Substation CIP Change Management Program · CIP Change Control Lessons Learned ... Configuration...

Post on 09-Sep-2020

1 views 0 download

Transcript of Substation CIP Change Management Program · CIP Change Control Lessons Learned ... Configuration...

1

Substation CIP Change Management Program

SPP CIP Users Group Dawn Berndt June 2014

2

Agenda Background Substation CIP Change Management Program Challenges Lessons Learned

3

Xcel Energy Background Serves 3.4 million electric customers in 8 states Three Operating Companies

Northern States Power (NSP) Public Service Company (PSCo) Southwestern Public Service (SPS)

NERC Compliance Regions MRO (NSP) WECC (PSCo) SPP (SPS)

4

CIP Change Control Substations

78 CIP substations with 1,100 Critical Cyber Assets 16,000 work orders per year at CIP substations More than 100 change control forms processed

each year Opportunity for change control errors is large

Change Control Program continues to evolve

5

CIP Change Control Key Players

CIP Consultant

Substation Field Engineering

Project Initiator

Engineering

Operations & Maintenance

Field Technician

6

CIP Substation Change Control

Pro

ject

/Wor

k In

tiatit

edC

IP S

ubst

atio

n / C

yber

Ass

ets

7 D

AYS

23 D

AYS

CIP Consultant

Project InitiatorsSFE -Substation Field Engineering

SED – Substation Engineering DesignSCE – Substation Commissioning

EngineeringSPE – System Protection Engineering

CO&M

YesNo

Store Project Spreadsheet in

ProjectWise

CIP Sub <AND>Cyber Assets

Impacted?

Record all affected Cyber

Assets in Spreadsheet

Update CIP ESP Diagram

Done

CIP Project Spreadsheet

Change Control not needed,

inform InitiatorProcess Done

Update CIP Asset Inventory

Issue Project Spreadsheet

to field

PROJECTS Small Capital or Maintenance Large Capital Small Special O&M Install or Upgrades

Normal or Emergency Maintenance

YesCIP Project

SpreadsheetRecord device information on Spreadsheet

Perform required configuration and testing

activities

Return data to CIP

Consultant

Substation Work

Is Substation Work Complete?<OR>

Has remote connectivity been established for the first time?

Yes 7 DAYS Start

Complete Project Spreadsheet

documentation

No

CIP Substation Change ControlP

roje

ct/W

ork

Intia

tited

CIP Consultant

Project InitiatorsSFE -Substation Field Engineering

SED – Substation Engineering DesignSCE – Substation Commissioning

EngineeringSPE – System Protection Engineering

Substation O&M

YesNo

CIP Sub <AND> Cyber Assets

Impacted?

CIP Project Spreadsheet

PROJECTS Small Capital or Maintenance Large Capital Small Special O&M Install or Upgrades

Normal or Emergency Maintenance

YesCIP Project

SpreadsheetRecord device information on Spreadsheet

Perform required configuration and testing

activities

7

CIP Substation Change Control

Pro

ject

/Wor

k In

tiatit

edC

IP S

ubst

atio

n / C

yber

Ass

ets

7 D

AYS

23 D

AYS

CIP Consultant

Project InitiatorsSFE -Substation Field Engineering

SED – Substation Engineering DesignSCE – Substation Commissioning

EngineeringSPE – System Protection Engineering

Substation O&M

YesNo

Store Project Spreadsheet in

ProjectWise

CIP Sub <AND> Cyber Assets

Impacted?

Record all affected Cyber

Assets in Spreadsheet

Update CIP ESP Diagram

Done

CIP Project Spreadsheet

Change Control not needed,

inform InitiatorProcess Done

Update CIP Asset Inventory

Issue Project Spreadsheet

to field

PROJECTS Small Capital or Maintenance Large Capital Small Special O&M Install or Upgrades

Normal or Emergency Maintenance

YesCIP Project

SpreadsheetRecord device information on Spreadsheet

Perform required configuration and testing

activities

Return data to CIP

Consultant

Substation Work

Is Substation Work Complete?<OR>

Has remote connectivity been established for the first time?

Yes 7 DAYS Start

Complete Project Spreadsheet

documentation

No

C

IP S

ubst

atio

n / C

yber

Ass

ets

YesNo

Record all affected Cyber

Assets in Spreadsheet

CIP Project Spreadsheet

Change Control not needed,

inform InitiatorProcess Done

Issue Project Spreadsheet

to field

YesCIP Project

SpreadsheetRecord device information on Spreadsheet

Perform required configuration and testing

activities

Substation Work

Is Substation Work Complete?<OR>

Has remote connectivity been established for the first time?

Yes 7 DAYS Start

No

8

CIP Substation Change Control

Pro

ject

/Wor

k In

tiatit

edC

IP S

ubst

atio

n / C

yber

Ass

ets

7 D

AYS

23 D

AYS

CIP Consultant

Project InitiatorsSFE -Substation Field Engineering

SED – Substation Engineering DesignSCE – Substation Commissioning

EngineeringSPE – System Protection Engineering

Substation O&M

YesNo

Store Project Spreadsheet in

ProjectWise

CIP Sub <AND> Cyber Assets

Impacted?

Record all affected Cyber

Assets in Spreadsheet

Update CIP ESP Diagram

Done

CIP Project Spreadsheet

Change Control not needed,

inform InitiatorProcess Done

Update CIP Asset Inventory

Issue Project Spreadsheet

to field

PROJECTS Small Capital or Maintenance Large Capital Small Special O&M Install or Upgrades

Normal or Emergency Maintenance

YesCIP Project

SpreadsheetRecord device information on Spreadsheet

Perform required configuration and testing

activities

Return data to CIP

Consultant

Substation Work

Is Substation Work Complete?<OR>

Has remote connectivity been established for the first time?

Yes 7 DAYS Start

Complete Project Spreadsheet

documentation

No

C

7

DA

YS23

DA

YS

Store Project Spreadsheet in

ProjectWise

Update CIP ESP Diagram

Done

Update CIP Asset Inventory

Return data to CIP

Consultant

Yes 7 DAYS Start

Complete Project Spreadsheet

documentation

9

10

11

12

13

14

15

16

CIP Change Control Challenges

Manual change control process Rely on personnel to initiate change control for CIP substations Multiple departments required to fill out information

Depend on human performance for documentation Time Accuracy Completeness

Large number of people had access to CIP Substations Almost 25% were external parties (other utilities, contractors) Paring this list down

Training and awareness for all affected personnel on correct procedure

17

CIP Change Control Lessons Learned

Workflow automation is crucial when dealing with many touch points in CIP Substations Identify process handoffs and consider controls

Importance of ongoing training and awareness Employee turnover Contractors/Consultants Face-to-face is valuable with field resources

Implementing compliance ‘controls’ can help prevent and detect issues

18

CIP Change Control Controls Implemented

Established controls to help identify substation work requiring change control upfront Automated biweekly report to review new work orders Established process for checking CIP status on new substation

design projects Implemented manual security testing of access points Conduct bi-weekly change control meetings in each Operating

Company with Engineering, Operations and CIP Compliance groups Quarterly monitoring program Implemented tagging of disconnected device cables Installed access point “CIP notice” labels

19

CIP Change Control Improved Field Awareness

20

Port plugs and locks to prevent inadvertent connections

Technician guide for connecting and making changes to cyber assets in the Electronic Security Perimeter

Restructuring process documentation Change control awareness posters in CIP substations

CIP Change Control Controls In Development

21

Implement additional controls Asset management solution (not Excel spreadsheets) Investigate automation solutions

Change control workflow Configuration management

Evaluate viability of additional testing facilities

CIP Change Control Preparation for CIP V5

22

Questions?