Solar Power Plant Designing & PV Syst
SUNRATOR ENERGY RESEARCH INSTITUTE
www.sunratorinstitute.com
The Outline1. About Software2. Check-List of required
information from client3. Geographical Details4. Import Meteo data5. System Design6. Input Parameters7. Simulation & Results
SUNRATOR TECHNOLOGIES LLPA-314, Shivalik, New Delhi-110017
011-41605551
1. About the Software• One of the oldest software, developed by
university of Geneva.• Main features. Meteorological data analysis. Complete database of PV Modules, Inverter
and Meteo data. Import of solar radiation data from
Meteonorm, NASA and many others database.
Create your self & Import PV Modules & Solar Inverter data from Photon international.
Shadow Analysis using 3D Models. Design simulation of grid connected,
standalone. Export the data into XPS & convert into pdf.
SUNRATOR TECHNOLOGIES LLPA-314, Shivalik, New Delhi-110017
011-41605551
2. Checklist for the client
SUNRATOR TECHNOLOGIES LLPA-314, Shivalik, New Delhi-110017
011-41605551
Location Details1. Coordinates:
Latitude and longitude2. Address
Technical Details1. Type of system2. PV Module
technology3. Module Capacity4. Inverter
SUNRATOR TECHNOLOGIES LLPA-314, Shivalik, New Delhi-110017
011-41605551
3. Geographical Details
• Check Location on Google Earth
latitude (N or S) longitude (E or W)• Azimuth Angle (South reference = 0 ̊)
SUNRATOR TECHNOLOGIES LLPA-314, Shivalik, New Delhi-110017
011-41605551
4. Import Meteo Data• Irradiation, temperature, wind speed
data fetch from various meteorological database
• Follow these steps Database Click on geographical site Go to new option Choose interactive map & enter location Get geographical coordinate section & verify
details choose meteodata source Click on import in Monthly meteo section, click
on OK button & save the file
SUNRATOR TECHNOLOGIES LLPA-314, Shivalik, New Delhi-110017
011-41605551
5. System Design• The section provide you – Optimum tilt,
Estimated Energy Yield, PR & Details Losses.
• Choose Project Design Option from main menu.
• Select New project > Go to parameter & click on site & meteo for importing meteo file.
• Select Country > Scroll Up-Down Choose Meteo file from Site option which you created > OK, Project details will display on Project Designation Section.
• Go to system Variant > Choose new variant, Save the file .
SUNRATOR TECHNOLOGIES LLPA-314, Shivalik, New Delhi-110017
011-41605551
6. Input Parameter• Under this section we computing
Orientation – Optimum tilt of module for collecting maximum radiation, pitch to limit the shading losses.
• System – project capacity or area, Selection the of PV Modules & Make, Inverter Rating & Make, Series & no. of Strings Combination.
• Details losses – Thermal parameter, Ohmic Losses, Module quality-LID-Mismatch, Soiling losses.
SUNRATOR TECHNOLOGIES LLPA-314, Shivalik, New Delhi-110017
011-41605551
Orientation • Simulate optimum plane tilt w.r.t.
yearly meteo yield & pitch selection to limit shading losses.
• Follow the steps Calculating optimum plane tilt (Calculating for
fixed tilt) Default page look like i.e. Tilt 30 ̊, Azimuth 0 ̊ Select Fixed Tilted Plane in field type option > enter the latitude value & Azimuth value in field parameter > Change the plane tilt value so that Loss by respected to optimum should be 0% & correspond Global radiation on collector plane should be Maximum.
SUNRATOR TECHNOLOGIES LLPA-314, Shivalik, New Delhi-110017
011-41605551
System• What u have with ? Plant capacity or
area , Module & Inverter details.• Follow the steps Enter the planned power or available area, the
information provided by the client. Select the PV Module > Sort the module base on
power or Technology > scroll down the button, Select the Manufacturing company from the list & along with their Module type.
SUNRATOR TECHNOLOGIES LLPA-314, Shivalik, New Delhi-110017
011-41605551
Inverter Selection Pre decide the type of inverter i.e. string or
central. Go to > Select the inverter make from the list >
sort the inverter based on Power or Voltage. Inverter should be sized in such a way that under
loading & over loading (DC to AC ratio) with in acceptable range.
A message will appear on dialog box i.e. indicate if there is any error during the selection of inverter.
Go the design the array > check no of modules, modules in series & module string.
Click on OK > Proceed the next steps.
SUNRATOR TECHNOLOGIES LLPA-314, Shivalik, New Delhi-110017
011-41605551
Losses Ohmic lossesGo to DC circuit: Ohmic losses for the array > Click on loss fraction at STC > Enter the value in between 1.10% - 1.30% (these losses computed considering ohmic losses of array to string combiner box / string monitoring box and string combiner box to inverter DC input.)These losses occur to due to resistance to DC wire in the Module string to string combiner box / String monitoring box and string combiner box to inverter DC input.
SUNRATOR TECHNOLOGIES LLPA-314, Shivalik, New Delhi-110017
011-41605551
Losses AC Ohmic Wiring lossesGo to AC circuit: Inverter to injection point > Click on loss fraction at STC > Enter the value in between 0.50% - 0.80% (these losses occur at inverter output to point of injection of energy into the grid (switch yard). The losses include Ohmic losses in inverter output to LT panel , HT panel.) Transmission line losses are not included on this because it depends upon the point of injection / joint metering panel as per PPA & respective state regulation.The Voltage Drop should be below 2.1%.
SUNRATOR TECHNOLOGIES LLPA-314, Shivalik, New Delhi-110017
011-41605551
External Transformer • Go to external transformer > iron loss > enter
0.10% or enter Fixed loss of transformer if known.
• Resistive/ Inductive losses > enter 0.10%• Iron loss : are fixed losses of transformer occur
due to hyterersis and eddy current loss in the core of transformer. Silicon is used to reduce these losses.
• Ohmic/ Inductive loss: are variable losses due to resistance / Inductance of copper winding and loading of the transformer.
SUNRATOR TECHNOLOGIES LLPA-314, Shivalik, New Delhi-110017
011-41605551
Module Quality Loss Go to module quality loss section > Enter the value the according to average deviation of the module tolerance power is positive +3% then module quality loss shall be +3/2= 1.5%.
SUNRATOR TECHNOLOGIES LLPA-314, Shivalik, New Delhi-110017
011-41605551
LID Light Induced Degradation Initial degradation of solar PV module occurs in the very first hours of operation in the actual site. After certain period of time (3.4 months) the power output of the module stabilizes on the certain level compare to STC power.Typically poly C-Si Module degrade @1.0%Mono C-Si Module degrade @ 1.5% Thin film Module degrade @ 2%
SUNRATOR TECHNOLOGIES LLPA-314, Shivalik, New Delhi-110017
011-41605551
Mismatch LossThe mismatch loss is mainly due to the fact that in a string of module, the lowest current drives the current of whole string. This is due to material property of Silicon which is used for the PV module manufacturing. Now when installing real modules in the field, the characteristics of the module are never rigorously identic.Power Loss at MPP The difference between the effective operation conditions and the maximum available power plant. Foe MPP use (grid inverter) the loss is neglected in PV Syst. For fixed operating voltage, it can be quantified from the output simulation result.Go to mismatch Section > Enter the value (it typically happen at 1%) & loss when running at fixed voltage not relevant when MPPT operation (it typically limit to 1.1%)
SUNRATOR TECHNOLOGIES LLPA-314, Shivalik, New Delhi-110017
011-41605551
Soiling LossAccumulation of dirt and its effect on the system performance is an uncertainty which strongly depends on the environment of the system, raining conditions etc.
Considering the project location in Rajasthan where module are frequent face the dust/dirt/sand the soiling loss so power loss can be up to 3% and location like Karnataka/Uttarakhand the power loss can be up to 2% because of less prone to dust & dirt environment.
This power loss can be reduce by increasing the frequency of module cleaning.
7 - Simulation & Results
Simulation Execution Go to simulation & result section > Click on simulation to perform simulation of projects > Click on Simulation
SUNRATOR TECHNOLOGIES LLPA-314, Shivalik, New Delhi-110017
011-41605551
Simulation Execution This simulation shall be perform with consideration of meteo value (Hourly/Daily/Monthly)Click on step by step section > click on continue > Click on OK and to get the simulation result.
Simulation Result This section show the following details • Project title • Site Location • System type • Project Capacity • Selected Module/Make • Inverter Make/ No of inverters• Energy Generation result Energy Yield (For first year of Operation) Specific Yield (in kWh/kWp/year) Performance Ratio• Details Report section You can generated the whole result as in report analyze the simulation result save the simulation studies.
MASTER DRAWING LIST
• SITE DETAILS• REPORTS• SLD (SINGLE LINE DIAGRAM)• Array• MODULE MOUNTING STRUCTURE• MAIN CONTROL ROOM - ELECTRICAL• MAIN CONTROL ROOM - CIVIL/ STRUCTURE• INVERTER STATION - ELECTRICAL• INVERTER STATION - CIVIL/ STRUCTURE• CALCULATIONS• EXTERNAL -ELECTRICAL/FA/CCTV• EXTERNAL -CIVIL
SITE DETAILS
• Site Contour Layout• Soil Test Report
REPORTS
• Shadow Analysis Report• PV Syst Report
SLD (SINGLE LINE DIAGRAM)• AC Single line diagram• Aux. single Line diagram• DC single Line diagram• PLC architecture schematic
Array • Array layout • HT cable routing layout • DC cable routing layout • PLC cable routing layout • Lightning Protection layout • PV Array earthing layout • External Lighting layout • Foundation details for light pole drawing
MODULE MOUNTING STRUCTURE
• GA of Module Mounting Structure • Foundation drawing for Module Mounting
Structure • Array• Foundation Design Calculations for Module
Mounting Structure • G.A drawing for SMB mounting structure
MAIN CONTROL ROOM – ELECTRICAL• Main control Room Equipment Layout• Main Control Room Cable Tray & Trench Layout• Main Control Room Earthing Layout• Main Control Room Lighting & Power Layout
MAIN CONTROL ROOM - CIVIL/ STRUCTURE • Main Control Room- Architectural drawing • Main Control Room- Foundation and Column
Details • Main Control Room- Beam Details • Main Control Room- Roof Slab Details
INVERTER STATION - ELECTRICAL• Inverter Station Equipment Layout• Inverter Station Earthing Layout• Inverter Station Lighting & Power Layout
INVERTER STATION - CIVIL/ STRUCTURE• Inverter Station Architectural Details • Inverter Station Foundation Details • Inverter Station Plinth Beam Details • Inverter Station Structural Details
CALCULATIONS• AC Cable schedule • DC cable schedule• Control cable schedule • MWS Sizing calculation • Battery Charger sizing calculations • Aux. transformer sizing • HT Cable Calculation• LT cable Calculation • DC cable Calculation • Earthing calculation • LA Protection Calculation
EXTERNAL -ELECTRICAL/FA/CCTV• Main Control room - Fire alarm layout• Main Control room -CCTV layout • Light fixture catalogue • Data sheet / Catalogue for CCTV equipment • Data sheet / Catalogue for Fire alarm system
EXTERNAL -CIVIL • Main Gate Details • Module Cleaning System Layout • Transformer Yard Fence and Gate Details Drawing
• Foundation Drawing for Inverter Transformer • Foundation Drawing for Auxiliary Transformer • Civil Drawing For Road • Precast boundary wall