Post on 15-Jan-2020
1
TENDER FOR PROPOSED PILING WORK OF UNDERGROUND TANK & COMPOUND
WALL OF INSTITUTIONAL BUILDING
At Navi Mumbai
FOR
THE INSTITUTE OF COST ACCOUNTANTS OF INDIA.
• Architects:
M/s. SHASHI DESHMUKH & ASSOCIATES
Architects, Regd. Valuer & Int. Designers.
102, Konark Towers, Opp. Saibaba Temple,
Ghantali Road, Thane(W)-400602.
Ph. 25333191, 25334420, 25369467.
Fax: 25332025
• Structural Consultants:
M/s. EPICONS CONSULTANTS Pvt. Ltd.
216/A, Margin Complex, Opp. S.T. Workshop,
L.B.S. MARG, Khopat,
Thane (W) - 400 601
Phone- 022-25475334, 25471144
2
I N D E X
SECTION PAGE
NOS.
INDEX 2-2
PREFACE
3-3
SECTION 1 : INVITATION TO TENDERER
4-5
SECTION 2 : INSTRUCTIONS FOR FILLING IN TENDER
6-7
SECTION 3 : LETTER OF SUBMISSION
8-9
: APPENDIX TO TENDER 10
SECTION 4 : ARTICLES OF AGREEMENT
11-12
SECTION 5 : GENERAL CONDITIONS OF CONTRACT
13-34
SECTION 6 : SPECIAL CONDITIONS OF CONTRACT &
ANNXEURE A,B&C
35-50
SECTION 7 : STANDARD SPECIFICATION
51-69
SECTION 8 : SAFETY SPECIFICATION
70-71
SECTION 9 : SAFETY INSTRUCTION
72-77
SECTION 10 : ANTI – TERMITE TREATMENT
78-79
SECTION 11 : SPECIFICATION – PILING 80-85
SECTION 12 : ANNEXURES 86-92
SECTION 13 : BASIC RATES 93
SECTION 14 : BILL OF QUANTITIES - FOR PILING 94-95
SECTION – 15 : SOIL TEST REPORT
SECTION – 16 : DRAWING
3
P R E F A C E
1. THE INSTITUTE OF COST ACCOUNTANTS OF INDIA (CMA Bhavan,12,
Sudder Street, Kolkata -700016) intends to construct institute building, At Navi
Mumbai. The recent tender is for construction of the piling work of underground tank
& compound wall of Institute building enumerated in the scope of work.
2. ‘SHASHI DESHMUKH & ASSOCIATES are the Architects for the work. Architects
shall provide drawings details and specifications including all service drawings
necessary for the project execution and also provide acceptance oriented inspection of
the work.
3. The Institute of Cost Accountants of India shall finance the project, and is the ultimate
owner. The Owner / Architect provide overall supervision and inspection and check the
measurement of the work done by the contractor, as per contract conditions.
4. M/s. Epicons Consultants pvt. Ltd. are the structural Consultants. They shall interpret
the document; provide acceptance oriented inspection of the work along with architect.
5. All right regarding ownership and use of drawings, specifications, reports, etc. prepared
by the Architects and Consulting Engineers are reserved by them. Such drawings,
specifications, reports etc. issued to the contractors shall be used only for the work
specified herein and are liable to be recalled.
Owner Contractors
4
SECTION - 1:
INVITATION TO TENDERER
Sealed item rate un-conditional tenders are invited from contractors of repute, having adequate
resources, well established in the line and experienced in the execution of similar General works
of comparable magnitude for the following work :
1. a Name & Nature of Work : Piling of underground tank & compound wall
of Proposed Institute Building
The Institute Of Cost Accountants Of India ,
CMA Bhavan,12, Sudder Street, Kolkata -
700016.
b Location : Navi, Mumbai – 400 708
c Time of Completion : Two Calendar months including
Monsoon.To be counted from date
Of issue of Letter of Intent
2 Tender document will be available in the website of the Institute www.icmai.in from
10th June 2015 to 17th June 2015 as well as from the office of the Architects at the
address given below on payment of Rs.5,000/- in way of Demand Draft in favour of
The Institute of Cost Accountants of India” payable at Kolkata
ARCHITECTS: SHASHI DESHMUKH & ASSOCIATES
102, Konark Towers, Opp. Saibaba Temple,
Ghantali Road, Thane(W)-400602.
Ph. 25333191, 25334420, 25369467.
Fax.: 25332025
3 Pre-bid meeting will be held in Architect’s office on 12th June 2015 at 11.00 a.m. The
contractors compulsorily need to attend the pre-bid meeting or otherwise they will be
dis-qualified.
4 Sealed Tenders shall be received at the office of the Architect on the above mentioned
address not later than 4.00 p.m. on 17th June 2015.
5 The contractor shall also enclose Earnest Money Deposit in the form of DD/Pay Order/
from Nationalized Bank in favour of ‘The Institute of Cost Accountants of India’
payable at Kolkata amounting to Rs. 35,000.00. This deposit shall be refunded after
5
the owners have awarded the work to one successful contractor, whose deposit shall be
adjusted against security deposit.
6 Tenders shall be valid for acceptance for full period of completion of the project from
the last date of submission.
7 The owner, The Institute of Cost Accountants of India, reserves the right to reject any
or all the tenders and accept the lowest or any other tender without assigning any
reasons therefore.
Owner Contractor
6
SECTION - 2:
INSTRUCTIONS FOR FILLING IN TENDER
1. The tender shall be submitted in accordance with these instructions and any Tender not
conforming thereto is liable to be rejected. These instructions shall form part of the
Tender and the Contract. Bidder should submit Two Sealed Envelopes separately
(Financial & Technical)
2. Bid Criteria, Volume I will be opened first & regular tender will be opened of those who
are eligible in the first bid
3. The Tender documents which will be issued to each tenderer comprise these
instructions, Tender with Appendices, Conditions of Contract, Form of Agreement,
Specifications, Bill of Quantities and Drawings, Each Tenderer shall be furnished one
complete set of above tender documents.
4. The tender shall be filled in, signed with all particulars complete and submitted by one
duly authorized to do so. The Tenderer shall satisfy the Owner that he is competent and
authorized to submit the tender and/or to enter into a legally binding contract with the
Owner by furnishing documentary evidence to that effect.
5. The Tender shall be complete with all the documents set out in para 2 above and other
documents set out in these instructions and elsewhere in the Tender documents. In
particular, the Tenderer shall complete and submit the following for his tender to be
considered as bonfire :
Form of Tender with Appendix.
a. Bill of Quantities and its Abstract, each page duly signed.
b. List of Plant/Equipment and Personnel to be employed on the works.
c. Details of other works tendered for and on hand on the date of Submission of tender.
6. The Owner reserves the right to adjust arithmetical or other errors in the tender in
accordance with the following general rules. In the event of discrepancy between words
and figures quoted, the description in words shall prevail. Similarly in the event of an
error in the amount column arising as a result of wrong extension, the unit or item rates
shall be regarded as firm and extension amended accordingly.
7. This is an item rate measurement contract based on priced Bill of Quantities. The item
rates shall be valid for the entire duration of the contract and / or extension thereof.
Tenderers shall note that the prices and rates inserted in the Bill of Quantities, are to be
the full inclusive value of works described under each item including all costs and
expenses including Govt. levies, royalties, taxes, duties & octroi etc., which may be
required in, and for the construction of the works described whether specifically
7
mentioned or not. However liabilities against all such levies shall be shown separately in
Tender. The tender rates shall also include all general risks liabilities and obligations set
forth or implied in the documents on which the tender is based. The Owner will not be
responsible for or pay for expenses or losses which may be incurred by any Tenderer in
the preparation and submission of the Tender, or in any activity connected therewith. As
soon as the successful tenderer is advised of the award of the contract to him all future
expenses and all taxes etc. to be incurred by him shall be deemed to be covered by the
prices quoted in his tender.
8. The tender shall remain valid for full period of completion of the project from the last
date of submission unless otherwise stipulated in the Tender Notice. Any tenderer
withdrawing or amending his tender within this period shall forfeit his earnest money to
the Owner.
9. Before tendering, the Tenderer shall visit the site of works and in any case shall be
deemed to have done so in order to acquaint himself with the nature of the site and the
conditions in which the works are to be executed.
10. The tender documents duly completed in all respects along with Tender drawings (if any)
and all other accompanying documents shall be submitted and delivered as required in
the Tender Notice in a plain sealed envelope superscribed "Tender For Educational
Building For M/s.“The Institute Of Cost Accountants of India”
11. Owner have a right to increase or decrease the quantity than mentioned in the tender for
which no compensation will be paid to the tenderer.
12. The Bill of Quantities is inclusive of Piling Work. Bill of Quantities for Piling &
Specification is the part of the agreement.
8
SECTION - 3:
LETTER OF SUBMISSION
Note : All blanks to be filled in by the Tenderer.
To,
The Institute of Cost Accountants of India
CMA Bhavan, 12, Sudder Street, Kolkata -700016.
Gentlemen,
TENDER FOR PILING WORK OF UNDERGROUND TANK & COMPOUND WALL OF
PROPOSED INSTITUTIONAL BUILDING, NAVI MUMBAI –
1. Having inspected the site and having examined the Drawings, Conditions of Contract,
Specifications, Bill of Quantities for the above named work and having obtained required
clarifications, we the undersigned offer to carry out the entire work for the sum of Rs.
________________ ( Rupees __________________________Only.) or such other sum as
may be ascertained in accordance with the said conditions, all in conformity with the said
Drawings, Conditions of Contract, Specifications, Bill of Quantities hereto.
2. We undertake, if our Tender is accepted, to commence the works and complete and deliver
the same within the time stipulated in the tender.
3. We agree to abide by this tender for full period of completion of the project from the date
fixed for receiving the same and it shall remain binding on us and may be accepted at any
time before the expiry of that period and or before the expiry of any further period extended
by mutual consent in writing.
4. Until and Unless a formal Agreement is prepared and executed, this tender, together with
your written acceptance thereof, shall constitute a binding contract between us together with
all the conditions of contract, specifications, bill of quantities and price, drawings and
instructions to tenderers.
9
We understand that you are not bound to accept the lowest or any other tender you may
receive without giving any reason.
5. We enclose herewith a DD/ Pay Order/Bank Guarantee from Nationalized Bank
amounting to Rs.35,000.00 of tender value in favour of The Institute of Cost Accountants of
India’ payable at Kolkata towards Earnest Money Deposit.
Signature of Contractor
Date :
(Authorized Signatory)
Address :
10
APPENDIX TO TENDER
1 Security Deposit : 5% of the contract value. Balance Security
Deposit after adjustment of EMD i.e. Rs.35,000/-
for the successful bidder to be paid to the Owner
within 14 days from the date of the date of
issuance of the formal Work Order by way of .
D.D. / Pay Order/Bank Guarantee from
Nationalized Bank.
Note 1: 100% of the initial security deposit i.e. 5% of the contract value shall be refunded
within 14 days of the issue of the defects liability certificate. .
Note 2: Retention money will be refunded on issue of no defects certificate to be made after
Liability Period.
2 Defect Liability Period : 12 Months
3 Retention Money 5% amount will be deducted from
Each running bill duly certified by Architect,
which will be distinct from initial security
deposit.
4 Refund of Retention Money : Retention money will be refunded after expiry of
Defect Liability Period i.e. six months from
virtual completion of the work.
4 Time of Completion : 2 Calendar Months including monsoon
5 Period of Mobilization : Seven Days from date of Letter of Intent
6 Amount of Damages : The time is the essence of this contract and if the
contractor fails to complete the work in period
as mentioned in column ‘4’ above ___ (2)
months time from the date of issuing Letter of
Intent, the owner will be entitled to recover
Penalty from the contractor for the delay @
0.5% of the total value of the contract per week
subject to a maximum of 5% of the total value of
the contract.
The above is with prejudice to the owner's right
to recover damages from the contract for breach
of any of the conditions of the contract elsewhere
provided.
7 Interim Payment : Adhoc payment of 70% of the bill submitted by
the Contractor on the basis of joint measurements
of work done within a 14 days after date of
receipt of bill & balance 30% within a month
thereafter.
11
8 Period of Submission of Final
Measurements & Valuation
: 15 Days
9 Period of Final Payment : 1 Months thereafter
SECTION - 4
ARTICLES OF AGREEMENT
made the ________ day of ______________ between The Institute Of Cost
Accountants Of India. CMA Bhavan, 12, Sudder Street, Kolkata -700016. (hereinafter called
"the Owner") of the one part and M/s. ___________________ (Hereinafter called "the
Contractor") of the other part.
Whereas the Owner is desirous of Awarding the Construction of Building (Hereinafter called
"the Work") at _________________________, NAVI MUMBAI -
And has caused Drawings and Bills of Quantities showing and describing the work to be done to
be prepared by or under the direction of ARCHITECTS.
And whereas the Contractor has supplied the Owner with a fully priced copy of the said Bills of
Quantities(which copy is hereinafter referred to as "the Contract Bills") and whereas the said
Drawings (hereinafter referred to as "the Contract Drawings") and the Contract Bills and
Contract Drawings have been signed by /and on behalf of the parties hereto and whereas the
Contractor has deposited the sum of Rs. _________________ (Rupees
______________________ Only.) with the Owner towards the Security Deposit for the due
performance of this Agreement.
12
NOW IT IS HEREBY AGREED AS FOLLOWS :-
1. For the consideration hereinafter mentioned the Contractor will subject to the Conditions
annexed carry out and complete the Work shown upon the Contract Drawings and
described by or referred to in the Contract Bills and in the said Conditions.
2. The Owner will pay the Contractor the sum of Rs. ___________________ (Rupees
__________________________ Only.) (hereinafter referred to as "the Contract Sum") or
such other sum as shall become payable hereunder at the time and in the manner
specified in the Conditions annexed.
3. The term "the Architect" in the said Conditions shall mean the said M/s. SHASHI
DESHMUKH & ASSOCIATES. or in the event of his ceasing to be the Architect for
the purpose of this Contract, such other persons as the Owner shall nominate for that
purpose, and it is hereby declared that the owner shall be entitled at its discretion to
terminate the appointment of the Architect for the time being and to nominate another
one in his place instead, with notice to the contractor.
4 The Conditions annexed and Appendix thereto shall be read and construed as forming
part of this contract Agreement, and the parties hereto shall respectively abide by, submit
themselves to the conditions and perform the agreements on their parts respectively in
such Conditions contained.
AS WITNESS our hands this day of 2015
Signed by the Owner
in the presence of
Witness
Name:
Address:
Signed by the Contractor
in the presence of
Witness
Name:
Address:
13
--------------------------------- ---------------------------- (Signature of the Contractor) (Signature of the Contractor)
SECTION: 5
GENERAL CONDITIONS OF CONTRACT
Definitions
1.(1) The contract document consists of the Agreement the General Conditions of the Contract
Specifications and drawings including all modifications thereof incorporated in the
document before the execution and the Contract Drawings prepared by the Architect from
time to time. These form the contract.
1.(2) Written notices shall be deemed to have been duly served if delivered in person to the
individual or to a member of the firm or to an office of the corporation for whom it is
intended, or if delivered at or sent by registered mail to the last business address known to
him who gives the notice.
1.(3) The term “Work” of the Contractor or Sub-Contractor includes labour, material,
equipments, transport or all of them.
1.(4) All Time Limits stated in the Contract Document are of the essence of the contract.
1.(5) The law of the place of work shall govern the construction under this contract.
1.(6) The date of virtual completion of a project or specified area of a project is the date when
construction is sufficiently completed, in accordance with the Contractor Documents as
modified by any change or variation orders agreed to by the parties, so that the Owner can
occupy the project for use it was intended.
2. Contract Document
The Contract Document is complementary. What is called for in any one shall be as binding as
if called for by all.
14
So soon as is possible after the execution of this contract, copies of the Specifications,
descriptive schedule or other like document necessary for use in carrying the work shall without
charge be supplied by the Architect to the Contractor.
After the award of the Contract the Contractor shall without charge be supplied with all such
further drawings and details as may be prepared by the Architect and his Consultant, from time
to time as the work proceeds as are reasonably necessary either or amplify the Contract
Drawings or to enable the Contactor to carry out and complete the work in accordance with
these Conditions provided all such drawings shall be a reasonable development of the work
described in the Contract Document.
The Contractor shall keep at site one copy of the Specifications, Description schedule or other
like document referred to in this clause and one copy of the Contract Drawing and such other
drawings and details supplied to him from time to time and referred to in clause and sub-clause
upon the site so as to be available to the Architect or his representative at all reasonable times.
3. Type of Contract
The Contract shall be an item-rate contract. The Contractor shall be paid for the actual
quantity of work done, as measured at site, at the rates quoted by him in the Contract Bills
and agreed to by the Owner.
3A. Schedule of Quantities
The Schedule of Quantities given in the Contract Agreement is provisional and is meant to
indicate the intent of the work and to provide a uniform basis for tendering. The Owner
reserves the right to increase or decrease any of the quantities or to totally omit any item of
work and the Contractor shall not claim any extras or damages on these grounds.
3B. We agree that, the quantities are for piling work of underground tank & compound wall for
proposed institute building at Navi Mumbai
Any error in description or in quantity or omission of items from the Contract Agreement shall
not vitiate this Contract Agreement but shall be treated as a variation.
4. Contract Drawings
4(1) In general the Drawings shall indicate dimensions, position and type of construction, the
Specifications shall indicate the quantities and the methods. Any work indicated on the
Drawings and not mentioned in the Specification or vice versa shall be furnished as
through fully set forth in both. Work not specifically detailed. Called for, marked or
specified shall be the same as similar parts that are details marked or specified.
4(2) The Contractor’s work shall not deviate from the Drawings and the Specifications. The
Architects interpretation of these documents shall be final and without appeal.
15
4(3) Errors or inconsistence discovered in the Drawings and Specifications shall be promptly
brought to the attention of the Architect through Engineer -in-charge, for interpretation or
correction. Local conditions which may affect the work shall likewise be brought to the
Architect attention. if at any time, it is discovered that work is being done which is not in
accordance with the Contract Drawings and specifications the Contractor shall correct the
work immediately. Corrections of defective work shall not be a basis for any claim for
extension of time. The Contractor shall not carry on work except with the approval of the
Engineer-in-charge.
4(4) Figured dimensions on the Scale Drawings and large size details shall govern. Large size
details shall take precedence over small scale drawings. Any work done before receipt of
such details if not in accordance with the same, shall be removed and replaced or adjusted,
as directed by the Engineer-in-charge without expense to the owner.
4(5) All drawings, Bill of quantities and specifications and copies thereof furnished by the
Architect are his property. They shall not be used on any other work and shall be returned
to the Architect at his request on completion or termination of the Contract.
5. Scope of Intent
5(1) Scope: The general character and the scope of the work is illustrated and defined by the
Specifications herewith attached and by the signed Drawings. If the Contractor shall find
any discrepancy in or divergence between the Contract Drawings and or the specifications
he shall immediately give to the Architect a written intimation specifying the discrepancy
or divergence and the Architect shall issue instructions in regard thereto.
5(2) Extent: The Contractor shall carry out and complete the work in every respect in
accordance with this Contract and with the directions of and to the reasonable satisfaction
of the Architect / Engineer -in-charge. The Architect may in his absolute discretion and
from time to time issue further drawings, details and /or written directions and written
explanations all of which are collectively referred to as Architect instructions. All such
Drawings and instructions shall be consistent with Contract Document, true developments
thereof and reasonably inferable there from.
5(3) Intent: The intention of the Document is to include all labour and materials, equipment and
transportation necessary for the proper execution of the work. All such drawings and
instructions shall be consistent with the Contract Document, true developments thereof and
reasonably inferable there from. Material of work described in words which so applied
have a well known technical or trade meaning shall be held to refer to such recognized
standard.
16
6. Facilities and Co-operation
6(1) In the case of work indicated on the Drawings but not indicated in the contract the
Contractor shall provide necessary facilities and co-operation for any Sub-contractor or
supplier who may be approved by the Owner. The Contractor shall do all cutting, filling or
patching of his work that may be required to make it’s several parts come together properly
and fit it to receive or be received by work of other Contractors shown upon or reasonably
implied by the Drawings and Specifications for the completed structure, and he shall make
good after them, as the Architect / Engineer-in-charge may direct. Any cost caused by the
defective or ill-timed work shall be borne by the party responsible therefore.
6(2) The Contractor shall not endanger any work by cutting, excavating or otherwise altering
the work and shall not cut or alter the work of any other Contractor except with the consent
of the Engineer-in-charge.
6. Site Visit: Before tendering, the Contractor shall have visited and examined the site and Satisfied himself
as to the nature of the existing roads or other means of communication and the character of the
soil and of the excavations, the correct dimensions of the work and the facilities for obtaining
any special articles called for in the Contract Document and shall have obtained generally his
own information on all matters affecting the continuation and progress of the works.
No extra charge made in consequence of any misunderstanding or incorrect information on any
of these points, or on the grounds of insufficient description, will be allowed. Should the
Contractor after visiting the site, find any discrepancies, omissions, ambiguities or conflicts in or
among the Contract Documents, or to be in doubt as to their meaning, he shall bring the
questions to the Architect / Owners attention, not later than ten days before the last date for
submission of the tender.
Site is affected by buffer zone from the mangroves. The land under the buffer zone is marked
on site. The originality of the land under the buffer zone is not to be disturbed even it is not to
be leveled. If any concreting or storing of the material is to be done in the buffer zone it has to
be ‘Tadpatri’. Otherwise, the contractor will be liable for the consequences under CRZ
provisions.
LICENSE TO ENTER ON SITE FOR THE WORKS ONLY IS GIVEN TO THE
SUCCESSFUL CONTRACTOR. :
The main contractor should allow the other contractor who has been awarded the other work &
co-ordinate for dumping the material, execution, allowing to use the water & electricity etc. for
successful completion of work by both the contractors.
The Contractor shall be allowed admittance to the site or given a license to enter on site on the
‘Date of Commencement’ stated in the appendix and he shall thereupon and forthwith begin the
17
work and shall regularly proceed with and complete the same on or before the ‘Date of
Completion’ stated in the appendix subject nevertheless to the extension of time hereinafter
contained.
8. Progress Chart or Bar Chart
The Contractor shall prepare progress charts and submit the same for approval of the Architect /
Engineer-in-charge and for his record within Fifteen days of the Award of the Contract. The
charts shall indicate the expected date of commencement and completion of each of the items of
the work and shall be in a form approved by the Engineer-in-charge. The Chart shall also
indicate the scheduling of samples, Shop Drawings and approvals.
9. Access for Architect to the Works
The Architect and his representative shall at all reasonable times have access to the Works and
to the Workshops or other places of the Contractor where work is being prepared for the
Contract and when work is to be so prepared in workshops or other place of a Sub-Contractor (
whether or not a nominated Sub-contractor of these Conditions) the Contractor shall have a term
in the Sub-Contract so as to secure a similar right of access to those workshops or places for the
Architect and his representative and shall do all things reasonably necessary to make such right
effective.
10. Architect Status and Decision
10(1) The Architect shall be the Owner’s representative during the Construction period. The
Architect shall periodically visit the site to familiarize himself generally with the
progress and the quality of the work and to determine in general if the work is proceeding
in accordance with the Contract Document. He shall not be required to make exhaustive
or continuous on site inspections to check the quality of the work and he shall not be
responsible for the Contractor failure to carry out the construction work in accordance
with the working drawings, specifications & Contract Document. During such
inspections and on the basis of his observations while at the site he shall keep the Owner
informed of the progress of the work, shall endeavor to guard the Owner against defects
and deficiencies in the work of the Contractor and he shall condemn to the Contract
Document. He shall have authority to act on behalf of the Owner only to the extent
expressly provided in the Contract Document or otherwise in writing which shall be
shown to the Contractor. He shall have authority to stop the work whenever such
stoppage may be necessary in his reasonable opinion to ensure the proper execution of
the Contract.
10(2) Decision: The Architect shall within a reasonable time make decisions on all claims of
the Owner or the Contractor and all other matters relating to the execution and progress
of the work or the interpretation of the Contract Document.
18
The Architect may in his absolute discretion and from time to time issue further
Drawings. Details and /or written instructions, written directions and written explanations
in regard to:
A. Variation or modifications of the design.
B. The quality or quantity of works or the additions or omission or substitution of any
work.
C. Any discrepancy in or divergence between the Drawings and/or specifications.
D. The removal and /or re-execution of any works executed by the Contractor.
E. The dismissal from the works of any persons employed thereon.
F. The opening up for inspection of any work covered up.
G. The amending and making good of any defects under Defects Liability Period.
H. The removal from the site of any materials brought thereon by the Contractor and the
substitution of any other material therefore.
J. Assignment and sub-letting.
K. Delay and extension time.
L. The postponement of any work to be executed under the provision of this contract.
10(3) Dismissal:
The Contractor shall on the request of the Owner / Architect / Engineer -in-charge immediately
dismiss from the works any person employed thereon by him who may in the opinion of the
Architect be incompetent or misconduct’s himself and such person shall not be again employed
on the work without the permission of Owner / Architect / Engineer-in-charge.
11. Engineer -in-charge
The term “Engineer-in-charge” shall mean the person appointed and paid by the Owner and
acting under the orders of the Owner / Architect to inspect the works in the absence of the
Architect; the Contractor shall afford the Engineer-in-charge every facility and assistance for
inspecting the works and materials and for checking and measuring time and materials. Neither
the Engineer -in-charge nor any representative of the Architect shall have power to set out works
or to revoke, alter, enlarge or relax any requirements of the Contractor or to sanction any day
work, additions, alternations, deviations or omissions, or any extra work whatever except in so
far as such authority may be specially conferred by a written order of the Architect.
The Engineer-in-charge or any representative of the Architect shall have to give notice to the
Contractor or to his representative of non-approval of any work or materials and such work shall
be suspended or the use of such materials shall be discontinued until the decision of the
Architect, is obtained. The works will from time to time be examined by the Architect, the
Engineer-in-charge or the Architect’s representative but such examination shall not in any way
exonerate the Contractor from the obligation to remedy any defects which may be found to exist
at any stage of the works or after the same is completed. Subject to the limitation of this clause
the Contractor shall take instructions only from the Architect.
19
12. Contractors filed organization and Equipment
12(1) Engineer -in-charge: The Contractor shall constantly keep on his work during it’s progress one or more qualified and
competent Engineer-in-Charge who will be responsible for the carrying out of the drawings.
Specifications and Schedule of the Quantities, Architects instructions and directions to the
satisfaction of the Architect / Engineer-in-charge. Any direction or instruction given to him by
the Architect / Engineer-in-charge shall be deemed to have been issued to the Contractor.
Attention is called to the importance of requesting instruction from the Architect before
undertaking an work where Architect’s direction or instructions are required. Any such work
done in advance of such instructions will be liable to be removed.
12(2) Equipment:
The Contractor shall provide and install all necessary concrete misers, vibrators, hosts,
scaffolding, tools, tackles, plants, all transport for labour material and plant necessary for the
proper carrying on execution and completion of the work to the satisfaction of the Architect.
12(3) Storage of Materials:
The Contractor shall provide, erect and maintain proper sheds for the storage and protection of
the materials including owner supplied materials and also for the execution of Work may be
prepared in the Site.
12(4) Sanitary Conveniences:
The Contractor shall provide and erect all necessary sanitary convenience for the Site-staff and
the workmen maintain in a clean orderly condition and clean and deodorize the ground after
removal.
12(5) Scaffolding, Staging, Guard-rails:
The Contractor shall provide scaffolding, staging, guardrails, temporary stair which shall be
required during construction. The support for the scaffolding, staging guard -rails and temporary
stairs shall be strong, adequate for the particular situation. The temporary access to the various
parts of the structure under construction shall be rigid and strong enough to avoid any chance of
mishaps. The arrangement proposed shall be subject to the approval of the Engineer-in-charge.
13. Taxes
The Contractor shall include in the amount of his tender or tender rate the amount of VAT,
works contract tax, Service Tax or any other tax duty/octroi or other duties or taxes legally
payable as on date of tender & these Taxes are to be shown separately in the Tender. However it
shall be assumed that his rates cover for all taxes and duties as applicable till the completion of
work and no claim on this account will be entertained by the owner. All new taxes, levies,
duties imposed after signing the contract shall be reimbursed by the Employer on production of
20
documentary evidence and only if the contract is fulfilled within the stipulated time period. If
there is any delay on the part of the party, there will be no reimbursement.
14. Statutory obligations, notices, fees and charges
14(1) The Contractor shall comply with and give all notices required by any Government
authority and instrument, rule or order made under any Act of Parliament or any
regulation or Bye-law of any local authority relating to the work or with system the same
is or will be connected.
14(2) The Contractor shall pay and indemnify the Owner / Architect against liability in respect
of any fees or charges (including any rates and taxes) legally demandable under nay Act
of Parliament, instrument, rule or order or any regulation or Bye-law or any local
authority in respect of the work.
15. Royalties and patent rights
All royalties or other sums payable in respect of supply and use in carrying out the Work as
desired by or referred to in the Contract Bills of any patented articles, process or inventions shall
be deemed to have been included in the Contract sum, and the Contractor shall indemnify the
Owner from and against all claims, proceedings, damages, costs and expenses which may be
brought or made against the Owner to which he may be put by reason of the Contractor
infringing or being held to have infringed any patent rights in relation to any such articles,
processes and inventions.
16. Licences and Permits for Materials under Government control
Licences and Permits for all materials under Government control shall be obtained by the
Contractor, the Contractor shall include in his tender all transport charges and other expenses
likely to be incurred to bring the material to the Site.
17. Water for construction Water for construction will be provided by owner at one point anywhere at site. The distribution
of water from source to upper floors shall be done by the contractor at his own cost. Contractor
has to provide pumps. G.I. pipe line, hose pipes etc & maintain them at his cost. Adequate
storage facility shall be made by the contractor for uninterrupted supply of water, however,
incase of shortfall of water from existing sources, the contractor has to arrange water through
tankers at his own cost.
18. Electricity Electricity charges shall be borne by the contractor on actual consumption basis. Electricity will
be provided at one point by the owner. Contractor has to make his own arrangement for further
distribution to upper floors or anywhere at site at his own cost. Contractor has to provide wires.
Main switches, switches and power meter etc. for distribution of power to upper floors &
maintain them at his cost. No loose wires switches are permitted. All cables, controls, light
fittings, safety devices shall be as per local bodies approved norms.
21
19. Assignment or sub-letting The Contractor shall not without the written consent of the Engineer-in-charge assign this
Contract, and shall not without the written consent of the Engineer-in-charge (which consent
shall not be unreasonably withheld to the prejudice of the Contractor) Sub-let any portion of the
work.
20. Separate contracts The Owner reserves the right to let other Contract (i.e. waterproofing, electrical, air
conditioning, firefighting, painting etc) in connection with his work under similar general
conditions. The Contractor shall afford other contractors reasonable opportunity for the
introduction and storage of their materials and the execution of their work, and shall properly
connect and co-ordinate his work with theirs. If any part of Contractors or Sub-Contractors work
depends for proper execution or results upon the work of any other Contractor shall inspect and
promptly report to the Engineer-in-charge, any defects in such work that render it unsuitable for
such proper execution and results. Failure of the Contractor to so inspect and report shall
constitute an acceptance of the other Contractors work as fit and proper for the reception of his
work, except as to defects which may develop in the other Contractor’s or Sub-Contractors work
after the execution of the work to ensure the proper execution of his subsequent work the
Contractor shall measure work already in place and shall at once report to the Engineer-in-
charge any discrepancy between the executed work and the Drawings. The main contractor has
to work in coordination with other contractors in respect of work schedule, material allowing the
work to be done at site etc.
21. Certificate and payment
21(1) Contractor should maintain the measurement book in triplicate and all the work to be bill
as per the measurements noted in the measurement book. The measurement book to be
signed by the Architect / Engineer-in-Charge. These books are to be maintained till the
completion of the work.
21(2) At the period of interim Certificates named in the appendix to these conditions the
Architects / Engineer-in-charge shall issue a certificate stating the amount due to the
Contractor from the Owner, and the Contractor be entitled to payment therefore within
the period for honoring certificates named in the appendix to these conditions, interim
valuations shall be made whenever the Architects / Engineer-in-charge considers them to
be necessary for the purpose of ascertaining the amount to be stated as due in an interim
Certificates.
21(3) The amount stated as due in an interim Certificates shall subjects to any agreement
between the parties as to stage payments, be the total value of the work executed and of
the materials and goods delivered to or adjacent to the work for use thereon up to and
including a date not more that seven days before the date of the said Certificates less any
amount which may be retained by the Owner (as provided in sub-clause of this
condition) and less any installments previously paid under this Condition, provide that
such certificates shall only include the value of the said materials and goods as and from
such time as they are reasonably, properly and not prematurely brought to or placed
adjacent to the work and then only if adequately protected weather or other causalities.
22
21(4) The Owner may retain the percentage of the work. Materials and goods referred to in
Sub-Clause of this condition which is named in the appendix to this conditions as
retention percentage. Provide always that when sum of the amount retained equals the
amount named in the said appendix as limit of retain fund or that amount as reduced in
pursuance of clause of these conditions, as the case may be, no further amounts shall be
retained by virtue of this Sub-Clause.
21(5) So soon as is practicable but before the expiration of the period the length of which is
stated in the appendix to these Conditions from the end of the Defects Liability Period
also stated in the said appendix or from completion of making good defects under clause
of these conditions or from receipt by the Architect / Engineer-in-charge of the
Documents whichever is the latest, the Architect / Engineer-in-charge shall issue the
Final Certificate.
22. Claim for Extra When any instruction or decision given at site involves an extra or whereby the Contractor may
plan to claim an extra, it shall be the responsibility of the Contractor to inform the Architect
/Engineer-in-charge of the extra amount and get written authorization from the Owner before
proceeding with the work involved.
Any modification carried out for expending or simplifying work at the request of the Contractor
or his representatives shall not be taken as the basis for claiming an extra. However if such
modification shall also involve an extra, the rate for such modification shall be settled in
advance and written authorization obtained by the Contractor from the Architect / Engineer-in-
charge before proceeding with work involved.
The rate of extra items to be worked out and produced as follows:
a) Cost of actual material (landed at site) & Labour.
b) 15% to cover all overheads; plant & equipment; supervision; profits, texes etc.
23. Deduction for uncorrected work If the Engineer-in-charge deems it inexpedient to correct work damaged or not done in
accordance with the Contract, an equitable deduction from the Contract price shall be made
therefore.
24. Fluctuations The Contractor shall not claim any extras for fluctuation of price and the Contract Price shall not
be subject to any rise or fall prices.
25. Unfixed goods and materials Unfixed materials and goods intended for, delivered to and placed on or adjacent to the work
shall not be removed except for use upon the work unless the Engineer-in-charge has consented
in writing to such removal which consent shall not be unreasonably withheld.
26. Materials and Workmanship
23
26(1) All material and workmanship shall be as per the relevant code of I.S.I Specification and
of approved type and the Contractor shall immediately remove from the works any
material and / or workmanship which in the opinion of the Engineer-in-charge are
defective or unsuitable and shall substitute proper materials and / or workmanship at his
own cost. The term approval used in connection with this contract shall mean the
approval of the Engineer-in-charge.
26(2) The Contractor shall if required submit satisfactory evidence as to the kind and quality of
material.
26(3) Where special makes or brands are called for they are mentioned as a standard. Others of
equal quality may be used provided approval is first obtained in writing from the
Engineer-in-charge. Unless substitutions are requested no deviation from the
Specifications will be permitted. Failure to propose the substitution of any article within
30 days after signing of the Contract will be deemed sufficient causes for denial of the
request for substitution.
26(4) All materials shall be delivered so as to insure a speedy and uninterrupted progress of the
work. Such material shall be stored so as to cause no obstruction and so as to prevent
overloading of any portion of the structure, and the Contractor shall be entirely
responsible for damage or loss by weather or other cause.
26(5) Within 10 days after signing the Contract, Contractor shall submit for approval of the
Architect / Engineer-in-charge, a complete list of all material he and his Sub-Contractors
propose to use in the work of definite brand or make which differ in any respect from
those specified; also the particular brand of any article where more than one is specified
as a standard. He shall also list items not specifically mentioned in the Specifications but
which are reasonably inferred and necessary for the completion of the work.
27. Inspection
All materials and workmanship shall be subject to inspection, examination, and workmanship
shall be subject to inspection, examination, and test by the Owner at any and all time during
manufactures and / or construction. The Owner shall have the right to reject defective material
and workmanship or require its correction. Rejected workmanship shall be satisfactorily
replaced with proper material without additional charge therefore and the Contractor shall
promptly and remove the rejected material from the works. If the Contractor fails to proceed at
once with the replacement of rejected materials and or the correction of defective workmanship,
Owner will replace the materials or corrective work for defective workmanship, and charge the
cost thereof to the Contractor, or may terminate the right of the Contractor to proceed further
with the work.
24
The Contractor shall furnish promptly without additional charge all reasonable facilities, labour
and materials necessary for the safe and convenient inspection and test that may be required by
the Owner.
28. Defect
28(1) The Contractor shall promptly make good at his own cost and to the satisfaction of the
Owner/ Engineer-in-charge, all defect, shrinkages or small faults, arising in the opinion
of the Architect / Engineer-in-charge from work or materials not being in accordance
with the Drawings or Specification or Schedule of Quantities or the Instruction of the
Architect, which may appear during construction period & “Defects Liability Period”
refereed to in the appendix.
28(2) Such defects, shrinkages shall upon direction in writing of the Engineer-in-charge, and
within such reasonable time as shall be specified therein be amended and made good by
the Contractor, at his own cost unless the Owner shall decide that he ought to be paid for
such amending and making good and in case of default the Owner may employ and pay
other Contractor to amend and make good such defects, shrinkage, settlement or other
faults and all damages loss and expenses consequent thereto shall be made good and
borne by the Contractor and such damage, loss or expenses shall be recoverable from
him by the Owner or may be deducted by the Owner upon the Architect / Engineer-in-
charges certificates in writing from any amount due amount due or may become due to
the Contractor or the Owner may, in lieu of such amending and making good by the
Contractor deduct from any money’s due to Contractor a sum to be determined by the
Owner as equivalent to the cost of amending such work and in event of the Retention
Amount being insufficient recover the balance from the Contractor, together with any
expenses the Owner may have incurred in connection therewith.
29. Possession completion and postponement
29(1) On the date for commencement stated in the appendix to these conditions possession of
the site shall be given to the Contractor by the Engineer-in-charge, who shall thereupon
being the works and regularly and, diligently proceed with the same, and who shall
complete the same on or before the date for Completion stated in the said appendix
subject nevertheless to the provisions for extension of time contained of these conditions.
29(2) The Owner may issue instruction in regard to the postponement of any work to be
executed under the provisions of this Contract.
29(3) The contractor’s license to enter on site will be automatically seized after completion of
the work or after issuing a letter by the Architect to the contractor to vacate the site under
circumstances.
30. If at any time or times before Virtual Completion of the work the Owner shall take
possession of any part or part of the same for handing over to the finishing Contractor or
25
other agency, then notwithstanding anything expressed or implied elsewhere in this
Contract:-
30(1) Such part or parts shall not be deemed to be Virtually Complete.
30(2) Virtual Completion of such part or parts would occur on the completion of the last part of
the structure under this Contract.
30(3) The Contractor shall not claim that such part or parts are complete and request refund of
payments in lieu thereof.
26
31. Extension
Upon it becoming reasonably apparent that the progress of the Works is delayed, the Contractor
shall forthwith give written notice of the cause of the delay to the Owner, and if in the opinion
of the Owner, the completion of the Work is likely to be or has been delayed beyond that date
for completion stated in the appendix to these conditions or beyond any extended time
previously fixed under this clause.
31(1) By force majure. Or
31(2) By reason of any exceptionally inclement weather. Or
31(3) By reason of loss or damage occasioned by any one or more of the contingencies
referred to in clause of these conditions Or.
31(4) By reason of civil commotion, local combination of workmen strike or lockout affecting
any of the trades employed upon the works or any of the trades engaged in the
preparation, manufactures or transportation of any of the gods or material required for the
work. Or
31(5) By reason of Architect’s / Engineer-in-charge’s instruction issued under clauses of these
Conditions. Or
31(6) By reason of the Contractor not having received in due time necessary instructions,
drawings, details or levels from the Engineer-in-charge for which he specially applied in
writing on a date which having regard to the date for completion stated in the appendix to
these conditions or to any extension of time then fixed under this clause was neither
unreasonably distant from nor unreasonably close to the date which it was necessary for
him to receive the same. Or
31(7) By delay on the part of artists, tradesmen or others engaged by the Owner in executing
work not forming part of this Contract. Or
Then the Architect / Engineer-in-charge shall as soon as he is able to estimate the length
of the delay beyond the date or time aforesaid make in writing a fair and reasonable
Extension of Time for completion of the works, provided always that the Contractor shall
use constantly his best Endeavor’s to prevent delay and shall do all that may reasonably
be required to the satisfaction of the Architect / Engineer-in-charge to proceed with the
work.
32. Damages for non-completion
If the Contractor fails to complete the works by the date specified in these Conditions or within
any extended time fixed under clause of these conditions and the Architect / Engineer-in-
charge’s certifies in writing that in opinion the same ought reasonably so to have been
27
completed, the Contractor shall pay or allow to the owner a sum calculated by the way of
penalty @ ½% of the Contract Price per week of delay, subject to maximum of 10% of the
contract price. As agreed Liquidated Damages for the period during which the said work shall
so remain or have remained incomplete the Owner may deduct such damages from any money
otherwise payable to the Contractor under this Contract.
33. Virtual Completion and Defects Liability Period
33(1) When in the opinion of the Architect / Engineer-in-charge the Works are practically
completed, he shall forthwith issue a certificate to that effect and Virtual Completion of
the Works shall be deemed for all the purpose of this Contract to have taken place on the
day named in such certificate. Date of defect liability period will start after ‘Taking over’
of site by Owner, as described on Page No.10.
33(2) Any defects shrinkage or other faults which shall appear within the “Defects Liability
Period” stated in the appendix to these conditions and which are due to materials and
workmanship not in accordance with this Contract shall be specified by the Engineer-in-
charge in a Schedule of Defects which he shall deliver to the Contractor not later than 14
days after the expiration of the said Defects Liability Period and within a reasonable time
after receipt of such Schedule the Defects Shrinkage and other faults therein specified
shall be made good by the Contractor and (unless the Owner shall otherwise instruct in
which case the Contract Sum shall be adjusted accordingly) entirely at his own cost, risk
& responsibility.
33(3) Notwithstanding sub-clause of this Condition the Engineer-in-charge / Architect may
whenever he considers it necessary so to do, issue instructions requiring any defect,
shrinkages or other fault which shall appear within the Defect Liability Period named in
the appendix to these conditions and which is due to materials and workmanship not in
accordance with this Contract to be made good and the Contractor shall within a
reasonable time after receipt of such instructions comply with the same ( and unless the
Architect / Engineer-in-charge shall otherwise instruct in which case the Contract sum
shall be adjust accordingly) entirely at his own cost, provided that no such instruction
shall be issued after 14 days from the expiration of the said Defects Liability Period.
33(4) When in the opinion of the Owner / Architect any defects shrinkages or other defaults
which he may have required to be made good under sub-clause of this Condition shall
have been made good he shall issue a certificate to that effects shall be deemed for all the
purpose of this Contract to have taken place on the day named in such certificates.
34. Payments withheld The Owner may without or on account of subsequently discovered evidence
nullify the whole or a part of any certificate to such extent as may be necessary in his reasonable
opinion to protect the Owner from loss on account of:
34(1) Defective work not remedied.
34(2) Failure of the Contractor to make payments properly to Sub-Contractor or for materials
or labour.
28
34(3) A reasonable doubt that the Contract can be completed for the balance then unpaid.
34(3) Damage to another Contractor or Sub-Contractor.
When the above grounds are removed payment shall be made for amount withheld because of
them.
35. Injury to Persons and property Owner
35(1) The Contractor shall be liable for and shall indemnify the Owner against any liability,
loss, claim or proceedings whatsoever arising under any statute or at common law in
respect of personal injury to or the death of any person whomsoever arising out of or in the
course of or in the course of or caused by the carrying out of the works, unless due to any
act or neglect of the Owner or of any person for whom the Owner is responsible.
35(2) Except for such loss or damages as is at the risk of the Owner under clause of these
Conditions ( If applicable) the Contractor shall be liable for and shall indemnify the Owner
against any expense, liability, loss, claim, or proceedings in respect of any injury or
damages whatsoever to any property real or personal in so far as such injury or damage
arises out of or in the course of or by reason of the carrying out of the works, and provided
always that the same is due to any negligence omission or default of the Contractor, his
servant or agents or of any Sub-Contractor, his servant or agent.
36. Insurance against injury to Person and Property
36(1) Without Prejudice to his liability to indemnify the Owner under clause of these
conditions, the Contractor shall maintain and shall cause any Sub-Contractor to maintain
36(A) Such insurance as are necessary to cover the liability of the Contractor or as the case may
be of such Sub-Contractor, in respect of personal injuries or deaths arising out of or in the
course of or caused by the carrying out of the work or incidental to work or stay at work
site; and
36(B) Such insurances as may be specifically required by the Contractor Bills in respect of
injury or damage to property real or personal arising out of or in the course of or by reason
of the carrying out the work or incidental to work or stay at work site, and caused by any
negligence, omission or default of the Contractor, his servants or agents or, as the case may
be of such Sub-Contractor, his servants or agents.
The Contractor shall produce or cause any Sub-Contractor to produce for inspection the
relevant policy or policies of insurance together with the receipt in respect of premiums
paid under such policy or policies as and when required so to do by the Engineer-in-charge
provided always that as and when may be reasonably required by the Engineer-in-charge,
the production by either the Contractor or any Sub-Contractor of a current certificate of
insurance from the company or firm which shall have issued the policy or policies
aforesaid shall be a good discharge of the Contractor’s obligation to produce or to cause
the production of the policy or policies and the receipts in respect of premium paid.
29
36(2) The Contractor shall maintain in the joint names of the Owner and Contractor such
insurances as may required in respect of any expenses, liability, loss, claim, or proceedings
which the Owner may incur or sustain by reason of injury or damage to property real or
personal arising out of or in the course of or by reason of the carrying out of the work, and
caused otherwise than by the negligence, omission or default of the Contractor, his servant
or agents or any Sub-Contractor, his servants or agents.
36(3) Any such insurance as is referred to in the immediately preceding paragraph shall be
placed with insurers to be approved by the Engineer-in-charge and the Contractor shall
have to deposit with him the policy or policies and the receipts in respect of premium paid.
37. Insurance of the works against fire etc.
37(1) The Contractor shall in the joint names of the Owner and Contractor, insure against loss or
damages by fire, storm. tempest, lighting, flood, earthquake, aircraft or anything dropped
there from, aerial objects, riot and civil commotion for the full value thereof all work
executed and all unfixed materials and goods intended for, delivered to and placed on or
adjacent to the work, labour camps and laborers and their material assets if located at sites
but excluding temporary building plant, tools and equipment owned or hired by the
Contractor or any Sub-Contractor and shall keep such work materials and goods so insured
until Virtual Completion of the work. Such insurance shall be with insurers approved by
the Owner and the Contractor shall deposit with the Owner the policy or policies and the
receipts in respect of premiums paid; and should the Contractor make default in insuring or
continuing to insure as aforesaid the Owner may himself insure against any risk with
respect of which the default shall have occurred and deduct a sum equivalent to the amount
paid by him in respect of premium from any monies due to or to become due to the
Contractor.
Provide always that if the Contractor shall independently of his obligations under this
contract maintain a policy of insurance which covers (inter alia) the said work, materials
and goods against the aforesaid contingencies to the full value thereof then the
maintenance by the Contractor of such policy shall if the Owners interest is endorsed
thereon, be a discharge of the Contractor’s obligation to insure in the joint names of the
Owner and Contractor and the production by the Contractor as and when may reasonably
required by the Owner, of a current certificate of insurance from the company or firm
which shall have issued the said policy shall be a discharge of the Contractors obligation to
deposit with the Owner a policy or policies and the receipts in respect of premiums paid.
37(2) Upon settlement of any claim under the insurances aforesaid the Contractor with due
diligence shall restore work damaged, replace or repair unfixed materials or goods which
have been destroyed or injured, remove or dispose of any debris and proceed with the
carrying out and completion of the work. All money received from such insurances shall
be paid to the Contractor by installments under certificates of the Engineer-in-charge
issued at the period of interim certificates named in the appendix to these conditions. The
Contractor shall not be entitled to payment in respect of the restoration of work damaged,
the replacement and repair of any unfixed materials or goods and the removal and disposal
of debris other than the monies received under the said insurances.
30
37(3) The contractor is in insured for the labour working at site and copy of the insurance letter
is to be submitted to the owner.
37(4) The contractor has to take all the safety precautions for the workers working at site
including fire safety.
38. Determination by the Owner
38(1) Default: If the Contractor shall make default in any one or more of the following respect,
that is to say:
38(1)A If he without reasonable cause wholly suspended the carrying out of the works before
completion thereof, or
38(2)B If he fails to process regularly with the works, or
38(1)C If he refuse or persistently neglects to comply with a written notice from the Owner /
Arcitect requiing him to remove defective work or improper material or goods and by such
refusal or neglect the work is materially affected or.
38(1) D If he fails to comply with the provision, then the Owner / Architect may give him the
notice by registered post or recorded delivery specifying the default and if the Contractor
either shall continue such a default for 14 days after receipt of such a notice and shall at
any time thereafter repeat such a default ( whether previously repeated or not). Then the
Owner without prejudice to any other rights or remedies may within 10 days after such
continuance or repetition of notice by register post or recorded delivery forth with
terminate not be given unreasonably or vexatious.
38(2) Bankruptcy of Contractor: In the event of the Contractor becoming bankrupt or making
a composition or arrangement with his creditors or being a company having a winding up
order made or (except for purpose of reconstruction) a resolution for voluntary winding
up passed or a received or manager of his business or undertaking duly appointed or
possession taken by or on behalf of the holders of any debentures secured by a floating
charge, of any property comprised in or subject to the floating charges, the employment
of the Contract under this Contract shall be forthwith automatically determined but the
said employment may be reinstated and continued if the Owner and the Contractor, his
trustee in bankruptcy, liquidator, receiver or manager as the case may be shall so agree.
38(3) The Owner shall be entitled to determine the employment of the Contractor under this
Contract, if the Contract shall have offered or given or agreed to give to any person any
gift or consideration of any kind as an inducement or reward for doing or forbearing to
do or for having done or forbore to do any action in relation to the obtaining or execution
of this Contract with the Contract or any other Contract with the Owner, or if the like acts
shall have been done by any person employed by the Contract or acting on his behalf
(whether with or without the knowledge of the Contractor), or if in relation to this
Contract or any other Contract with the Owner the Contractor or any person employed by
him or acting on his behalf shall have committed any offence under the prevention of
corruption act. Or shall have given any fee or reward of which is an offence under the
Local Government Act.
31
38(4) In the event of the employment of the Contractor being determined as aforesaid and so
long as it has not been reinstated and continued the following shall be the respective
rights ad duties of the Owner and Contractor.
38(4)AThe Owner may employ and pay other persons to carry out and complete the works and
he or they may enter upon the Works and use all temporary buildings, plant, machinery,
appliances, goods and materials intended for, delivered to and placed on or adjacent to
the works and may purchase all materials and goods necessary for the carrying out and
completion of the Works.
38(4)B The Contractor shall if so required by the Owner or Architect within 14 days of the date
of determination, assign to the Owner without payment the benefit of any Agreement for
the supply of materials or goods and / or for the execution of any works for the execution
of any works for the purpose of this Contracts but on the terms that a supplier or Sub-
Contractor shall be entitled to make any reasonable objection to nay further assignment
thereof by the Owner. In any case the Owner may pay any supplier or Sub-Contractor for
any materials or goods delivered or works executed for the purpose of the Contract (
whether before or after the date of determination ) in so far as the price thereof has not
already been paid by the Contractor. The Owners right under this paragraph is in addition
to his rights to pay nominated Sub-Contractors as provided in clause and payments made
under this paragraph may be deducted from any sum due or to become due to the
Contractor.
38(4)C The Contractor shall as and when required in writing by the Engineer-in-charge remove
froms the works any temporary building, plant, tool, equipments, goods and materials
belonging to or hired by him. if within a reasonable time after any such requirements has
been made to the contractor, has not complied therewith, then the owner may (but
without being responsible for any loss or damage) remove and sell any such property of
the contractor, holding the proceeds less all costs incurred to the credit of the contractor.
38(4)D The contractor shall allow or pay to the owner in the manner hereinafter appearing the
amount of any direct loss and/or damage caused to the owner by the determination. Until
after completion of the works under paragraph (a) of this sub-clause the Owner shall not
be bound by any provisions of this Contract to make any further payment to the
Contractor, but upon such completion and the verification within a reasonable time of the
accounts therefore the Engineer – in – charge shall certify the amount of expense
properly incurred by the owner and the amount of any direct loss and/or damage caused
to the Owner by the determination and if such amounts when added to the monies paid to
the Contractor before the date of determination exceed the total amount which would
have been payable to the Owner by the Contractor, and if the said amounts, when added
to the said money be less than said total amounts the difference shall be a debt payable
by the Owner to the contractor.
Determination by the Contractor
39(1) Without prejudice to any other rights and remedies which the Contractor may possess,
if:
32
39(1) A The carrying out of the whole or the whole of the substantially uncompleted works
(other than the execution of work required under clause of these conditions) is
suspended for a continuous period of the length by reason of:
Force majoure, Or
Loss or damage occasioned by any one or more of the contingencies referred to in
clause of the conditions (if applicable). Or
Civil commotion, Or
Owner/ Architects instructions issued under clause of these conditions, Or
Then Contractor may thereupon notice by registered post or recorded delivery to the
Owner or Architect forthwith to determine the employment of the Contractor under this
Contract; provided to such notice shall not be given unreasonably or vexatiously.
39(2) Upon such determination, then without prejudice to the accrued or remedies of either
party or to any liability of the classes mentioned in clause of these conditions which
may accrue either before the Contractors or any Sub-Contractors shall have removed
his or their temporary buildings, plant, machinery, appliances, goods or materials or by
reason of his or their so removing the same, the respective rights and liabilities of the
Contractor and the Owner shall be as follows that is to say:
39(2) A The Contractor shall with all, reasonable dispatch and in such manner and with such
precautions as will-prevent injury, death or damage of the classes in respect for which
before the date of determination he was liable to indemnify the Owner under clause of
these Conditions remove from site all his temporary buildings, plant, machinery,
appliance, goods and materials and shall give facilities for his Sub-Contractors to do
the same.
39(2) B After taking into account amounts previously paid under this Contract the Contractor
shall be paid by the Owner.
39(2)B(I)The total value of the work completed at the date of determination.
39(2)B(II) The total value of the work begun and executed but not completed at the date of
determination the value being ascertained mutatis in accordance with clause of
these Conditions.
39(2) B (III) The cost of materials and good s properly ordered for the works for which the
Contractor shall have paid or of which the Contractor is legally bound to pay, and
on such payment by the Owner materials or goods so paid for shall become the
property of the Owner.
33
Provided that in addition to all other remedies the Contractor upon such determination may take
possession of and shall have lien upon all unfixed materials which may have before the property
of the Owner under clause until payment of all monies due to the Contractor from the Owner.
Co-ordination of work At the commencement of work, and from tome to time, the Contractor shall confer with the Sub-
Contractors, persons, engaged on separate contracts in connection with the work, and with the
Architect for the purpose of the Co- ordination and execution of various phases of the work.
Labour The Contractor shall employ no child labour 14years of age on the work. If female labour is
engaged the Contractor shall make necessary provision for safeguarding small children and
keeping them clear of the site of Operations. No labour shall reside within the compound except
the authorized guards. ‘Crèche’ facility shall be provided by the Contractor.
Guarantee
42 (1) Besides guarantees received elsewhere, the Contractor shall guarantee the work in
general for one year as noted under clause of the conditions.
42(2) All required guarantees shall be submitted to the Owner by the Contractor when
requesting certification for accounts for payment by the Owner.
Arbitration:
43(1) Architect is the sole and first arbitrator. His decision is binding upon both the
parties. If both the parties decide, they may appoint a separate arbitrator and
umpire.
43(2) Subject to any dispute between the parties hereto arising out of any notified
claims of the Contractor in his final bill and/or arising out of any claimed by the
owner (whether or not the amount claimed by the Owner or any part thereof shall
have been deducted from the final bill of Contractor or any amount paid by the
Owner to the Contractor in respect of the work) shall be referred to arbitration by
a Sole Arbitrator selected by the Contractor from a panel of three persons
nominated by the Engineer-in-charge.
43(2) The provisions of the Indian Arbitration Act, 1940 and all statutory reenactments
and modifications thereof and the rules made there under shall apply to all such
arbitrations subject further to the following conditions (a) the Arbitrations shall
give has award separately in respect of each claim (b) In so for as any dispute or
difference referred to arbitration shall relate to any matter or thing in respect of
which the decision opinion or determination (howsoever) express of the Owner or
Engineer-in-charge or Site Engineer or any other person has been expressed to be
final in terms of Contract such decision opinion and/or determination , as the case
may be shall be binding upon the arbitrator
34
Protection and Cleaning
44 (1) The Contractor shall protect and preserve the work from all damage or providing
any temporary roof, window and door coverings, boxing or other construction as
required by the Engineer-in-charge. This protection shall be provided for all
property adjacent to the site as well as on the site.
44 (2) The Contractor shall properly clean the work as it progresses and shall remove all
rubbish and debris from the site from time to time as is necessary and as directed.
On completion the contractor shall ensure that the premises and/or site are cleaned
surplus materials debris, sheds etc. removed, areas under floors cleared of rubbish
gutters and drains cleared, doors and sashes eased, locks and fastenings oiled,
keys clearly labeled and handed to the Engineer-in-Charge co that the whole is
left fit for immediate occupation or use and to the satisfaction of the Owner.
45. Tolerance
The Contractor shall exercise every care to ensure that all structural members are sufficiently
plumb and true to dimensions called for on the drawings to receive prefabricated finishing
elements, such as doors, windows, cabinet work, ceramic work, concrete, tiles etc. Any
variations may require rectification in the structural members or may involve remaking or
replacing the finishing elements, fabricated to fit into the openings or spaces, as called for on the
Drawings, the cost of which will be borne by the contractor.
In all cases , the Contractor whose work does not conform to dimensions called for, shall be
liable for all the expenses which may have to be incurred for rectification or replacement as may
be required by the Architect for the purpose of installation of the finishing elements. The
Architect’s decision in this respect shall be final and binding on the parties concerned.
46. EMD / BID SECURITY AMOUNT
EMD / Bid Security amount should be in shape of Demand Draft from any Nationalized Bank in
favour of the “Institute of Cost Accountants of India’ If any bidder backs out after opening of
Bid, their EMD shall be forfeited, with right of management or any other disciplinary action
against the party. The EMD of the successful bidder may be adjusted against the Security
Deposit.
Earnest Money of unsuccessful bidders shall be refunded not later than 21 days after the expiry
of the bid validity.
Bids without appropriate Bid Security / EMD shall be treated as un-responsive & no further
evaluation of such Bids shall be made.
35
46. SECURITY DEPOSITE
The value of security money to be deposited by the successful tenderer in the form of Demand
Draft from any nationalized Bank in favour of ‘Institute’ shall be 5% value of the awarded
contract without having any ceiling. This Security Deposit shall be refunded within 30 days of
satisfactory execution of the contract with the approval of tender approving authority. For
successful tenderer, EMD shall be converted to security deposit. In case the firm fails to deposit
the security money, the order shall be cancelled and firms non-performance shall be kept
recorded for future dealings.
36
SECTION – 6
SPECIAL CONDITIONS OF CONTRACT
THESE CONDITIONS WILL BE READ IN CONJUNCTION WITH RELEVANT
ARTICLES OF GENERAL CONDITONS OF CONTRACT (G.C.C). IN CASE OF
VARIANCE/ DISCREPANCIES BETWEEN S.C.C AND G.C.C THE CONDITIONS
LAID DOWN IN S.C.C. SHALL TAKE PRECEDENCE.
Special conditions of contract shall be read in conjunction with the General Conditions of
Contract, Specifications of work, Drawings and any other documents forming part of this
contract wherever the context so requires.
Notwithstanding, the sub-division of the documents into these separate sections and volumes
every part of each shall be deemed to be supplementary to and complementary of every other
part and shall be read with and into the contract so far as it may be practicable to do so.
Where any portion of the General Conditions of Contract is repugnant to or at variance with any
provisions of the Special Conditions of Contract, then unless a different intention appears, the
provisions of the Special Conditions of Contract, shall to the extent of such repugnancy, or
variance, prevail.
1 The Contractor should note that one connection for water supply shall be given free of
cost at one point inside the plot. The Contractor will lay a suitable size of pump/ pipeline
distribution network for his work at his cost and shall remove the same after the work is
completed. Storage of water will be solely the contractors responsibility and at his
expense. The contractor will not have any claim whatsoever on account of failure of
water supply at any time. Water bill will be paid by the contractor till completion of the
work.
An electric power of 440V - 3 phase shall be made available at one location inside the
plot. Necessary connections/ tapings shall be made by the contractor at his cost. The
contractor shall extend his cable, etc, from this point and shall provide all necessary main
switches, control board-cutouts etc. These equipments shall be protected from weather,
rain etc. and shall conform to normal safety standards. Until power and water is made
available by the owner, contractor shall make his own arrangement of power and water
for the construction work. Civil contactor shall also give power to other contractors from
his distribution board and shall charge them. Electricity bill will be paid by the contractor
till completion of the work
Since there is likelihood of frequent power shutdown from MSEDC, Contractor shall
make adequate standby arrangement with appropriate capacity DG sets to achieve the
target date of stage wise completion of work.
37
2. The quantities are for piling work for underground tank and compound wall of institute
building. Site is affected by buffer zone from the mangroves. The land under the buffer
zone is marked on site. The originality of the land under the buffer zone is not to be
disturbed even it is not to be leveled. If any concreting or storing of the material is to be
done in the buffer zone it has to be ‘Tadpatri’. Otherwise, the contractor will be liable for
the consequences under CRZ provisions.
3. All materials provided by Contractor shall be new and of approved quality manufactured by
renowned concerns, conforming to Indian Standards or equivalent. The materials shall have
ISI mark as far as possible unless otherwise approved by Architect in writing prior to
procurement and use. The Contractor shall furnish manufacturers certificate for the materials
supplied when asked for.
Further to that he shall get the materials tested from an approved test house as per codal
requirement of relevant IS codes & as per additional test requirement if asked by
ENGINEER INCHARGE/ Architect. The cost of all tests & test certificate shall be borne by
the Contractor. No separate payment shall be made for testing even if the materials are
procured by the owner. Any materials procured or brought to site and not confirming to
specification and satisfaction of the Architect shall be rejected and Contractor shall have to
remove the same immediately from the site at his own expenses and without any claim for
compensation due to such rejection.
4. All the scaffolding/propping material shall be MS tubular which shall be supplied by the
Contractor. All staging platforms shall have hand rails. Wooden planks used for platform to
be 1" thick and firmly secured. Safety regulations and rules shall be strictly observed.
Staging/scaffolding shall be as per IS 3696.
5. All the materials and services issued by the Client to the contractor will not be abused by the
contractor. If such materials and/or services are abused, lost and/or damaged while in the
custody of the contractor the cost of such materials and/or services will be recovered from
the contractor at the rates fixed by the Architect. The decision of the Architect whether any
materials/services are abused, lost and/or damaged will be final and binding on the
contractor.
6. All materials to be used for construction shall be stored by contractor in a manner as directed
by the Architect. Necessary storage sheds and at approved location from time to time shall
be provided by the contractor at his own cost. The security arrangements for such sheds shall
be the responsibility of the Contractor. The Contractor shall remove the above sheds on
completion of the work or as required by the exigency of work.
7. The contractor shall prepare and maintain at his own cost all temporary roads & ramps
within the premises required for transporting materials, equipments and carrying out the
construction activities. Necessary arrangements shall be made by the contractor to drain out
38
the storm water and keep the site as clean as possible for which no extra payment shall be
made. These accesses for vehicles shall be laid out in concurrence with the Architect.
8. The proposed work to be executed under this contract is in the form of invitation to tender.
The tender is essentially an item rate tender. The items of work and their quantities indicated
in the schedule of quantities are only approximate and for the guidance of the tenderers and
are subject to variation. Measurement shall be carried out as indicated in the tender
specification and as per schedule of quantities and prices. Any claim by the contractor for
such variations and/or deletions of any item shall not be entertained. The Owner does not
bind themselves for any such variations and/or deletion of item of work and its quantities.
9. The price quoted by the contractor shall not be subjected to any change due to increase or
decrease in cost of materials and labour or due to any reasons whatsoever.
10. Tax deduction at source (TDS) at the rate applicable will be deducted from all proceeds and
payments by owner.
11. The drawings if any attached with the tender & forming part of this contract are subject to
additions & alterations to suit the requirements of the Owner for which no extra claim shall
be entertained.
12. The specifications forming part of this contract have been drawn up with all possible care
and are intended to cover the supply of all the materials, tools, plants and equipments labour
in the execution and completing the entire work in all respects under this contract. In case
there are any details of construction or materials which have not been referred to in the
specifications detailed descriptions of items, schedule of quantities, or the drawings but
which have not been referred to in the true completion of the purpose of the work, the same
shall be deemed to have been included in the price quoted by the tenderer. Where ever
specifications are not stipulated, the work shall be as per latest ISI specifications and/or as
directed by the ENGINEER INCHARGE following good Engineering practices.
13. Contractor shall provide at his own expense necessary sanitary and drinking water facilities
for his workers at work site. Contractor shall ensure that no workers move about in areas
other than the work site without prior permission of the Architect. He shall ensure that his
workers shall not commit any nuisance anywhere on the site or in the near-about area.
14. Contractor shall observe all safety precautions during construction work. The contractor
shall ensure that his workers are working in normal safe working conditions. The Contractor
shall take out adequate necessary insurance policies to cover his workmen as per the
Workmen’s Compensation Act. The Contractor shall also take out appropriate third party
insurance.
14.1 Contractor shall provide at his cost safety and security of his workmen, machine and
materials (including those supplied by owners). The owners shall not accept any
responsibilities for the same.
39
15 The Contractor shall keep necessary number of supervisors and atleast one qualified and
experienced Civil Engineer for full time for execution of work for entire project.
16 The Contractor shall provide free of cost a site office with normal furniture and facilities for
toilet in accordance with Owners Engineers, Architects requirements, for the use of
Owners/Architects and his site Engineer and his staff. He shall maintain these offices properly
during the entire duration of the contract. Contractor should also maintain a triplicate book, Bar
Chart, Set of Drawings etc.
17 Contractor has to provide labour accommodation on his own. Toilets, canteen, crèche, etc. as
required under labour laws shall be provided by the contractor, free of cost, outside the plot
premises.
18 The owner reserves the right to change the name to any other company and sub divide the works
to the other name/s on the same terms and conditions.
19 No extra payment shall be made for removal of water due to sub- soil, rain seepage, or by any
reason, water on ground or floor during all items of construction and at all phases of
construction.
20 SITE : Since the work involves construction of Piling, the Contractor shall visit and examine the site at
the place described in the Appendix to General Instructions to Contractors and satisfy himself as
to the nature of existing roads or other means of communication, the character of the soil and of
the excavations, the correct dimensions of the work and facilities for obtaining materials and
shall obtain generally his own information on all matters affecting the execution of the work.
21 BENCH MARKS :
The Contractor is to construct and maintain proper benchmarks to indicate the intersection of all
main walls in order that the lines and levels may be accurately checked at all times. The
Contractor shall provide suitable stones with flat tops and build the same in concrete for
temporary or permanent bench marks. All the pegs for setting out the work and fixing the
necessary levels required for the execution thereof shall, if desired by the Architect likewise be
built in masonry at such places and in such manner as the Architect may determine. Contractor's
rates shall cover for these factors.
22. PROGRESS CHART :
22.1 The Contractor shall submit time and progress chart and CPM Network fitted within the
specified overall period of completion (as stated in the Conditions of Contract) within 7
days of the communication of acceptance of the Tender, for the approval of the Architect.
22.2.1 Ancillary work should be so started that all such work is completed before the specified
overall contractual period of completion.
40
22.2.2 Any failure on the part of the Contractor to adhere to the starting and completion dates
of individual items mentioned in the chart shall entail liquidated damages clause in
whole or part at the discretion of the Architect notwithstanding the overall period of
completion stated in the conditions of Contract.
23. MATERIALS AND WORKMANSHIP :
23.1 All the materials, (except those which will be issued free to the Contractor by the owner
for incorporation of work) stores and equipment required for the full performance of the
Contract must be provided through normal trade channels and must include octroi, excise
and import duties, Sales tax payable to all authorities and other charges. They shall be of
approved quality and the Contractor must be entirely responsible for the proper and
efficient carrying out of the work. The Contractor shall order all materials required for
the execution of the work from local/outside sources as early as necessary and to ensure
that such materials are on site well ahead of requirement for use in the work.
23.2 The Contractor shall furnish well in time before work commences, at his own cost, any
samples of materials or workmanship that may be called for by the Architect for his
approval or rejection and any further samples in case of rejection until such samples are
approved. Such samples when approved shall be the minimum standard for the work to
which they apply. In case of items like suspended ceiling, timber partitions, etc. typical
sample panels or prototypes shall be erected in position for approval before undertaking
work. Rates quoted shall cover for such preliminary work.
The work involved calls for a high standard of workmanship combined with speed.
Inferior quality of materials/workmanship will not be permitted under any circumstances
on the pretext of "Prevailing Practice".
Any workmanship or materials not complying with the specific requirements or approved
samples or which have been damaged, contaminated or deteriorated, must be removed
immediately from the site and replaced at the Contractor's expense as directed.
In regard to alternative items if any specified in the Schedule of Quantities, Contractor
should note that the Architect reserves the right to replace the principal item of the
schedule with an alternative.
If the contractor wishes to make bulk-purchases of any item, he shall inform Architect in
this regard, as a safeguard against a probable Design-Change, due to any reasons. No
claim in this regard will be entertained.
41
24. MATERIAL TESTING :
The quality of all materials proposed to be used in the works will be as per the relevant
Indian Standard Specifications and will be generally in accordance with the provisions of
the Technical Specifications.
The Contractor will carry out routine tests on all building materials for ascertaining the
various qualities of the same as per the relevant tests procedure on samples collected at
intervals stipulated in respective IS codes and submit the reports in triplicate to the
Architects promptly.
The Contractor shall set up a field laboratory with necessary equipments for day to day
testing of materials, like grading of coarse and fine aggregates, silt content and bulkage
of sand etc. and for conducting routine, regular Field Tests like Sieve-Analysis, Silt
Content, Cube-Test, slump cone etc. as directed by the Architect.
25. INTERPRETATIONS:
26.1 Wherever the words "directed”, “as required”, “selected" or words of like effect are used,
it is to be understood that the selection, direction or requirement of the Architect are
intended.
26.2 The words "approved", "satisfactory “or words of like import shall mean "approved by"
or "satisfactory to" the Architect whose approval must first be obtained before the
materials ordered or the works to which the words refer to are put in hand.
The word "allow" shall mean that the Contractor shall include in his rates for the
particular matter referred to.
26.3 The words "as described" shall mean the description in the trade preambles, general
preambles, specifications, general instructions etc.
26.4 The word 'Providing' would mean to include 'Supply' (of approved make size., type,
colour, etc.) unless supply is categorically excluded from the item-description.
27. Proper Execution of Work:
27.1 The Contractor shall at his cost provide any necessary temporary enclosures, gates,
entrances, etc for the protection of the work and materials and for altering and adopting
same as may be required and removing the same at completion of the works and making
good all disturbances caused therefore. During inclement whether the Contractor shall
suspend concreting or plastering for such time as the Architect/Site Engineer may direct
and shall protect from damage such work in course of execution by approved measures.
27.2 Should the work be suspended by reason of rain, strike, lockouts or any other cause, the
Contractor, shall at his cost take all precautions/insurances necessary for the protection of the
work and shall make good any damage arising from any of these causes.
42
27.3 The Contractor shall at his expense cover up and protect from injury from any cause all
new work and supply all temporary doors, protection to windows, and any other requisite
protection for the whole work executed, whether by himself or special tradesmen or sub-
contractors and any damage caused must be made good by the Contractor at his own
expense.
27.4 All fences, trees, shrubs, grass, lawns and other surfaces around the buildings or
approaches thereto, which are required to be maintained are to be kept free from damage
due to operations in connection with the work, at Contractor's expense.
27.5 The Contractor shall, at his expense protect all projecting sills, jambs, copings, stone or
concrete treads and moldings and all concrete steps, woodwork and joinery and the like from
injury during the progress of the work by rough timber casings securely fixed. The
Contractor shall at his cost protect joinery and make good all damage to same from any
cause whatsoever during the performance of the Contract and leave perfect to the satisfaction
of the Architect at completion. Before giving up possession the Contractor must see that all
doors, windows, and ventilators, etc. work easily and shall make all necessary adjustments.
27.6 Idle-time will not be payable, under any circumstance. The Contractor is expected to
plan his resources, keeping in view site-conditions.
27.7 The contractor shall provide at no extra cost temporary masonry or protective barriers
upto 1200 mm height from the floor level to all lift wells and/or shafts openings on all floors
to safeguard against any accidental fall and maintain them till such time as permanent
enclosures are installed.
27.8 Any instructions given verbally shall be deemed instructions for the proper execution of
the works not involving extra charges.
27.9 The contractor shall not carry out any work between hours of sunset and sunrise without
the permission of the Engineer in charge in writing. However, proper illumination will be
provided during the execution of work by the contractor at his own cost.
28.A ARCHITECT'S REPRESENTATIVES :
The duties of Architect's Representative are to watch and supervise the works and to test
and examine any materials to be used for workmanship employed in connection with the
works. He shall have no authority to relieve the Contractor of any of his duties or
obligations under the Contract nor except as expressly provided hereunder to order any
work involving delay or any extra payment by the Employer nor to take any variation of
or in the works.
Architect may from time to time in writing delegate to Architect's Representative further
powers and authorities and shall furnish to the Contractor a copy of all such written
delegations of powers and authorities. Any written instructions or written approval given
43
by Architect's Representatives to the Contractor within the terms of such delegation (but
not otherwise) shall bind the Contractor and the Employer as though it had been given by
Architect provided as follows:
1. Failure of Architect's Representative to disapprove any work or materials shall
not prejudice the power of Architect thereafter to disapprove such work or
materials and to order the pulling down, removal or breaking up thereof.
2. If the Contractor shall be dissatisfied by reason of any decision of Architect's
Representative, he shall be entitled to refer the matter to Architect who shall
thereupon confirm, reverse or vary such decision.
The contractor shall on the written request of Architect's representative on the site
immediately dismiss from the works any person employed by him there on who
may in the opinion of the Architect be incompetent or misconduct himself and
such person shall not again be employed on the works without the written
permission of the Architect.
B OWNERS REPRESENTATIVE :
Owners representatives shall be responsible to instruct all the works, materials, checking
and measuring time and materials. He shall have power to give notice to the contractor or
to his representative of non-approval of any work or materials and such work shall be
suspended or the use of such materials shall be discontinued until the decision of the
Architect is obtained.
The Contractor shall assist in any work to be carried out by the owners representative.
29. ACCESS TO WORK :
The Contractors shall at all times give access to authorized representative of the local or
other authorities or any men directly employed by the owner or other agencies or the
consultants and their representatives.
30. SUB-CONTRACTORS :
30.1 CO-ORDINATION:
The Contractor shall be responsible for the Co- ordination of all the work including that of other
sub-contractors and nominated sub-contractors or any other agencies deployed by the owner &
working on the site for arranging runs of all services and working to the requirements and
layouts of the specialist trades, in all matters necessary for the complete execution of the work.
30.2 Rates quoted by the Contractor shall be inclusive of all attendance on sub-contractors or
other contractors nominated by the Architect/Owner. Contractor must allow for provision
of the use of his scaffolding to sub-contractors and for its retention until such time that all
relevant sub-contract works are completed.
44
30.3 The Contractor shall accept liability for and bear the cost of the supply of all necessary
water, electricity, lighting, security, etc, for the sub-contractors work.
30.4 The contractor must allow in his rates for making good any holes and chases left by the
sub-contractors or other contractors nominated by the Architect before the Contractor's
work is completed and handed over.
30.5 Contractor may appoint a Sub-Contractor if required at his cost after taking prior written
approval from the Architect. The owner shall not be responsible for any liabilities
towards such sub-contractors.
31. WORK COMPLETION : The whole work including all extra and additional items is to be completed in the
completion period stated in the Appendix to conditions of contract and the Contractor
will be required, if necessary to work overtime to fulfill the Architect's instruction to
complete the work by the Contract date. No extra will be allowed on the Contract Sum,
for such overtime work. If part premises are occupied by the owners, contractor shall
provide necessary barricades to ensure that further construction activity does not hamper
and nuisance does not happen in the occupied area.
32. MEASURMENTS :
32.1 The contractor or his representative shall accompany the Site Engineer when required to
do so and assist in taking the measurements and shall agree to the measurements
recorded on the spot.
32.2 If the Contractor fails to accompany the Site Engineer or any other person that has been
duly authorized by the Architect to take measurements then in such a case, the
measurements recorded by the Site Engineer or Architect's representative shall be
binding on the Contractor.
32.3 All measuring tapes shall be of steel and scaffolding and ladders that may be required
for taking measurements shall be supplied by the Contractor at his expense,
Measurements of all items of work including extra items, if any, such as work in
foundations including excavations, plinth filling, masonry concrete etc, steel in all R.C.C
works, pipe to be encased etc. shall be got recorded from the authorized Site Engineer by
the Contractor before they are covered up. Immediately the work is ready for
measurements, Contractor will give specific notice to Architect and Site Engineer for
recording the measurements. If the Site Engineer fails to record the measurements, the
Contractor will refer the matter to the Architect for instructions but in no case shall cover
up the work without his permission.
The measurements for any item shall be as per IS 1200.
The contractor shall provide necessary access and assistant to verify the measurement by
the owner / Architects / ENGINEER INCHARGE.
45
33. EXTRA WORK & CLAIMS:
It must be clearly understood that the whole of the conditions and specifications are
intended to be strictly enforced, and that no extra charges in respect of extra work will be
allowed unless they are clearly outside the spirit and meaning of the conditions nor
unless such works shall have been ordered in writing by the Architect/Owner.
Rate Analysis must accompany every claim for Extra-work, for scrutiny and
recommendation by Architect/Owner.
No Extra work should be executed, without prior written instructions from
Architect/Owner.
The Contractor is not entitled to refuse to do any Extra-item or Exceeded-item, on the
plea of not being in the existing scope for all such works which are related to this Tender
& akin to the awarded scope.
The intent & spirit of work described is always to be reckoned with, before lodging any
Extra claim.
For extra items, mode of measurements shall be followed as per I.S. 1200.
Rates for non-tendered items of work ordered which cannot be worked out
proportionately shall be settled by the Architect & paid for accordingly by the Owner on
the basis of Actual cost of labour expended, landed cost of materials used, depreciation
charges of equipment plus 15% to cover overheads and profits.
34. MINIMUM WAGES ACT / LABOUR STATUTES : The Contractor shall pay rates of Wages and observe hours of work and conditions of
employment according to existing rules under Minimum Wages Act. Further, it shall be
Contractor's responsibility to ensure that he pays his workmen wages which are not lower
than the minimum prescribed by the Union Government and State Government in which
area this contract is being operated. The contractor shall be responsible to pay all
statutory payments to relevant authorities towards ESI, PF etc., as per the rules in vogue
or amended by government in case of execution of the contract. Contractor shall not
employ any labourer under the age of 18 years.
36. STORAGE OF MATERIALS: The cement issued by owner shall be stored at the site in weatherproof Cement godown
built by the contractor in such a manner so as to prevent deterioration due to moisture or
intrusion of foreign matter.
The aggregate shall be stored in such a way as to prevent admixture of foreign materials.
The heaps of fine and coarse aggregates shall be kept separately. When different sizes of
fine or coarse aggregates are procured separately they shall be stored in separate stock
piles sufficiently away from each other to prevent the material at the edges of the piles
from getting intermixed.
46
Steel reinforcement shall ordinarily be stored in such a way as to avoid distortion and to
prevent deterioration and corrosion. It is a good practice to coat reinforcement with
cement wash before staking to prevent scale and rust.
All materials shall be so stored as to prevent deterioration or intrusion of foreign matter
and to ensure the preservation of their quality and fitness for the work. Any material,
which has deteriorated or has been damaged or is otherwise considered defective by the
Architect shall not be used for the concrete.
As far as possible contractor should not store the material in buffer zone area, however, if
it is needed, contractor should not disturb the existing ground, its nature, its levels etc.
the contractor should put the wooden planks or tadpatri before storing the material.
37. REINFORCED CEMENT CONCRETE (RCC) WORK
a) Ready mixed concrete ( RMC) of pumpable workability shall be used in the
work. RMC shall be designed to achieve characteristic strength required for the
RCC elements stipulated in Drawings. RMC shall be obtained from approved
manufactures like Larsen & Toubro ( L & T ), ACC, RMC Ltd etc. Admixture of
Fly Ash upto the limit of 15% ( Fifteen percent) of cementations material in RMC
is allowable provided desired strength is achievable. Concrete Pumps from the
said manufacturer shall be obtained for pumping concrete to the required height of
the building. RMC shall be designed to achieve required characteristic strength &
as per Acceptance criteria defined in IS : 456 : 2000. RMC supplied shall
conform to stipulation made in IS:4926:2003. Before placing order for Ready
Mixed Concrete, the following information shall be got approved from
ENGINEER INCHARGE.
a) Physical & Chemical properties of cement
b) Physical & Chemical properties of Fly Ash
c) Sieve Analysis of coarse & fine aggregates
d) Slump of Concrete, both at the time of dispatch at the RMC Plant & at site
when delivered –since concrete is pumpable.
e) Temperature of Concrete at delivered end.
f) Test Report of Water admixed in RMC
g) Mix Design details of RMC – especially Cement content, details of
manufacture of Cement & its cost
h) Taking cubes at site by the RMC manufactures & testing at their
Laboratories & submitting reports -This shall be done every day of supply.
i) In addition, contractor shall take cubes & test the same at site concrete
Laboratory.
47
The reports shall be obtained from RMC supplier such as material Testing requirements
etc as per Annexure B of IS:4926:2003 to ensure quality of RMC Supplied. All material
including Cement & admixture shall be procured by the Contractor & the Scope of
supply of RMC is inclusive of all materials.
a) Site Mixed Concrete
In some exigencies, site mixed concrete will be permitted to avoid loss of construction
time. In order to ensure quality of work used for site mixed concrete, the contractor shall
carry out Mix Design for concrete as per IS: 456: 2000 & the mix so designed shall be
approved by the ENGINEER INCHARGE. Fine aggregate & stone aggregates to used in
concrete shall conform to IS: 383. Fine aggregate for the concrete shall be ‘River sand’
and shall conform to zone 1 or zone 2 of IS 383.
The concrete shall be so designed as to produce grade of concrete shown in respective
drawings & shall have moderate workability of 75-90 mm slump & characteristic
strength not less than the appropriate value given in IS : 456:2000, Table 2 ‘Acceptance
Criteria’ concrete shall be as defined the IS code.
Suitable water reducing admixture shall be added in green concrete to achieve
workability without disturbing water – cement Ratio. Cement to be used for manufacture
of concrete shall be Port land Puzzolana cement (PPC)
While laying concrete for RCC work either with RMC or site mixed concrete, a bond
coat of polymer SBR of approved manufacturer viz. Sunanda, Pedilite etc. shall be
applied for bonding old concrete to new concrete. Direction for use of such Polymer
application shall be in conformity with the procedure recommended by the Manufacturer.
Contractor shall establish ‘Concrete Testing Laboratory’ at site which shall be furnished
with equipment shown in Annexure - C
For site mixed Concrete only Cement will be issued for incorporation of work, all other
materials including admixtures shall be procured by the contractor.
40. MINIMUM REQUIREMENT OF IMPLEMENTS TO BE MADE AVAILABLE BY THE CONTRACTOR AT SITE.
List of minimum requirement of implements to be made available at site by the contractor is
as below:
1. Two sets of measuring boxes each of capacity 20 Ltrs, 25 ltrs, 30 Ltrs, 40 Ltrs and 45 ltrs
shall be provided.
2. 5 liter can & 1 liter can for measuring water.
3. 2 Nos. of 200 liters capacity drums for storing water near concrete mixer.
48
4. 500 ml slotted plastic beaker for measuring construction chemicals to be admixed in
concrete.
5. 100 Kg weigh balance for cement weighing.
6. 100 Kg spring weigh balance for weighing fly ash.
7. Black board for writing concrete mix design. Details near the mixer.
8. G.I. Tray for mixing concrete / cement mortar.
9. 15 cm Cube moulds – 16 Nos with 16 mm dia tamping rod.
10. Slump cone.
11. One bucket for storing construction chemical.
12. Half round supra near mixer.
13. Necessary High level tank for storing water for concrete, rubber hose from the tank upto the
mixer and tap.
14. G.I. pan for collecting concrete.
15. Proper shed to be put up for cube curing tanks and over concrete Mixer ( to cover the mixer
hopper and concrete unloading area) & the place where cubes are filled by the Lab-
Technician.
16. Cube Kanda should be available with labours while fixing cube moulds & Set Square should
be available for checking right angle of cubes.
17. Permanent Bins with separators should be made by constructing partitions from UCR
Masonry for stacking of aggregates separately.
18. Calibrated weigh balance for weighing Cubes of 10 kg capacity with weights varying from 5
kg to 5 gram.
19. Hand pump for removing construction chemicals from drum.
41. QUALITY NORMS TO BE ADHERED DURING EXECUTION OF
CONCRETING WORK
A) Shuttering/ Scaffolding
1) Shuttering Oil should be of good quality. Motor waste oil should not be used. Excess oil
should not be applied over slab shuttering.
49
2) Staging/ Platform made for concreting of columns shall not touch to the column
shuttering to avoid disturbing the plumb / alignment of columns.
3) Damaged, distorted shuttering plates / planks shall not be used so that proper line, level
& finish of the concrete could be achieved.
4) All shuttering materials like acrow spans, props, shuttering plates etc shall be in good
working condition.
5) Masking tape (3” width) shall be affixed on the joints of the MS Plates/ Plywood
shuttering to avoid leakage of slurry during concreting.
6) Staging design required for shuttering for slabs of more heights, shall be got approved
before erecting the same. Necessary hooks in concrete at lower floors for erecting of
staging are to be provided for upper floors if required & for fixing safety nets.
7) In case of MS Plates, cleaning shall be done thoroughly so to remove old skin of
concrete, before erecting same at site. No bent plates shall be used.
B ) Reinforcement Tying
1) Top stirrups of column shall not be buried half inside the concrete & half outside. It shall be
at least 40 mm below top level of concreted column. Same is to be ensured for column
starter also.
2) Winged cover kanda shall be provided to ensure correct cover to rebar.
3) Tying of rebars shall be arranged in such a way that 60/40 mm needle of the vibrator could
go down till bottom of column concrete to ensure complete compaction.
4) Consumption of binding wires should be at least 9 Kg/MT, which shall be procured by the
contractor at his cost
5) Joggling of column reinforcement (Longitudinal steel ) shall not be done within starter. It
shall be at column portion below. Lapping for longitudinal steel & reinforcement tying at
beam –column junctions shall conform to the requirement indicated in RCC
C Concreting
1) Cement slurry with w/c ratio same as that of column/ slab concrete shall be prepared and
splashed over re-bars and at the interface of old and new concrete.
50
2) Concrete mix for RCC work shall be so designed as to achieve respective grade of concrete
as shown in RCC drawings. The concrete mix is to be designed as per clause 3.23 above.
Gunny bags shall be spread over the slab for the purpose which shall be kept continuously
wet for 24 hours by mist spray of water. After 24 hours, curing shall be done by ponding of
water for 10 days, since Puzzolona admixture is used in concrete.
3) Sequence to be followed for loading material in hopper of mixer shall be as follows:-
CA II + FA + CA I + Cement + Fly ash + CA II + FA + CA I
4) Cement bags shall be weighed periodically to ensure that 50 Kg. of cement is added for the
concrete mix and is not less.
D Good Engineering Practice
1) Chipping shall be done on the top of the columns to remove laitance before de-shuttering
which shall be done taking care that no corners of columns are damaged. Chipping shall be
done on the next day of column casting.
2) Extra vibrator shall always be kept ready as a standby, along with spare needle.
3) Date of casting shall be written on all concrete surfaces to ensure curing regime.
4) Sufficient lighting arrangements shall be done during work done at night.
5) When vertical stopper is required at construction joints, Sausages made out of empty
cement bags is kept below reinforcement to prevent slipping of concrete beyond the joint
at the time of concreting. Above the reinforcement, wooden planks shall be properly fixed
at the joint in a staggered manner, so that the joint is made in two vertical strips of 30 cm
width ( Ell shaped joints)
6) During monsoon, proper covering (pandal) shall be provided to protect from rain fresh
concrete especially over slabs.
7) Gaps between mixer blades and gap between mixer blade & drum shall not be more than
25 mm. (maximum size of aggregate) to ensure proper mixing of concrete. If necessary
mixer blades are to be modified as required by ENGINEER INCHARGE for proper
mixing of concrete.
8) Contractor shall strictly follow Safety Norms as required.
9) Contractor shall always maintain Good House Keeping at site , especially throwing
51
wooden planks with nails protruding above , cutbits of reinforcement lying scattered etc.
10) Reinforcement steel shall be stacked in raised platform to avoid contact with ground.
11) Hacking of concrete atleast at 2’’ spacing shall be done to ensure adhesion of plaster
12) Waterproofing work shall be got done through Specialized Agencies viz. India
Waterproofing CO. or Likproof
42. PROCEDURE FOR SUBMISSION OF INTERIM & FINAL BILL
The following procedure & shall be strictly followed for submission of Interim bill & the final
bill
a) Measurements shall be recorded in measurement Books jointly
b) Thereafter the same shall also be done on computer Excel Format.
c) Abstract sheet shall also be done on computer Excel Format.
d) 4 copies shall be submitted along with each bills
e) Recording of measurement shall be done in a systematic manner so that no time is lost
not only in verification of R.A. Bills but will also facilitate verification final bill early.
Measurement shall be finalized in stages.
52
SECTION - 7
STANDARD SPECIFICATION
PART I - LIST OF SPECIFICATIONS
MATERIALS :
Material used shall conform to appropriate standards specified by the Indian Standards
Institution and unless otherwise specified, these standards will form a part of these
specifications. In particular, the following standards have been referred to :
AGGREGATE :
IS : 383 : 1952 : Specifications for coarse & fine aggregates from Natural
Sources for Concrete.
IS : 383 : 1963 : -do-
IS : 515 : 1959 : Specification for natural &manufactured aggregates for use in
mass concrete.
IS : 1542 : 1960 : Specification for sand for plaster.
IS : 1607 : 1960 : Methods for dry sieving method of test for aggregates for
concrete.
IS : 2386 : 1963 : Part-I particles size and shape.
IS : 2386 : 1963 : Estimation of deleterious material Part-Inorganic impurities.
Part II
IS : 2386 : 1963 : Specific gravity, density, voids.
Part-III
IS : 2386 : 1963 : Mechanical properties.
53
Part-IV
IS : 2386 : 1963 : Soundness.
Part-V
IS : 2386 : 1963 : Measuring mortar making properties of Part-VIfine aggregates.
IS : 2386 : 1963 : Alkali aggregates reactivity.
Part-VII
IS : 2386 : 1963 : Petrographic examination.
Part-VIII
CEMENT :
IS : 269 : 1958 : Specification for ordinary rapid hardening and low heat portland
cement.
IS : 1258 : 1958 : Methods of test for determination of free lime in Portland
Cement.
IS : 1489 : 1962 : Specification for portland pozzolana cement.
IS : 455 : 1962 : Specification for portland blast furnace slag cement.
IS : 4032 : 1968 : Method of Chemical Analysis of Hydraulic cement.
CONCRETE :
IS : 1199 : 1959 : Methods of sampling and analysis of concrete.
IS : 516 : 1959 : Methods of tests for strength of concrete.
REINFORCED CONCRETE :
IS : 456 : 2000 : Code of practice for plain and reinforced concrete for general
building construction (Revised).
PRESTRESSED CONCRETE :
IS : 1345 : 1960 : Code of practice for prestressed concrete.
54
IS : 2090 : 1962 : Specifications for High Tensile bars used in prestressed concrete
STEEL IN REINFORCEMENT :
IS : 432 : 1960 : Specification for mild steel and medium tensile bars and hard
drawn steel wire for concrete reinforcement.
IS : 432 : 1966 : -do- (Part -I)
IS : 432 : 1966 : -do-
Part-II
IS : 816 : 1956 : Code of practice for use metal are welding for general
construction in mild steel.
IS : 1139 : 1966 : Specification for hot rolled mild steel and medium tensile steel
deformed bars for concrete reinforcement.
IS : 1566 : 1961 : Specification for hard drawn steel wire fabric for concrete
reinforcement.
IS : 1785 : 1967 : Specification for plain hard drawn.
Part -II
IS : 1786 : 1966 : Specification for cold twisted steel bars for concrete
reinforcement (Revised).
IS : 1786 : 1961 : Specification for cold twisted steel bars for concrete
reinforcement.
MISCELLANEOUS :
IS : 1200 : 1962 : Mode of measurement of buildings.
IS : 1255 : 1958 : Code of building by-laws.
IS : 1020 : 1957 : Conversion tables on ordinary
IS : 1256 : 1967 : Code of practice for building
IS : 1200 : 1968 : Method of measurement of building Civil Engineering work
(Part) concrete works -2nd revision.
55
Signature of the Contractor Signature of the Employer
Place : Place :
Date : Date :
56
STANDARD SPECIFICATIONS
PART II - MATERIALS AND WORKMANSHIP :
01 GENERAL :
All materials brought on the site of works and meant to be used in the same, shall be the best of their
respective kinds and to the approval of the Architect. The architect or his representative will accept
that the material are really the best of their kinds, when it is approved beyond doubt that no better
materials of the particular kind in question are available in the market.
02 SAMPLES : a) Samples of all materials shall be got approved by the Architect and shall be deposited
with him before the order for the materials is placed with the supplier. The materials
brought on the works shall confirm in every respect to the respective approved samples.
b) Contractors shall make one mock up for Clean Room & other lab after discussing with
the owner / Architect for approval.
03 CHECK :
The contractors shall check each fresh consignment of materials, as it is brought on to the site
of the works, to see that they conform in all respects to the specification and/or the samples
approved by the Architect.
04 TESTING :
The architect will have the option to have any of the materials tested to find whether they are in
accordance with the specification, and the contractors will bear all expenses in that connection.
All bills vouchers and test certificate which, in the opinion of the Architect or his representatives
are necessary to convince him as to the quality of the materials or their suitability shall be
produced for his inspection on requisition.
05 REJECTION :
Any material that have not been found to conform to the specifications will be rejected
forthwith and shall be removed from the site by the contractors at their own cost.
06 STORING : The materials shall be stored or stocked on the site as directed by the Architect and if any
additional space is to be hired for this purpose, the contractors will do so at their own expense
07 PURCHASE : The Architect shall have power to cause the contractor to purchase and use such materials from
any particular source as may in his opinion be necessary for the proper execution of the work.
57
08 SPECIAL MATERIALS : Any special materials that may be required on the works which are supplied by any other
person or firm selected by the employers or by the architect on their behalf shall be taken over in
writing by the contractors for safe custody until they are required on the works when called
upon to do so by the Architect. The contractors will be responsible for all special materials or
articles which may be supplied by specialists.
09 CEMENT : a) The cement used throughout the work shall be ordinary portland cement of an approved
manufacture and shall comply in every respect with the conditions, analysis and tests laid
down in the latest I.S.S. Quick-setting cement should not be used without the special
permission of the Architect.
b) Any particular consignment of cement from which the sample has been taken shall not be
used on the works till the test certificate is received. If the cement is found no the
conform to the latest I.S.S. by the test, it will be rejected and shall be removed forthwith
from the works.
c) The Architect reserves to himself the option to have every consignment of cement
tested before use if he thinks it desirable in view of the varying qualities of the cement
used on the works from whatever cause such variance may be.
d) the cement shall be stored in a weather proof shed on dry wooden platform floor at least
a foot above ground level and an equal distance from any wall so that fee circulation of
air shall take place. The cement shall be stored in such a manner as to prevent
deterioration or contamination and to permit easy access for inspection.
e) No cement that has been kept stored for too long a period to deteriorate in quality or that
has become caked or damaged by dampness or otherwise, shall under any circumstances
be used on the works but shall be removed from the works. If cement is stored in high
stacks for a long period causing the lower layer to harden on account of pressure this so
called "Warehouse set" shall be no reason for rejection.
f) If a clogged bag of cement after dropping on a solid floor becomes thoroughly reduced to
power again the hardening shall be considered "warehouse set". Whether the hardening is
caused by dampness or by "warehouse set", shall be decided by the Architect.
10 CEMENT MORTAR :
a. The cement mortar shall be in the exact proportion of the mix as specified for that
particular item of work in the schedule of quantities and rates. The cement and sand to be
used for cement mortar shall be carefully gauged in suitable sized boxes thoroughly
mixed in a dry state on a clean wooden platform or masonry plastered over specially
constructed for the purpose by the contractor as instructed by the Architect, and mixed
again after the addition of the requisite quantity of fresh water. It shall be prepared in
58
such quantity as can readily be used up and mortar which has partially set shall under no
circumstance be re-tempered by being mixed with additional material or water.
11 SAND :
a) The sand used shall be river or pit sand free from any clay, loan earth or vegetable matter
and shall be clean and fir for use in the opinion of the Architect or his representative. The
same shall be screened or washed in clean water if necessary as directed by the Architect
or his representative.
b) The sand used for concrete shall be of sharp, angular, grit type, and well graded and shall
pass through a sieve having meshes 3/16" square measured in the clear. Fine sand will
not under any circumstances be used for the concrete or mortar.
c) The sand for the first coat of plaster mortar shall pass through a sieve of 64 meshes per
square-inch and for the 2nd and 3rd coats of plastering, pointing etc. shall be clean, sharp
and gritty to the touch and shall pass through 324 meshes to the square-inch.
d) The sand will not contain any trace of salt or other harmful matter and it shall be tested
for its sand contents, when the architect chooses at the expenses of the contractors. The
contractors shall provide for this purpose measuring glasses dilute nitric acid, silver
nitrate solution etc. all as required by the architect or his representative. Sand containing
any trace of salt will be rejected at the option of the architect.
12 AGGREGATE :
a) The aggregate for the works shall be blue stone. It shall be obtained form sources
approved by the Architect. It shall be angular and with sharp corners and well graded and
shall have granular or crystalline (not glossy) non-powdery surfaces. The aggregate
should be clean and free from all clay or loamy admixtures or any vegetable matter and
will be gauge specified. All coarse aggregate shall be stored in the works in such a
manner as to prevent the introduction of foreign matter. If not perfectly clean and found
not to conform fully to the gauge specified it shall be washed and screened before use.
b) For all reinforced concrete work the aggregate shall pass through 3/4" gauge for no. 1
metal and 1" gauge for no.2 metal. If any rounded peddles flaky or decayed stones are
found in the aggregate the whole consignment is liable to be rejected. The architect
reserves the right to vary the gradion as stated above.
c) The grading of the aggregate will be down in accordance with the specification issued by
the concrete association of India and the said specification shall be followed in regard to
samples of test, requirements of screens, sieves etc. and as instructed by the architect. All
59
sieves, screens, etc., that may be necessary to carry out any tests as to ascertaining the
suitability of the aggregate for that particular work in hand will be provided by the
contractor at his own expense.
13 WATER :
Water shall be clean and free from oil, acid , alkali, earthy or organic matter and other
deleterious substances & generally fit for drinking, Water shall be taken from the Municipal
main. Arrangement for storing of water if necessary in drums or tanks shall be made. Due care
shall be exercised to see that water is not contaminated in any way.
14 REINFORCEMENT :
a) Unless otherwise specified in writing by the Architect all reinforcing steel used on the
works shall be Fe 500 conforming in every respect to the latest "ISI" for Fe 415/Fe 500.
b) The Architect reserves to himself the right to have any test pieces taken from the steel
that is brought to be used on the works, and tested in the recognized test house at the
contractors expenses to see whether the steel used really conforms to the latest I.S.S.
c) The steel reinforcement used for the reinforced concrete work shall be free
from any scales of rust, oil, grease, or other coating of any character which would reduce
or destroy the bond and shall be of the size and length as specified. Too many lap joints
will not be allowed and the architect or his representative will reject all such
reinforcement.
d) All other steel works shall also conform to the relevant I.S.S.
16 WORKMANSHIP
a) All works shall be of level, plumb and square, and corners, edges and arises in all cases
shall be unbroken & finished neat.
b) Any workmanship not to the satisfaction of the architect or his representative will be
rejected and the same shall be removed and replaced with works of the required standard
workmanship at no extra cost.
17 CHECKING : Skilled masteries for the respective traders shall be employed by the contractor to check the
work of the bricklayers, plasterers, joiners or any other tradesmen as the work is in progress and
to instruct and extract the right kind of workmanship from the men employed on the works.
Instructions given to such masteries by the architect or his representative shall be carried out
with a view to get the works executed in a neat and workmanlike manner, according to these
specifications.
60
18 TESTING : The architect may order the testing of any finished work as he chooses and in a manner he
decides and the contractor shall bear all expenses in that connection. If the results of such tests
prove that the workmanship is not of the standard required, the total work will be rejected and
removed forthwith and be replaced by the works of the acceptable standard of quality.
Read and confirmed as above
Signature of the Contractor
61
PART III - STRUCTURAL / CONCRETE WORK
01 GENERAL :
a) All concrete work shall be done as per the drawings and the instruction of supervising
officer.
b) Concrete work shall be carried out under the direct supervision of capable foreman,
experienced in reinforced concrete construction. The clerk-of-works shall watch and
supervise all stages of the work. No concrete shall be prepared or placed in the absence
of the clerk-of-works.
c) The proportioning of ingredients for concrete shall be such as to ensure that the resultant
concrete will be sound, dense, durable and of the strength and have the other properties
as specified.
d) All concrete should be machine mixed and vibrated immediately after placing in the
position.
2 MATERIALS :
a) AGGREGATES: All aggregates shall conform to IS : 383-1970. The maximum size of
coarse aggregate should be as large as possible within the limits specified but restricted
to one fourths of the minimum thickness of the member or such that the concrete can be
placed without difficulty so as to surround all reinforcement thoroughly and fill the
corner of the form. Fine aggregates shall be natural sand free from salt, dust and other
impurities. 25% of the total requirement of the sand can be replaced by stone dust with
the approval of Engineer-in-charge.
b) WATER : Water used for both mixing and curing shall be free from injurious amounts
of deleterious materials. Potable water will be considered satisfactory for mixing and
curing concrete.
c) ADMIXTURES : Admixtures may be used in concrete only with the approval of the
ENGINEER-IN-CHARGE based upon evidence that with the passage of time neither the
compressive strength of concrete is impaired nor other requisite qualities of concrete and
steel impaired by the use of such admixture. Calcium chloride or any other corrosive
admixture should not be used.
d) REINFORCEMENT : The reinforcement shall be (a) Fe415/Fe 500 and medium
tensile steel bars and hard drawn steel wire conforming to IS : 432-1979 (b) Cold twisted
bars conforming to IS : 1786-1979. All reinforcement shall be cleaned and free from
62
loose mill scales, dust, loose rust and coats of paints, oil or other coatings which may
destroy or reduce bond. Welded joints in reinforcement may be used but in all cases of
important connections, tests shall be made to prove that the joints have atleast full
strength of bars connected. Welding of reinforcement shall be done in accordance with
the recommendations of relevant Indian Standard for welding of mild steel bars used in
reinforced concrete construction.
03 TESTS :
Appropriate tests as per codal requirement are required to ascertain that the materials used in
Construction conform to these specifications. Wherever there is a change in size or proportion
of materials tests should be carried out for materials. It is to be noted that cement is stored for
more than three months or is affected by moisture, it shall be tested before use.
04 WORKMANSHIP – FIXING OF REINFORCEMENT:
a) The contractor shall assemble all reinforcement in accordance with the drawings by
binding wire. Cover shall be maintained by the proper use of chairs, spacers or non-
porous concrete blocks.
b) A steel fixer shall be in attendance during concreting to rectify any unavoidable
displacement as the concrete is placed.
c) Column starter bars shall be held accurately in position with suitable template. Placement
of reinforcement alongside with the concreting shall not be permitted.
d) Where splices are provided in the reinforcement they shall be away from the sections of
maximum stress and shall be staggered. For compression members such as columns the
splice shall be at floor level unless mentioned otherwise. Lap strength shall be provided
as follows - compression member : 40 x dia of bar-tension member : 60 x dia of bar or as
directed by the structural consultants.
05 - WORKMANSHIP - FORMWORK :
a) The responsibility for the safety and adequacy of the formwork shall rest entirely
with the contractor.
b) The Contractor shall give 24 hours minimum notice when formwork is ready for
inspection and allow a sufficient time for inspection and adjustment.
c) The ENGINEER-IN-CHARGE may reject formwork which in his opinion is
unsatisfactory either in construction or finish but this shall in no way diminish or
relieve the contractors responsibility.
d) Form linings shall be such as to produce concrete to the shapes, lines, levels and
dimensions required by the contract drawings and with the surface finish and
63
within the tolerance specified. Form lining joints shall be kept to a minimum.
Lining edges shall be smooth even and tightly butted and sealed with water
proofed sensitive tape.
e) Form work shall be constructed from sound material, properly supported and
braced or tied so as to maintain the true position and shape of form linings during
and after the placing of the concrete.
f) M S Tabular vertical supports shall be sufficient in number and shall be
wedged or adjustable to allow lowering of form work before stripping and shall
have sole plates of adequate bearing area to prevent any settlement after loading.
g) The contractor shall remove all debris from the interior of form lining before
concrete is placed. The surface which are to be in contact with concrete shall be
cleaned and wetted or treated with an approved form releasing agent before
placing reinforcement.
06 - WORKMANSHIP - DESIGNED MIX CONCRETE :
a) Concrete mixes for various specified characteristic strength shall be worked out by the
contractor by any of the recognized methods of design concrete grades 15, 20, 25, 30
shall be comprised of not less than 270 kg. 350 kg. 400 kg. and 450 kg. of cement per
cu.m. of concrete respectively. Maximum aggregate size shall not exceed 20 mm.
b) The water cement ratio and the proportions by weight of fine to coarse aggregate and of
cement of aggregate shall be such that the concrete produced is homogeneous free from
voids watertight and of maximum density consistent with proper workability. Both
possible to minimize shrinkage. Six preliminary laboratory cubes shall be made and
tested for each mix and shall have a mean 28 days cube strength of not less than 25 N/m.
Sq.mtrs., 30 N/m. Sq.mtrs., 35 N/m. Sq.mtrs. & 40 N/m/ Sq.mtrs. for concrete grades 15,
20, 25, and 30 This is based on standard deviation of +/- 5%
c) Full information regarding the materials their sources and mix design shall be forwarded
to the consultant for his approval before placing concrete on site. However it shall be
clearly understood that such approval shall not absolve the contractor of his
responsibility for compliance of works test results.
d) All designed mix concrete shall be prepared by weigh- batching.
e) If the design mix concrete cannot be used nominal mix may be use in compliance with IS
: 456-1978. Concrete mixed in the proportion stated would have compressive strength at
28 days after placing not less than the following :
07 - WORKMANSHIP - CONCRETE MIXING : Concrete shall be mixed in a mechanical mixer. The mixer should comply with IS : 1791-
1968. The mixing shall be continued until there is a uniform in colour and consistency.
Maximum time for mixing shall be 2 min. The mixer shall at all times be kept free from set or
partially set concrete.
64
08 - WORKMANSHIP - CONCRETE PLACING :
a) All concrete shall be placed under the direct supervision of a engineer-in-charge. All
concrete shall be vibrated with mechanical or electrical vibrators.
b) The contractor shall maintain on the site one spare mechanical vibrators over and above
those in use.
c) Concrete shall not be placed at any time under conditions which would prevent the
standard of concrete required from being attained.
d) Concrete shall be conveyed to final position and deposited in formwork by methods
which will prevent segregation or loss of materials. For high-rise building concrete shall
be transported at higher level by mechanical hoisting. In thin walls or columns over 1200
mm. high concrete shall be purred through enclosed chutes kept as vertical as possible
during placing.
e) Concrete shall be deposited continuously in such a manner so as to maintain a wet edge.
Uncompleted edges shall not be left for longer than 30 min.
f) Construction joints shall be formed where indicated and to detail on Structural
Engineering Drawings. Where it is necessary to form construction joints other than those
indicated their location shall be to the approval of engineer-in-charge.
g) Hardened concrete surface shall be kept ready to receive fresh concrete by cleaning to
remove all loose or soft materials, foreign matter and laitance and roughened for key.
Immediately before depositing fresh concrete a coat of neat cement slurry shall be
applied to the surface. Concrete shall be deposited before the slurry dries out.
h) Immediately after depositing the concrete shall be compacted by means of a mechanical
vibrator (having not less than 6000 vibrations per min.) carefully worked around the
reinforcement and embedded fixtures etc.
i) The coarse aggregate shall be worked back from the forms so as to bring a full surface of
mortar against the form without the formation of excessive surface voids.
J) The compaction shall be such that all air or stone pockets which may cause honey
combing, pitting or places of weakness are eliminated.
65
09 - CUBE TESTS :
a) The contractor shall ensure that the crushing of the concrete when tested within twenty-
eight days after mixing in accordance with IS : 156-1959 shall not be less than that
specified in the drawings.
b) The crushing strength of the concrete used in the works shall be determined by means of
works cube tests which shall be taken from samples as before specified and tested in
accordance with the procedure laid down in IS :516 and complete records relating to the
samples and test cubes shall be made by the contractor in accordance with this
specification. A slump test shall be carried out on each sample. The works test cubes
shall be of 150 mm std. size and shall be made in batches of four from each selected
concrete sample. Two cubes from each set of four shall be tested at seven days and two at
twenty-eight days. Each cube shall be marked with the date of casting and a reference
number from which its position of origin in the works can be clearly identified.
c) The crushing strength of work cubes tested at seven days after mixing shall be not less
than two-thirds of the required crushing strength of the concrete at twenty-eight days
shall however be accepted as true works cube strengths at twenty -eight days. The
crushing strength of the works test cubes at 28 days shall be not less than the specified
minimum crushing strength of the corresponding grade of concrete. If the results of tests
show crushing strength less than those specified all concrete work may be stopped by the
consultant. The contractor may be required to cut out and re-execute or otherwise rectify
to the satisfaction of engineer-in-charge at his own expenses any work failing to comply
with this specification.
d) Concreting shall not proceed until the engineer-in-charge is satisfied that all necessary
remedial measures have been taken to ensure that the specified strength of the concrete
will be consistently attained. All such remedial measures shall be at the contractors
expenses.
THE CONTRACTOR SHALL : a) In addition to testing of concrete cubes at the site Laboratory set up by the Contractor, he
shall at his own expenses supply concrete for test specimen, provide cubes and cylinders,
labours and materials required in preparing the test specimens for testing at external
Laboratory chosen by Owner.
b) He shall also pay for all costs and charges involved in dispatching the test specimens to
the said external testing laboratory.
c) He shall pay for all fees charged by the external Testing Laboratory for testing and
issuing of certificates.
66
STANDARD SPECIFICATIONS
PART IV - PREAMBLES
SECTION A : EARTH WORK
Rates for respective items shall include for these specifications
1. Existing ground levels shall be taken jointly and recorded before commencing the excavation
work. Depth of excavation in cutting shall be computed from these spot levels. For pits at least
five spot levels shall be recorded, four at the corners and one at the centre of the pit. Average of
these five readings shall be taken as the average ground level for the pit. For trenches, spot
levels spaced at every 1.500 metre centres along the centre line of the trench shall be taken as
the average ground level for the sectional lengths of the trenches.
2. Bottom width for excavation shall be measured as given in the foundation drawings and details
showing the width of bedding concrete only and hence side clearance if any will not be
measured separately. The contractor shall cover for this in his rates.
3. Battering of benching of excavation sides if required to be done shall not be measured
separately, that is the sides of excavation shall be treated as vertical for computing the quantity o
excavation. Contractor should cover for this in his rates
4. The following shall not be measured and the allowance for the same shall be made by the
Contractor
I Setting out of work and site clearance removal of shrubs etc.
Ii Excavation for insertion of planking and strutting.
Iii Removal of slips or falls in excavation due to any reason
whatsoever.
Iv Forming steps in the sides of excavation and their removal.
v Bailing or pumping out water in excavation from rains, springs,
underground water sources, underground pipe lines, etc., for keeping it dry
during excavation and construction upto ground level.
Vi Refilling the excavated materials in all sides of foundations and filling on
top of foundations upto required level including consolidation by ramming
and watering.
67
Vii Carting away of excavated materials if ordered to be removed away from
site (excavated materials will be given free of cost to the Contractor for
this purpose).
Viii Stacking of excavated materials within site as directed.
5 Where individual boulders of any kind of rock are found in the soil and which can
be separated from the parent matrix by crow bars without breaking the boulders
such boulders shall be removed from the excavation and stacked separately on site
within a lead of 1.50 feet as directed. Removal of such individual boulders from
the excavation shall not be paid for separately and therefore will be considered
only as the excavation in "any kind of soil" and not as the excavation in any kind
of rock.
6 a) Where ordinary rock and hard rock are mixed, the two kinds of rocks shall
be stacked separately on even and level ground and measured in stacks. The net
measurement of the two kinds of rocks shall be arrived at by applying deduction
at 40% (forty percent) for voids. If the total of the net measurement of two kinds
of rock exceeds the measurement of mixture assessed by means of cross sectional
measurement then the volume of mixture shall be apportioned in the proportion of
the net measurements of two kinds of rock.
b) Where soil, ordinary rock and hard rock are mixed the ordinary rock and
hard rock shall be stacked separately and measured in stacks and their net
quantities determined as mentioned in 6 (a) above.
The measurement of the soil shall then be arrived at by deducting the net
measurement of rock from the total measurement of cutting.
7 Deductions in the case of fills :
Deductions in the case of fills shall be made as follows :
a) Ten percent deductions shall be made from actual measured cubic contents in all
cases of consolidated fills to arrive at net cubic measurements, except where the
consolidations is done by heavy mechanical machinery, in which case the
deduction shall be five percent.
b) No deduction shall be made in the case of consolidated fills in confined situations
like plinth filling below floors.
8 All excavated materials will be the property of the Owner.
68
9 If the excavated materials, rock, etc., obtained from the excavation are allowed to
be used in the work, the Contractor shall pay to the Owner at the market rate the
cost of such materials, unless otherwise mentioned "Free of Cost to the
Contractor" in particular items.
10 All kinds of fillings and re-fillings in the sides of foundations, in pits, trenches,
plinth etc., and the fillings shall be thoroughly consolidated layer by layer (not
exceeding 200m thick) ramming with heavy cast iron rammers with optimum
moisture in soil and watering upto saturation.
11 Work of pre-construction anti-termite treatment should be carried out through
renowned agency and member of Pest Control Association with guarantee period
of 10 years.
The name of the Pest Control agency proposed for pre-constructional anti-termite
treatment, should be mentioned.
12 Particular attention of the Contractor is drawn to the thorough consolidation in
layers required in back filling in sides and top of foundations within the building
area, as the heights of fillings further required on top of low lying areas in the plot
range upto 3.0 m underneath the plinth area of the building. Item (9) of Section
'K': "Work Outside the Building " deal with the filling and consolidation in the
plot area underneath the plinth as well as in areas outside the plinth.
69
SECTION "B" : R.C.C. WORK
(Concrete plain and reinforced, Form work, Reinforcement, Structural Steel Work)
PREAMBLES : Rates for respective items shall include for these additional specifications.
1 1.01 Specifications to be followed for items of concrete work, Reinforced
cement concrete work, prestressed concrete work shall be the specifications for
these work as enclosed with the tender. These specifications and specific
provisions in the wordings of the items in the schedule of quantities shall be
precedence over relevant ISI specifications.
1.02 However relevant I.S.I. specifications shall be followed if not covered by the
specifications stated in para 1.01 above.
2 All RCC work shall be executed in strict accordance with the instructions, drawings and
details forwarded for the work by the Architect.
3 The rate of RCC items shall include for all labour, material, binding wire 18 Gauge
equipment gangways required, tools and all the operations, involved but shall exclude
Form Work and reinforcement, which shall be measured and paid for separately.
4 Rates quoted for reinforcement bars shall include for providing cutting and bending of
reinforcement bars in any size and shape and placing in any position as per the detailed
drawings including providing precast cement concrete cover blocks of required thickness
for keeping reinforcement bars in position. Cutting and bar bending schedule should be
submitted by the Contractor for reinforcement steel. Binding wire for tying of
reinforcement, shall be 18 gauge and shall be provided by the Contractor, but will not be
measured and hence will not be paid. The Contractor should cover for this in his overall
rate for the reinforcement bars. Spacer bars, pins, chairs, etc., required for keeping the
reinforcement bars in position shall be provided by the Contractor and the same will be
measured for payment.
5 Rates quoted for Form Work shall include shuttering, centering, propping, bracing,
tightening with nuts and bolts staging, providing camber etc. Form Work shall be
measured for the area actually in contact with in-sit concrete laid. Lapping of form work
with previously laid and set concrete will not be measured and will not be paid for Form
Work design should be submitted by the Contractor for approval of the R.C.C.
Consultants. Shuttering made from new plywood will be allowed for use upto nine
repetitions only.
6. Items given in the schedule of this section applies to all positions and in all floors and at
all heights-lift or materials will not form any criteria for extra payment.
70
7. Minimum cement content per cubic meter of cement concrete has been specified in each
item of cement work. However, if extra cement is required to be used so as to obtain the
minimum strength specified for the grade of cement concrete the Contractor will not be
paid for extra cement used.
71
SECTION 8
SAFETY SPECIFICATION
INTRODUCTION
This specification provides amplification of certain aspects of safety procedures and
requirements covered within the General conditions of contract.
1 SCOPE
The requirements of this specifications shall apply equally to Contractors and Sub-Contractors.
Where the word "Contractor" is used this shall be taken to include "Sub-Contractors".
Contractors shall be responsible for ensuring that their Sub-Contractors are notified of and
comply with these requirements.
2 REQUIREMENTS
Throughout the course of the Contract the Contractor shall assure and demonstrate to the
Engineers Representative on site that he has suitable and sufficient knowledge, experience,
procedures and resources to carry out the works safely. The contractor shall demonstrate that his
employees are suitably trained in the above procedures and are aware of potential hazards.
2.1 Personal Protective Equipment
The Contractor shall ensure that the following items of personal protective equipment are
available to all his employees :
a Safety helmets (to BS 5240)
b Safety footwear (to BS 1870) (+over protection where required).
c Overalls (Either disposable or with suitable laundry arrangements)
d Light eye protection (to BS 2092 "General Purpose")
e Safety goggles (to BS 2092 "Grade 1")
f Hearing Protectors (to BS 6344)
g Appropriate Protective Gloves.
h Safety Belts
The Contractor shall ensure that safety helmets, safety footwear, Safety Belts overalls and light
eye protection are worn by all his employees at all times whilst on the site.
Deviation from the above requirements shall only be permitted with the prior written agreement
of the Construction site Manager responsible for the site in question.
72
The Contractor shall further ensure that safety goggles, hearing protectors and protective
gloves are worn in areas where such protection is a statutory requirement, a plant
requirement or where it is judged that the risk of injury during the execution of a
construction task would be reduced.
The Contractor shall list in A.1 of this specification any other personal protective
clothing that he shall provide which is a trade requirement and any specialized personal
protective equipment he deems necessary to execute the work safely.
3 Control of Hazards to Others
Where the work activities of the Contractor produce risk to others, the Contractors shall
take all reasonably practicable, steps to remove the hazard. Where this is not possible, the
Contractor shall list in A.2 of this specification those arrangements he shall make to
minimize the risks arising from such hazard, for example, erection of protective screens
and barriers or location of the area.
4 Contract Safety Plan
The Contractor shall provide in A.3 of this specification a safety plan for the Contract
which is based on his Company’s safety policy. If the contractor is registered with the
construction Groups Safety Award Scheme, his safety plan may be related to his safety
action plan.
5 Cleanliness of the Site and contractor establishment.
Knowing the work content and the consequent debris produced, the contractor shall
unless otherwise instructed by the Engineers Representative on site :
a) Establish, at strategic points, suitable rubbish bags and/or bins, ensure
their correct use and arrange for the removal and disposal of the same.
b) State the frequency and method of site and Contractors establishment
cleaning in A.4 of this specification.
c) Provide for the safe stacking and storage of materials, fuel and consumables.
73
SECTION 9
SAFETY INSTRUCTION
A. Contractor's Barricades :
Contractor shall erect and maintain barricades required in connection with his operation
to guard or protect.
(a) Excavations and blasting work (if permitted by the Owner) (necessary permission
for
blasting to be taken by contractor from local authorities)
(b) Hoisting areas.
(c) Areas adjudged hazardous by Contractor or Owner's inspectors
(d) Owner's existing property subject to damage by Contractor's operations.
(e) Road unloading spots if provided.
Contractor's employees and those of its sub-contractors shall become acquainted with
barricading practice and shall respect the provisions thereof.
Barricades and hazardous areas adjacent to, but not located, in normal routes of travel
shall be marked by red flasher lanterns at nights.
B. Excavation and Trenching :
All trenches 1.2 metres or more in depth, shall at all times be supplied with at least one ladder
for each 50 metres length or fraction thereof. Ladder shall be extended from bottom of the
trench to atleast 1 metre above the surface of the ground. The sides of the trenches which are 1.5
metres in depth shall be stepped back to give suitable slope or securely held by timber bracing,
so as to avoid the danger of sides to collapse. The excavated materials shall not be placed within
1.5 metres of the edge of the trench or half of the trench width whichever is more. Cutting shall
be done from top to bottom. Under no circumstances undermining or under cutting shall be
done.
C. Demolition : Before any demolition work is commenced and also during the progress of the work
(a) All roads and open areas adjacent to the work site shall either be closed or
suitably protected.
(b) No electric cable or apparatus which is liable to be a source of danger shall
remain electrically charged.
(c) All practical steps shall be taken to prevent danger to persons employed from
risks of fire or explosion or flooding. No floor, roof or other part of the building
shall be so overloaded with debris or materials as to render it unsafe.
74
D. All necessary personal safety equipment as considered adequate by the Architect, should
be kept available for the use of persons employed on the site and maintained in condition
suitable for immediate use, and the Contractor shall take adequate steps to ensure proper
use of equipment by those concerned.
(a) Workers employed on mixing asphaltic material, cement and lime mortars shall
be provided with protective footwear and protective gloves.
(b) Those engaged in white washing and mixing or stacking of cement bags or any
materials which are injurious to the eyes shall be provided with protective
goggles.
(c) Those engaged in welding and cutting works shall be provided with protective
face and eye-shields, hand gloves etc.
(d) Stone breakers shall be provided with protective goggles and protective clothing
and seated at sufficiently safe intervals.
(e) When workers are employed in sewers and manholes, which are in use, the
contractor shall ensure that the manhole covers are opened and are ventilated at
least for an hour before the workers are allowed to get into the manholes, and the
manholes so opened shall be cordoned off with suitable railing and provided with
warning signals or board to prevent accident to the public.
(f) The Contractor shall not employ men below the age of 18 years and women on
the work of painting with products containing lead in any form. Wherever men
above the age of 18 years are employed on the work of lead painting, the
following precautions should be taken :-
(1) No paint containing lead or lead product shall be used except in the form of paste
or readymade paint.
(2) Suitable face masks should be supplied for use by the workers when paint is
applied in the form of spray or a surface having lead paint dry rubbed and
scrapped.
(3) Overalls shall be supplied by the Contractor to the workmen and adequate
facilities shall be provided to enable the working painters to wash them during
and on cessation of work.
E. Use of hoisting machines and tackles including their attachments, anchorage and
supports shall conform to the following standard or conditions :-
(a) These shall be of good mechanical construction, sound materials and adequate
strength and free from patent defect and shall be kept in good working order.
75
(b) Every rope used in hoisting or lowering materials or as means of suspension shall
be of durable quality and adequate strength and free from patent defects.
(c) Every crane driver or hoisting appliance operator shall be properly qualified and
no person under the age of 21 years should be in charge of any hoisting machine
including scaffolding winch or give signals to the operator.
(d) In case of every hoisting machine and of every chain ring hook, shackle swivel
and pulley block used in hoisting or lowering or as means of suspension, the safe
working load shall be ascertained by adequate means. Every hoisting machine and
all gears referred to above shall be plainly marked with the safe working load of
the conditions under which it is applicable which shall be clearly indicated. No
part of any machine or any gear referred to above in this paragraph shall be
loaded beyond the safe working load except for the purpose of testing.
F. In case of departmental machine, the safe working load shall be notified by the
Architect. As regards Contractor's machines, the Contractor shall notify the safe
working load of the machine to the Architect when ever he brings any machinery
to site of work and get it verified by the Engineer concerned.
G. Motors, gearing transmission, electric wiring, electrical gadgets and other
dangerous parts of hoisting appliances should be provided with efficient safety-
guards. Hoisting appliances should be provided with such means as to reduce to
the minimum the accidental descent of the load, adequate precautions should be
taken to reduce to the minimum the risk of any part or any part of a suspended
load becoming accidentally displaced. When workers are employed on electrical
installations which are already energized, insulating mats, wearing apparel, such
as gloves, sleeves, and boots as may be necessary should be provided. The
workers shall not wear any rings, watches and carry keys or other materials which
are good conductors of electricity.
H. All scaffolds, ladders and other safety devices mentioned or described herein
shall be maintained in safe conditions and no scaffold, ladder or equipment shall
be altered or removed while it is in use. Adequate washing facilities should be
provided at or near places of work.
I. These safety provisions should be brought to the notice of all concerned by
displaying on notice boards at a prominent places at the work site. The person
responsible for compliance of the safety code shall be named therein by the
Contractor.
J. To ensure effective enforcement of the rules and regulations relating to the safety
precautions. the arrangements made by the Contractor shall be open to inspection
by the Owner or Architect or their representatives.
76
K. There shall be maintained in a readily accessible place first aid appliance
including adequate supply of sterilized dressings and cotton wool.
L. An injured person shall be first taken to the nearest Medical Centre without loss
of time and in cases where the injury necessities hospitalization, patient should be
taken to public hospital on advice from Medical Officer.
M. Contractor shall provide safety Belts to all the workers, craftsmen, and Engineers
who are engaged in working on any external face or openings above ground floor
level. Similarly, helmets shall be provided to workers in areas where head injuries
may be expected.
N. Notwithstanding the above clauses there is nothing in these to exempt the
Contractor from the operations of any other Act or rules in force in the Republic
of India. The works throughout including any temporary works shall be carried
out in such a manner as not to interfere in any way whatsoever with the traffic on
any roads or footpaths at the site or in the vicinity thereto or any existing works
whether the property of the Owner or of a third party.
O. Government Regulations
(1) The contractor shall comply and ensure strict compliance by his employees and
subcontractor's employees, if approved, of all applicable Central and State laws
and regulations and undertake to indemnify The Institute Of Cost Accountants Of
India from and against all levies, damages, penalties and payments whatsoever as
may be imposed by reasons of any breach or violation of any law, rules.
(2) Before starting any job, please ensure that the Contractors fulfill all statutory
requirements in consultation with our Personnel Department.
(3) Contractor proposing to employ 20 or more employees shall obtain Registration
Number given by the Deputy Commissioner as a licensed contractor and submit a
copy before starting the job.
(4) All the workmen employed by the contractor, before entering the site, must be
covered under the provisions of Employees State Insurance Act, Provident Fund
Act. All entries to the site of persons/materials shall be through a system of gate
passes.
(5) The contractor shall ensure to keep and maintain all the statutory registers,
records as required under provisions of Contract Labour (R&A) Act 1970,
Minimum Wages Act and the rule made there under, Employees Provident Fund
77
Act, 1952 and keep the same available at the work site for inspection by
Company's representatives and Government authorities.
(6) The contractor, will ensure that necessary contributions towards PF are deposited
with the authorities concerned. Also all the records as per provisions of ESIS Act
are maintained.
(7) The Contractor shall be solely responsible for safety of workmen and to provide
them required personal protective equipments (safety shoes, helmets, safety belt
etc.) and shall ensure to have all his workmen properly covered under the
insurance policy for liability under Workmen Compensation Act. The Institute Of
Cost Accountants Of India will not be liable for any injury or loss of life of the
contractor's personnel.
(8) The contractor shall strictly follow the rules relating to engaging female workers
at site.
P. Safety Training of Contractor's Supervisor/PPE
Before starting the job, every supervisor of the Contractor shall undergo a safety
training conducted by the Safety Officer. The availability and use of personal protective
equipment (safety shoes and helmet etc.) will be clearly emphasized in this training.
Q. Work Clearance Certificate
(1) No job will be started without a proper clearance certificate, issued by competent
authorities and accepted by construction engineer or his nominee.
(2) A separate clearance certificate will be taken for digging/ excavation jobs, duly
signed by electrical supervisor.
(3) A separate clearance certificate will be taken for hot/ welding jobs in each area.
(4) For working at height (3 M and above), the clearance certificate will have to be
authorized by ENGINEER-IN-CHARGE before starting the job.
(5) All the clearance certificates shall be renewed next day morning on revalidation
sheet and kept available in construction office.
R. Inspection of Electrical Tools & Lifting Tackles
All the electrical tools, welding machines and cable etc. shall be offered to. for checking
before any use at site. All the lifting tackles and tools shall be brought with certificates
and offered to ENGINEER-IN-CHARGE representative for checking before any use at
site.
78
The responsibility to ensure above shall lie with Contractor.
In addition to the above, the Contractor shall abide by the Safety Code provision as per
Indian Standard Safety Code framed from time to time.
Contractor Architect
79
SECTION 10
ANTI-TERMITE TREATMENT
1. CHEMICALS: The chemicals used for the soil treatment shall be any one or a combination of the
following the concentration shown against each in aquous emulsion:
Chemicals (EC's) Concentration
Chlorpyriphos 1.0% (by weight)
2. TREATMENT OF COLUMN PITS, WALL TRENCHES AND BASEMENT
EXCAVATIONS: The bottom surface and sides (upto a height of 30 cm. from the bottom) of the excavation
made for column pits, trenches and basements shall be treated with the chemical
emulsion mentioned above at 5 litres per Sq.mtrs of surface area.
3. TREATEMENT TO BACKFILL EARTH
After the column foundations, wall foundations and retaining walls of the basement come
up, the back filling immediate contact with the foundation structure shall be treated with
the chemical emulsion at the rate of 7.5 litre/Sqm of the vertical surface of the
substructure of each side. The earth is usually returned in layers and treatment shall be
carried our in similar stages. The chemical emulsion shall be directed towards the
concrete or masonry surface of the columns and walls so that the earth in contact with
these surfaces is well treated with chemicals.
4. TREATMENT TO R.C.C. FRAMED STRUCTURES: The treatment in 2 and 3 above applies essentially to masonry foundations where there
are voids through which termites an seek entry in to the superstructure. Hence the
foundations require to be completely enveloped by a chemical barrier. In the case of
R.C.C. framed structures with columns and plinth beams and R.C.C. basements the
concrete mix is rich and dense (being 1:2:4 or M. 150 or richer), the termites are unable
to penetrate it. It is therefore unnecessary to start the treatment from the bottom of
excavation the treatment shall start at a dept of 50 cm .below ground level, except when
ground level is raised or lowered by filling or cutting after the foundations have been cast
in such cases the dept of 50 cm shall be determined from the new soil level resulting
from filling or cutting mentioned above and soil in immediate contact with the vertical
surface of RCC foundations. From this depth, the backfill around the columns, beams
and RCC basement walls shall be treated at the rate 7.5 litres Sq.mtrs. The other details
of the treatment shall be as laid down in 3 above.
5. TREATMENT TO SOIL ALONG EXTERNAL PERIMETER OF BUILDING : After the building is complete, the earth along the external perimeter of the building
should be rodded at intervals of 15 cm and to a depth of 30 cm. The rods should be
moved backward and forward, parallel to the wall to break up the earth and emulsion
80
poured along the wall at the rate of 7.5 litres per sq. m. of vertical surfaces. After the
treatment, the earth should be tamped back into place. Should the earth outside the
building be graded on completion of building, this treatment should be carried out on the
completion of such grading. In the event of filling more than 30 cm the external
perimeter shall extended to the full depth of filling up the ground level so as to ensure
continuity of the chemical barrier.
6 TREATMENT OF SOIL UNDER APRON ALONG EXTERNAL PERIMETER
OF BUILDING Top surface of the consolidated earth over which the aprom is to laid shall be treated with
chemical emulsion at the rate of 5 litres per Sq.mtrs. of the vertical surface before the
aporn laid. If consolidated earth does not allow emulsion to seep through holes upto 50 to
75 mm deep at 150 mm centres both ways may be made with 12 mm dia mild steel rod
on the surface to facilitate saturation of the soil with the chemical emulsion.
7 TREATMENT OF SOIL SURROUNDING PIPES,WASTES AND CONDUITS :
When pipes, wastes and conduits enter the soil inside the area of the foundations, the soil
surrounding the point of entry must be loosened around each such pipe, waste or conduits
for a distance of 15 cm. and upto a depth of 7.5 cm. before treatment is commenced.
When they enter the soil external to the foundations, they shall be similarly treated,
unless they stand clear of the walls of the building by about 7.5 cm. for a distance of over
30 cm.
11. TREATMENT FOR EXPANSION JOINTS
Expansion joints at ground floor level are one of the biggest hazards for termite
infestation. The soil beneath these joints should receive special attention when the
treatment under 5 is carried out. This treatment should be supplemented by treating the
expansion joints after the subgrade has been laid, at the rate of 2 litres per linear metre.
12. SPRAYING EQUIPMENT A Pressure pump shall be used to carry out spraying operations to facilitate proper
penetration of chemical into the earth.
13. The above specifications are in line the I.S. Code of practice for Antitermite Measures in
Building, IS 6313 (Part-II)-1981 (First Revision)
81
SECTION 11
SPECIFICATION FOR PILING WORK (Bored Precast RCC Piles) (R1)
(I) MATERIALS:
1. Materials shall be of the best approved quality obtainable and they shall comply with the
respective Indian Standard Specifications which are inforce during construction.
2. Samples of all materials shall be got approved before placing order and the approved
sample shall be deposited with the Site Incharge.
3. If directed, materials shall be tested in any approved testing laboratory and the test
Certificate in original shall be submitted to the Structural Engineer and the entire charges
for repeated tests, if ordered, will be borne by the Contractor.
4. It shall be obligatory for the Contractor to furnish certificate, if demanded by the Site
Incharge, from the Manufacturer or the material supplier that the work has been carried
out by using their material and as per their recommendations.
5. Unless otherwise shown on the Drawings or mentioned in the Schedule of Quantities or
Special Specifications, the quality of materials, workmanship, etc. shall be specified
hereunder.
6. All equipment and facilities for carrying field tests on materials shall be provided by the
Contractor without any extra cost.
A) CEMENT:
Cement shall comply in every respect with the requirements in the latest publication of IS:
269 and, unless otherwise specified, Portland blended cement shall be used.
The weight of ordinary Portland cement shall be taken as 1440 kg per Cu.m Cement shall be
measured by weight and in whole bags, and each undisturbed and sealed 50 kg bag being
considered equivalent to 35 liters in volume. Care should be taken to see each bag contains
full quantity of cement. When part bag is required, cement shall be taken by weight or
measured in measuring boxes.
No other make of cement, but that approved by the Structural Engineer, will be allowed on
works and the source of supply shall not be changed without approval of the Structural
Engineer in writing.
Test Certificate to show that cement is fully complying the specifications shall be submitted to
the Structural Engineer and not withstanding this, the Structural Engineer may at his
82
discretion, order that the cement brought on site and which he may consider damaged or of
doubtful quality for any reason whatsoever, shall be retested in an approved testing laboratory
and fresh certificate of its soundness shall be produced. Cement ordered for re-testing shall not
be used for any work, pending result of retest.
Cement shall be stored in waterproof shed with raised wooden flooring to prevent
deterioration by dampness or intrusion of foreign matter. It shall be stored in such a way as
allows removal and use of cement in chronological order of receipt i.e. first received being
first used. Cement deteriorated and / or clodded shall not be used on work but shall be
removed at once from the site. However allowing use of warehouse set cement shall be
determined by the Structural Engineer.
Weekly record of cement received and consumed shall be maintained by the contractor in an
approved form and submitted to the Structural Engineer.
B) FINE AGGREGATE:
Sand shall conform to IS 383 and relevant portion of IS 515. It shall pass through a IS sieve
4.75 mm (3/16 B.S.) test sieve, leaving a residue of not more than 5%. It shall be from natural
source or crushed stone screenings (if allowed), chemically inert, clean sharp, hard, durable,
well graded and free from impurities like dust, clay , shale, large pebbles, salt, organic matter,
loam or other deleterious substances. The sum of % of such deleterious materials shall be
within acceptable limits. Sand shall not contain any trace of salt and it shall be tested and
sand containing any trace of salt shall be rejected.
The fine aggregate for concrete shall be graded within limits as specified in IS 383 and the
fineness modules may range between 2.60 to 3.20.
The fine aggregate shall be stacked carefully on a clean hard dry surface so that it will not get
mixed up with deleterious foreign materials. If a such a surface is not available, a platform of
planks or corrugated iron sheets or brick floor or a thin layer of lean concrete shall be
prepared.
C) COARSE AGGREGATE: Coarse aggregate shall consist of broken stone 95% of, which shall be retained on 4.75 mm IS
test sieve. It shall be obtained from crushing Granite, Quartzite, Trap, Basalt or similar
approved stone quarry and shall conform to IS: 383 and IS :515 Coarse aggregate shall be
chemically inert when mixed with cement and shall be cubical in shape and free from soft,
tribal, thin porous, laminated or flaky pieces. It shall be free from dust and any other foreign
matter.
Gravel / Shingle of desired grading may be permitted as a substitute in part or full in plain
cement concrete if the Structural Engineer is otherwise satisfied about the quality of the
aggregate. For all RCC works the size of coarse aggregate shall be 20 mm and down gauge.
83
D) REINFORCEMENT:
Reinforcement shall be of or deformed bars conforming to IS: 1786 and IS: 1139 All finished
bars shall be free from cracks, surface flaws, laminations, jagged and important edges.
E) WATER:
Water for mixing Cement/Lime/ Surkhi mortar or concrete shall not be salty or blackish and
shall be clean, reasonably clear and free from objectionable quantities of silt and traces of oil,
acid and injurious alkali, salt , organic matter and other deleterious material which will either
weaken the mortar or concrete. Water shall be obtained from sources approved by the
Structural Engineer. Potable water is generally considered satisfactory for mixing and curing
concrete, mortar, masonry etc. Where water other than main source is used, this shall be
tested in an approved testing laboratory to establish its suitability. All charges connected
therewith shall be borne by the Contractor.
(II) CONCRETE PLAIN OR REINFORCED:
The materials, workmanship, inspection and testing of plain and reinforced concrete shall be
in accordance with IS:456 – 2000 and additionally as described in following sections and as
directed by the Structural Engineer from time to time.
(A) MIX, PROPORTION, PRODUCTION, CONTROL, TRANSPORT, PLACING
AND CURING OF CONCREATE:
The mix proportions shall be selected to ensure that the workability of fresh concrete is
suitable for the conditions of handling and placing, so that after compaction, it surrounds all
reinforcement and completely fill the formwork and when the concrete is hardened, it shall
have reached the required strength, durability and surface finish.
The determination of proportions of cement aggregates and water shall be made either with
design mix concrete or nominal mix concrete which shall be approved be approved by the
Structural Engineer. Unless otherwise specified, the concrete shall be of M-30 grade and shall
have minimum cement content as per HIL specs. Even if the strength of concrete is found to
be more during the execution of work, minimum cement content criteria shall apply. The
water cement ratio if required to be changed for the workability requirement, the same shall
be got approved by the Structural Engineer. It shall be advisable to keep the same source of
fine and coarse aggregates with constant grading of materials to keep proper control on mix
proportioning.
All the concrete shall be machine mixed and mechanically vibrated. The water cement ratio,
aggregate cement ratio, fine to coarse aggregate ratio shall be maintained as per instructions
from the Structural Engineer throughout the process of concreting.
84
The machine mixing shall be carried out for 2 minutes so as to give uniform distribution of
materials and mass in uniform in color and consistency. The fresh concrete shall be placed
before 30 minutes from mixing of the same. No hand mixing of the concrete shall be
permitted. All concrete shall be placed from maximum height of 1.2m to avoid segregation.
The honey-combed concrete shall be completely removed and replaced at the cost of the
Tenderer. The construction joints during construction shall be treated as per IS: 456-2000.
The concrete shall be cured for the period specified in IS 456.
B) SAMPLING & TESTING OF CONCRETE:
The Tenderer at his own cost shall bring on site a cub crushing strength machine, nine
number of 150” x 150” cube moulds, set of sieves, and weighing machine to check the
grading of fine and coarse aggregates, Samples from the fresh concrete being used shall be
taken and cubes shall be casted and tested in the following manner;
i) 3 cubes after 7 days
ii) 3 cubes after 28 days
In all cases the result of 28 days compressive strength specified in IS: 456-2000 shall alone
be the criteria for acceptance or rejection of the concrete. Frequency of the sampling test
strength and acceptance criteria shall be as per IS: 456-2000.
No extra payment shall be made for sampling, testing and keeping records of the same as
directed by the Structural Engineer.
D. REINFORCEMENT DETAILING & ASSEMBLY:
All the reinforcement shall be placed and maintained in position as per the structural drawing
with the help of cover blocks of specified thickness. The detailing shall be carried out strictly
as per schedules and details shown on Structural Drawings or as instructed by Structural
Engineer. No lap shall be provided without approval of the Structural Engineer. The top
holding bars shall be continuous over continuous supports. Chairs shall be provided in
sufficient numbers to hold top bars in position. No concrete shall be placed into formwork
unless the entire assembly of reinforcement detailing is completed and checked by the
Structural Engineer.
E. PRECAST BORED RCC PILES
i) Standard- The requirement of IS-2911 (part- I) shall generally apply in respect of the
piles.
ii) Plant – The tenderer shall furnish for the approval of the Structural Engineer the
details of plants and equipment which he intends to use for installation of the piles.
iii) Boring – The boring may be done by any of the approved methods found suitable for
the strata conditions prevalent on the site. The Structural Engineer shall decide the
depth at which boring should stop and the extent to which casings or Bentonite slurry
85
should be used. Distributed samples shall be collected and preserved from 5% of the
pile bores for classification as directed by the Structural Engineer.
iv) Driving – The tenderer shall get approved from the Structural Engineer the method of
driving tubes, types and weight of hammer, type of cushioning etc. No two piles shall
be driven closer than 2.5 times dia. of piles and also within 48 hours of placing of
adjacent pile. Adequate measures shall be taken to overcome detrimental effect of
ground have no piles.
v) Concreting – Concrete shall be of M-30 grade as per BOQ with minimum cement
content as per HIL. Concrete shall conform to IS 456-2000 as described in
‘CONCRETE’ part hereinbefore. The slump of concrete shall be 60 mm
Special plasticizing admixtures may be added to improve the slump without
Extra cost if approved by the Structural Engineer.
vi) Reinforcement : The cages of reinforcement shall be well wired or spot welded
to withstand handling without damage. Proper care shall be taken to maintain
Uniform specified cover. (75 mm unless otherwise shown on drawings)
And alignment of the reinforcement.
vii) Tolerances : Precautions shall be taken to maintain positional accuracy and
Strict verticality of the permissible tolerance as under:-
a) Position deviation – 75 mm at cut-off level
b) Vertically - 2 degrees
If the above tolerances are exceeded, either modification may be made in design or actual
rectification carried out, or the piles shall be entirely rejected at the discretion of the Structural
Engineer
viii) Pile Heads: The top of the piles shall be brought up sufficiently above the finishing
level to permit all laitance and weak concrete to be removed. The reinforcement in the pile
shall be sufficiently exposed to permit specified lapping in pile cap.
iv) Pile Records: The Contractor shall submit to the Engineer for his information and use
four copies of piling record for each pile. Such record shall include details as follows –
A) Structure ------------------------------- Ref. Drg.
No--------------- Pile Designation ---------------------------------
B) Pile ----------
i) Dia. Nominal------------------------------
ii) RL of ground ----------------------------------
iii) RL at bottom of pile------------------------
iv) RL at cut-off-----------------------------------
v) Grade of Concrete-----------------------
vi) Concrete volume--------------------------
vii) Reinforcement-----------------------------
C) Operation Start Complete
86
i) Boring ----------------------at ------------------------------at----------------
ii) Chiseling-----------------at--------------------------------at-------------
(Indicate weight of chisel ---------------------------------------)
D) Pile Records –
Final set ---------------------------------- (for driven piles)
Wt. Of hammer ------------------------Drop of hammer -----------------
E) Any special feature ------------------------------ obstructions
(V) LOAD TEST ON PILES:
The contractor shall submit the details of his proposal for carrying out the load test for approval
of the Structural Engineer.
(a) Non – Destructive Test : (NDT) on piles
NDT on piles may be carried out as follows:
a) Pile integrity Test - 50% of Total piles
b) Pile dynamic Test - 2% of Total piles
These Tests to be carried as per the guidance of Structural Engineer
(b) Arrangement for Test:
i) Pile to be tested shall have been cast at least 28 days before the testing unless
otherwise directed by the Structural Engineer.
ii) All the arrangement for conducting the load test including surface preparation etc.
Shall be arranged for by the Contractor at his own cost. The equipment and
instruments shall be got approved by the Structural Engineer prior to taking up the
test in hand.
iii) Load tests shall be made under the supervision of the Structural Engineer.
(c) If the tested pile does not satisfy the specified requirements of a successful and if the
failure is attributable to defective workmanship or negligence on the part of the Contractor, all
costs of the load test, the cost of providing and Installing additional piles, cost of additional or
enlarged pile caps and other work necessitated because of the defective pile shall be at the cost
of the Contractor.
87
SECTION 12
Annexure I
Contractor to Submit Along with Tender :-
1. List of similar jobs executed in the last 2 years.
2. List of Manpower Proposed to be deployed for the job.
3. List of Equipment/Machinery proposed to be deployed for the job
4. I.T Clearance certificate for the last 3 years.
5. Partnership Deed.
6. Power -of - Attorney, in favour of person signing the Bid/Contract
7. Business Turnover Details of organization for last 2 years.
8. List of Senior-Permanent Staff, in the employment of the organization.
9. Solvency Certificate from your bankers.
10. Current Order-Booking and Order-backing.
88
Annexure II
Contractor to Submit the Following Documents After Receipt of Letter of -Intent, within 15
days.
1. Proposed construction Schedule (progress chart and CPM net work) for timely
completion for acceptance by Architect.
2. Lay-out showing places for stacking construction materials, Location of cement-
Godown, Stores, Site-Office, Labour-Hutments, Temporary water-tanks, laboratory,
owners representatives office etc, so as not to foul with future permanent construction.
3. Manpower planning, month to month, of important, skilled category.
4. Site organization chart with Bio-data of site-in-charge.
5. A phased indication of requirement by you, of Owners' materials, if and as applicable,
to be issued to you on free/ chargeable basis.
6. A rough Schedule, indicating the peak Months.
7. Following Insurance-Policies, to adequately cover, as advised by Architect.
(a) Men, Machineries, equipment of project
(b) Group Personal Accident Insurance
(c) Fire/Theft/All risk
(d) Third party
(e) Complete building in all stages of construction.
8 Planning of Excavation in phases for.
89
Annexure III
Apart from other factors mentioned elsewhere in the Tender, RATES SHALL INCLUDE, the
following, unless specifically excluded from item-description,
1. All works at all height/depths, all floors and all leads within battery limit of project site.
2. Conducting tests of all construction materials, concrete, steel, aggregates, bricks etc.
3. Maintaining all records and preparing progress reports as advised.
4. Providing all necessary consumables, tools, tackles, machineries equipment, instruments,
as the job quantum/quality/urgency may demand.
5. Compliance of all local, regional, state and central laws of land, as applicable in
relation to place of work, of all authorities, having jurisdiction in the areas.
6. Compliance of standard safety-practices and fire-protection.
7. Premium for various insurance-policies.
8. Fetching water by tankers from approved sources, if situation so demands.
9. General house-keeping, cleanliness, hygienic work environment.
10. Construction of all enabling works(and dismantling after work completion and
removal of debris) including access road, cement godown, site office, labour colonies,
etc.
11 Employing only licensed workers for blasting, electrical, plumbing and similar other
works.
12. All taxes, levies, royalties, duties, octroi, etc. as may applicable during the tenure of
the Contract including sales tax.
13. Buying items from open market, for urgent works
14. Working in monsoons, Sundays, holidays, overt-time & extra shifts.
15. Barricading work areas for safety reasons and suitable displaying warning
notices/signals.
16 Setting-out of works and maintaining Bench-marks.
90
17. Satisfactory accounting of Materials issued by Owner either as Free issue or
chargeable basis. Wastage allowable for cement = 5%. For steel 3%.
18. Making, providing Cover-blocks to match with main concrete-grade.
19. Supply & application of primer coats as specified by Manufactures/Architect as per
specification.
20. Maintaining line level, slope, plumb and dimensions of all works as per
Drawing/instructions.
21. Shifting away immediately from place to work, all rejected materials and ensure its non-
use in permanent works.
22. Guarantees/ Warranties
23. Supply and fixing sleeves/conduits etc. in position and grouting as directed.
24. Liosoning with the Authorities for getting municipal connection for water, drainage,
electricity.
25. All wastage-allowance, scrap allowance, cutting allowance, variation in Rolling-Margin,
breakages etc. (Wastage of Materials, supplied by owner should be returned to owner).
26. Compliance of
a) Minimum Wages Act
b) Equal Remuneration Act
c) Contract Labour
d) Workmen's Compensation Act
e) P.F
f) E S I S
g) Labour Inspector's Regulations and other relevant and applicable Acts of the land
27. Preparation of As-Built Drawings for all Civil, Structural works.
28. Bailing out water due to seepage/leakage/broken mains/Tidal action/water table/springs
etc. & keeping work area dry at all times, till the works in contractors scope is completed
29. Producing Test Certificates for steel & other materials as required. (The test fees shall be
reimbursed to the contractor).
30. Scaffolding, Re-scaffolding, Single-stage and double-stage.
91
31. Construction of all enabling sheds like cement godown, stores, site office, Temporary
water tanks etc. & dismantle the same, on work completion remove debris as directed
and level the areas, to match with surroundings.
32. Wet materials for excavation.
33. Curing of concrete, masonry, plaster etc, including wetting the surface before plaster
coats.
34. Labour cost for reinforcement fixing in position, in half brick walls.
35. Shifting & stacking of materials, dispatched by Owner/Architect to site, pertaining to the
contractors scope of work.
36. Scaffolding work for lift-erection is included in civil-Contractor's scope.
37. Providing Chicken wire mesh on inside and outside, at all junctions of masonry and
concrete, as per specification.
38. Drawing temporary electrical/waterlines beyond the feeder provided by the owner for
equipment, lighting/captive use respectively (limited to civil work requirement).
92
Annexure IV
QUOTED RATES ONLY:
The contractor may at his option, quote Rates only, for all such items, which in his opinion are
likely to be operative, but for which rates are not specifically invited.
Soon after award of work, the Contractor will however have to back-up all such rates, by a
proper Rate-Analysis, for approval by Architect/owner and definitely before commencement of
activity.
All extra-claims are liable to be summarily rejected, for which rates are not approved in writing,
prior to work commencement.
SL Probable Extra-item Units Rate in Rate in words
No Brief Description figures
93
ANNEXURE V
LIST OF MATERIALS OF APPROVED BRAND AND/OR MANUFACTURE
Regarding use of materials of approved brand/manufacture wherever specified in the contract,
the order of preference for selection of materials of approved brand/ manufacture shall rest with
the Architect. The contractor shall obtain in writing the approval of Architect regarding this
before arranging/procuring the materials.
1. CEMENT
43 & 53 grade ordinary portland
cement
ACC, Ultratech, Gujarat Ambuja,
Birla Gold.
2 REINFORCEMENT TISCO
6 WATERPROOF CEMENT PAINTS Sandtex matt or any other brand
CEMENT PAINTS with ISI mark.
9 ANTITERMITE PCI, EXPRESS PESTICIDE,
GODREJ.
10 ANTITERMITE PAINT SOLIGNUM - BERGER PAINTS
94
SECTION 13
BASIC RATES OF MATERIALS AT SITE
SR
NO. MATERIAL UNIT
RATE
(Rs.)
1 CEMENT BAG 325.00
2 REINFORCEMENT STEEL MT 45000.00
3 SAND (NATURAL ) BRASS 8000.00
4 SAND (CRUSHED) BRASS 3500.00
95
Project Project Project Project –––– PROPOSED ICWAI BUILDINPROPOSED ICWAI BUILDINPROPOSED ICWAI BUILDINPROPOSED ICWAI BUILDING ON PLOT NO. 97, SECTOR NO.15, AT CBD BELAPUR, NAVI G ON PLOT NO. 97, SECTOR NO.15, AT CBD BELAPUR, NAVI G ON PLOT NO. 97, SECTOR NO.15, AT CBD BELAPUR, NAVI G ON PLOT NO. 97, SECTOR NO.15, AT CBD BELAPUR, NAVI MUMBAI.MUMBAI.MUMBAI.MUMBAI. BILL OF QUANTITIES FOR PILING WORK BILL OF QUANTITIES FOR PILING WORK BILL OF QUANTITIES FOR PILING WORK BILL OF QUANTITIES FOR PILING WORK (Micro Pile work) Sr.No.Sr.No.Sr.No.Sr.No. DescriptionDescriptionDescriptionDescription UnitUnitUnitUnit QntyQntyQntyQnty RateRateRateRate Amt.Amt.Amt.Amt. 1 Mobilisation charges for Micro Pile Machine including labours, hutments and allied equipments all complete. Per Rig 1 2 Boring & Constructing Cast - In - Situ bored piles in M:30M:30M:30M:30 grade concrete by using Ready Mix Concrete with Micro Micro Micro Micro Pilling rig machine, Pilling rig machine, Pilling rig machine, Pilling rig machine, setting out cardinal points, driving 4mm thickness of permanent steel casing up to non – collapsible strata, boring in overburden through whatever strata encountered up to weathered rock, all as directed by RCC Consultant & Site In Charge - in soft soil, soft weathered rock or locally encountered boulders including dewatering, placing concrete by tremie pipe method, compacting of concrete, withdrawal of steel casing, mobilization of Micro Pile Machine and other equipments, necessary personnel and erecting them etc complete. On completion of piling work, demobilizing all the equipments including cleaning and reinstating the site to original condition as acceptable by the site in charge. (Length of pile shall be measured from bottom of the pile to (Length of pile shall be measured from bottom of the pile to (Length of pile shall be measured from bottom of the pile to (Length of pile shall be measured from bottom of the pile to cut off level for payment)cut off level for payment)cut off level for payment)cut off level for payment) 300mm dia. @ 39 nos. approx.
Rm
500
3 Extra over Item no. 2 for Drilling in Hard rock up to the desired depth as per the requirement of the structural drawing. Rm 60 4 Reinforcement steel : Decoiling, straightening, cutting, bending and placing in position (Lowering) at all levels and binding with approved quality GI binding wire (18g G.I. / M.S. ) Quantity of steel as per structural drawing and including concrete cover blocks etc. complete (Only approved overlaps shall be measured and paid for) MT .
4.5 5 Removal and disposal of muck generated while piling and disposing it out of the site. L/s 6 Applying Epoxy coating to surface of permanent steel casing. Sqm 400 7 Casting of RCC coping beam with M: 30 M: 30 M: 30 M: 30 grade concrete using
96
RMC and including form work, adequate cover blocks etc. complete. Cum 5 TOTAL Note:Note:Note:Note: 1 These quantities are tentative. Any variation in quantities shall be acceptable to the contractor. 2 The rates shall be exclusive of all taxes, levies, octrai, work contract tax etc. and all statutory requirements such as labour insurance, ESIS etc. 3 The contractor shall bear the cost of water, electricity and other services required for the construction purpose. 4 Disposal of the bored muck is the responsibility of the Piling Contractor. No separate payment shall be made on this account.
97
BILL OF QUANTITIES FOR PILING WORK (BORED PRECAST PILES)
PROPOSED BLDG. ON PLOT NO.96, SECTOR 15, AT BELAPUR, NAVI MUMBAI
(By Conventional Method)
Sr.No.
Description
Quantity
Unit
Rate
Amount
1 Mobilization and demobilization of rigs with all equipment, tools tackle in good working condition.
a) For 600 dia. (4 Nos.)
1
Nos.
2 Providing, laying and fixing in position reinforcement as per RCC drawings for precast piles including cutting, bending and binding with 16 gauge MS annealed binding wire including placing of proper concrete cover/ plastic cover blocks, chair supports etc. Only as laid weight will be measured .The rate to include all cuts, chairs, and support and wastage etc.compite as specified and directed. a) High Yield Deformed Bars Grade Fe:415
1
MT
3 Providing and laying in position RCC M:30 Grade for casting of precast piles using 20 mm and down grade aggregate (unless otherwise specified) including form work, machine mixing, consolidating with mechanical vibrators, ramming with iron rods, curing, (excluding Steel reinforcement) etc. complete as directed and instructed.
a) For 600 dia. (4 Nos.)
50
R.M.
4 Applying Epoxy paint to surface of precast pile such as Nitocoat (Fosroc)
100
Sqm.
5 Taking bore of specified diameter for precast RCC piles using conventional method, including withdrawal of shell, removal of earth/ muck and disposal muck etc. complete.
a) For 600 dia. Pile (4 Nos.)
50
R.M.
6 Carrying out chiseling work in hard strata like boulders, soft and hard rock including removing and stacking the loose material etc. by conventional method
4
Cum.
98
7 Erecting the precast piles (approx. 10 to 12 m long) and placing it in required bore hole, including flushing of bore hole, etc. complete.
a) For 600 dia. Pile (4 Nos.)
4
Nos.
Sr.No
Description
Quantity
Unit
Rate
Amount
8 Providing and carrying of grouting work for the pile using cement : Quartz sand (1:1) and FOSROC Cebex 100 admixture
5
Cu.m.
9 Chipping and dressing of precast RCC piles including cleaning reinforcement and removal of dismantled material etc.
1
Cum.
10 Carrying out NDT on piles through the approved testing agency
a) Pile integrity test (4 Nos.)
4
Nos.
TOTAL FOR PILING WORK
Note 1 These quantities are tentative. Any variation in quantities shall be acceptable to the
contractor. 2 The time limit for completion shall be 45 days from the date of commencement of
work.
3 The rates shall be inclusive of cost of material, labour, tools & equipments, all taxes, levies, octrai, work contract tax etc. all statutory requirements such as labour insurance, ESIS etc.
4 The contractor shall bear the cost of water, electricity and other services required for the construction purpose.