- The Software Development Life Cycle (SDLC) For Small To Medium
Database Applications Document ID: REF-0-02 Version: 1.0d 1 /
22
- The Software Development Life Cycle (SDLC) REF-0-02 For small
to medium database applications Version 1.0d 2
- The Software Development Life Cycle (SDLC) REF-0-02 For small
to medium database applications Version 1.0d TABLE OF CONTENTS
INTRODUCTION
.......................................................................................................
4 THE SDLC W ATERFALL
............................................................................
4 ALLOWED VARIATIONS
..............................................................................
5 OTHER SDLC MODELS
.............................................................................
6 REFERENCES
...........................................................................................
7 GENERIC STAGE
.....................................................................................................
8 KICKOFF PROCESS
...................................................................................
8 INFORMAL ITERATION PROCESS
................................................................. 9
FORMAL ITERATION PROCESS
....................................................................
9 IN-STAGE ASSESSMENT PROCESS
........................................................... 10
STAGE EXIT PROCESS
............................................................................
11 SDLC STAGES
......................................................................................................
12 OVERVIEW
.............................................................................................
12 PLANNING STAGE
...................................................................................
13 REQUIREMENTS DEFINITION
STAGE.......................................................... 14
DESIGN STAGE
.......................................................................................
16 DEVELOPMENT STAGE
............................................................................
17 INTEGRATION & TEST STAGE
...................................................................
18 INSTALLATION & ACCEPTANCE STAGE
...................................................... 19
CONCLUSION
.........................................................................................................
20 SCOPE RESTRICTION
..............................................................................
20 PROGRESSIVE ENHANCEMENT
.................................................................
20 PRE-DEFINED STRUCTURE
......................................................................
21 INCREMENTAL PLANNING
.........................................................................
21 3
- The Software Development Life Cycle (SDLC) REF-0-02 For small
to medium database applications Version 1.0d INTRODUCTION This
document describes the Software Development LifeCycle (SDLC) for
small to medium database application development efforts. This
chapter presents an overview of the SDLC, alternate lifecycle
models, and associated references. The following chapter describes
the internal processes that are common across all stages of the
SDLC, and the third chapter describes the inputs, outputs, and
processes of each stage. Finally, the conclusion describes the four
core concepts that form the basis of this SDLC. THE SDLC WATERFALL
Small to medium database software projects are generally broken
down into six stages: Project Planning Requirements Definition
Design Development Integration & Test Installation &
Acceptance The relationship of each stage to the others can be
roughly described as a waterfall, where the outputs from a specific
stage serve as the initial inputs for the following stage. During
each stage, additional information is gathered or developed,
combined with the inputs, and used to produce the stage
deliverables. It is important to note that the additional
information is restricted in scope; new ideas that would take
4
- The Software Development Life Cycle (SDLC) REF-0-02 For small
to medium database applications Version 1.0d the project in
directions not anticipated by the initial set of high-level
requirements are not incorporated into the project. Rather, ideas
for new capabilities or features that are out-of-scope are
preserved for later consideration. After the project is completed,
the Primary Developer Representative (PDR) and Primary End-User
Representative (PER), in concert with other customer and
development team personnel develop a list of recommendations for
enhancement of the current software. PROTOTYPES The software
development team, to clarify requirements and/or design elements,
may generate mockups and prototypes of screens, reports, and
processes. Although some of the prototypes may appear to be very
substantial, they're generally similar to a movie set: everything
looks good from the front but there's nothing in the back. When a
prototype is generated, the developer produces the minimum amount
of code necessary to clarify the requirements or design elements
under consideration. No effort is made to comply with coding
standards, provide robust error management, or integrate with other
database tables or modules. As a result, it is generally more
expensive to retrofit a prototype with the necessary elements to
produce a production module then it is to develop the module from
scratch using the final system design document. For these reasons,
prototypes are never intended for business use, and are generally
crippled in one way or another to prevent them from being
mistakenly used as production modules by end-users. ALLOWED
VARIATIONS In some cases, additional information is made available
to the development team that requires changes in the outputs of
previous stages. In this case, the development effort is usually
suspended until the changes can be reconciled with the current
design, and the new results are passed down the waterfall until the
project reaches the point where it was suspended. The PER and PDR
may, at their discretion, allow the development effort to continue
while previous stage deliverables are updated in cases where the
impacts are minimal and strictly limited in scope. In this case,
the changes must be carefully tracked to make sure all their
impacts are appropriately handled. 5
- The Software Development Life Cycle (SDLC) REF-0-02 For small
to medium database applications Version 1.0d OTHER SDLC MODELS The
waterfall model is one of the three most commonly cited lifecycle
models. Others include the Spiral model and the Rapid Application
Development (RAD) model, often referred to as the Prototyping
model. SPIRAL LIFECYCLE The spiral model starts with an initial
pass through a standard waterfall lifecycle, using a subset of the
total requirements to develop a robust prototype. After an
evaluation period, the cycle is initiated again, adding new
functionality and releasing the next prototype. This process
continues, with the prototype becoming larger and larger with each
iteration. Hence, the spiral. The theory is that the set of
requirements is hierarchical in nature, with additional
functionality building on the first efforts. This is a sound
practice for systems where the entire problem is well defined from
the start, such as modeling and simulating software.
Business-oriented database projects do not enjoy this advantage.
Most of the functions in a database solution are essentially
independent of one another, although they may make use of common
data. As a result, the prototype suffers from the same flaws as the
prototyping lifecycle described below. For this reason, the
software development team has decided against the use of the spiral
lifecycle for database projects. RAPID APPLICATION DEVELOPMENT
(RAD) / PROTOTYPING LIFECYCLE RAD is, in essence, the try before
you buy approach to software development. The theory is that end
users can produce better feedback when examining a live system, as
opposed to working strictly with documentation. RAD-based
development cycles have resulted in a lower level of rejection when
the application is placed into production, but this success most
often comes at the expense of a dramatic overruns in project costs
and schedule. The RAD approach was made possible with significant
advances in software development environments to allow rapid
generation and change of screens and other user interface features.
The end user is allowed to work with the screens online, as if in a
production environment. This leaves little to the imagination, and
a significant number of errors are caught using this process. The
down side to RAD is the propensity of the end user to force scope
creep into the development effort. Since it seems so easy for the
developer to produce the basic screen, it must be just as easy to
add a widget or two. In most RAD lifecycle failures, the end users
and developers were caught in an unending cycle of enhancements,
with the users asking for more and more and the developers trying
to satisfy them. The participants lost sight of the goal of
producing a basic, useful system in favor of the siren song of
glittering perfection. 6
- The Software Development Life Cycle (SDLC) REF-0-02 For small
to medium database applications Version 1.0d For this reason, the
software development team does not use a pure RAD approach, but
instead blends limited prototyping in with requirements and design
development during a conventional waterfall lifecycle. The
prototypes developed are specifically focused on a subset of the
application, and do not provide an integrated interface. The
prototypes are used to validate requirements and design elements,
and the development of additional requirements or the addition of
user interface options not readily supported by the development
environment is actively discouraged. REFERENCES The following
standards were used as guides to develop this SDLC description. The
standards were reviewed and tailored to fit the specific
requirements of small database projects. ANSI/IEEE 1028: Standard
for Software Reviews and Audits ANSI/IEEE 1058.1: Standard for
Software Project Management Plans ANSI/IEEE 1074: Standard for
Software Lifecycle Processes SEI/CMM: Software Project Planning Key
Process Area This document makes extensive use of terminology that
is specific to software engineering. A glossary of standard
software engineering terms is available online at:
http://www.elucidata.org/refs/seglossary.pdf 7
- The Software Development Life Cycle (SDLC) REF-0-02 For small
to medium database applications Version 1.0d GENERIC STAGE Each of
the stages of the development lifecycle follow five standard
internal processes. These processes establish a pattern of
communication and documentation intended to familiarize all
participants with the current situation, and thus minimize risk to
the current project plan. This generic stage description is
provided to avoid repetitive descriptions of these internal
processes in each of the following software lifecycle stage
descriptions. The five standard processes are Kickoff, Informal
iteration, Formal iteration, In-stage assessment, and Stage exit:
SDLC Stage Kickoff Process Informal Iteration Formal Iteration
In-Stage Assessment Stage Exit KICKOFF PROCESS Each stage is
initiated by a kickoff meeting, which can be conducted either in
person, or by Web teleconference. The purpose of the kickoff
meeting is to review the output of the previous stage, go over any
additional inputs required by that particular stage, examine the
anticipated activities and required outputs of the current stage,
review the current project schedule, and review any open issues.
The PDR is responsible for preparing the agenda and materials to be
presented at this meeting. All project participants are invited to
attend the kickoff meeting for each stage. 8
- The Software Development Life Cycle (SDLC) REF-0-02 For small
to medium database applications Version 1.0d INFORMAL ITERATION
PROCESS Most of the creative work for a stage occurs here.
Participants work together to gather additional information and
refine stage inputs into draft deliverables. Activities of this
stage may include interviews, meetings, the generation of
prototypes, and electronic correspondence. All of these
communications are deemed informal, and are not recorded as
minutes, documents of record, controlled software, or official
memoranda. The intent here is to encourage, rather than inhibit the
communication process. This process concludes when the majority of
participants agree that the work is substantially complete and it
is time to generate draft deliverables for formal review and
comment. FORMAL ITERATION PROCESS In this process, draft
deliverables are generated for formal review and comment. Each
deliverable was introduced during the kickoff process, and is
intended to satisfy one or more outputs for the current stage. Each
draft deliverable is given a version number and placed under
configuration management control. As participants review the draft
deliverables, they are responsible for reporting errors found and
concerns they may have to the PDR via electronic mail. The PDR in
turn consolidates these reports into a series of issues associated
with a specific version of a deliverable. The person in charge of
developing the deliverable works to resolve these issues, then
releases another version of the deliverable for review. This
process iterates until all issues are resolved for each
deliverable. There are no formal check off / signature forms for
this part of the process. The intent here is to encourage review
and feedback. At the discretion of the PDR and PER, certain issues
may be reserved for resolution in later stages of the development
lifecycle. These issues are disassociated from the specific
deliverable, and tagged as "open issues." Open issues are reviewed
during the kickoff meeting for each subsequent stage. Once all
issues against a deliverable have been resolved or moved to open
status, the final (release) draft of the deliverable is prepared
and submitted to the PDR. When final drafts of all required stage
outputs have been received, the PDR reviews the final suite of
deliverables, reviews the amount of labor expended against this
stage of the project, and uses this information to update the
project plan. The project plan update includes a detailed list of
tasks, their schedule and estimated level of effort for the next
stage. The stages following the next stage 9
- The Software Development Life Cycle (SDLC) REF-0-02 For small
to medium database applications Version 1.0d (out stages) in the
project plan are updated to include a high level estimate of
schedule and level of effort, based on current project experience.
Out stages are maintained at a high level in the project plan, and
are included primarily for informational purposes; direct
experience has shown that it is very difficult to accurately plan
detailed tasks and activities for out stages in a software
development lifecycle. The updated project plan and schedule is a
standard deliverable for each stage of the project. The PDR then
circulates the updated project plan and schedule for review and
comment, and iterates these documents until all issues have been
resolved or moved to open status. Once the project plan and
schedule has been finalized, all final deliverables for the current
stage are made available to all project participants, and the PDR
initiates the next process. IN-STAGE ASSESSMENT PROCESS This is the
formal quality assurance review process for each stage. In a small
software development project, the deliverables for each stage are
generally small enough that it is not cost effective to review them
for compliance with quality assurance standards before the
deliverables have been fully developed. As a result, only one
in-stage assessment is scheduled for each stage. This process is
initiated when the PDR schedules an in-stage assessment with the
independent Quality Assurance Reviewer (QAR), a selected End-user
Reviewer (usually a Subject Matter Expert), and a selected
Technical Reviewer. These reviewers formally review each
deliverable to make judgments as to the quality and validity of the
work product, as well as its compliance with the standards defined
for deliverables of that class. Deliverable class standards are
defined in the software quality assurance section of the project
plan. The End-user Reviewer is tasked with verifying the
completeness and accuracy of the deliverable in terms of desired
software functionality. The Technical Reviewer determines whether
the deliverable contains complete and accurate technical
information. The QA Reviewer is tasked solely with verifying the
completeness and compliance of the deliverable against the
associated deliverable class standard. The QAR may make
recommendations, but cannot raise formal issues that do not relate
to the deliverable standard. Each reviewer follows a formal
checklist during their review, indicating their level of
concurrence with each review item in the checklist. Refer to the
software quality assurance plan for this project for deliverable
class standards and associated review checklists. A deliverable is
considered to be acceptable when 10
- The Software Development Life Cycle (SDLC) REF-0-02 For small
to medium database applications Version 1.0d each reviewer
indicates substantial or unconditional concurrence with the content
of the deliverable and the review checklist items. Any issues
raised by the reviewers against a specific deliverable will be
logged and relayed to the personnel responsible for generation of
the deliverable. The revised deliverable will then be released to
project participants for another formal review iteration. Once all
issues for the deliverable have been addressed, the deliverable
will be resubmitted to the reviewers for reassessment. Once all
three reviewers have indicated concurrence with the deliverable,
the PDR will release a final in-stage assessment report and
initiate the next process. STAGE EXIT PROCESS The stage exit is the
vehicle for securing the concurrence of principal project
participants to continue with the project and move forward into the
next stage of development. The purpose of a stage exit is to allow
all personnel involved with the project to review the current
project plan and stage deliverables, provide a forum to raise
issues and concerns, and to ensure an acceptable action plan exists
for all open issues. The process begins when the PDR notifies all
project participants that all deliverables for the current stage
have been finalized and approved via the In- Stage Assessment
report. The PDR then schedules a stage exit review with the project
executive sponsor and the PER as a minimum. All interested
participants are free to attend the review as well. This meeting
may be conducted in person or via Web teleconference. The stage
exit process ends with the receipt of concurrence from the
designated approvers to proceed to the next stage. This is
generally accomplished by entering the minutes of the exit review
as a formal document of record, with either physical or digital
signatures of the project executive sponsor, the PER, and the PDR.
11
- The Software Development Life Cycle (SDLC) REF-0-02 For small
to medium database applications Version 1.0d SDLC STAGES OVERVIEW
The six stages of the SDLC are designed to build on one another,
taking the outputs from the previous stage, adding additional
effort, and producing results that leverage the previous effort and
are directly traceable to the previous stages. This top-down
approach is intended to result in a quality product that satisfies
the original intentions of the customer. Project Planning
Requirements Definition Design Development Integration & Test
Installation & Acceptance Too many software development efforts
go awry when the development team and customer personnel get caught
up in the possibilities of automation. Instead of focusing on high
priority features, the team can become mired in a sea of nice to
have features that are not essential to solve the problem, but in
themselves are highly attractive. This is the root cause of a large
percentage of failed and/or abandoned development efforts, and is
the primary reason the development team utilizes the Waterfall
SDLC. 12
- The Software Development Life Cycle (SDLC) REF-0-02 For small
to medium database applications Version 1.0d PLANNING STAGE The
planning stage establishes a bird's eye view of the intended
software product, and uses this to establish the basic project
structure, evaluate feasibility and risks associated with the
project, and describe appropriate management and technical
approaches. Application Lifecycle Goals Model Planning Stage
Software Software Quality Project Plan Configuration Assurance Plan
& Schedule Management Plan The most critical section of the
project plan is a listing of high-level product requirements, also
referred to as goals. All of the software product requirements to
be developed during the requirements definition stage flow from one
or more of these goals. The minimum information for each goal
consists of a title and textual description, although additional
information and references to external documents may be included.
The outputs of the project planning stage are the configuration
management plan, the quality assurance plan, and the project plan
and schedule, with a detailed listing of scheduled activities for
the upcoming Requirements stage, and high- level estimates of
effort for the out stages. 13
- The Software Development Life Cycle (SDLC) REF-0-02 For small
to medium database applications Version 1.0d REQUIREMENTS
DEFINITION STAGE The requirements gathering process takes as its
input the goals identified in the high-level requirements section
of the project plan. Each goal will be refined into a set of one or
more requirements. These requirements define the major functions of
the intended application, define operational data areas and
reference data areas, and define the initial data entities. Major
functions include critical processes to be managed, as well as
mission critical inputs, outputs and reports. A user class
hierarchy is developed and associated with these major functions,
data areas, and data entities. Each of these definitions is termed
a Requirement. Requirements are identified by unique requirement
identifiers and, at minimum, contain a requirement title and
textual description. High-Level Requirements (Project Plan)
Requirements Definition Stage Updated Requirements Requirements
Project Plan Traceability Document & Schedule Matrix These
requirements are fully described in the primary deliverables for
this stage: the Requirements Document and the Requirements
Traceability Matrix (RTM). the requirements document contains
complete descriptions of each requirement, including diagrams and
references to external documents as necessary. Note that detailed
listings of database tables and fields are not included in the
requirements document. The title of each requirement is also placed
into the first version of the RTM, along with the title of each
goal from the project plan. The purpose of the RTM is to show that
the product components developed during each stage of the software
development lifecycle are formally connected to the components
developed in prior stages. 14
- The Software Development Life Cycle (SDLC) REF-0-02 For small
to medium database applications Version 1.0d In the requirements
stage, the RTM consists of a list of high-level requirements, or
goals, by title, with a listing of associated requirements for each
goal, listed by requirement title. In this hierarchical listing,
the RTM shows that each requirement developed during this stage is
formally linked to a specific product goal. In this format, each
requirement can be traced to a specific product goal, hence the
term requirements traceability. The outputs of the requirements
definition stage include the requirements document, the RTM, and an
updated project plan. 15
- The Software Development Life Cycle (SDLC) REF-0-02 For small
to medium database applications Version 1.0d DESIGN STAGE The
design stage takes as its initial input the requirements identified
in the approved requirements document. For each requirement, a set
of one or more design elements will be produced as a result of
interviews, workshops, and/or prototype efforts. Design elements
describe the desired software features in detail, and generally
include functional hierarchy diagrams, screen layout diagrams,
tables of business rules, business process diagrams, pseudocode,
and a complete entity-relationship diagram with a full data
dictionary. These design elements are intended to describe the
software in sufficient detail that skilled programmers may develop
the software with minimal additional input. Requirements Document
Design Stage Updated Updated Design Requirements Project Plan
Document Traceability & Schedule Matrix When the design
document is finalized and accepted, the RTM is updated to show that
each design element is formally associated with a specific
requirement. The outputs of the design stage are the design
document, an updated RTM, and an updated project plan. 16
- The Software Development Life Cycle (SDLC) REF-0-02 For small
to medium database applications Version 1.0d DEVELOPMENT STAGE The
development stage takes as its primary input the design elements
described in the approved design document. For each design element,
a set of one or more software artifacts will be produced. Software
artifacts include but are not limited to menus, dialogs, data
management forms, data reporting formats, and specialized
procedures and functions. Appropriate test cases will be developed
for each set of functionally related software artifacts, and an
online help system will be developed to guide users in their
interactions with the software. Design Document Development Stage
Updated Online Software Project Plan Help & Schedule Updated
Implementation Requirements Test Plan Map Traceability Matrix The
RTM will be updated to show that each developed artifact is linked
to a specific design element, and that each developed artifact has
one or more corresponding test case items. At this point, the RTM
is in its final configuration. The outputs of the development stage
include a fully functional set of software that satisfies the
requirements and design elements previously documented, an online
help system that describes the operation of the software, an
implementation map that identifies the primary code entry points
for all major system functions, a test plan that describes the test
cases to be used to validate the correctness and completeness of
the software, an updated RTM, and an updated project plan. 17
- The Software Development Life Cycle (SDLC) REF-0-02 For small
to medium database applications Version 1.0d INTEGRATION & TEST
STAGE During the integration and test stage, the software
artifacts, online help, and test data are migrated from the
development environment to a separate test environment. At this
point, all test cases are run to verify the correctness and
completeness of the software. Successful execution of the test
suite confirms a robust and complete migration capability. During
this stage, reference data is finalized for production use and
production users are identified and linked to their appropriate
roles. The final reference data (or links to reference data source
files) and production user list are compiled into the Production
Initiation Plan. Online Implementation Software Test Plan Help Map
Integration & Test Stage Integrated Implementation Online
Software Map Help Updated Production Acceptance Project Plan
Initiation Plan Plan & Schedule The outputs of the integration
and test stage include an integrated set of software, an online
help system, an implementation map, a production initiation plan
that describes reference data and production users, an acceptance
plan which contains the final suite of test cases, and an updated
project plan. 18
- The Software Development Life Cycle (SDLC) REF-0-02 For small
to medium database applications Version 1.0d INSTALLATION &
ACCEPTANCE STAGE During the installation and acceptance stage, the
software artifacts, online help, and initial production data are
loaded onto the production server. At this point, all test cases
are run to verify the correctness and completeness of the software.
Successful execution of the test suite is a prerequisite to
acceptance of the software by the customer. After customer
personnel have verified that the initial production data load is
correct and the test suite has been executed with satisfactory
results, the customer formally accepts the delivery of the
software. Production Acceptance Integrated Online Initiation Plan
Plan Software Help Implementation Map Installation & Acceptance
Stage Customer Production Completed Acceptance Software Acceptance
Test Memorandum Archived Archived Software Project Plan Artifacts
& Schedule The primary outputs of the installation and
acceptance stage include a production application, a completed
acceptance test suite, and a memorandum of customer acceptance of
the software. Finally, the PDR enters the last of the actual labor
data into the project schedule and locks the project as a permanent
project record. At this point the PDR "locks" the project by
archiving all software items, the implementation map, the source
code, and the documentation for future reference. 19
- The Software Development Life Cycle (SDLC) REF-0-02 For small
to medium database applications Version 1.0d CONCLUSION The
structure imposed by this SDLC is specifically designed to maximize
the probability of a successful software development effort. To
accomplish this, the SDLC relies on four primary concepts: Scope
Restriction Progressive Enhancement Pre-defined Structure
Incremental Planning These four concepts combine to mitigate the
most common risks associated with software development efforts.
SCOPE RESTRICTION The project scope is established by the contents
of high-level requirements, also known as goals, incorporated into
the project plan. These goals are subsequently refined into
requirements, then design elements, then software artifacts. This
hierarchy of goals, requirements, elements, and artifacts is
documented in a Requirements Traceability Matrix (RTM). The RTM
serves as a control element to restrict the project to the
originally defined scope. Project participants are restricted to
addressing those requirements, elements, and artifacts that are
directly traceable to product goals. This prevents the substantial
occurrence of scope creep, which is the leading cause of software
project failure. PROGRESSIVE ENHANCEMENT Each stage of the SDLC
takes the outputs of the previous stage as its initial inputs.
Additional information is then gathered, using methods specific to
each stage. As a result, the outputs of the previous stage are
progressively enhanced with additional information. 20
- The Software Development Life Cycle (SDLC) REF-0-02 For small
to medium database applications Version 1.0d By establishing a
pattern of enhancing prior work, the project precludes the
insertion of additional requirements in later stages. New
requirements are formally set aside by the development team for
later reference, rather than going through the effort of backing
the new requirements into prior stage outputs and reconciling the
impacts of the additions. As a result, the project participants
maintain a tighter focus on the original product goals, minimize
the potential for scope creep, and show a preference for deferring
out-of-scope enhancements, rather than attempting to incorporate
them into the current effort. PRE-DEFINED STRUCTURE Each stage has
a pre-defined set of standard processes, such as Informal Iteration
and In-stage Assessment. The project participants quickly grow
accustomed to this repetitive pattern of effort as they progress
from stage to stage. In essence, these processes establish a common
rhythm, or culture, for the project. This pre-defined structure for
each stage allows the project participants to work in a familiar
environment, where they know what happened in the past, what is
happening in the present, and have accurate expectations for what
is coming in the near future. This engenders a high comfort level,
which in turn generates a higher level of cooperation between
participants. Participants tend to provide needed information or
feedback in a more timely manner, and with fewer miscommunications.
This timely response pattern and level of communications quality
becomes fairly predictable, enhancing the ability of the PDR to
forecast the level of effort for future stages. INCREMENTAL
PLANNING The entire intent of incremental planning is to minimize
surprises, increase accuracy, provide notification of significant
deviations from plan as early in the SDLC as possible, and
coordinate project forecasts with the most current available
information. In this SDLC, the project planning effort is
restricted to gathering metrics on the current stage, planning the
next stage in detail, and restricting the planning of later stages,
also known as Out Stages, to a very high level. The project plan is
updated as each stage is completed; current costs and schedule to
date are combined with refined estimates for activities and level
of effort for the next stage. The activities and tasks of the next
stage are defined only after the deliverables for the current stage
are complete and the current metrics are available. This allows the
planner to produce a highly accurate plan for the next stage.
Direct experience has shown that it is very difficult to develop
more than a cursory estimate of anticipated structure and level of
effort for out stages. 21
- The Software Development Life Cycle (SDLC) REF-0-02 For small
to medium database applications Version 1.0d The estimates for out
stages are included to allow a rough estimate of ultimate project
cost and schedule. The estimates for out stages are reviewed and
revised as each stage is exited. As a result, the total project
estimate becomes more and more accurate over time. As each stage is
exited, the updated project plan and schedule is presented to the
customer. The customer is apprised of project progress, cost and
schedule, and the actual metrics are compared against the
estimates. This gives the customer the opportunity to confirm the
project is on track, or take corrective action as necessary. The
customer is never left in the dark about the progress of the
project. 22