Rinconada Water Treatment PlantReliability Improvement Project

Saratoga City CouncilOctober 7, 2015

The purpose of this presentation is to inform you about the Rinconada Reliability Project• Provide Project Background• Describe the Phases of the Project• Explain how you can stay informed

Purpose

• Original Rinconada WTP finished in 1968• Sole District Water supply to West Valley

Service Area• Current Project Planning completed June 2012 Design completed January 2015 Construction started July 2015 Construction completion July 2020?

Project Background

• Replace facilities and components that are near the “end of their useful life”• Meet increasingly stringent water quality

standards• Comply with current seismic codes• Improve plant safety

Project is needed to

• Increase Water Production Capacity from• 80 MGD to 100 MGD• Provide new facilities• Raw Water Ozonation• Flocculation and Plate Settler

Clarification• Dual Media Filtration

Improvements

Jan 2018

July 2015

July 2020

Residuals

July 2017

July 2018

July 2019

July 2016

Jan 2016

Jan 2017

Jan 2019

Jan 2020

Ops Bldg Seismic

Quito Bridge

Rinconada Reliability Improvement Project Construction PhasesPhase

1 Phase 2 Phase 3 Phase 4 Phase 5

Coordinating Schedule with Other Activities

Stay Informed:• Visit the District’s website and blog at

www.RinconadaReliabilityProject.com • Contact District’s Public Affairs Representative