Total Space Requirements

Art & Art History

Theater and Dance

Music

Museum of Art

General

Interdisciplinary

TOTAL

Existing

37,642

35,099

29,627

7,064

0

0

109,432

Needs

40,732

33,018

29,949

12,075

9,699

23,335

148,808

Difference

(3,090)

2,081

(322)

(5,011)

(9,699)

(23,335)

(39,376)

Space Distribution

CFA (ph1)

0

0

11,821

1,000

6,107

23,335

42,263

+ 42,263

PCAC

22,800

27,760

18,128

11,075

3,592

0

83,355

- 2,887

NHH

0

5,258

0

0

0

0

5,258

0

Service

17,932

0

0

0

0

0

17,932

0

Art & Art History

Theater and Dance

Music

Museum of Art

General

Interdisciplinary

TOTAL

Phase 1 Options

Current CFA Program (Phase 1)

Remove Visualization Suite

Remove 100% Residence

Include Museum (No Storage)

Program Reduction/50% Res

42,263

38,813

39,228

51,338

37,353

Scenario ASF Difference

0

(3,450)

(3,035)

9,075

(4,910)

Center for the Arts Program – Full Build

Center for the Arts Program – Full Build Center for the Arts Program – Phase I Elements

Center for the Arts Program – Full Build Center for the Arts Program – Phase I Elements Center for the Arts Program – Phase I

Option 1 – Add The Museum

Center for the Arts Program – Phase I

Recommended Site: Adjacent to Lot C

Illustration of walking times

Flexible Performance / Presentation HallInstrumental & Vocal Performances, Films, Presentations

Phase 1 – Center for ArtsExamples of the functions that would be included in Phase 1

Arts Residency

White Box Theater

Gallery

Phase 1 Engelhardt Demolished

Center for the Arts adjacent to Lot C, near Lot B, proximate to downtown, and other campus public venue buildings

Full Build toward Lot BHunter & Gibbs Demolished

There are 3 options for the Future Full Build Out of the Center for the Arts.

Full Build on Lot C

There are 3 options for the Future Full Build Out of the Center for the Arts.

Full Build toward Mill Road

There are 3 options for the Future Full Build Out of the Center for the Arts.

The PCAC will continue to be used to satisfy the rest of the space needs for the Arts until the Full Build Out of the Center for the Arts occurs.

Not until all phases of the Center for the Arts are built can the PCAC be decommissioned. This site could then be used for new buildings that would serve science and technology programs.

Phase 1

Lot C

An illustration of the massing and scale of the Center for the Arts