conflicts related to common resource utilization for project purposes are resolved quickly.
Contractor
The contractor will prepare guidelines for the workers for minimizing the wastage of water during construction activities and at campsites.
Contractor
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 9-22
Social Risk Mitigation Responsibility Construction Stage
The presence of a large number of construction workers and other associated personnel may lead to the spread of communicable diseases such as hepatitis.
The Contractor should excise due diligence in avoidance and control of such mishaps. Contractor will arrange awareness programs for the communicable diseases in the field camps on regular basis by a qualified expert/doctor. Contractor will provide recreational facilities such as playing volleyball of football after the work hours. Similarly, he will provide indoor recreation in terms of radio and TV at the eating-place. The Contractor will ensure regular medical check–up of the camp staff from a qualified doctor on fortnightly basis. If any person found affected with any of the transmittal diseases will be immediately shifted from the camp to the hospital for detailed check–up and treatment. The cost will be borne by the Contractor. Contractor will restrict his permanent staff to mix with the locals to avoid any social and health problems.
Contractor Post -Construction
The construction activities may damage any nearby parks or recreation areas used by the local population or the tourists.
The Contractor will ensure the restoration and rehabilitation of construction and campsites on completion of the project. Works and Service Department (FATA) will develop parks, particularly for children and ladies, at appropriate sites along the road to provide them better recreational opportunities. This will also attract the outside tourists as well, thus increasing the incomes of the local people through increased socio–economic activities. The Works and Service Department (FATA) would carry out tree plantation along the road.
8. Restricted Mobility
During the construction phase the general mobility of the local residents and their livestock in and around the project area is likely to be hindered. Likewise access to the natural resource may be affected. This
The contractor will ensure that the mobility of the local communities and their livestock is not hindered by the construction activities. The contractor will provide crossing points at the road at appropriate places to facilitate the people for going across the road for their daily works and having free access to the natural resources.
Contractor / XEN Construction
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 9-23
Social Risk Mitigation Responsibility Construction Stage
particularly implies to the women folk and children, especially in the context of FATA where women observe proper veil and do not interact with non-locals. Construction activities, particularly excavation and movement of haul truck and machinery may disrupt the existing tracks leading from the main road to settlements. This will limit the accessibility of the local population to the main road.
Generally the contractor will avoid using the village tracks for hauling the construction material. However, if it is unavoidable, the existing ones will be widened, overlaid with shingle or surface treated to accommodate local as well as contractors traffic under the approval of the Project Engineer.
9. Adverse Effects on Graveyards and Archaeological Sites (if any)
The shifting of graves falling in the RoW may cause social disruption leading to possible conflicts, ultimately affecting the project works
A detailed consultation with the local communities would be carried out. After the agreement and approval of the local community the affected graves would be shifted to some other site. For this, a proper shifting allowance would be provided. The Contractor will be required to instruct the construction crew(s) and site supervisors in archaeological / cultural / historical site and artifact recognition, conservation procedures, and temporary site protection. In case of a chance find during excavation, the Contractor must halt work at the site immediately, inform the XEN and notify the Department of Archaeology and Museums through the Works and Services Department.
Contractor / XEN Contractor / XEN / Archaeological Department
Construction Construction
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 9-24
Table 9.4: Operational Phase
1. Strict application of prescribed Monitoring & Engineering plan
Works and Services Department Staff
Works done through contractor to according to strict specification and in commutation with communities
XEN In charge of the road
Officer(s), authorized by Works and Services Department
2. Continuous evaluation of design efficiencies
Works and Services Department Staff
Works done through contractor to according strict specification and in communication with communities
XEN In charge of the road
Works and Services Department or whosever is i/c of the road
3. Understanding and training of operational manual
Works and Services Department Staff
Works done through contractor to according to strict specification and in communication with communities
XEN In charge of the road
Works and Services Department or whosever is i/c of the road
4. Environmental Annual Audit
Works and Services Department Staff
Works done through maintenance contractor to according to strict specification and in communication with communities
XEN In charge of the road
Works and Services Department or whosever is i/c of the road
5. Regular Maintenance of engineering works
Works and Services Department Staff
Works done through maintenance contractor to according to strict specification and in communication with communities
XEN In charge of the road with the assistance of contractor
Works and Services Department or whosever is i/c of the road
6. Continued Public Consultant
Works and Services Department Staff
Works done through contractor to according to strict specification and in communication with communities
XEN In charge of the road
Works and Services Department or whosever is I/c of the road
7. Continued Gender issues and women Consultants
Works and Services Department Staff
Works done through contractor to according to strict specification and in communication with communities. To have gender-neutral policy
XEN In charge of the road with the assistance of contractor
Works and Services Department or whosever takes over the management and maintenance of the road
8. Refresher courses for the operational staff
Works and Services Department Staff
Works done through contractor to according to strict specification and in communication with communities.
XEN In charge of the road with the assistance of contractor
Works and Services Department or whoever takes the management and maintenance of the road
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 9-25
9.10 Environmental Monitoring
9.10.1 Compliance Monitoring
The environmental monitoring will be carried out with the help of checklists prepared on the
basis of the mitigation plans provided in Tables 9.2 and 9.3. These checklists will be filled by the
contractor’s environment specialist on a regular basis, and provided to the CSC. All non-
compliances recorded in the filled checklists will be followed up for remediation. The summary
of filled checklists, non-compliances and remedial actions will be included in the progress
reports.
9.10.2 Effects Monitoring
Works and Services Department will engage a competent consultant to conduct effects
monitoring on a periodic basis. The effects monitoring plan is provided in the Table 9.5. The
overall objective of the effects monitoring is to ensure that the key environmental parameters in
the project area remain within the acceptable limits specified by the National Environmental
Quality Standards (NEQS) (and other relevant benchmarks) throughout the project execution.
For this purpose, the Independent Environmental Monitor (IEM) will carry out the periodic
sampling, monitoring, and analysis of the key environmental parameters specified in the ESMP
and provide their results to the Works and Services Department.
9.10.3 Third Party Monitoring
Works and Services Department will engage a suitable consultant to carry out environmental
audit of the project on a bi-annual basis. During these audits, the ESMP compliance and its
effectiveness will be assessed. This monitoring will help identify weaknesses in the ESMP
implementation and also recommend the corrective measures.
9.10.4 Checklist for Environmental Monitoring
For the purpose of conducting environmental monitoring, the following checklists will be
prepared and used at the site:
i. Campsite Checklist
a. Location of labor camps, material dumps, equipment yards and approach roads
b. Pollution from diesel and other oil spills from machinery
c. Smoke from burning of waste material or burning firewood
d. Soil Compaction due to Labor Camps and machinery yards.
e. Infection diseases in Labor employees and nearby public.
f. Water sources used and its impact on community water sources
ii. Borrow Area and Quarries Checklist (for each site)
a. Impact of taking borrow material from earth borrow site.
b. Access to other construction materials.
iii. Waste Material Disposal
a. Site for disposal of waste construction material
b. Material and construction waste management after completion of road
construction
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 9-26
c. Diesel and other fluids spilling over to the construction site machinery.
iv. Construction Site Checklist
a. Adjustments with unstable locations appearing during construction.
b. Limitations of construction sites resolved appropriately.
c. Earthen embankment or concrete work edge Scouring.
d. Discharge to unstable slopes or leakages on construction.
e. Any damage / discharge diversion of water to any spur/bund avoided.
f. Any discharge spill or dumping on any building or house on any surface water
body
g. Effect on surface flow conditions in case of rain.
h. Dust smoke and other polluting impacts from construction machinery.
i. Dust or other pollutants from stored material / spoil heaps.
j. Noise from use of old or outdated machinery.
k. Noise due to blasting in hilly tract
l. Public safety at construction site.
m. Health and safety of labor and employees at construction site.
v. Water Extraction Point Checklist
a. Impacts on source of construction water.
b. Impacts on sources of surface water.
c. Impacts on sources of groundwater.
d. Impacts on sources of drinking water.
vi. Road Checklist
a. Drains, paths roads crossed by moving machinery and the damage suitably
repaired.
b. Impacts on roads used for transport of construction material.
c. Impact of stone quarrying.
vii. Operational Checklist
a. Strict application of prescribed M&E plan.
b. Continuous evaluation of design efficiency.
c. Understanding and training of operational manual.
d. Annual environmental audit.
e. Regular maintenance.
f. Staff welfare.
g. Continued public consultation.
h. Continued mitigation of gender issues and women consultation.
i. Refresher courses for operational staff.
j. Staff and labor colony reconstruction.
k. Construction of some additional / support structures.
viii. Biological Checklist
a. Damage to Flora.
b. Damage to Fauna.
c. Damage to Fisheries (where applicable)
d. Impact on adjacent open lands.
e. Impact on Endangered species.
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 9-27
ix. Sociological Checklist
a. Impact on existing services, education, health, electricity, water supply,
communication.
b. Impact on local ethnicity, tribal tension, community rivalries and canal water
disputes.
c. Impact on land ownership.
d. Adverse effect on cultural and archaeological heritage.
e. Chance find during construction.
f. Graveyards or burials.
g. Employment.
h. Women status, exposure to employment and education opportunities
i. Cultural reunion through better communication.
j. Market opportunities.
k. Recreation opportunities and Tourism.
x. General Check List
a. Is ESIA complete
b. Is ESIA, IEE, training complete
c. Is HSE management complete
This monitoring plan will cover the entire project implementation period, which will be 24
months.
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 9-28
Table 9.5: Effects Monitoring Plan
Project Stage Parameters Details Applicable Standard
Location Frequency Duration
Air Quality
Pre-construction PM10, SO2, NOX, CO
15 m downwind from the edge of the pavement and asphalt plant location
NEQS for Ambient Air Quality; WHO
Three locations along the road, and near the asphalt plant site
Once; prior to construction commencement
Continuous 24 hours
Construction
PM10, SO2, NOX, CO, HC
40 m downwind from Hot Mix Plant and Asphalt Plant
NEQS for Ambient Air Quality; WHO
Three locations along the road, and near the asphalt plant
Once in 4 months Continuous 24 hours
PM10, SO2, NOX, CO, HC
15 m from pavement NEQS for Ambient Air Quality; WHO
Stretch of highway where work is in progress
Once in 4 months Continuous 24 hours
Water Quality
Pre-construction Pb, BOD5, total coliforms, fecal coliforms, TDS
Community water sources NEQS for Drinking Water; WHO
5 locations near the CoI-2 (RoW, campsite, asphalt plant site)
Once about a fortnight before contractor mobilization
-
Construction
Common ions, Pb, BOD5, total coliforms, fecal coliforms, TDS
Community water sources NEQS for Drinking Water; WHO
5 locations near CoI-2 (number of locations to be determined according to requirement)
Once in 4 months -
Common ions, TSS, TDS, Turbidity
River water near the CoI-2 NEQS/other relevant standards
5 locations near CoI-2 (number of locations to be determined according to requirement)
Once in 4 months -
32 parameters per the NEQS
Waste effluents from camps, asphalt plant and offices
NEQS camps, asphalt plant and offices Once in 4 months -
Noise
Pre-construction Noise level on dB(A) Scale
15 m from edge of pavement /site for other facilities
NEQS standards for Ambient Noise; WHO
Three locations along stretch of highway where work is in progress; near asphalt plant site; near camp site
Once about a fortnight before contractor mobilization
24 hours
Construction
Noise level on dB(A) Scale
7 m from equipment / machinery
NEQS; WHO At equipment yard, asphalt plant and construction site
Once in 4 months 24 hours
Noise level on 15 m from edge of NEQS standards Three locations along stretch of Once in 4 months 24 hours
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 9-29
Project Stage Parameters Details Applicable Standard
Location Frequency Duration
dB(A) Scale pavement /other facilities for Ambient Noise; WHO
highway where work is in progress; near asphalt plant site; near camp site
Soil
Construction Oil and grease Relevant international standards
Three locations in equipment yard and other locations specified by CSC
Once in 4 months -
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 9-30
9.11 Environmental and Social Trainings
The capacity building and awareness raising of the project staff for the environmental and social
aspects is critically important to ensure effective implementation of the ESMP and its various
elements particularly the EMMP. The Construction Supervision Consultants (CSC) and the
contractor will be responsible to impart these trainings. The indicative training plan is presented
in Table 9.6, which will be finalized by the CSC.
Table 9.6: Environmental and Social Trainings
Contents Participants Responsibility
General environmental and socioeconomic awareness; Environmental and social sensitivity of the project area; Key findings of the ESIA; Mitigation measures; EMMP; Social and cultural values of the area.
Selected project management staff
CSC
General environmental and socioeconomic awareness; Environmental and social sensitivity of the project area; Mitigation measures; Community issues; Safety issues; Awareness of transmissible diseases Social and cultural values.
All site personnel CSC and Contractor’s Environment Specialist
EMMP; Safety issues; Waste disposal
Construction crew Contractor’s Environment Specialist
Road safety; Defensive driving; Waste disposal; Cultural values and social sensitivity.
Drivers Contractor’s Environment Specialist
Camp operation; Waste disposal; Natural resource conservation; Safety Housekeeping.
Camp staff Contractor’s Environment Specialist
Restoration requirements; Waste disposal
Restoration teams CSC and Contractor’s Environment Specialist
9.12 Environmental and Social Management Budget
The environmental and social management cost includes tree plantation program and health
and safety measures. The environmental monitoring cost has been worked out on the basis of
Effects Monitoring Plan is given in Table 9.5 As the project is Scheduled for completion in two
years, therefore, environmental monitoring cost has been worked out for two years. The staff
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 9-31
responsible for operation of the project road will be trained to implement environmental
safeguard in post construction period and respective cost has been worked out. The total
environmental and social management cost including the resettlement cost is estimated to be
about Rs. 12.692 Million.
Table 9.7: Cost Estimates for Environmental Management
Environmental Component Quantity Amount Pak Rs.
Details/Basis
i. Tree Plantation 1,060 1,272,000 Cost includes plantation and maintenance up to three years
ii. Health & Safety Measures L.S. 530,000 Lump sum
iii. Miscellaneous Cost L.S. 265,000 Lump sum
iv. Air Quality Monitoring 80 2,400,000 50 samples @ Rs. 30,000/sample
v. Water Quality Monitoring 130 1,950,000 80 samples @ Rs. 15,000/sample
vi. Noise Level Monitoring 105 525,000 65 samples @ Rs. 5,000/sample
vii. Soil Tests 45 3,100,000
Training 2,650,000 Lump sum
External Monitoring 6,650,000
Total Environmental and Social Management Cost 12,692,000
9.13 Recommendations
9.13.1 Avoidance
Based upon the lessons learnt from the past experience regarding rural roads the Works and
Services Department designers or their design consultants will avoid any model that may
become environmental or social hazard at any stage.
9.13.2 Contractor’s Obligations
The following conditions should be included, in addition to general conditions provided for
environmental and socioeconomic impact mitigation in the tender document(s):
Clause regarding disposal of waste construction material
The Contractor will in consultation with and with the approval of the project XEN and the
recommendation of the environmental experts, select a site for disposal of waste construction
material. Contravention to this clause may tantamount to non–compliance to the contract and
the contractor will be responsible for removing the npn-approved material dumped at his own
expense and pay a fine for the negligence.
Clause regarding adjustment with unstable locations appearing during construction especially
the foundation
In case an unstable location appears during construction, especially the foundation, of the road,
contractor will immediately inform the XEN providing full technical details about the problem.
The XEN will inspect the site; preferably the same day the report is received and will, if
necessary, agree to make modifications and changes in the design to stabilize the situation such
as change in the depth of foundation. Contractor will not make any changes in the specification
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 9-32
without express approval of the XEN. Contravention to this provision will mean unauthorized
construction carried out for which XEN may issue dismantling orders.
Clause regarding Location of Labor Camps, Material Dumps / Depots, Equipment and
Machinery Yards, approach roads and routes
State land is available for location of labor camps, material depots, equipment and machinery
yard, link road / diversion or any other facility(s) related to the proposed project. The Contractor
will choose particular sites within the overall campus indicated in consultation with XEN. These
activities will not be allowed outside the state land, located on either side of highway. If the
Contractor chooses to locate his facilities on a private land, he will himself be responsible for any
compensation, resettlement or rehabilitation process and related costs and XEN or Works and
Services Department will not be involved in acquiring or using the land in making any payments
for doing so.
Clause regarding Rehabilitation of Construction and extraction sites
The Contractor will carry out construction work exactly on the same site and according to the
same design as provided in the tender documents. Also the campsite, material depot, machinery
and equipment yard, link roads, borrow areas will, after the completion of construction, be
restored and rehabilitated and brought to at least the same condition, in which these were
handed over to the contractor. A set of photographic and video record will be made of the sites
prior to construction to ensure proper restoration and rehabilitation. Final payments and the
release of securities deposited will be subject to compliance with this clause.
Clause regarding drainage, paths, roads, Linear Fixtures crossed / damaged by Machinery
moving to and from the construction sites
During the construction, if the contractor’s vehicles moving to and from the construction site(s)
causing any damage or disruption of services pertaining to drainage systems, paths, roads linear
fixtures e.g., transmission lines and fences, the contractor, will get the damage repaired and
services restored within 24 hours of the damage, failing which the XEN will get an assessment of
the damage and losses and debit that amount to the contractors account and the next payment
will be made to the contractor after deducting the debited amount.
Clause regarding earthen embankments or Concrete Work vicinity Scouring
All such spots where there is a possibility of Scouring of earthen embankments or concrete work
as mentioned in the tender and the subsequent construction contract, the contractor will
protect the embankments by erecting protection walls and stone rip–rap work, failing which the
payment of the contractor will be withheld.
Clause regarding discharge spill or dumping on any building, House, graveyard, archaeological
site (established or newly found), unstable slopes, un-compacted embankment or leaking into
construction area
The contractor will be contractually bound to not to allow or cause discharge spill or dumping on
any building, house, graveyard, archaeological site (established or newly found), unstable slopes,
un-compacted embankment or leakage into the construction area. Any such failure will be duly
noted by the XEN during site inspections and the contractor will immediately remedy the
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 9-33
situation failing which the payment of the contractor will be withheld and the damage so caused
will be debited to contractor’s account under the contractual provisions.
Clause regarding diesel and other fluids spilling over to stream water or open areas from
construction machinery
The contractor will ensure that his construction machinery is always in an excellent working
order and no spilling of diesel or any other fluids into the water stream or open areas, is caused
by the contractor’s machinery. For any such spill the contractor will pay the environmental
compensation to be assessed by XEN in consultation with Pak–EPA and the said amount will be
debited towards the payment of the contractor.
Clause regarding providing proper diversion of water
The contractor will, in consultation with the XEN provide proper diversion to water flowing cross
stream, and by collaboration with local communities as per the Social Framework Agreement
and preparing them for any such diversions or closures. Losses caused to construction work due
to poor or mismanaged stream flow diversion will be considered as negligence on the part of
contractor any damages or losses caused due to this negligence will be borne by the contractor.
Clause regarding control on air quality by not allowing machinery to cause dust, smoke or
noise pollution
The contractor will not cause deterioration of air quality by using old or ill maintained machinery
that cause excessive dust emissions, smoke or noise pollution. The contractor will follow strict
standards of maintenance of machinery, provide qualified and trained drivers and operations for
the vehicles. The contractor will also sprinkle water on dirt roads to be used as link roads, and
sites where the earth is to be dumped to suppress dust emissions. Furthermore, the contractor
will provide protective masks to his work force. Failure to do so will be taken as serious
contravention of the contract and will cause the payment to be deferred till the correction of the
situation.
Clause regarding control on dust or other pollutants from Stored materials, material depots or
spoil heaps
The Contractor will:
locate his material depots and spoil dump as far away from the villages / community
“Hujras” as possible.
keep all such materials covered for effective control of the fugitive dust.
Failing to do so the contractor will bear the cost which may have to be incurred on remedial
actions or compensation to be paid to the local community member(s).
Clause regarding use of outdated machinery
The Contractor will obtain a certificate from the Vehicle Examiner working under the XEN but
paid by the contractor, that all the machinery employed is either new or in first class working
condition so as not to cause smoke or oil leakages. XEN will not allow the use of any outdated
machinery.
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 9-34
Clause to Protect the Biological Resources
The Contract will ensure that:
ix. Unnecessary and out of bound activities/movements are not conducted outside the
campus allotted for setting–up the labor camp, material depots and machinery yard.
x. No firearms are carried by any of the employees or labor except for any security officers
/ guards.
xi. All Forest, Wildlife and Fisheries Laws are fully respected and abided by both the
contractor and the work force.
xii. The Biodiversity is respected and protected along with its terrestrial, aquatic and aerial
habitats.
xiii. Necessary signboards are displayed to remind the labor force, visitors and members of
public about their obligations towards the biological resources of the project area.
xiv. Inspections by Wildlife, Forest and Fisheries Officers are facilitated in camps to facilitate
a proper implementation of relevant Laws.
xv. Communities are made aware and are involved in proper protection of the biological
resources within and around the project site(s).
xvi. Any contravention to any of the above sub–clauses will be considered as breach of
contract and could lead to disqualification of the contractor.
Clause regarding respect for Socio–economic and Cultural Values and physical cultural
The Contractor will be bound to:
vi. Ensure that no damage or disruption is caused to the social infrastructure or public
services being provided to the people e.g., education, health, electricity supply, drinking
water supply facilities for public gathering or religious congregations.
vii. Ensure the Contractor or his employees remain aloof of the local tribal tensions
especially the strife’s over distribution of canal water.
viii. Ensure that existing ownership of land around the project is respected.
ix. Ensure that if some construction material has to be procured from or through a member
of the local community, it must be carried out under the provisions of the Social
Framework Agreement with the local communities.
x. Ensure that no damage or adverse effect is caused to archaeological (present or chance
find) sites, graveyards and burial places.
Clause regarding Public Safety, Health and Safety at Construct Site, including measures against
HIV/AID and Life insurance.
The Contractor will:
viii. put up temporary but prominent sign boards warning people against likely hazards
which can be caused due to certain activities. (Also to be reflected in SFA).
ix. arrange to run a proper campaign in the labor camp, to make people aware of the
causes, mode of transmission and consequences of HIV/AIDS and other infectious
diseases particularly Hepatitis and Cholera.
x. upgrade the nearest existing BHU(s) for the benefit of the labor as well as the
surrounding villages.
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 9-35
xi. ensure proper cleanliness and hygienic conditions at labor camps by ensure a clean
mess, proper drainage and suitable disposal of solid waste. Inoculation against Cholera
and Hepatitis will be arranged at intervals as recommended by the Health Department.
xii. keep all the camps, offices, material depots, machinery yards and work sites open for
the inspection of health and safety measures and related documents.
xiii. provide proper safety gear such as overalls, helmets, field boots and earplugs to all the
workers as a precaution against any mishap, interlink various parts of the construction
complex with local wireless telephones for quick reporting of any accident / mishap and
also provide standby vehicles for transportation in case of a serious injury.
xiv. Provide a group insurance cover to the workers and labor working on site or in the
camp, against accidents, mishaps or loss of life on duty.
Clause regarding employment of Locals in the Construction work
The Contractor as an obligation of the Contract will employ, subject to availability and work
ability, maximum number of local labor for construction work.
Note: The aforementioned clauses have been suggested purely from a technical point of view.
These may be vetted by a qualified legal professional / officer before incorporating them into
the tender or contract document(s).
9.13.3 Social Frame Work Agreement (SFA)
A social Frame Work Agreement (SFA) will be signed through mutual open consent between the
local village leaders project contractor and the XEN of the Project. At least two confirmed
leaders / elders will be chosen from each of the villages situated adjacent to the area where
construction activity is going to be witnessed. These leaders / elders will constitute a villagers
committee and they will choose a Chairman from among themselves. The SFA will be signed by
the XEN, the Contractor and by the Chairman of villager’s committee from the village’s side. SFA
will be drafted on the lines of legal agreements signed amongst three parties and should
preferably be on a stamped paper to be provided by the XEN at the project cost. All the
mitigation measures where reference to SFA has been made in the ESMP, will be included in the
SFA. The Works and Services Department obligations through XEN, village’s social obligations
and Contractor’s obligations will be listed separately. Copies of SFA will be kept by XEN, the
villagers chairman and the Contractor. The SFA will be considered as a natural follow up of the
public consultation and public hearing and an indication that Works and Services Department
and the local people are mutually facilitating the construction of new the proposed road
infrastructure.
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 9-36
9.13.4 Social Frame Work Agreement
1. This is a sample Social Frame Work Agreement between Executive Engineer (XEN) and
the villagers committee of the project Area.
Village Name
(Two of each village) Father’s Name
1. 1
2
2. 1
2
3. 1
2
4. 1
2
5. 1
2
6. 1
2
7. 1
2
8. 1
2
9. 1
2
10. 1
2
2. We the committee of village leader / elders of the project area have agreed unanimously
to nominate ________________________________S/O ______________________ as
our chairman and authorize him to enter into an SFA with the project XEN on our behalf
and on his own behalf. We understand and pledge that this SFA will be a binding
between us and the XEN throughout the duration of the construction work as well as the
operational phase.
SR. No. Name Signatures / LTI
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 9-37
3. By mutual consent it is agreed the Works and Services Department, their consultants
and contractors:
g. Will not occupy any agricultural land or acquire any other land during the construction
of this project.
h. Will not cause any damage or reduction in the water supply in the stream flowing in the
area through any of actions to the projects.
i. Will not cause any disturbance to Forest Wildlife, any public archeological heritage or a
place of worship.
j. Will not interfere in the social political or tribal balance of the area.
k. Will / wherever possible, facilitate better services and supplies to the area e.g.
Schooling, health, awareness on epidemic diseases, electricity and road/rail
communication.
l. (More commitments can be added if required)
Also, by mutual consent it is agreed that all the villagers residing in the area located within 2 km
on either side of the roads proposed in the project (names of villages listed in para I above,
collectively and severally:
i. Will not interfere in the location of labor camps, material depots, equipment yards and
all the approach roads to be used during project construction phase, all of which will be
located on the state land.
j. Will not interfere if the Works and Services Department decides to shift the construction
to a more suitable site as long as the activity remains on state land.
k. Will not receive any discharge of water slurry or oil spills to any graveyard or
archaeological site.
l. Will not cause any damage to wildlife, or fisheries forest resources of the area. No
villagers will be involved in killing, poaching or hunting of animals.
m. Will not allow reduction or official interference in our existing services and facilities e.g.
education, health, electricity, drinking water supply, religious and social congregations.
n. Will not allow any interference in our tribal, commercial or social norms, and we
understand that no land acquisition is involved under the project.
o. Agree that in case the contractor wishes to obtain some material from the private lands
or wishes to make use of any piece of land outside the state land that would invoke a
new bi-lateral agreement between the villager(s) and the contractor and the Works and
Services Department (FATA) will not be involved in that in any way.
p. Agree to respect and observe the cautions on the sign boards displayed by project
authorities and will not remove or cause to be removed any signboards or installations
authorized by the XEN.
Note: Add more conditions if required as per the prevailing circumstances.
This SFA has been signed this _____________day of _________, at _________
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 9-38
Signatures Signatures Executive Engineer Chairman Villager’s Committee (Name and address) (Name and Address)
Signatures Signatures Local XEN Contractor (Name and address) (Name and Address) Counter singed
Signature Project Director, Works and Services Department (Name and address)
ESIA of FATA Emergency Rural Roads Project (FATA ERRP)
Page 9-39
9.13.5 Operational Manual
For post construction phase of the project, it is recommended, that a broad based team of
experts is assigned the development of a comprehensive operation manual for the proposed
roads. The manual should also include a provision for continuous training of the staff that have
to be assigned operational or maintenance duties. An effective monitoring and evaluation (M&E)
system should make an integral part of the operation manual by way of providing a check list for
every operational and maintenance stage. As stated in the ESMP, the following points must be
part of the operation manual:
i. Strict application of the prescribed M&E plan.
j. Continuous evaluation of design efficiency.
k. Training sessions for understanding and operating the manual.
l. Annual audit of environment (comparison of what is happening vis-à-vis set standards)
to be conducted by an independent party.
m. Regular maintenance.
n. Staff welfare.
o. Continuous public consultation and Public Relations (PR).
p. Continue address of gender issues and women consultation.
Refresher courses for the operational staff are recommended
Page 10-1
10 References
ADB (2005) Summary Initial Environmental Examination of Federally Administered Tribal Areas Rural Development Project ADB (2010) Post-Crisis Needs Assessment PCNA (http://www.pdma.gov.pk/PaRRSA/documents/PCNA.pdf) ADB, WB (2009) Preliminary Damage and Needs Assessment (Immediate Restoration and Medium Term Reconstruction in Crisis Affected Areas) (http://www.pdma.gov.pk/PaRRSA/documents/DNA.pdf) CAMP, IUCN (2003) Status and Red List of Pakistan’s Mammals CAMP (Community Appraisal and Motivation Program) (2004 2011), Understanding FATA, Volumes I to V. FATA Secretariat (2012) Physical Features and Climate (http://fata.gov.pk/index.php?option=com_content&view=article&id=51&Itemid=85) G. Pfeffer & D. K. Behera (2002) Concept of Tribal Society (Contemporary Society: Tribal Studies, Vol 5). New Delhi-Concept Publishers Geological Survey of Pakistan (1997) Atlas of Pakistan GoP (1997a) Guidelines for the Preparation of Environmental Reports. Government of Pakistan, November 1997 (http://www.environment.gov.pk/eia_pdf/D_rev_enReprt.pdf) GoP (1997b) Pakistan Sectoral Guidelines for Major Thermal Power Stations. Government of Pakistan (http://www.environment.gov.pk/eia_pdf/h_Power.pdf) GoP (2005) Pakistan Social and Living Standards Measurement (PSLM) Survey, 2004-5, Federal Bureau of Statistics GoP (2006) Pakistan Millennium Development Goals (PMDG) Report 2006. Government of Pakistan GoP (2008a) Labour Force Survey (2007 – 2008) Twenty seventh issue Government of Pakistan Statistics Division, Federal Bureau of Statistics. December 2008. GoP (2008b) Quality Drinking Water Standards for Pakistan. Government of Pakistan (http://www.environment.gov.pk/act-rules/DWQStd-MAY2007.pdf ) Govt of KP (2006) FATA Sustainable Development Plan 2006-2015 H. Ahmad, S. Khan, A. Khan and M. Hamayun (2003) Ethnobotanical Resources of Manikhel Forests, Orakzai Tirah, Pakistan
Page 10-2
Iftikhar uz Zamana (2002) Conservation of Pheasants in North West Frontier Province (NWFP), Pakistan. IPIECA Report Series (2004) Guidelines for Oil Spill Waste Minimization and Management “Volume-12” IUCN Red List (2010) International Union for Conservation of Nature and Natural Resources Red List of Threatened Species (http://www.iucnredlist.org/ ) Mian Sayed Badshah (Undated) Geology of Bajaur and Northern part of Mohmand Agency S. K. Marwat, Fazal-ur-Rehman, K. Usman, A. A. Khakwani, S. Ghulam, N. Anwar, M. Sadiq and S. J. Khan (2011) Medico-ethnobotanical studies of edible wild fruit plants species from the flora of north western Pakistan Shaheed Bhutto Foundation (2008). Mainstreaming FATA. (www.sbp.org.pk) Shaheed Bhutto Foundation (2009) SBF FATA Figures (www.sbp.org.pk) Shamsad, K.M. (1988) The Meteorology of Pakistan. Royal Book Company, Karachi, Pakistan. 1988. T.J Roberts (1991) The Mammals of Pakistan. Oxford University Press, London, England. UNICEF, WFP (2009) Multiple Indicator Cluster Survey MICS Federally Administered Tribal Areas (http://floods2010.pakresponse.info/Nutrition/surveys/MICS.pdf) UN-Habitat (2010) Seismic Zoning Map Paksitan - UN-HABITAT Pakistan (http://www.unhabitat.org.pk/Maps-updated/UNH-PAKOV_SZ_A3_02122010.pdf) USAID (1991), Socioeconomic Profile of Orakzai Agency. For Plannig and Development Department of NWFP, Government of Pakistan. WBG (2007/2008) Environmental, Health and Safety General and Industry Sector Guidelines of the World Bank Group. 2007 and 2008. (http://www.ifc.org/ifcext/sustainability.nsf/Content/EHSGuidelines ) WFP (2007) Rapid Needs Assessment Report of FATA (http://documents.wfp.org/stellent/groups/public/documents/ena/wfp153748.pdf) WHO (1991) Guideline levels for methylmercury in fish. CAC/GL-7-1991. FAO/WHO Food Standards. World Health Organization CODEX alimentarius. (http://www.codexalimentarius.net/download/standards/21/CXG_007e.pdf )
Page 1
Annexures
Annexure 1: Flora of FATA
No. Botanical Name Local Name Family Folk Uses
1 Acacia modesta Palosa Mimosaceae FW, FP, MP,HP, F
2 Acacia catechu Kikar Mimosaceae FW, FP, HP, F
3 Acer caesium Shanda wanyae Aceraceae O, FW
4 Achyranthus aspera Buch Kanda Amaranthaceae MP, FP
5 Albezia lebbeck Srekh Mimosaceae FW, FP
6 Adhatoda vasica Bezya Acanthaceae FW, MP
7 Adiantum cappillus veneris Bar sumbal Adiantaceae MP, SP, U
8 A. incisum Barsumbal Adiantaceae MP, SB
9 A. venustum Bbozayae Adaintaceae MP, SB
10 Agaris campestris Kholkae Acgaricaceae PN, S, R
11 Ailanthus altissima Asli shandai Simarubaceae FW, FP, SB, WB, FU, F
12 Ajuga bracteosa Soor Boutai Lmiaceae MP,
13 A parviflora Beth Tarkha booti Lamiaceae MP, FN,
14 Allium ascalonium Piazakae Alliaceae MP,S
15 Aloe vera Zahar boutyae Liliaceae MP
16 Onosoma sp. Ratan Jok Boraginaceae MP
17 Amaranthus caudatus Chalwai Amaranthaceae PH, FP, FO
18 Anethum sow Sawah Umbeliferaceae MP
19 Anthoroxan pronodes Gaya Poaceae FP, FO
20 Arisema utile Kukar mar Araceae MP, PN
21 A. tortuosum Kukar mar Araceae MP, PN
22 Artimisia miritima Tarkha Astraceae MP, PN, GP, SB
23 A. Scopania Jaokae Astraceae MP, GP, BR, FW
24 Aristida adscensionis Mashkar Poaceae FP, FO, BR
25 Asparagus adscendens Thindorae Liliaceae M, MP
26 Astragalus anisacanthus Mamol Liliaceae MP, M
27 A. phyrrhotrichus Mamol Liliaceae MP, M
28 A. psilocentros - Liliaceae MP, M
29 Atropa accuminata Barkak Solanaceae MP, PN
30 Avena Fatua Jamdarae Poaceae FP, FO
31 Bauhinia varriegata Karyal Caesalpinaceae PH, FW, SP, FU
32 Berberis vulgaris Zark Berberidaceae MP, F, FW
33 Berberis lycium Zark azghayae Berberidaceae MP, F, FW
34 Berginia ciliata Gat panra Saxifragaceae MP, 0
35 Brumus japanicus Jaokae Paceae FP, FO
36 Buxus wallichiana Shamshad Buxaceae MP, FW, U
37 Calendula arvensis Ziar Gulae Astraceae MP
38 Calendula officinalis Ziar Gulae Astraceae MP
39 Calotropis procera Ak Thandorayae Aecelpediaceae MP, PN
40 Cannabis sativa Bang Cannabidaceae MP, SH, FS
41 Capsella bursa-pastoris Bambesa Brassicaceae FP, MP
42 Carrisa ophaca Khkar Mewa Carricaceae WF, FP, FW, HP, F
43 Carthamus oxycantha Kareza Astaraceae MP
44 Celtis australis Tagha Ulmaceae MP, AT, FU, SP
45 Celtis leavigata - Ulmaceae WF,U
Page 2
46 Chrysopogon aucheri Spin wakha Poaceae FP, FO, PR
47 Chrysopogon montanus Spin wakha Poaceae FP, FO, PR
48 Chinopodium album Sarmae Chenopodiaceae PH, MP, FP
49 Chenopodium botrys Darshool Chenopodiaceae MP
50 Cenchrus pennise tiformis Pisho Lamyae Poaceae FP, FO
51 Cenchrus cilliaris Pisho Lamyae Poaceae FP, FO
52 dchorium intybus Shin guluk Astraceae PH, MP
53 Clematis orientalis Zelai Ranunculaceae MP
54 Corydalis stewartii Mamera Papveraceae MP
55 Cotoneaster affinis Kharawa Rosaceae MP,FW
56 Cotoneaster microphylla Kharawa Rosaceae MP, FW, WF
57 Cotoneaster numularia Mamanra Rosaceae MP, FW
58 Cotinus coggyria Miswakae Anacardiaceae MP, FW, SB
59 Crataegus oxycantha Ghwanza Rosaceae MP, FW, F
60 Cuscuta reflexa Nela Danai Convolvulaceae GP, FP
61 Cynodon dactylon Kabal Poaceae FP, FO, 0
62 Dicliptera blupiroides Oodi gulae Acanthaceae FP, FO
63 Dalbergia sissoo Shawa Papilionaceae FW, R, C, U, FU
64 Daphne papaveracae Leghonae Thymeleaceae MP, FW
65 Datura stramonium Tura Solanaceae MP
66 Datura metal Tura Solanaceae MP
67 Desmostachya bipinnata Drab Poaceae FP, FO
68 Diospyrus lotus Ami ok Ebenaceae FW, AT, SP, F, FU
69 Dodonia viscosa Ghwarawonyae Sapindaceae FW, PR, F
70 Elaeguns umbellata Ghanamranga Elegnaceae WF, FW, MP, F, HP
71 Euphorbia hirta - Euphorbiaceae MP
72 Euphorbia prostata Warmaga Euphorbiaceae MP
73 Ficus glomerata Urmal Moraceae WF
74 Ficus palmata Inzar Moraceae WF, FP, FW
75 Fragaria indica Tha Bouti Manzakha
Rosaceae MP, WF
76 Fragaria nubicola Tha Bouti Manzakha
Rosaceae WF, MP
77 Fraxinus excurlsior Khang Oleaceae FP, WF, HP
78 Fumaria indica Papra Papaveraceae MP, FP, FO
79 Grewia optiva Pastha Wanyae Tiliaceae FP, WF, FW, C, F
80 Gymnosporia spinosa Gandejareyae Celastraceae HP, FW, FS
81 Hedra hilex Prewatyae Araliaceae FP, MP
82 Hypericum perforatum Shin chai Guttiferaceae B, MP
83 Impatiens brachycentra Thor lakayae Balsaminaceae FP, MP, D
84 Impatiens edgeworthii Thor lakayae Balsaminaceae D, FP, MP
85 Impatiens flemingi Thor lakayae Balsaminaceae D, FP, MP, WF
86 Indigofera weithii Ghwareja Papiolionaceae FP
87 Jasminium humile Prewatyae Oleaceae FW, D, 0, IP
88 Jasminum officinale Prewatyae Oleaceae FW, D, 0, IP
89 Juglans regia Ghouz Juglandaceae WF, FP, MP, FS, AT, SP, S, O, DF, M, SM
90 Malva neglecta Panerak Malvaceae FP, PH, FO
91 Malva sylvestris Panerak. Malvaceae FP, PH, FO, MP
92 Matricaria chmomilla
Astraceae MP
93 Mallotus philippensis Kambela Euphorrbiaceae FP, MP, FW, SP,FU
94 Malvastrum coramondilianum Gaya Malvaceae MP, FW, FP D
95 Melia azedarech Draka. Meliaceae F, MP, FW, SP, FU
Page 3
96 Mentha longifolia
Lamiaceae MP
97 Mentha spicata Nanalyea. Lamiaceae B, MP, S
98 Mentha sylvestris Nanalyea. Narey Lamiaceae B, MP, S
99 Micromeria biflora Narey Shamakey.
Lamiaceae MP, BA
100 Morus alba Baidanaa. Moraceae WF, FP, MP, FW, AT, WB, SP, F, FU
101 Morus nigra Thoot. Moraceae WF, MP, FP, FW, AT, FO, F, FU
102 Myrsine africana Maraghoneyea. Myrsinaceae MP, FW, C
103 Nanorrhophs ritchieana Mazaryae Palmaceae WP, PR, FU, BR, U
104 Nasturtium officinale Sharyea. Brassicaceae PH, FP, MP
105 Nasturtium microphyllum Sharyea. Brassicaceae PH, FP, MP
106 Olea ferruginea Khona. Oleaceae WF, FP, FW, AT, SP, C
107 Onopordeum acanthium Wrejakai. Asteraceae FP, MP
108 Origanum vulgase Shamakai. Lamiaceae MP, C
109 Oxalis corniculata Manzakin Tarokey.
Linaceae FP, S, IP
110 Parrotiopsis jacquemontiana Pechoo Hamamelidaceae FW, PR, SH, C
111 Peroskia artiplicifolia Sensobyae Lbiateae GB, MP, BR
112 Phragmites communis Sharghashyae Poaceae U
113 Pimpinella diver sifolia Desi Zankai Pinaceae MP, S, FU
114 Pinus roxberghii Nakhtar Pinaceae FW, WF, L, SB, O, T, R, F
115 Pinus wallichiana Nakhtar Pinaceae FW, L, SB, O, T, R, F
116 Pistacia integerrima Shnai Pistaciaceae FP, MP, FW, F
117 Pistacia khinjik Shnai Pistaciaceae WF, F, FW, FP
118 Phytolacca lathenia Tamakoo saag Phytolocaceae PH, MP, D, I
119 Plantigo lanceolata Jabbai Plantaginaceae MP, FP
120 Plantigo major Chawayo Jabai Plantaginaceae MP, FP
121 Plectranthus ragosus Spina baiza Lamiaceae MP, FP, BA
122 Polygonum amplexicaul - Latiaceae
123 Polygonatum verticillatum Nooi Alam Latiaceae MP, FP
124 Podophyllum emodi Soor Marchakai Podophyllaceae MP
125 Polygonum aviculare Palpolak Polygonaceae MP, FN
126 Prangos pobularia Kamasla Zankai Umbillefereae MP
127 Portulaca oleraceae Warkharai Portulaceae PH, MP
128 Prunus cornuta Nangawar Rosaceae FW, F, DF
129 Punica granatum Anangorae Punicaceae WF, FW, F
130 Pteridium equilinum Kwanae Dennstaediaceae PH, CP
131 Pyrus pashia Tanga Rosaceae RS
132 Quercus ilex Khara serai Fagaceae FW, F, CH, C
133 Quercus dilatata Ghwara serai Facgaceae WF, FP, FW, F, CH, C
134 Rananculus muricatus Quazi ban Rununculaceae MP, FP
135 Ricinus communis Asila harhanda Euphorbiaceae FW, SB, F, HP
136 Robinia pseudocacia Kikar Papilionaceae FP, FW, F, HP
137 Rosa brunonii Thandorayae Rosaceae HP, FC
138 Rubus fruticosus Karwara Rosaceae WF, MP, F, FU
139 Rubus sanctus Largai manzakha Rosaceae WF, MP, F
140 Rumex acetosa Tarokai Pohygonaceae PH, MP
141 Rumex dentatus Shlkhi Pohygonaceae PH, MP
142 Rumex nepalensis Zanda Pohygonaceae PH, MP
143 Sacchrum monja Nal Poaceae SB, HP, U
144 Sacchrum spontaneum Sharghashae Poaceae SB, U
Page 4
145 Salix baby Asila wala Salicaceae SB, SP, FP, FW
146 Salvia lanata - Lamiaceae MP
147 Salvia mubicala - Lamiaceae MP
148 Sarcococca saligna Ladanr Buxaceae MP, FW
149 Sedum ewersii The Gat warkharae
Crasulaceae MP
150 Solarium nigrum Tore ninae Solanaceae PH, MP
151 Solarium xanthocarpum Mara ghoonae Solanaceae MP
152 Soncus asper Shawda pai Leguminaceae FP
153 Sorghum helepense Dadam Rosaceae FP, FO
154 Stychus parviflora Sper bootae Labiataceae MP, FW
155 Taraxucyn officinale Ziar gwalae Tamaricaceae MP
156 Taxus buccata Srap Taxaceae FP, FW, AT, C
157 Tecoma crucigera Lowar Begnonicaceae FW, 0
158 Thalictrum faleoneri Mamera Combritaceae MP
159 Thalictrum minus Mamera Combritaceae MP
160 Thymus helepens Pannay/Mray
MP
161 Tribulus terristris Markoondai Zygophyllaceae MP
162 Utrica dioca Lewane seznak Utricaceae PH, MP
163 Utrica pilulefora Sezoonkai Utricaceae MP
164 Valeriana jatamansi Makhkak Velerianaceae MP
165 Varbascum thapsus Khar dag Scrophul ari aceae MP
166 Veronica ciburia Shamakae Scrophul ari aceae MP
167 Viburnum cotinifolium Ghamzewa Caprifoliaceae WF, MP, F, HP
168 Viola serpens Banafsha Viol aceae MP, PH
169 Vitex negundo Marwandai Verbenaceae MP, GP
170 Withania sommifera - Solanaceae MP, PN
171 Xanthium strumarium Gishkae Asteraceae MP, FW
172 Zizypus jujuba Bera Rhamnaceae WF, HP, FW, AT Source: H. Ahmad, S. Khan, A. Khan and M. Hamayun (2003) Ethnobotanical Resources of Manikhel Forests, Orakzai
Tirah, Pakistan
AT Agricultural Tools FN Fish Poison S Spice
B Beverage FC Fishing Check SA Snuff Ash
BE Beeds FU Furniture R Resin
BR Broom GP Green Pesticide RS Root Stock
BA Bee Attractants HP Hedge Plant SB Soil Binder
C Construction I Ink SF Soil Fertility
CH Charcoal IP Incense/Perfume SP Shade Plant
CP Cash Plant L Light SH Sticks/Handles
D Dye M Miswak SR Soil Reclamation
DF Dry Fruit MP Medicinal Plant SM Smoking Medicine
F Fence O Ornamental T Timber
FO Forage P Paper U Utensil
FP Fodder Plant PH Pot Herb WB Wind Break
FS Fiber Species PN Poison WF Wild Fruit
FW Fuel Wood PR Packing/Rope WC Wood Carving
Key to the Table Above
Page 5
Annexure 2: Socio-Economic Indicators of FATA
No. Indicators Unit Year FATA Bajaur Orakzai
1 AREA & POPULATION
a. Area Sq. Km 1998
Census 27,220 1,290 1,538
b. Total Population (Projected) Persons 2006-07 3,846,188 865,560 272,986
c. Male Population Persons 2006-07 2,000,460 443,720 136,548
d. Female Population Persons 2006-07 1,845,728 421,840 136,438
e. Density Per./Sq. Km 2006-07 141 671 177
f. Annual Growth Rate % 1988-98 2.19 4.33 2.69
2 AGRICULTURE
a. Reported Area 000 hect. 2005-06 2,722.04 129.04 153.76
b. Cultivated Area 000 hect. 2005-06 216.18 75.10 16.31
c. Cultivable Waste 000 hect. 2005-06 173.99 11.19 3.45
d. Cultivable Area 000 hect. 2005-06 390.17 86.29 19.76
e. Irrigated Area 000 hect. 2005-06 83.24 19.92 2.21
f. Forest Area 000 hect. 2005-06 43.18 11.30 5.00
g. Cultivated Area as % of Reported % 2005-06 7.94 58.20 10.61
h. Irrigated Area as % of Cultivated % 2005-06 38.50 26.52 13.55
i. Forest Area as % of Reported Area, % 2005-06 1.59 8.76 3.25
j. Land Use Intensity % 2005-06 55.14 87.03 82.54
k. Population per Cultivated Area Persons 2005-06 17.00 11.00 16.00
l. Population per Irrigated Area Persons 2005-06 45.00 42.00 121.00
Yield Per Hectare
m. Maize Kgs 2006-07 1,524 1,561 1,063
n. Rice Kgs 2006-07 1,504 1,487 1,478
o. Wheat Kgs 2006-07 1,280 1,147 1,229
Animal Husbandry
p. Veterinary Hospital Nos 2006-07 25 1 2
q. Veterinary Dispensaries Nos 2006-07 207 15 13
r. Civil Veterinary Centers Nos 2006-07 208 9 27
Forest/Fisheries
s. Fish Hatchery Nos 2005-06 - - -
t. Fruit Plants Distributed Nos 2005-06 184,238 42,780 53,657
3 ELECTRICITY
Villages Electrified Nos 2005-06 3,952 413 438 Source: Shaheed Bhutto Foundation FATA Figures
Page 6
Uni
t Year
FATA Bajaur Orakzai
Male Femal
e Total Male
Female
Total Male Fema
le Total
4 EDUCATION
Indicators
Educational Institutions
a. All Primary Level Schools
Nos
2006-07 2,628 1,905 4,533 366 165 531 226 174 400
b. Middle Schools Nos
2006-07 287 136 423 23 12 35 16 10 26
c. High Schools Nos
2006-07 226 32 258 22 2 24 22 4 26
d. Higher Secondary Schools
Nos
2006-07 8 4 12 1 0 1 1 0 1
e. Inter/Degree Colleges Nos
2006-07 22 11 33 3 1 4 1 1 2
f. Universities Nos
2006-07 - - - - - - - - -
Participation Rate
g. Primary Level (5-9) % 2006-
07 61.37 29.49 44.83 58.77 14.42 36.07 60.64 30.30 45.04
h. Middle Level (10-12) % 2006-
07 48.28 10.86 31.21 42.59 3.14 24.04 57.70 7.67 33.13
i. High Level (13-14) % 2006-
07 8.25 1.36 5.15 5.10 0.34 2.86 8.51 0.74 4.69
Teaching Staff
j. Primary Schools Nos
2006-07 6,788 4,348
11,136 910 370 1,280 580 366 946
k. Middle Schools Nos
2006-07 136 70 206 141 72 213
l. High Schools Nos
2006-07 3,899 444 4,343 307 17 324 300 41 341
m.
Higher Secondary CSChools
Nos
2006-07 234 75 309 18 - 18 27 - 27
Enrolment by Level
n. Primary Schools Nos
2006-07
231,794
134,270
366,064
60,584
15,407
75,991
13,846 8,739
22,585
o. Middle Schools Do 2006-
07 52,20
2 17,50
1 69,70
3 2,617 356 2,973 2,659 955 3,614
p. High Schools Do 2006-
07 88,48
4 13,82
1 102,3
05 9,309 376 9,685 6,274 486 6,760
q. Higher Secondary Schools Do
2006-07 6,305 1,671 7,976 469 0 469 697 0 697
Literacy Ratio % 1998 29.50 3.00 17.40 22.3
2 3.38 13.4
1 19.6
5 1.28 10.6
3 Source: Shaheed Bhutto Foundation FATA Figures
Page 7
No. Indicators Unit Year FATA Bajaur Orakzai
5 HEALTH
Indicators Unit Year
a. Hospital Nos 2007 33 2 3
b. Dispensary Nos 2007 302 8 16
c. R.H.Cs Nos 2007 8 2 2
d. B.H.Us functioning Nos 2007 172 20 25
e. B.H.Us Non-functioning Nos 2007 - - -
f. Hospital & Dispensary Beds Nos 2007 1,654 211 108
g. Population/Hospital & Dispensary Bed Nos 2007 2,325 4,102 2,527
h. Doctors including Radiologist Nos 2007 550 129 50
i. Population per Doctor Nos 2007 6,993 6,710 5,460
J Nurses Nos 2007 117 22 4
k. Population per Nurse Nos 2007 32,873 39,343 68,246
6 PUBLIC HEALTH ENGINEERING
a. Tube wells Nos 2006-07 - - -
b. Drinking Water Coverage % 2006-07 58 56 50
7 COMMUNICATIONS
a. Total Roads Kms 2005-06 5,398.72 673.79 513.32
b. High Type Kms 2005-06 3,398.06 372.05 285.24
c. Low Type Kms 2005-06 2,000.66 301.74 228.08
d, Road per Sq. Km. of Area Kms 2005-06 0.20 0.52 0.33
e. Post Offices Nos 2003-04 188 13 11
f. Population per Post Office Persons 2005-06 20,020 63,818 24,285
g. Telephones Nos 2004-05 59,094 6,433 2,054
h. Population per Telephone Persons 2004-05 64 129 130
8 MINERAL
a. Barite Tons 2005-06 10 - -
b. Chromites Tons 2005-06 66,381 350 -
c. Coal Tons 2005-06 266,490 141,160
d. Fluorite Tons 2005-06 892 - -
e. Limestone Tons 2005-06 1,461,859 2,686 -
f. Manganese Tons 2005-06 - - -
g. Marble Tons 2005-06 818,987 30,398 -
h. Mecu Tons 2005-06 34,935 1 -
i. Quartz Tons 2005-06 1,760 - -
j. Scrap Marble Tons 2005-06 3,405 20 -
k. Soapstone Tons 2005-06 16,600 526 - Source: Shaheed Bhutto Foundation FATA Figures
Page 8
Annexure 3: Checklists for ESMP
A. Checklist for Campsite Establishment
Sr. No. Description Status
1 Have the photographs been taken to record the pre-camping conditions? Y/N
2 Is reducing the camp size environmentally important? Y/N
3 If yes, is it possible to reduce the camp size? Y/N
4 If yes, has the camp size been minimized? Y/N
5 Is the campsite within critical wildlife habitat or within 2 km of important reproductive areas during breeding season?
Y/N
6 Is the campsite within 1 km of a settlement or area of ecological importance? Y/N
7 Has the camp been established in the existing clearings? Y/N
8 Has any vegetation been cleared? Y/N
9 If yes, is the vegetation loss significant? Y/N
10 If yes, have mitigation measures been discussed and agreed? Y/N
11 Has the topsoil been damaged significantly or rootstock destroyed? Has a bulldozer or grader been used?
Y/N
12 If yes, have mitigation measures been discussed and agreed? Y/N
13 Have the trees or bushes been burnt? Y/N
14 Have the trees or bushes been disposed in water body or dry streambed? Y/N
15 Has the natural drainage been disturbed or blocked? Y/N
16 Has the septic tank been built for sewerage? Y/N
17 Has the sump been built for wastewater disposal? Y/N
18 Has the sump been built in absorbent soil? Y/N
19 Has the sump been built down-slope from the camp? Y/N
20 Is the sump large enough to contain the camp wastewater and rainwater? Y/N
21 Can surface water enter the sump? Y/N
22 Is the sump within 300 meters of any water hole, stream or dry streambed? Y/N
23 Is the sump bottom at least 3 m above the groundwater level? Y/N
24 Is the sump covered, in order to reduce access of insects and animals? Y/N
25 Has plastic sheeting been placed under all concrete? Y/N
Notes:_________________________________________________________________________
_______________________________________________________________________________
_______________________________________________________________________________
_____________________
Date:____________ Signature:_______________ Name:___________________________
Page 9
B. Checklist for Camp Operation
Sr. No. Description Status
1 Has any vegetation been cleared or damaged? Y/N
2 Have trees or bushes been burnt? Y/N
3 Have any trees or bushes been disposed in a water body or dry streambed? Y/N
4 Is water drawn from the local water sources? Y/N
5 If yes, has the yield and demand been determined to ensure there is enough to meet the requirements of the locals and the camp?
Y/N
6 If yes to point 4, is the water level in the well checked and recorded regularly? (record the quantity used by the camp)
Y/N
7 If yes to point 4, has compensation been paid for the water use? Y/N
8 Has the natural drainage been disturbed? Y/N
9 Are the fuels and oils handled in a safe manner, ensuring no leakage or spillage?
Y/N
10 Are there any fires being built in the open? Y/N
11 If yes, are fires supervised and controlled? Y/N
12 Are fire extinguishers available? Y/N
13 Is there any local wood being used for building fires or cooking the food? Y/N
14 Has any surface water entered the sump? Y/N
15 Is the sump kept covered, in order to reduce access of insects and animals? Y/N
16 Are there enough waste bins around the camp? Y/N
17 Are the waste bins emptied daily? Y/N
18 Is food waste disposed in the open? Y/N
19 Are the containers placed in the vehicles to store trash being discharged at the campsite regularly?
Y/N
20 Is the combustible waste incinerated regularly? Y/N
21 Is the non-combustible waste sent to nearest waste contractor for disposal? Y/N
22 Is the hazardous material incinerated, spilled or spread on the ground? Y/N
Notes:_________________________________________________________________________
_______________________________________________________________________________
_______________________________________________________________________________
_____________________
Date:____________ Signature:_______________ Name:___________________________
Page 10
C. Checklist for Road Travel
Sr. No. Description Status
1 Is the number of routes kept to a minimum? Y/N
2 Are short cuts been used? Y/N
3 Are dry stream beds being used for travel where no existing track exists Y/N
4 Has vegetation been cleared or any grading/leveling been done along the routes?
Y/N
5 Are vehicles used off the road/routes? Y/N
6 Are the routes that are close to animal water holes, their feeding, nesting or breeding areas used?
Y/N
7 Is the travel on the access roads minimized with the help of good upfront planning
Y/N
8 Do vehicles travel in single file? Y/N
9 Are signs posted to mark the start and end of approved tracks, vehicle speed and sensitive areas?
Y/N
10 Is the vehicle speed limit of 40 kmph followed when passing through or near towns or critical habitat?
Y/N
11 Are heavily traveled routes watered on a daily basis to minimize dust (where applicable)?
Y/N
12 Are the drivers careful and watchful about wild and domestic animals? Y/N
13 Has any natural drainage been disturbed or altered? Y/N
14 Is any soil erosion observed? Y/N
15 If yes, have the mitigation measures been discussed and agreed? Y/N
16 Is stream crossing carried out at places that are approved by the IMC? Y/N
17 Is night travel avoided near the wildlife sensitive areas? Y/N
18 Is the use of horns avoided as far as possible? Y/N
19 Is the horn used during the night? Y/N
20 Is a pressure horn used/fitted in any vehicles? Y/N
21 Are litter or cigarettes thrown outside the vehicles? Y/N
22 Do the vehicles carry adequate containers for litter/garbage and are they emptied at the campsite or other designated location regularly?
Y/N
23 Are proper repairs carried out in case of damage to the route caused by the project related activities?
Y/N
Notes:_________________________________________________________________________
_______________________________________________________________________________
_______________________________________________________________________________
_____________________
Date:____________ Signature:_______________ Name:___________________________
Page 11
D. Checklist for Vehicles
Sr. No. Description Status
1 Are the vehicles maintained and inspected regularly? Y/N
2 Are the oil, fuel, acid or water leaks from the vehicles immediately attended? Y/N
3 Are the vehicles with leaks operated? Y/N
4 Do the vehicles have fire extinguishers? Y/N
5 Has there been any spillage during vehicle fuelling or maintenance? Y/N
6 If yes, are the mitigation measures needed? Y/N
7 If yes, have the mitigation measures been discussed and agreed? Y/N
8 Are the vehicles washed or serviced in the field? Y/N
9 Are the vehicles washed on a concrete pad and the water collected? Y/N
10 Is vehicle-related waste, such as oils, filters, old tires or parts left lying around or disposed of inappropriately?
Y/N
11 Are the vehicles kept in good working condition? Y/N
12 Are the vehicles properly tuned? Y/N
13 Do the vehicles have excessive smoke emissions? Y/N
14 Is the fuel injection system of the diesel vehicles properly maintained? Y/N
15 Do the vehicles have properly functioning silencers (mufflers)? Y/N
16 Do the vehicles carry a container to store trash/refuse? Y/N
Notes:_________________________________________________________________________
_______________________________________________________________________________
_______________________________________________________________________________
_____________________
Date:____________ Signature:_______________ Name:___________________________
Page 12
E. Checklist for Fuels, Oils, and Chemicals
Sr. No. Description Status
1 Do the fuel storage facilities have adequate secondary containment up to 120% capacity in case of leakage or spillage?
Y/N
2 Is the fuel storage facility located at least 100 m and down-slope from any water body and not located on fissured or cavernous limestone?
Y/N
3 Is the firefighting equipment available near the fuel storage? Y/N
4 Is the fuel storage downwind and downslope from the camp? Y/N
5 Is there any other combustible or flammable material in the fuel storage area? Y/N
6 Is regular inspection carried out to check leaks and spills? Y/N
7 Are the isolation valves installed, in case of multiple tanks connected together?
Y/N
8 Are the fuel tanks properly marked with their contents? Y/N
9 Are the fuel transfer arrangements protected against spills? Y/N
10 Are the drip trays used? Y/N
11 Are tarpaulins placed under equipment and fuel containers that have the potential to spill or drip fuels, oils or chemicals?
Y/N
12 Are the fuel transfer operation supervised? Y/N
13 Are the equipment, materials and trained personnel available to clean up spills?
Y/N
14 Are the spills and leaks thoroughly cleaned? Y/N
15 Are the spilled oil or fuel and used clean-up material disposed properly? Y/N
16 Are the spills and leaks reported and recorded? Y/N
17 Are the stained soils removed or covered following clean-up of spills in consultation with the IMC?
Y/N
18 Is the emergency response plan implemented for spills and leaks? Y/N
Notes:_________________________________________________________________________
_______________________________________________________________________________
_______________________________________________________________________________
_____________________
Date:____________ Signature:_______________ Name:___________________________
Page 13
F. General Checklist
Sr. No. Description Status
1 Are activities taking place in agricultural or grazing areas? Y/N
2 If yes, has the implementing agency made arrangements with the local people for access and compensation?
Y/N
3 Is contractor staff informing village leaders of location and timing of all major activities?
Y/N
4 When entering settlements, is contractor staff accompanied by local men and avoiding all contact with women?
Y/N
5 Are visitors from local areas restricted from entering the camp? Y/N
6 Are locally hired camp employees medically screened and trained in good hygiene practices?
Y/N
7 Is trash, wrappers, shopping bags, paper, cans, bottles or any other kind of litter left in the open?
Y/N
8 Is the IMC immediately notified of any wildlife sightings and are the sightings logged?
Y/N
9 Are ravines used for climbing or descending from the hills? Y/N
10 Are the wild animals or domestic animals harassed? Y/N
11 Is the "no hunting, fishing or trapping" policy strictly enforced? Y/N
12 Are there any pets in the field or the camp? Y/N
13 Are any archeological sites or places of cultural or religious significance disturbed?
Y/N
14 Are any artifacts taken or removed by the survey crew? Y/N
15 In the event of incidental discoveries of archaeological sites, are the contingency measures followed?
Y/N
16 Are existing trails used for walking? Y/N
17 Is the "no shortcuts" policy followed? Y/N
Notes:_________________________________________________________________________
_______________________________________________________________________________
_______________________________________________________________________________
_____________________
Date:____________ Signature:_______________ Name:___________________________
Page 14
Annexure 4: Survey Instruments
Settlement Questionnaire
Date of Interview Questionnaire Number
Background Information
Name of Investigator(s)
Settlement Name Coordinates
District/Tehsil Zone
Closest Main City/Town Distance to City/Town (km)
Name and Contact Details of Village/Community Leader:
Respondent Information
Name(s) Role/Title/Responsibility Contact Details
Demography
Household: A household may be either a single person or a multi-person household. Household members may be related or unrelated and essentially include people who make common provisions for food and other essentials of living and have no usual place of residence elsewhere.
Men/Women: More than 15 years and less than 65 years of age.
Old Men/Women: 65 years and above.
Boys/Girls: Less than 15 years of age.
Masonry: Houses with brick walls and concrete or tin roof.
Adobe: Houses made of mud or unbaked bricks of clay and straw.
Total Households Masonry Adobe
Total Population Men Women Boys
Girls Old Men Old Women
Education
Available: A facility is considered available if the settlement residents consider the structure of the facility a part of the settlement or if it is at an approachable distance of less than 2 km from the settlement peripheral; unless at a distance of less than 2 km, it falls within the boundary of an adjoined settlement
Functional: The facility is functional if over the last two years it was utilized by the settlement resident for the relevant reason
Level/Type: Primary (Nursery to Class V); Middle (Up to Class VIII); High (Up to Class X); Intermediate (Up to Class XII); Graduate (Bachelors); Madrassah; Informal
Page 15
Provider: 1 = NGO 2 = Government 3 = Private Individual(s) 4 = Other
Are there any educational facilities available in the area: Yes No If yes:
Available Facility Functional (Y/N)
Level/Type Provider (NGO, govt.,
Pvt.)
Monthly Fee
1
2
3
4
5
Enrolment for the above Facilities:
Available Facility Enrolment
Male Female Total
1
2
3
4
5
Health
Access to Health Care: Available: A facility is considered available if the settlement residents consider the structure of
the facility a part of the settlement or if it is at an approachable distance of less than 2 km from the settlement peripheral; unless at a distance of less than 2 km, it falls within the boundary of an adjoined settlement
Functional: The facility is functional if over the last two years it was utilized by the settlement resident for the relevant reason
Type: 1 = Dispensary 2 = BHU 3 = Private Local Clinic 4 = LHV 5 = Local Healer 6 = Immunization (e.g. polio drops) 7 = Trained Midwife 8 = Untrained Midwife 9 = Public Hospital 10 = Other
Provider: 1 = NGO 2 = Government 3 = Private Individual(s) 4 = Other
Are there any Health facilities available in the area: Yes No If yes:
Available Facility Functional (Y/N)
Type Provider (NGO, govt.,
Pvt.)
Consultation Fee
1
2
3
4
5
Health Status: Common Ailments: Men:
Women:
Children:
Number of mentally/ physically challenged people in the settlement:
Number of widows in the settlement:
Page 16
Water Supply and Sanitation
Water Supply: Available: A water source is considered available if the settlement residents consider the
structure of the facility a part of the settlement or if it is at an approachable distance of less than 2 km from the settlement peripheral; unless at a distance of less than 2 km, it falls within the boundary of an adjoined settlement
Source: 1 = Surface Water – Water Channels 2 = Surface Water – Lift Irrigation 3 = Ground Water – Tube-wells 4 = Ground Water – Dug-wells 5 = Ground Water – Hand Pumps
Provider: 1 = NGO 2 = Government 3 = Private Individual(s) 4 = Other
Are there any water sources available in the area: Yes No If yes:
Purpose Source Provider (NGO, govt., Pvt.)
Monthly Cost to Residents
Drinking
House-hold Use
Agricultural Use
Perception of Water Quality: Good Turbid Saline Odor Other Problems:
Sanitation: Pit Latrine Septic Tanks Sewerage Plant Open air
Agriculture and Fruit Production
Total land (acres): Total land cultivated(acres):
No. of landowners:
No. of tenants:
Summer corps:
Winter corps:
Type of Irrigation:
Type/Source of Irrigation Total Are Cropped (acres)
Water Consumption (cubic meter per acre)
Rain-fed
Surface Water
Water channels
Lift irrigation
Other (specify)
Ground Water
Tube-wells
Dug-wells
Other (specify)
Crops:
Page 17
Description (cereals, fruits, vegetables)
Estimated Annual Yeild (in kgs,
munds or trucks)
Self Consumption
(%)
Sold (%) Income Earned
Livestock
Type Goats Sheep Cows Donkeys Camels Other
Number
Value per Unit
Access to veterinary care: Yes No Distance from settlement (km):
Fuel Sources and Consumption
Is electricity available in the area: Yes No
Type Estimated Annual Consumption
Price Per Unit Source (e.g. grid, power plant name, forest, market)
Electricity
Fuel wood
LPG
Kerosene
Diesel
Other
Occupational Groups
Men/Women: Equal to and more than 15 years.
Boys/Girls: Less than 15 years of age.
Occupational Group Men (No.)
Women (No.)
Boys (No.)
Girls (No.)
Average Income per Earner, Yearly
Farming/Livestock Herding
Informal Trading
Business (Shopkeeper, etc.)
Mining Quarrying
Government Service
Privately Employee
Overseas
Handicraft
Other
Page 18
Infrastructure
Available: A facility is considered available if the settlement residents consider the structure of the facility a part of the settlement or if it is at an approachable distance of less than 2 km from the settlement peripheral; unless at a distance of less than 2 km, it falls within the boundary of an adjoined settlement
Provider: 1 = NGO 2 = Government 3 = Private Individual(s) 4 = Other
Facility Available (Y/N) Number (persons, facilities)
Provider
Telephone
Mobile
Post Office
Police Station
Police Check-post
Blacktop Road
Unsealed Road
Bank
Market
Public Transport:
Type Air Coaches Pickups Jeeps Rental Cars
Available (Y/N)s
Number
Capacity
Rout (description in terms of destination – country A to B, city A to B or local and frequency – weekly, daily, twice a day etc)
Route 1
Route 2
Route 3
Route 4
Migration Patterns
Out-migration: Has any households migrated from the settlement in the last 7 years? Yes No If yes, how many: Migrated to:
Purpose/reasons of out-migration:
In-migration: Has any households settled in the settlement during the last 7 years? Yes No If yes, how many: Migrated from: Purpose/reasons of in-migration:
Page 19
Community Support
Non-governmental Organizations (NGOs) and Community Organizations (COs):
Are NGOs active in the settlement: Yes No If yes:
NGO Name Facility Provided
Year Provided
Contact Person
Number of Beneficiaries
Perception of Performance
(Good, Average, Poor)
Are there any Settlement Organizations: Yes No If yes then specify type and purpose:
Total Members: Male: Female:
Are there any Women Organizations in the Settlement: Yes No If yes then specify type and purpose:
Total Members:
Government’s Ongoing Programmes and Schemes
Name of the Programme/
Scheme
Facility Provided
Duration Contact Person
Number of Beneficiaries
Perception of Performance
(Good, Average, Poor)
Need Assessment
(In order of importance)
1.
2.
3.
4.
5.
Page 20
Socio-cultural Characteristics
Social Setup
Main Tribes and Clans:
Tribe/Clan Name Estimated Share in Population (%)
Social Role (rulers, wazirs, farmers, lower casts etc.)
1
2
3
4
5
6
7
8
9
10
Are tribal conflicts common occurrence? Yes No
What are the main reasons of conflicts?
Reason Occurrence(rarely, sometimes or
frequently)
Intensity (murders, outcaste,
excommunication etc.)
Settlement Method (Discussed later)
Land
Water
Economic
Women
Other (Specify)
What are the traditional and judicial means of conflict resolution?
Do the tribal and spiritual leaders exert influence on the local communities and are they regarded a superior authority over the law enforcing authorities, for settling conflicts?
Main Religious and Sectarian Groups:
Religion/Sect Name Estimated Share in Population (%)
Social Status
1
2
3
4
5
Major Languages Spoken:
Name Estimated Share in Population
Page 21
(%)
1
2
3
4
5
What is the status of mobility of women and children in the village and outside area?
List the types of land, and property rights regime. Name the ultimate authority to settle land disputes?
List all festivals celebrated in the area.
Where do people gather on occasions and ceremonies (religious, political and personal)?
Provide information about the types of dresses worn. (male and female)
What relations/friendships does the settlement enjoy with other tribe (s)?
How does the community help the sick/poor/widows/elderly women?
How many settlement youth possess vocational skills and what type?