TDC2TCC2 Réunion de chantier 7

13.12.2013In sharepoint:

https://espace.cern.ch/sba-workspace/tcc2wg/LS1%20worksite%20meeting/

Statut

• Retrait MDLV • Mise en place protection table plug-in TCSC• Manutention et stockage chambre a vide• Visite GS-CE à planifier en S51• Bilan des doses

MDLV

MDLV

Protection TCSC

Liste des ImpactsIntitule Numero Dose cumulee (uSv)

Retrait TCSC 37401 (closed) 363

Suite et remontage TCSC 38522 209

Retrait 5 aimants 37405 2369

Consolidation vide 37404 81

Survey EN-EL 39450 0

Signalisation TDC2-TCC2 39150 9

Total 3031