Detailed investigation and performance evaluation of Dhaka Metropolitan city road intersection.

Transcript of Thesis Proposal of MSc (Transportation Engineering)

THESIS PROPOSAL

TENTATIVE TITLE

Tentative title:-DETAILED INVESTIGATION AND PERFORMANCE EVALUATION OF ROAD INTERSECTIONS OF DHAKA METROPOLITON CITY.

04/05/2013 2M.M.A.Kader Chowdhury.

ROAD NETWORK.

The way on the earth surface to move from a point

to another is called a Road. The web of Road inside a city / system, is called

Road Network.

04/05/2013 3M.M.A.Kader Chowdhury.

DHAKA CITY ROAD NETWORK

04/05/2013 4M.M.A.Kader Chowdhury.

ROAD NETWORK ELEMENT

Node.Link.

04/05/2013 5M.M.A.Kader Chowdhury.

DEFINATION OF INTERSECTION

• An Intersection is the general area where two or more highways join or cross.

04/05/2013 6M.M.A.Kader Chowdhury.

CHARECTERISTICS OF INTERSECTION

• Intersections are the modal points of a road network where vehicles are distributed and redirected towards desired destination.

04/05/2013 7M.M.A.Kader Chowdhury.

CHARECTERISTICS OF INTERSECTION

• In Intersection, pedestrians are moved in a safe and systematic way.

04/05/2013 8M.M.A.Kader Chowdhury.

CHARECTERISTICS OF INTERSECTION

It is not the wide roads that increase the roadway capacity ,rather it is the Intersection that :-

Reduces Congestion, Increases roadway Capacity and Promotes Safety for vehicles and pedestrians.

04/05/2013 9M.M.A.Kader Chowdhury.

CHARECTERISTICS OF INTERSECTION

• In a road traffic system, intersections are one of the important bottlenecks.

• Which interrupt smooth flow of traffic and thereby cause delays.

04/05/2013 10M.M.A.Kader Chowdhury.

CHARECTERISTICS OF INTERSECTION

• To avoid unnecessary delay or to get an efficient traffic flow movement, these intersections need to be planned and designed properly and carefully.

• Along with the appropriate road network and geometry, the necessary traffic control devices also need to be applied wisely.

04/05/2013 11M.M.A.Kader Chowdhury.

INTERSECTIONS CLASSIFICATION

Intersection can be classified in following categories:-

1)3 Legged Intersection (T and Y type)

2)Staggered Intersection

3)Four Legged intersection/Cross Roads---• Rotary Intersection• Mini Round About• Uncontrolled intersection• Controlled Intersection---

Signalized intersection Priority Controlled Intersection

4)Multi-legged Intersection

04/05/2013 12M.M.A.Kader Chowdhury.

DEVELOPED COUNTRIES TREND

To obtain orderly movement of vehicles through intersections----

a) They have strict traffic control rules, regulations and well established planning.

b) They have designing methodology for geometric design of road intersection and as well as standard guide lines for the application of traffic control devices.

c) Because of these practice, clear pattern in queue formation and discharging can be seen from road junctions of these countries.

04/05/2013 13M.M.A.Kader Chowdhury.

INTERSECTIONS OF DHAKA CITY.

04/05/2013 14

From CASE Project

PRESENT CONDITION OF DHAKA CITY

All major signalized intersections in Dhaka city have got the severe traffic congestion which produce---

a) Long delay and

b) Insurmountable sufferings of the road users.

04/05/2013 15M.M.A.Kader Chowdhury.

PRESENT CONDITION OF DHAKA CITY

Main cause of these hazardous situation of Dhaka city---

a) Inappropriate / ill planned road network inside the Dhaka city.

b) Faulty layout of the intersections.

c) Inappropriate synchronization of traffic signals in road network.

d) Arbitrary setting of signal time / phase.

e) Poor policing activities in signal control.

04/05/2013 16M.M.A.Kader Chowdhury.

FIELD OBSERVATION OF DHAKA CITY PROBLEM.

Main causes of traffic congestion in our intersections (Dhaka City) mainly because of---

a) Insufficient traffic data,

b) Ill planned / controlled traffic signal,

c) Inappropriate road network and

d) Mismanaged traffic control by police.

04/05/2013 17M.M.A.Kader Chowdhury.

FIELD OBSERVATION REVEALED….

a) Faulty geometrical condition of the intersection is responsible for the delay and accidents in many cases.

b) Presence of illegal structures by the side of the road.

c) Unnecessary roundabouts.

d) Un important speed breakers.

e) Improper turning radius.

f) Absence of medians and sign.

g) Faulty control operation of police.

h) Absence of following the lane system.

04/05/2013 18M.M.A.Kader Chowdhury.

PROBLEMS IN SIGNAL AT INTERSECTION

a) Manual operation by police.

b) Irrational distribution of signal phases time.

c) Increase delay and queue.

d) Decreases the Level of Service of intersection.

04/05/2013 19M.M.A.Kader Chowdhury.

OBJECTIVE OF THIS THESIS

a) To identify the traffic operational problems within intersection area associated faulty geometric plan and design.

b) To determine the better, well planned, low cost traffic signal system under the supervision of police.

c) To identify the proper road network inside the Dhaka city, this can help the traffic operation system.

d) To increase the Level of Service of intersections inside the Dhaka city.

04/05/2013 20M.M.A.Kader Chowdhury.

POSSIBLE OUTCOME OF THIS THESIS.

a) Identifications of types and nature of geometrical faults.

b) Identification of the better, well planned, low cost and adaptable traffic signal system.

c) Identifications of the inappropriateness of pattern in road network of Dhaka city, these cannot help the operation system.

d) Identify the techniques of increments of the Level of

Service of intersections in the Dhaka city.

04/05/2013 21M.M.A.Kader Chowdhury.

OUTLINED OF PROPOSED

METHODOLOGY.Observing, how junction is operated?a) Red violation

b) Long cycle time

c) Over ride by police

04/05/2013 22M.M.A.Kader Chowdhury.

OUTLINED OF PROPOSED METHODOLOGY.

Identifying –a) Poor performance of signalized junction.

b) Faulty geometry.

c) Poor road net & hierarchy –Right turn restriction is not possible.

d) Exclusive left/right turn (left channel at Rangs intersection).

e) High number of phasing.

f) Closely spaced junction/non-uniform midblock hindrance for coordinated signal.

g) Pedestrian facilities & behavior.

h) Bus stoppages.

i) NMV (Non Motorized Vehicle).

j) Ineffective pre-timed signal (Why & identify events – vehicle conflict at junction; unpredicted arrival pattern due to VIP; procession, sudden change of demand).

k) Other side frictions.

l) Why police override signal?

m) SEE pre-requisite of signal design & observed v/c ratios.

n) Unpredictable arrival flow and unmatched green time.

o) Fluctuating Right turn demand.

04/05/2013 23M.M.A.Kader Chowdhury.

REDUCE SIGNAL PHASING

Attempt would be taken to reduce signal phases by introducing---

• Improved circulation plan through road network.[ One way in Tikatoli, Shantinagar]

04/05/2013 24M.M.A.Kader Chowdhury.

THANK YOU.