STARK ST BEAVER CREEK CULVERT
Dec. 9, 2015 Open House
Agenda
Project Timeline
Current Design
Right of Way (ROW)
Construction
Questions?
Project Background Concept Plan Funding Secured – 2014
Federal Highway Administration
Multnomah County
City of Troutdale
Total Estimate ($1.177 million)
Design started – July 2014 County staff: Roadway and Structure
CH2MHILL: Geotechnical - Hydraulic
DEA: Right-of-Way acquisition
Construction: Summer 2016 County Inspectors
CH2MHILL: support
Project Plan view
Example of Culvert
ROW Impact
Construction
Detour
Pedestrian
Vehicle Mid June – Mid September
Ped/ Bike Detour
Vehicular Detour
Next Steps Receive your feedback: Today 60% Design Submittal to ODOT
ROW Process: Winter 2016 95% Design Submittal: Winter 2016 Final Design: Spring 2016 Hiring Contractor: Late Spring 2016 Preconstruction Public Outreach
(newsletter) Construction: Summer – Fall 2016
For More Information
Project website: multco.us/roads/webform/beaver-creek-culvert-replacement
Staff Contacts: Carrie Warren (503) 988-0169
Discussion & Feedback