Scope and Field of Application
SNC Supplier quick guide for Danfoss Cooling & Danfoss Power
Solution
SAP SNC Version 7.02 1st Issue, Oct-2016
Created by Rajan Katheeravan Approved by Kumar Sivashanmugam Language: EN
This document is meant for SNC suppliers which describes the steps and procedure on how to work with
SNC Forecast, PO, ASN etc. on SNC web portal. It applies to both suppliers in Danfoss Cooling Segment
& Danfoss Power Solution.
Table of contents: 1 How do I log on? ....................................................................................................................... 1
2 General navigation in SNC. ....................................................................................................... 1
3 How do I see forecasts? ............................................................................................................. 3
3.1 How do I make a Time Bucket Profile .............................................................................. 3
3.2 How do I see forecasts? ..................................................................................................... 5
4 How is the normal order flow? .................................................................................................. 6
5 How do I see new orders and confirm them? ............................................................................ 7
5.1 What if I cannot confirm as
requested?..................................................................................8
5.2 What if I want to check the drawing number of
order?........................................................9
5.3 How do i Print an order?...............................................................................................10
6 How do I make Advance Shipping Notifications? ................................................................ 111
7 How do I make an order change, if the order is already confirmed? .................................... 113
8 How to Cancel wrong ASN and Create new ASN?.................................................................15
9 How do I logoff from SNC ?....................................................................................................17
1 How do I log on? Use the following common link for both Danfoss cooling & Danfoss power solution:
https://suppliers.danfoss.com/
The SNC logon screen comes up. Read the text regarding terms for using SNC and press logon.
When the password screen comes up, enter your user name and password and press OK – you are
in!. You can change password from this screen anytime.
2 General navigation in SNC. Quick View
Menu -> Exceptions -> Quick View. To set as standard entry screen, press the star button in the
upper left corner . When you enter SNC ‘Quick view screen’, you see 3 tabs as standard
settings done by Danfoss.
DCS & DPS SNC Supplier Quick Guide
1st Issue, Oct 2016
Microblog:
Danfoss Cooling Segment:
It is very good for message sharing between supplier and Danfoss, but as of now Danfoss cooling
segment doesn’t use it. We will come back when to start using this with proper document.
Danfoss Power Solution:
The Microblog is used to communicate short Twitter type messages of 140 characters or less
between Danfoss Power Solutions and our Suppliers. Suppliers from Danfoss power solution use
Microblog only from Danfoss side to communicate suppliers, but not used from supplier side to
respond over microblog.
Go to next tab ‘Confirmation’ where you will see Purchase orders categorized into two tables as
below. The green boxes explain the content of each part.
Third table is ‘Shipping’ as below
DCS & DPS SNC Supplier Quick Guide
1st Issue, Oct 2016
Please be aware of the “Refresh” link (here it is at the top left of the screen). SNC will only update
the screens you work on if you press this link. So if you cannot find an order or similar, you will
probably have to press the “Refresh” link. This goes for all screens in SNC.
3 How do I see forecasts? Please be aware, that forecasts in SNC represent Danfoss best guess on future requirements on
code number level. They change weekly depending on Danfoss order situation, production orders
and purchase orders. They are the “raw data” from our ERP system and can contain errors. If you
suspect the forecast is wrong, contact planner or purchaser for clarification.
Danfoss has a monthly medium term production planning process, and normally the production
forecasts are updated shortly before the 20th in each month. The purchasing forecasts will therefore
change most around this date.
The first time you log on to SNC and want to see the forecasts, you have to define exactly how
you want to see it. This is done by creating a Time Buckets Profile.
3.1 How do I make a Time Bucket Profile
Select the menu Demand – Order Forecast Monitor – Time Buckets Profile.
DCS & DPS SNC Supplier Quick Guide
1st Issue, Oct 2016
Select the menu point “Save for all my location products” (see below) – this will give the same
way of seeing forecasts for all products. Press the “Edit” button. Below screen shot, we have
provided Forecast time bucket for both DCS & DPS
Forecast Time bucket for Danfoss cooling
In Display Horizon select Months and type 0018. Danfoss will normally only show forecasts for
one year, but sometimes 18 months.
In No. of Months type “0001”. This will show the forecasts for the first month per week, and for
the rest of the months per month.
Press “Save” – and you are ready to see the forecasts.
Forecast time bucket for Danfoss Power solution
In Display Horizon select Months and type 0018. Danfoss will normally only show forecasts for
one year, but sometimes 18 months.
In No. of Months type “0003”. This will show the forecasts for the first 3 months per week, and
for the rest of the months per month.
Press “Save” – and you are ready to see the forecasts.
DCS & DPS SNC Supplier Quick Guide
1st Issue, Oct 2016
3.2 How do I see forecasts?
Select the menu Demand – Order Forecast Monitor – Order Forecast Details
In the selection area, press the “Go” button. You can now see the forecasts for all code numbers.
“Customer Planned Requirements” are the forecasts in the relevant time bucket.
“Customer Firm Requirements” are actual open orders – NOT FORECAST!
“Personalise” button at the right side above months can be used to add or remove the rows in the
DCS & DPS SNC Supplier Quick Guide
1st Issue, Oct 2016
Grid.
If you want to export the forecast to Microsoft Excel, press the button “Export” and select “Export
to Microsoft Excel”
Excel will then open with the selected data – if you have Microsoft Excel installed on your
computer.
4 How is the normal order flow in SNC ? The drawing below shows the normal order flow.
SNC always shows the current order situation. Basically the supplier see the same as the Danfoss
planner see.
Please keep the first confirmed delivery date. If this is not possible, see the chapter regarding order
changes.
Danfoss Supplier
Danfoss makes purchase
order. It is transmitted to
SNC
Supplier confirms
purchase order in SNC
Confirmation is
registered on order
Supplier ships goods
and make Advance
Shipping Notification
(ASN) in SNC
Goods are received at
Danfoss based on ASN
Supplier can see in SNC
that the goods are
received at Danfoss –
Refer document “ASN
Status_GR Status”
DCS & DPS SNC Supplier Quick Guide
1st Issue, Oct 2016
5 How do I see new orders and confirm them?
There are two option you have to confirm a Purchase order in SNC. If you use either of the way,
you will be redirected to Purchase order Worklist session. They are given below:
1. Go to Quick view screen -> Go to ‘Confirmation’ tab -> Click on the list of Pos available
in table ‘PO: Items To Be Confirmed by Change Date’ -> You will now get the PO worklist screen
to confirm the orders.
PO Worklist screen
2. Select the Menu –> Purchase order –> Purchase order worklist
The purchase order worklist will open. Before confirming an order, always make sure that you
refresh the page by clicking on ‘Refresh’ link on right bottom of the page.
Now, Confirm the order by putting a checkmark in “Cnf. Rqstd” and pressing “Save and publish”.
See below. The order is now confirmed as requested.
DCS & DPS SNC Supplier Quick Guide
1st Issue, Oct 2016
Note: In ‘PO Worklist’ screen, you have option to sort the PO in descending/ascending order
which will help you to know the no of products available for each PO as seen below. Inorder to
sort the PO, click on the column ‘PO No’.
5.1 What if I cannot confirm as requested?
Before confirming a PO, If you want to make any changes in the delivery date/Quantity of PO
then use any one of the below option. Option 1 is used when you don’t want to split the PO line
but only Quantity/Delivery date changes need to be done. Option 2 is used when you want to Split
the PO line and also changes in the Delivery date/Quantity is needed.
Option 1: Go to Menu -> Purchase Order -> PO Worklist.
Select the PO line where you want to change delivery date / quantity and these fields becomes
editable now, update new quantity or date or both and Click on ‘Save and Publish’. As the
confirmed delivery date / quantity is different than the requested one, please contact your planner
immediately to approve your confirmation. Please remember you should not check the field
‘Conf.Reqtd’ as you are not using confirming as requested by danfoss.
OPTION 2:
If you want to deliver an order on two different delivery date as you want to split the quantity then
click the link 1:0 in PO Worklist.
DCS & DPS SNC Supplier Quick Guide
1st Issue, Oct 2016
In the Confirm window press the button “Confirm” to create a new confirmation line. Edit the new
line to make your confirmation.
In the picture below the supplier can deliver 400 pieces on 2015.06.08 and the last 600 pieces on
2015.06.15. He has pressed the “Confirm” button 2 times to make 2 confirmation lines. Please be
aware, that you always have to confirm the total quantity.
To finish the confirmation press the “OK” button and then in the purchase order worklist press the
“Save and publish” button. As the confirmed delivery date / quantity is different than the
requested one, please contact your planner immediately to approve your confirmation.
5.2 What if I want to check the drawing number of an order?
For Danfoss Cooling Suppliers:
It is your responsibility as a supplier to deliver according to the correct drawing number. The
drawing number can be found by clicking the PO number.
The purchase order detail screen will then open.
DCS & DPS SNC Supplier Quick Guide
1st Issue, Oct 2016
If you click the “Notes” button, the purchase order notes window will open. Here you can see the
drawing number.
For Danfoss Power solution Supplier:
DPS Supplier can see Revision Level/Drawing No from both Purchase order details Notes as
well as on “Due list for Purchasing Document” session.
Path: Menu Delivery Receipts and Requirements Due list for Purchasing Documents.
Here you can see the Revision level on the field “Drawing / Change No”
5.3 How do I Print an order?
Use either option 1 or option 2 at your convenience to print an order.
Option 1:
Menu --> Purchase order -> Purchase order details -> Input PO no. and Click ‘GO’ then Print or
save the order
OPTION 2:
DCS & DPS SNC Supplier Quick Guide
1st Issue, Oct 2016
Go to Menu ->Purchase order -> Purchase order overview -> Input PO no and click ‘GO’ ->Click
on ‘PRINT PO’ tab to print order.
Note: These are the only places where you can print the order.
6 How do I make Advance Shipping Notifications?
Points to be noted before ASN creation:
If there is any change in order confirmation, please re-confirm / change order confirmation and
this change confirmation from supplier should be approved by Danfoss planner before creating
ASN.
ASN will be created when shipping the goods from your location, so that Danfoss
will do ‘Goods receipt’ with respect to this ASN.
ASN Creation from Quick View:
ASN can be created from Quick view by clicking on corresponding category:
Go to Shipping tab where you can see category: Due today, Due within 7 days & Due within 30 days (Marked in green color)
ASN Creation from Menu
Select the menu Delivery – Receipts and requirements – Due list for purchasing document
DCS & DPS SNC Supplier Quick Guide
1st Issue, Oct 2016
If you are not able to see the ASN to be created after selecting the above screen then refresh the
screen which is available at the right bottom of the screen.
Even if not visible then follow the below steps,
Enter Customer location as required (eg.0001 for Nordborg) and select Apply, this is for one time.
By doing this you will be able to see the list of PO for ASN to be created.
Also refresh the page at the right bottom of the screen.
Please contact respective Planner or me immediately when you have this kind of issue.
Select the purchase order you are going to ship by pressing the grey box to the left.
Please make one ASN per delivery note you send to Danfoss. If you send more purchase orders on
the same delivery note, you have to select more purchase order lines. This is done by selecting
each line by holding down the Ctrl key and pressing the grey box for each line.
When all lines are selected, press the “Create ASN” button. The ASN window will open.
Fill out ASN number with your delivery note number. Please check, that the shipping date and the
delivery date at Danfoss are correct. By default, Shipping date and document date should be
current date which is not supposed to be changed and Delivery date will be calculated with respect
to transportation time from Current Shipping date.
If you want to change the Shipping date then remove the Delivery date, change Shipping date and
click ‘Check’ which will update the delivery date according to Transportation time from Shipping
date.
DCS & DPS SNC Supplier Quick Guide
1st Issue, Oct 2016
If Danfoss wants the supplier to send the material faster than normal mode of transport then select
‘Shipping Detail’ tab and change the ‘Means of Transport’ as needed. Whenever you do any
changes in the transportation mode it changes the Delivery date automatically according to the
transport duration time maintained in SNC backend system.
Then press the button “Publish ASN” to publish the ASN.
Now, you will see a new window pop up for your confirmation on the price & quantity, Please
click on ‘YES’ to agree for price & quantity. ASN will now get published and sent to Danfoss.
7 How do I make an order change, if the order is already
confirmed? Requests for order changes can come from Danfoss or from the supplier. In any case the supplier
will have to go into SNC and change the order confirmation.
Note: If ASN is already created, then you are not allowed to re-confirm / change the order confirmation.
If there is any partial ASN to be created which can be created in SNC without reconfirming the
order.
DCS & DPS SNC Supplier Quick Guide
1st Issue, Oct 2016
Select the menu Purchase Order – Purchase Order Worklist
Select Change Confirmation
Select Change Query and change the no. of days since last to 100 days(This will shows 100 days
PO’s) and click ‘Apply’
Now you will see 100 days back confirmes PO’s where you can change the qty and delivery date
here.
DCS & DPS SNC Supplier Quick Guide
1st Issue, Oct 2016
Once changed, select the line and click ‘Save and Publish’
8 How to Cancel the wrong ASN and Create New ASN ?
To view the created ASN, click here in Quick view
Select the ASN no. and click cancel ASN.
This will cancel the ASN in SNC and will remove the ASN(LA line) from our system also.
If Danfoss has already used the SNC ASN for Goods receipt then this ASN cancellation will not
update in our system even if SNC allow it to cancel.
Note: SNC will not accept same ASN no. even after the ASN has been cancelled.
You have to add extra character in the old ASN no., example: ‘-1’, etc to the old ASN no.
Or else you can append the letter “A” to the end of your previously used ASN number when
creating the new ASN. This way it’s clear that the ASN is a revision of a previously published
ASN.
Example:
Original ASN: 123 this is the ASN that will be cancelled.
Revised ASN: 123A this is the revised ASN.
DCS & DPS SNC Supplier Quick Guide
1st Issue, Oct 2016
9. How do I logoff from SNC Portal ?
Danfoss Cooling Segment & Power Solution: You can logoff from SNC portal by pressing
‘Logoff’ on top right of screen. Click on ‘Yes’.
******************************END OF DOCUMENT******************************