TDC2TCC2 Réunion de chantier 7 13.12.2013 In sharepoint: workspace/tcc2wg/LS1%20worksite%20meeting
6
TDC2TCC2 Réunion de chantier 7 13.12.2013 In sharepoint: https://espace.cern.ch/sba-worksp ace/tcc2wg/LS1%20worksite%20meeti ng/
-
Upload
tyler-morrish -
Category
Documents
-
view
216 -
download
1
Transcript of TDC2TCC2 Réunion de chantier 7 13.12.2013 In sharepoint: workspace/tcc2wg/LS1%20worksite%20meeting
TDC2TCC2 Réunion de chantier 7
13.12.2013In sharepoint:
https://espace.cern.ch/sba-workspace/tcc2wg/LS1%20worksite%20meeting/
Statut
• Retrait MDLV • Mise en place protection table plug-in TCSC• Manutention et stockage chambre a vide• Visite GS-CE à planifier en S51• Bilan des doses
MDLV
MDLV
Protection TCSC
Liste des ImpactsIntitule Numero Dose cumulee (uSv)
Retrait TCSC 37401 (closed) 363
Suite et remontage TCSC 38522 209
Retrait 5 aimants 37405 2369
Consolidation vide 37404 81
Survey EN-EL 39450 0
Signalisation TDC2-TCC2 39150 9
Total 3031