Water, Water Everywhere

Post on 18-Dec-2014

738 views 1 download

Tags:

description

Presented by Brenda Mainwaring, Union Pacific Railroad

Transcript of Water, Water Everywhere

1

Union Pacific 2011 Flood Recovery Efforts

Brenda Mainwaring, Director Public Affairs

2

Runoff Components

145%-150% of Normal May - June

3

Platte River – East of North Platte

Proposed Berm

North

4

Platte River – UPRR looking toward airport

Kearney Sub

North

5

Platte River – East of North Platte

Proposed BermNorth

6

Platte River – Berm constructionNebraska National Guard

7

Temporary outlets under track

Temporary cut through Hwy 30 to improve natural waterway flow

8

Platte River at North Platte– Height of berm = 3 feet

– Length of berm = 3600 feet

– Length of haul road = 6000 feet

– Additional 36” culverts = 4

– Sandbags placed = 2000 (industrial size)

– Sandbags stationed for backup = 800

– 32,106 tons of rip rap for berm (366 cars)

– 30,425 tons of ballast/rip rap (340 cars)

9

Missouri River Runoff above Sioux City

10

Missouri River Basin

11

Terminal Areas

Line

Milwaukee

Woodland Jct

North

Platte

Poplar Bluff

Council

St.Louis

Denver

S.Morrill

Fremont

Marysville

Sharon Springs

Jefferson City

Granger

Findlay Jct.

Salina

Cheyenne

Mason City

Minneapolis St.Paul

Janesville

Mankato

Clinton

Boone

Sioux City

Bill

Altoona

Adams

Bluffs

Gorham

Sheboygan

Topeka

Dexter

Rawlins

Dalhart

Hutchinson

Lincoln

PaolaHerington

Mo Valley

Ft.Madison

QuincyCity

Falls City

KenoshaLe Mars

GrandIsland

Kansas

Green River

Des Moines

Springfield

S.Pekin

W.Chicago

Aurora

Joliet

Provo Bond

Helper

Grand Jct.

Chicago

Salem

12

Traffic to/from major West Coast ports crosses the BasinTraffic to/from Mexican crossings traverse the Basin

Portland

Oakland

LA

Calexico

Nogales El Paso

Seattle

Eagle Pass

SLC

Eastport

Brownsville

Houston

KC

St. Louis

Omaha

Twin Cities

Duluth

Denver

Laredo

Dallas

Memphis

Chicago

New Orleans

Port access

Border crossings

13

Terminal Areas

Milwaukee

Woodland Jct

North

Platte

Poplar Bluff

Council

St.Louis

Denver

S.Morrill

Fremont

Marysville

Sharon Springs

Jefferson City

Granger

Findlay Jct.

Salina

Cheyenne

Mason City

Minneapolis St.Paul

Janesville

Mankato

Clinton

Boone

Sioux City

Bill

Altoona

Adams

Bluffs

Gorham

Sheboygan

Topeka

Dexter

Rawlins

Dalhart

Hutchinson

Lincoln

PaolaHerington

Mo Valley

Ft.Madison

QuincyCity

Falls City

KenoshaLe Mars

GrandIsland

Kansas

Green River

Des Moines

Springfield

S.Pekin

W.Chicago

Aurora

Joliet

Provo Bond

Helper

Grand Jct.

Chicago

Salem

1. Protect the “Red X”2. Protect Missouri line3. Protect Omaha to Kansas City

Priorities:

14

Missouri River Basin

Do we need to raise the track and if so, HOW MUCH?

• Army Corp model~Showed river elevation based on max release plus rain fall

~Inundation Maps

~River cross sections

• Railroad elevation data~Precision Measurement Vehicle data (+/- 3-4 feet)

~Survey key locations along route

15

Yes, we need to raise the track. Now what?

• Profile Sheets~Showing existing grade

~High water level

~Planned track raise

~Bridge work

• Surveyors~Stake track for planned raise

• Field Forces work the plan~…while keeping the track open for rail traffic

16

Other Tools Used:

• Aerial Photos

• Google Earth

• NOAA website (River Gages)

• Local Websites (Atchison River Bridge)

• Weather Forecasting (Inflow of Rivers/Streams)

• Army Corps of Engineers daily conference call

• Regional Army Corps locations (Omaha, Kansas City)

17

Blair Sub

Missouri Valley

Blair Sub

1940-52 levee system

• Blair, Omaha, Sioux City Subdivision– Length of track to raise

– Blair to Mo Valley 11 miles

– Council Bluffs to Mo Valley 19 miles

– Raise Average = 2.88 ft, max. = 6 ft

– Raised crossings = 11 Public & 2 Private

– Raised turnouts = 32

– Additional 48” culverts = 6

– Bridges raised = 5

– Aggregate delivered = 1884 Carloads

18

Council Bluffs and Missouri Valley

Missouri Valley

Blair Sub

– Losing the main line through Iowa was not an option

– Raised track height through CB federal levee in close coordination with City of Council Bluffs and Corps of Engineers

– Water levels did not reach Corps projections but UP would have been under water north of CB if we had not raised the track

– Sandbagged Missouri Valley’s water treatment plant and swimming pool/water park

– Coordinated street closures with City of Missouri Valley

– Readily available to City officials to voice concerns

19

Typical Bridge Raise

20

Blair Sub Track Raise

21

Missouri Valley, Canal Street(note valley between tracks)

Missouri Valley yard tracks (foreground) and through

tracks (rear). Note elevation difference.

22

Missouri Valley, 6th Street (Hwy L20) Alternate I-29 route

Borden Road private crossing Joslin Ave was underwater

(Private vehicles used UP ROW)

23

Joslin Ave (underwater)

CN track (rebuilt)

UP track (raised)

24

CN Railroad, UP Railroad, Flood line Monument Road, north of Council Bluffs

25

Railroad Stratigraphy Joslin Avenue at Monument Road, Council Bluffs

26

Atchison to Leavenworth, Kansas

• Preliminary review showed some areas could be 6-9 feet under water.

• Decision to monitor and provide a 48hr countdown to take the sub out of service.

• With Corps model not having the full impact on mainline, we decided to do what we could to keep the Kansas and Missouri lines open as long as possible.

27

Falls City Sub MP 313 – MP 320

Non federal levees

Federal levee

28

6/23/2011

FALLS CITY SUB MP 313.9

Fort Leavenworth levee after main track raise of 18”+/-Gage reading:Atchison……….29.3Leavenworth…..24.9

29

6/28/2011

FALLS CITY SUB MP 313.9

Fort Leavenworth levee after non federal levee over topped or failed to the north.Gage reading:Atchison……….30.3Leavenworth…..26.25

UP sandbags on siding

30

6/29/2011

FALLS CITY SUB MP 313.9

Fort Leavenworth levee after sandbags failed on siding. Gage reading:Atchison……….31.0Leavenworth…..28.0

31

6/30/2011

FALLS CITY SUB MP 313.9

Fort Leavenworth levee 24 hrs after breach. Gage reading:Atchison……….30.9Leavenworth…..30.0

32

7/3/2011

FALLS CITY SUB MP 313.9

Fort Leavenworth leveeGage reading:Atchison……….30.5Leavenworth…..30.2

33

7/7/2011

FALLS CITY SUB MP 313.9

Fort Leavenworth levee from access road looking east.Gage reading:Atchison……….30.3Leavenworth…..30.0

• Falls City Subdivision (Omaha to KC)– Water rose 3 feet in one hour after non-federal levee failure

– Reached Corps inundation predictions after levee failure

– Total miles raised = 26.62 miles plus 2 miles of sidings

– Raise average= 1.4 ft, Max. = 4.55 ft

– Raised crossings. = 3 Public & 10 Private

– Bridges raised = 4

– Aggregate delivered = 1,341 Carloads

34

River Sub, Kansas City to Jefferson City, MOShut down for a month

35

River sub Bridge 240.45

BRIDGE CONSTRUCTED IN 2007(4)PCB-119 [SIMN]

Gage reading 6/30/2008:Napoleon………(not available)Waverly…….…..20.5

36

7/3/2011

RIVER SUB MP 240.45

AFTER LEVEE BREACH NEAR MP 241.0.THIS LEVEE IS NOT ON FED OR NON FED LIST (FARMER LEVEE) Gage reading:Napoleon………27.3Waverly…….…..29.5

37

7/3/2011

RIVER SUB MP 240.45

LEVEE BREACH NEAR MP 241.0.THIS LEVEE IS NOT ON FED OR NON FED LIST (FARMER LEVEE) Gage reading:Napoleon……….27.3Waverly…….…..29.5

38

7/5/2011

RIVER SUB MP 239.5 TO MP242.0

BR 240.45

LEVEE BREACH NEAR MP 241.0.THIS LEVEE IS NOT ON FED OR NON FED LIST (FARMER LEVEE) Gage reading:Napoleon……….27.0Waverly…….…..29.9

39

7/5/2011

BR 240.45

RIVER SUB MP 239.5 TO MP242.0

LEVEE BREACH NEAR MP 241.0.THIS LEVEE IS NOT ON FED OR NON FED LIST (FARMER LEVEE)

40

BR 240.4516” +/- OVER TOP OF RAIL

RIVER SUB MP 239.5 TO MP243.0

LEVEE BREACH NEAR MP 241.0.THIS LEVEE IS NOT ON FED OR NON FED LIST (FARMER LEVEE)

7/5/2011

• River Subdivision– Total miles raised = 14.4 miles plus 1 mile of

sidings

– Aggregate delivered = 619 Carloads

•Jefferson City Subdivision– Total miles raised = 14.74

– Aggregate delivered = 276 Carloads

41

Scope of the Work

• Estimated cost: $50 million, including both lost revenue and repairs

• Flood desk staffed 24-7 from June through August and extra dispatching shifts for flooded areas

• 74 mile of mainline track raised as much as 6 feet

• 3 miles of siding track raised

• 9 bridges raised and cleared

• 458,000 tons (4,800 rail cars) of ballast, rip-rap and other stabilizing material

• Six dozen pieces of specialized equipment

• 90 percent customer satisfaction rating in July

• NO injuries or incidents!

42

Key Takeaways

• We had time to plan and react

• Years of investment in infrastructure and surge resources (locomotives, crews) paid off

• Collaboration with US Army Corps of Engineers resulted in benefits for all

• There are LEVEES and there are “levees”

• Lessons learned for the future about staging resources for weather emergencies

• Improved communication with customers about anticipated traffic problems and proposed solutions