Dubai AUH SHJ AjmanGCC Wastewater Projects Map
3,000m3/daySTP-MBBR Process
Yas Island, Abu Dhabi, UAE
1,100m3/daySTP-EA Process
Sharjah Municipality, Sharjah, UAE
1,100m3/daySTP-SBR Process
Sharjah Municipality, Sharjah, UAE
1,000m3/daySTP-MBBR Process
Al Reef Villas, Abu Dhabi, UAE
1,000m3/daySTP-MBBR Process
Al Moosa Labour Camp, SHJ, UAE
300m3/daySTP-UTB Process
Sharjah Expo Centre, Sharjah, UAE
200m3/daySTP-UTB Process
Domestic Sewage, Abu Dhabi, UAE
1
2
3
4
5
6
7
DUBAI
ABU DHABI
SHARJAH
1
1425
4
6
11
108
9
123
AJMAN
7
13
UAE
140m3/daySTP-UTB Process
Wadi Al Helo, Sharjah, UAE
120m3/daySTP-UTB Process
Al Maha Desert Resort, Dubai, UAE
Sewage Treatment Plant, Sharjah, UAE
80m3/daySTP-EP Process
60m3/daySTP-GW Process
50m3/daySTP-UTB Process
CNIA Bu Hasa Camp, Abu Dhabi, UAE
40m3/daySTP-UTB Process
Ajman City Centre, Ajman, UAE
8
9
10
11
12
13
14
Grey Water Treatment, Sharjah, UAE
80m3/daySTP-UTB Process
Sewage Treatment Plant, Dubai, UAE
Al Ula Winter Camp Development Project – Kingdom of Saudi ArabiaCASE STUDY
Al Ula Winter Camp Development Project.
Al Ula, Kingdom of Saudi Arabia
STP processing 10m3/day, 36m3/day, 53m3/day, 60m3/day,
Design, supply, installation & commissioning of Sewage Treatment Plant
Underground Trickling Bio-filter(UTB) including Pump Stations
PROJECT NAME:
PROJECT LOCATION:
PROJECT SIZE:
SERVICES PROVIDED:
PRODUCTS PROVIDED:
Septech manufactured, supplied and installed varioussizes of underground wastewater tanks to
Al Ula, Kingdom of Saudi Arabia
Yas Island, Abu Dhabi, UAECASE STUDY
Yas Island Worker Camp Sewerage Treatment Plant (STP)
Yas Island, Abu Dhabi
STP processing 3,000m3/day
Concept, design and installation of STP for Yas Island construction worker camp
STP with Moving Bed Biological Reactor (MBBR) producing water suitable for irrigation purposes
PROJECT NAME:
PROJECT LOCATION:
PROJECT SIZE:
SERVICES PROVIDED:
PRODUCTS PROVIDED:
Our STP Plant in Yas Island treats sewage water suitable for service to population equivalent of 15,000
Wadi Al Helo, Sharjah,UAECASE STUDY
Wadi Al Helo Villas (80 nos. villas)
Wadi Al Helo, Sharjah, UAE
STP processing 80m³/day, 25m³/day and 15m³/day
Supply and Installation of Sewage Treatment Plant
Underground Trickling Biofilter (UTB)
PROJECT NAME:
PROJECT LOCATION:
PROJECT SIZE:
SERVICES PROVIDED:
PRODUCTS PROVIDED:
Septech’s UTB Technology - Sharjah Municipality’s choice for Wadi Al Helo Community
Al Reef Villas, Abu Dhabi,UAECASE STUDY
Al Reef Villas
Abu Dhabi,UAE
STP processing 1,000m3/day
Concept, design and installation of STP for Al Reef Villas (1,100 villa complex)
STP with Moving Bed Biological Reactor (MBBR) producing water suitable for irrigation purposes
PROJECT NAME:
PROJECT LOCATION:
PROJECT SIZE:
SERVICES PROVIDED:
PRODUCTS PROVIDED:
Septech’s MBBR Technology treats 1,000m3 of waste water per day at Al Reef Villas
UAEAbu DhabiP. O. Box 73374Abu Dhabi, UAET: +971 2 550 7553F: +971 2 550 5781
DubaiP. O. Box 27930Dubai, UAET: +971 4 408 8777F: +971 4 408 8788
Dubai (DIFC)P. O. Box 27930Dubai, UAET: +971 4 369 7090F: +971 4 369 7092
SharjahP. O. Box 5985Sharjah, UAET: +971 6 542 0888F: +971 6 542 0332
AustraliaHWT Tower, Level 23,40 City Road, Southbank,VIC 3006T: +61 3 9077 5453F: +61 3 9939 7099
6th FL, Tower A, 1 CybercityEbene, MauritiusT: +230 403 6000F: +230 403 6060
Tlalnepantla, EdodeMexico 54135T: +5255 5367 1693F: +5255 5367 1258
Mauritius
MexicoJL, Letjen, TB.Simatupang Kav. 35,Suite# 3,4,5Jakarta Selatan 12430
Indonesia
SpainC/Veira, Y Clavijo,52,10, 35002.Las Palmas
EuropeP. O. Box 583Muscat, Postal Code 115Sultanate of Oman
Oman
RiyadhP. O. Box 86334Riyadh 11622Saudi ArabiaT: +966 1148 68547F: +966 1148 68548
KSA
Corporate Office Courier AddressFirst Floor, Block B, Al Naboodah Bldg., Sheikh Zayed Road, Dubai, UAE
septechwastewatersignatureprojectsSeptech - Corp. Overview.pdfSlide Number 23
Septech - Corp. Overview.pdfSlide Number 45Slide Number 46Slide Number 47Slide Number 48
Septech - Corp. OverviewSlide Number 68