STARK ST BEAVER CREEK CULVERT

Dec. 9, 2015 Open House

Agenda

Project Timeline

Current Design

Right of Way (ROW)

Construction

Questions?

Project Background Concept Plan Funding Secured – 2014

Federal Highway Administration

Multnomah County

City of Troutdale

Total Estimate ($1.177 million)

Design started – July 2014 County staff: Roadway and Structure

CH2MHILL: Geotechnical - Hydraulic

DEA: Right-of-Way acquisition

Construction: Summer 2016 County Inspectors

CH2MHILL: support

Project Plan view

Example of Culvert

ROW Impact

Construction

Detour

Pedestrian

Vehicle Mid June – Mid September

Ped/ Bike Detour

Vehicular Detour

Next Steps Receive your feedback: Today 60% Design Submittal to ODOT

ROW Process: Winter 2016 95% Design Submittal: Winter 2016 Final Design: Spring 2016 Hiring Contractor: Late Spring 2016 Preconstruction Public Outreach

(newsletter) Construction: Summer – Fall 2016

For More Information

Project website: multco.us/roads/webform/beaver-creek-culvert-replacement

Staff Contacts: Carrie Warren (503) 988-0169

Discussion & Feedback