Post on 13-Mar-2018
US AIR FORCE BIM PROJECT EXECUTION PLAN (USAF PxP) VERSION 1.0
FOR
[PROJECT TITLE] DEVELOPED BY
[AUTHOR COMPANY]
This template is a tool that is provided to assist in the development of a BIM project execution plan as required per contract. It was adapted from the buildingSMART alliance™ (bSa) Project “BIM Project Execution Planning” as developed by The Computer Integrated Construction (CIC) Research Group of The Pennsylvania State University. The bSa project is sponsored by The Charles Pankow Foundation (www.pankowfoundation.org), Construction Industry Institute (CII) (www.construction-institute.org), Penn State Office of Physical Plant (OPP) (www.opp.psu.edu), and The Partnership for Achieving Construction Excellence (PACE) (www.engr.psu.edu/pace). The BIM Project Execution Planning Guide can be downloaded at www.engr.psu.edu/BIM/PxP.
Contributors to the template:
Steve Hutsell, U.S. Army Corps of Engineers Van Woods, U.S. Army Corps of Engineers Ralph Kreider, The Pennsylvania State University John I. Messner, The Pennsylvania State University Eric Baker, Mason & Hanger Mark Butler, HDR, Inc. Shawn Foster, Jacobs Global Buildings North America David Fouche, CH2M Hill Dan Klancnik, The Walsh Group Will Love, CH2M Hill Jeff Prashaw, HDR, Inc Model Output Matrix developed by Cory West and Shawn Pelowitz with M. A. Mortenson Company
Please direct any questions about this template to Capt. Eric Kellogg (eric.kellogg.1@us.af.mil), Steve Hutsell (Steve.Hutsell@usace.army.mil) or Van Woods (Van.Woods@usace.army.mil). Please do not contact any of the other contributors pertaining to this template. This coversheet can be replaced by a company specific coversheet that includes at a minimum document title, project title, project location, author company, and project number.
View this project and many more for free at http://bids.ContractorsPlanRoom.com
[PROJECT TITLE] [DATE]
USAF BUILDING INFORMATION MODELING PROJECT EXECUTION PLAN VERSION 1.0
ii
US AIR FORCE BIM PROJECT EXECUTION PLAN (USAF PxP) VERSION 1.0
FOR
[PROJECT TITLE] DEVELOPED BY
[AUTHOR COMPANY]
TABLE OF CONTENTS
SECTION A: BIM PROJECT EXECUTION PLANNING GUIDE OVERVIEW ..............................................................1
SECTION B: PROJECT INFORMATION .....................................................................................................................2
SECTION C: KEY PROJECT CONTACTS ..................................................................................................................3
SECTION D: PROJECT GOALS / BIM OBJECTIVES .................................................................................................4
SECTION E: ORGANIZATIONAL ROLES / STAFFING ..............................................................................................5
SECTION F: BIM PROCESS DESIGN ........................................................................................................................6
SECTION G: BIM INFORMATION EXCHANGE WORKSHEET ..................................................................................7
SECTION H: BIM AND FACILITY DATA REQUIREMENTS........................................................................................8
SECTION I: COLLABORATION PROCEDURES .....................................................................................................12
SECTION J: QUALITY CONTROL............................................................................................................................13
SECTION K: TECHNOLOGICAL INFRASTRUCTURE NEEDS ................................................................................14
SECTION L: MODEL ORGANIZATION.....................................................................................................................16
SECTION M: PROJECT DELIVERABLES .................................................................................................................17
SECTION N: ATTACHMENTS...................................................................................................................................18
View this project and many more for free at http://bids.ContractorsPlanRoom.com
[PROJECT TITLE] [DATE]
USAF BUILDING INFORMATION MODELING PROJECT EXECUTION PLAN VERSION 1.0
1
SECTION A: BIM PROJECT EXECUTION PLANNING GUIDE OVERVIEW
To successfully implement Building Information Modeling (BIM) on a project, [AUTHOR COMPANY] has developed this detailed BIM Project Execution Plan. The BIM Project Execution Plan defines uses for BIM on the project (e.g. design authoring, design reviews, 3D coordination, and record modeling), along with a detailed process for executing BIM on this project.
[INSERT ADDITIONAL INFORMATION: FOR EXAMPLE, A BIM MISSION STATEMENT. This is the location to provide additional BIM overview information up to one paragraph. Additional detailed information can be included as an attachment to this document.]
Please note: Instructions and examples to assist with the completion of this guide are currently in grey. The text can and should be modified to suit the needs of the organization filling out the template. If modified, the format of the text should be changed to match the rest of the document. This can be completed, in most cases, by selecting the normal style in the template styles.
View this project and many more for free at http://bids.ContractorsPlanRoom.com
[PROJECT TITLE] [DATE]
USAF BUILDING INFORMATION MODELING PROJECT EXECUTION PLAN VERSION 1.0
2
SECTION B: PROJECT INFORMATION
This section defines basic project reference information and BIM related project milestones.
1. FACILITY OWNER: [E.G. US AIR FORCE, ETC.]
2. PROJECT NAME: [E.G. BARRACKS]
3. PROJECT LOCATION: [E.G. Fairchild AFB, WA]
4. CONTRACT TYPE: [E.G. DESIGN-BUILD]
5. FACILITY TYPE: [LIST ALL FACILITIES IN THE CONTRACT]
6. BRIEF PROJECT DESCRIPTION: [NUMBER OF FACILITIES, GENERAL SIZE, ETC]
7. ADDITIONAL PROJECT INFORMATION: [UNIQUE BIM PROJECT CHARACTERISTICS AND REQUIREMENTS]
8. PROJECT NUMBERS:
PROJECT INFORMATION NUMBER
USACE CONTRACT NUMBER: [E.G. W9126G-08-D-0000]
TASK ORDER: [E.G. 0001]
USACE PROJECT NUMBER: [E.G. PN055198]
PROJECT NUMBER(S): [IF APPLICABLE]
View this project and many more for free at http://bids.ContractorsPlanRoom.com
[PROJECT TITLE] [DATE]
USAF BUILDING INFORMATION MODELING PROJECT EXECUTION PLAN VERSION 1.0
3
SECTION C: KEY PROJECT CONTACTS
The following is a list of the lead BIM contacts for each organization on the project. Additional contacts can be included later in the document.
ROLE ORGANIZATION NAME EMAIL TIME ZONE PHONE
Project Manager USACE [John Doe]
Project Manager AFCEE
District BIM Manager
USACE
Project Manager(s) [Company]
BIM Manager(s) [Company]
Architecture Lead [Company]
Civil Lead [Company]
Electrical/Telecom Lead
Fire Protection Lead
Mechanical Lead
Plumbing Lead
Structural Lead
Other Project Roles
View this project and many more for free at http://bids.ContractorsPlanRoom.com
[PROJECT TITLE] [DATE]
USAF BUILDING INFORMATION MODELING PROJECT EXECUTION PLAN VERSION 1.0
4
SECTION D: PROJECT GOALS / BIM OBJECTIVES
Describe how the BIM Model and Facility Data are leveraged to maximize project value (e.g. design alternatives, life-cycle analysis, scheduling, estimating, material selection, pre-fabrication opportunities, site placement, etc.) Reference www.engr.psu.edu/bim/download for BIM Goal & Use Analysis Worksheet.
1. MAJOR BIM GOALS / OBJECTIVES: State BIM Goals / Objectives
BIM GOAL DESCRIPTION
2. BIM USES:
The BIM Uses currently highlighted/shaded/checked(x) are required by USAF BIM Requirments. Highlight in yellow and place an X next to the additional BIM Uses as selected by the project team. See BIM Project Execution Planning Guide at www.engr.psu.edu/BIM/BIM_Uses for Use descriptions. Include additional BIM Uses as applicable in empty cells.
OPERATE X CONSTRUCT X DESIGN X PLAN XBUILDING MAINTENANCE
SCHEDULING SITE UTILIZATION PLANNING DESIGN AUTHORING X PROGRAMMING
BUILDING SYSTEM ANALYSIS CONSTRUCTION SYSTEM
DESIGN DESIGN REVIEWS X SITE ANALYSIS
ASSET MANAGEMENT 3D COORDINATION X 3D COORDINATION X SPACE MANAGEMENT /
TRACKING DIGITAL FABRICATION STRUCTURAL ANALYSIS
DISASTER PLANNING 3D CONTROL AND PLANNING LIGHTING ANALYSIS
RECORD MODELING RECORD MODELING X ENERGY ANALYSIS
MECHANICAL ANALYSIS
OTHER ENG. ANALYSIS
LEED EVALUATION
CODE VALIDATION
BUILDING MAINTENANCE SCHEDULING (4D) CONSTRUCTION
SCHEDULING (4D) PRELIMINARY
CONSTRUCTION SCHEDULING (4D)
PHASE PLANNING (4D )
COST ESTIMATION COST ESTIMATION COST ESTIMATION COST ESTIMATION EXISTING CONDITIONS
MODELING EXISTING CONDITIONS MODELING EXISTING CONDITIONS
MODELING EXISTING CONDITIONS MODELING
COBIE COBIE COBIE COBIE
View this project and many more for free at http://bids.ContractorsPlanRoom.com
[PROJECT TITLE] [DATE]
USAF BUILDING INFORMATION MODELING PROJECT EXECUTION PLAN VERSION 1.0
5
SECTION E: ORGANIZATIONAL ROLES / STAFFING
For each BIM Use selected, identify the team within the organization (or organizations) who will staff and perform that Use. Submittal of this section to USACE IS NOT REQUIRED.
BIM USE ORGANIZATION NUMBER OF TOTAL STAFF FOR BIM USE
LOCATION(S) LEAD CONTACT
3D coordination Contractor A
B
C
View this project and many more for free at http://bids.ContractorsPlanRoom.com
[PROJECT TITLE] [DATE]
USAF BUILDING INFORMATION MODELING PROJECT EXECUTION PLAN VERSION 1.0
6
SECTION F: BIM PROCESS DESIGN
Provide process maps for each BIM Use selected in section D: Project Goals/BIM Objectives. These process maps provide a detailed plan for execution of each BIM Use. They also define the specific Information Exchanges for each activity, building the foundation for the entire execution plan. The plan includes the Overview Map (Level 1) of the BIM Uses, a Detailed Map of each BIM Use (Level 2), and a description of elements on each map, as appropriate. Level 1 and 2 sample maps are available for download at www.engr.psu.edu/BIM/download. (Please note that these are sample maps and should be modified based on project specific information and requirements). Please reference Chapter Three: Designing BIM Project Execution Process in the BIM Project Execution Planning Guide found at www.engr.psu.edu/BIM/PxP
1. LEVEL ONE PROCESS OVERVIEW MAP: ATTACHMENT 1
2. LIST OF LEVEL TWO DETAILED BIM USE PROCESS MAP(S): ATTACHMENT 2
a. Existing Conditions Modeling b. Cost Estimation c. 4D Modeling d. Programming e. Site Analysis f. Design Reviews g. Design Authoring h. Energy Analysis i. Structural Analysis j. Lighting Analysis k. 3D Coordination l. Site Utilization Planning m. 3D Control and Planning n. Record Modeling o. Maintenance Scheduling p. Building System Analysis
[Delete unused or add additional process maps from list]
View this project and many more for free at http://bids.ContractorsPlanRoom.com
[PROJECT TITLE] [DATE]
USAF BUILDING INFORMATION MODELING PROJECT EXECUTION PLAN VERSION 1.0
7
SECTION G: BIM INFORMATION EXCHANGE WORKSHEET
Model elements by discipline, level of detail, and any specific attributes important to the project are documented using information exchange worksheet. See Chapter Four: Defining the Requirements for Information Exchanges in the BIM Project Execution Planning Guide for details on completing this template. Submittal of these worksheets to USACE IS NOT REQUIRED.
1. LIST OF INFORMATION EXCHANGE WORKSHEET(S): ATTACHMENT 3 (The following are examples. Modify for specific project. Some Information Exchanges may need to be removed, while some information exchanges may need to be added.)
a. Existing Conditions Modeling b. Cost Estimation c. Phase Planning d. Programming e. Site Analysis f. Design Reviews g. Design Authoring h. Energy Analysis i. Structural Analysis j. Lighting Analysis k. 3D Coordination l. Site Utilization Planning m. 3D Control and Planning n. Record Modeling o. Maintenance Scheduling p. Building System Analysis
[Delete unused and add additional information exchange worksheets from list]
View this project and many more for free at http://bids.ContractorsPlanRoom.com
[PROJECT TITLE] [DATE]
USAF BUILDING INFORMATION MODELING PROJECT EXECUTION PLAN VERSION 1.0
8
SECTION H: BIM AND FACILITY DATA REQUIREMENTS
1. MODEL OUTPUT MATRIX In this template, the non-shaded sub-category rows may be added or modified per project requirements. Select the column that best describes the type of information that will be delivered.. SEE USAF BIM REQUIREMETNS, SECTION 4.0 FOR REQUIREMENTS. Please note: No graphical representation without Facility Data is to be contained in the Model. Below are descriptions of the columns:
3D w/ facility data – 3D graphical representation with associated intelligent attribute data. 2D w/ facility data – 2D graphical representation with associated intelligent attribute data. 2D w/o facility data – 2D graphical representation without associated intelligent attribute data. Description/Remarks – Additional information used to explain facility data.
MODEL ELEMENT BREAKDOWN 3D W/ FACILITY DATA
2D W/ FACILITY DATA
2D W/O FACILITY DATA
DESCRIPTION/REMARKS
4.2 Architectural/Interior Design
4.2.1 Spaces
Net Square Footage and Volumes
Room Name and Number
Programmatic Information
4.2.2 Walls and Curtain Walls
Wall Dimensions/Thickness
Wall Type (A1, A2, B, etc)
Wall Composition (CMU, Concrete)
Wall Rating (1 hr., 30 min.)
Details
Sections
4.2.3 Doors, Window and Louvers
Windows, Doors and Louvers
Type
Hardware Type, Frame Mat'l, Glass Type, Door Leaf
Signage
Door Legend
Head, Sill, Jam Details
4.2.4 Roof
Roof Dimensional Information
Type (EPDM, Standing Seam, etc)
Composition (Membrane, insulations, deck, joist, etc)
4.2.5 Floors
Floor Dimensional Information
Rating
Finishes (Carpet, VCT, etc)
Floor Composition (Concrete, Deck, Joist, etc)
4.2.6 Ceilings
Ceiling Plane/Dimensions
Layout (grids, patterns, etc)
Composition (ACT, GWB, Exposed)
4.2.7 Vertical Circulations
Finished Dimensions of Openings
Shaft Clear Dimensions
Shaft Construction Materials
4.2.8 Architectural Specialties and Woodwork
Toilet Acc. (tp holder, garbage, paper towel disp.)
Toilet Partition
Dimensions
Materials
Grab Bars
Dimensions
Cabinets and Casework
View this project and many more for free at http://bids.ContractorsPlanRoom.com
[PROJECT TITLE] [DATE]
USAF BUILDING INFORMATION MODELING PROJECT EXECUTION PLAN VERSION 1.0
9
MODEL ELEMENT BREAKDOWN 3D W/ FACILITY DATA
2D W/ FACILITY DATA
2D W/O FACILITY DATA
DESCRIPTION/REMARKS
Dimensions
Materials
Trim (e.g. chair rail)
Countertops
Dimensions
Materials (Plam, Solid Surface, etc.)
4.2.9 Signage
Type
Mounting Height
Legend
4.2.10 Schedules
Type, materials, and Finishes generated from Model
4.3 Furniture
4.3.1 Furniture Coordination
Furniture Dimensions
Type
Electrical Needs
Communication Needs
4.4 Equipment
Dimension
4.4.1 Schedules
Type, materials, and Finishes generated from Model
4.5 Structural
4.5.1 Foundations
Dimensional Info (L,W,D, Elevation)
Ftg Type (e.g. F1, F2, etc)
Legend
Footing Schedule
4.5.2 Floor Slabs
Slab Dimensional Info
Composition
Sections and Details
4.5.3 Structural Steel
Columns
Dimensional Information
Primary/Secondary/Roof Framing Members
Dimensional Information
Sections and Details
Floor Systems (Decks)
Dimensional Information (L,W,D, Elevation)
Sections and Details
4.5.4 Cast‐in‐Place Concrete
Footing
4.5.5 Expansion/Contraction Joints
4.5.6 Stairs
Dimensional Information
4.5.7 Shafts and Pits
Finished Dimensions
4.6 Mechanical
4.6.1 HVAC
Equipment (AHU's, fans, VAV's, Boilers, Pumps)
View this project and many more for free at http://bids.ContractorsPlanRoom.com
[PROJECT TITLE] [DATE]
USAF BUILDING INFORMATION MODELING PROJECT EXECUTION PLAN VERSION 1.0
10
MODEL ELEMENT BREAKDOWN 3D W/ FACILITY DATA
2D W/ FACILITY DATA
2D W/O FACILITY DATA
DESCRIPTION/REMARKS
Ductwork
Registers, diffusers, grilles, etc.
4.6.1.1 Mechanical Piping
Equipment (System specific pumps, tanks, etc.)
Piping >= 1.5"
Piping < 1.5"
4.6.2 Plumbing
Piping >= 1.5"
Piping < 1.5"
Fixtures
Toilets, Urinals
Showers, Jan Sink, Drinking Fountains, DCVs
Sinks
Drains
Boiler Storage Tanks, Pumps
4.6.3 Equipment Clearances
Dimensions
4.6.4 Elevator Equipment
Car
Beam/Structure
Fly Wheel
4.7 Electrical/Telecommunications
4.7.1 Interior Electrical Power and Lighting
Lights
Receptacles
Panel Boards
Cable Tray
Conduit >1.5"
Conduit <=1.5"
4.7.2 Special Electrical Systems
Security
Mass Notification
Public Address
Controls
4.7.3 Grounding Systems
Devices
Wire
Rebar
4.7.4 Communications
Cable Tray
Conduit >1.5"
Conduit <=1.5"
Controls, Connections Racks
4.7.5 Exterior Building Lighting
Fixtures
4.7.6 Equipment Clearances
Dimensions
4.8 Fire Protection
4.8.1 Fire Protection System
Piping
Fittings
Pumps
Tanks
Sensors
Panels
4.8.2 Fire Alarms
Devices
View this project and many more for free at http://bids.ContractorsPlanRoom.com
[PROJECT TITLE] [DATE]
USAF BUILDING INFORMATION MODELING PROJECT EXECUTION PLAN VERSION 1.0
11
MODEL ELEMENT BREAKDOWN 3D W/ FACILITY DATA
2D W/ FACILITY DATA
2D W/O FACILITY DATA
DESCRIPTION/REMARKS
4.9 Civil
4.9.1 Terrain (DTM)
Site Conditions
Grading
4.9.2 Drainage
Drain System
4.9.3 Storm Water and Sanitary Sewers
Systems
4.9.4 Utilities
Systems
Gas lines
4.9.5 Roads and Parking
Dimensions
Composition
2. VARIANCES
List variances from minimum modeling requirements as specified in contract. Note: Variances must exceed minimum contract requirements of USAF BIM REQUIREMENTS. (i.e. using newer release of AEC CAD Standard or IFC Version.)
VARIANCE JUSTIFICATION
View this project and many more for free at http://bids.ContractorsPlanRoom.com
[PROJECT TITLE] [DATE]
USAF BUILDING INFORMATION MODELING PROJECT EXECUTION PLAN VERSION 1.0
12
SECTION I: COLLABORATION PROCEDURES
1. COLLABORATION STRATEGY: Describe how the project team will collaborate. Include items such as communication methods, document management and transfer, and record storage, etc.
2. MEETING PROCEDURES: The following are examples of meetings that should be considered.
MEETING TYPE REQUIRED PER
CONTRACT PROJECT
STAGE FREQUENCY PARTICIPANTS LOCATION
BIM REQUIREMENTS KICK-OFF
BIM EXECUTION PLAN DEMONSTRATION
YES w/ USACE
DESIGN COORDINATION
OVER-THE-SHOULDER PROGRESS REVIEWS
YES
ANY OTHER BIM MEETINGS THAT OCCURS WITH
MULTIPLE PARTIES
View this project and many more for free at http://bids.ContractorsPlanRoom.com
[PROJECT TITLE] [DATE]
USAF BUILDING INFORMATION MODELING PROJECT EXECUTION PLAN VERSION 1.0
13
SECTION J: QUALITY CONTROL
1. OVERALL STRATEGY FOR QUALITY CONTROL Describe the strategy to control the quality of the model.
2. QUALITY CONTROL CHECKS The following checks should be performed to assure quality.
CHECKS DEFINITION RESPONSIBLE
PARTY SOFTWARE
PROGRAM(S) FREQUENCY
VISUAL CHECK Ensure there are no unintended model components and the design intent has been followed
INTERFERENCE CHECK
Detect problems in the model where two building components are clashing including soft and hard
STANDARDS CHECK
Ensure that the BIM and AEC CADD Standard have been followed (fonts, dimensions, line styles, levels/layers, etc)
MODEL INTEGRITY
CHECKS
Describe the QC validation process used to ensure that the Project Facility Data set has no undefined, incorrectly defined or duplicated elements and the reporting process on non-compliant elements and corrective action plans
View this project and many more for free at http://bids.ContractorsPlanRoom.com
[PROJECT TITLE] [DATE]
USAF BUILDING INFORMATION MODELING PROJECT EXECUTION PLAN VERSION 1.0
14
SECTION K: TECHNOLOGICAL INFRASTRUCTURE NEEDS
1. SOFTWARE: List software used to deliver BIM. Remove software that is not applicable.
BIM USE USER SOFTWARE VERSION
DESIGN AUTHORING ARCH XYZ DESIGN APPLICATION
DESIGN AUTHORING STRUCTURAL XYZ DESIGN APPLICATION
DESIGN AUTHORING MECHANICAL XYZ DESIGN APPLICATION
DESIGN AUTHORING ELECTRICAL/TELECOM XYZ DESIGN APPLICATION
DESIGN AUTHORING PLUMBING XYZ DESIGN APPLICATION
DESIGN AUTHORING FIRE PROTECTION XYZ DESIGN APPLICATION
DESIGN AUTHORING CIVIL XYZ DESIGN APPLICATION
4D MODELING 4D MODELING SOFTWARE
COST ESTIMATION COST ESTIMATION SOFTWARE
EXISTING CONDITIONS MODELING
EXISTING CONDITIONS MODELING SOFTWARE
SITE UTILIZATION PLANNING
SITE UTILIZATION PLANNING
SOFTWARE
CONSTRUCTION SYSTEM DESIGN
CONSTRUCTION SYSTEM
DESIGN SOFTWARE
DIGITAL FABRICATION DIGITAL FABRICATION
SOFTWARE
3D CONTROL AND PLANNING
3D CONTROL AND PLANNING
SOFTWARE
3D COORDINATION 3D COORDINATION SOFTWARE
DESIGN REVIEWS DESIGN REVIEWS SOFTWARE
STRUCTURAL ANALYSIS STRUCTURAL ANALYSIS
SOFTWARE
LIGHTING ANALYSIS LIGHTING ANALYSIS
SOFTWARE
ENERGY ANALYSIS ENERGY ANALYSIS
SOFTWARE
LEED EVALUATION LEED EVALUATION SOFTWARE
CODE VALIDATION CODE VALIDATION
PROGRAMMING PROGRAMMING
SITE ANALYSIS SITE ANALYSIS
View this project and many more for free at http://bids.ContractorsPlanRoom.com
[PROJECT TITLE] [DATE]
USAF BUILDING INFORMATION MODELING PROJECT EXECUTION PLAN VERSION 1.0
15
2. BIM AND CAD STANDARDS: Identify items such as the BIM and CAD standards, and the version of IFC, etc.
STANDARD VERSION CAD Standard: IFC: VERSION/MVD(s)
View this project and many more for free at http://bids.ContractorsPlanRoom.com
[PROJECT TITLE] [DATE]
USAF BUILDING INFORMATION MODELING PROJECT EXECUTION PLAN VERSION 1.0
16
SECTION L: MODEL ORGANIZATION
1. FILE NAMING STANDARD: List examples of file names by discipline based on USACE BIM FILE NAMING STANDARD.
2. MODEL STRUCTURE: Describe and diagram how the Model is divided up. For example, by building, by floors, by zone, by areas, and/or discipline.
3. MEASUREMENT AND COORDINATE SYSTEMS: Describe the measurement system (Imperial or Metric) and coordinate system (geo-referenced) used.
View this project and many more for free at http://bids.ContractorsPlanRoom.com
[PROJECT TITLE] [DATE]
USAF BUILDING INFORMATION MODELING PROJECT EXECUTION PLAN VERSION 1.0
17
SECTION M: PROJECT DELIVERABLES
In this section, list the BIM deliverables for the project and the format in which the information will be delivered. SEE SECTION FOUR OF USAF BIM REQUIREMENTS
BIM SUBMITTAL ITEM STAGE FORMAT NOTES
QA/QC reports – Model Standards Check Report (2.3.1)
QA/QC reports – CAD Standards Check Report (2.3.2)
QA/QC reports - Other Model QA/QC Reports (2.3.3)
QA/QC reports - Visual Check Report (2.4.1)
QA/QC reports - Interference Report (2.4.2)
IFC file (2.4.3)
QA/QC reports - Other Design QA/QC Reports (2.4.4)
Visualization Model (Navigator, Navisworks, 3dPDF, Google Earth, etc) (3.1.3)
List of all submitted files (Excel spreadsheet preferred) (3.1.3)
Interim Design Submittal(s) (3.3.1)
Final Design Submittal (3.4.1)
Construction Submittals - Over-The-Shoulder Reviews (3.5)
As-Built Submittal (3.6)
[Other BIM Deliverables]
View this project and many more for free at http://bids.ContractorsPlanRoom.com
[PROJECT TITLE] [DATE]
USAF BUILDING INFORMATION MODELING PROJECT EXECUTION PLAN VERSION 1.0
18
SECTION N: ATTACHMENTS
1. LEVEL 1 PROCESS OVERVIEW MAP [FROM SECTION F]
2. LEVEL 2 DETAILED BIM USE PROCESS MAP(S) [FROM SECTION F]
3. INFORMATION EXCHANGE REQUIREMENT WORKSHEET(S) [FROM SECTION G]
4. FILE NAMING STANDARD [FROM SECTION L]
View this project and many more for free at http://bids.ContractorsPlanRoom.com