Requirements of Pebble Bed Reactor's Plant Information Model

Post on 22-Jan-2017

216 views 0 download

Transcript of Requirements of Pebble Bed Reactor's Plant Information Model

Requirements of Pebble Bed Reactor'sPlant Information Model

Topan Setiadipura Research Group on Design and Computational Aspect of HTGRCenter for Nuclear Reactor Technology and Safety

BATAN - Indonesia

Tech. Meeting to Review First Draft of the Document on Application of the Modern Plant Information Models to Support and Manage Design Knowledge throughout NPP Life Cycler.22 – 26 June 2015, IAEA Headquarters, Vienna, Austria.

Introduction

Among the Audiences

Contribution to the Objectives of the Meetings

Indonesia's Experimental Power Reactor

Project

In Indonesia, we call it RDE a 'Reaktor Daya Eksperimental'

Reactor Type: Act. No 10/1997 dan PP 2/2014

Power Reactor

Non­Power Reactor

Commercial

Non­Commercial

Commercial

Non­Commercial

Non­Commercial: BATANCommercial : State­Own­Company, Private Company

Impact of RDE

Electricity

Heat Applicat

ion

R&D on HTGR

RDE will produce electricity . 

RDE

RDE will be used in the R&D of nuclear­heat cogeneration.

RDE akan dimanfaatkan sebagai sarana litbang teknologi HTGR untuk pengembangan desain dan konstruksi HTGR di Indonesia.

RDE Project Plan

6/9/15Badan Tenaga Nuklir Nasional

8

6/10/15Badan Tenaga Nuklir Nasional 9

Future RDE Utilization Plan in Indonesia

Wilayah Pengembangan 

HTGR/SMR(Komersialisasi 

RDE)

Wilayah Pengembangan 

PLTN Besar

Kepadatan Penduduk

RDE will become one of “NPP Model” in Indonesia with huge demand for electricity and/ heat application.

6/9/15Badan Tenaga Nuklir Nasional 10

Tahun

2015 2016 2017 2018 2019

Engineering DesignKontrak

RDE Project Schedule

2020

Engineering, Procurement and Construction (EPC)

Construction Permit

Process

2021

Site Permit Process

Construction Management

OUT PUT:1. Feasibility Study2. Conceptual Design4. Safety Analysis Report [SAR}5. Front­End­Engineering­Design [FEED]6.  EPC Tender Document

Pengawas

Progress of the Project

We finish compiling the RDE Requirement

Currently we are working with Consultant for the Basic Engineering Design Package of RDE.

The consultant is a consortium of● Rekayasa Engineering (Indonesian EPC Company)● Kogas Driyap Consultant (Indonesian Technical

Consultant)● NUKEM Gmbh. (German Company which own by

ROSATOM)

Basemap:Worldview­225/08/2013

Lokasi Lintang Bujur

Desa Muncul Desa Kranggan, Kec. Situ, Kota Tangerang Selatan, Banten

6° 21' 26" LS 106° 39' 37" BT

Site Location

General Specification of RDE

- HTGR type Pebble Bed Reactor (PBR)

- Refere to the HTR-Module design.

 RDE Fuel : Pebble Fuel

- HTGR tipe Pebble Bed Reactor (PBR)

- Mengacu pada desain HTR-Module Jerman.

General Specification of  RDE

Safety Feature(1): ControlInherently the core able to control unepected increase of

fission reaction rate.

6/9/15 16

HTR-Module Siemens Design

Safety Feature(2): CoolingIn the case of accident, it able to transfer heat outside

only by natural mechanism.

6/9/15 17

rcore

Safety Feature (3): Contain

Low radiactive release to the environment even in the most severe accident.

6/9/15 18

PBR : Ex. Of Master Logic Diagram

6/9/15 19

Source: G.Brinkmann et.al / NED 236(2006)463-474

PBR : A Moving Core Reactor

6/9/15 20

RDE will follow the Multipass cycle.

PBR : Fuel Handling Mechanism

6/9/15 21

PBR : Analysis requirements

6/9/15 22

Source: IAEA Course on HTGR by F.Reitsma

PBR General Feature (Part of SAR)

6/9/15 23

Remarks on RDE Project and PIM Development

6/9/15 24

Establisment of PIM is a huge help for the newcomer to comprehend the design and assure that the design feature is fulfilled.

For instance, in our RDE requirement development we need to carefully differentiate between the direct or indirect cycle related technology.

Indonesia's RDE Project can take a huge advantage from a PBR-compatible PIM.

It is important for us to involve in the PIM innitiatives lead by IAEA.

Milestone to PBR-Compatible PIM

6/9/15 25

- Development of PBR's Taxonomy and Basic Requirements (as have been done for FR)- Identify the Common NPP Requirements- Identify the specific PBR Requirements