Regional Connector Transit CorridorAugust 2012 Community Update Meetings
1
1st St/Central Av Station Community Meeting May 30, 2013
7/28/2019 Regional Connector PPT
2/22
2
Agenda> Project Overview and Update
> Presentation on Extended Work Hours
Request> Community Outreach and Notification
> Next Steps
> How to Contact Us
7/28/2019 Regional Connector PPT
3/22
Project Overview> $1.366 Billion
underground Light RailTransit System
> Connect Metro GoldLine to Metro Blue andExpo Lines
> 1.9-miles with 3underground stations
> 90,000 Daily ProjectedTransit Trips
> 17,700 Daily New
Transit Trips3
7/28/2019 Regional Connector PPT
4/22
4
Project Update> Request for Proposal issued to prequalified
Design/Builders
>Proposals due July, 2013
> Contract Award and Notice to Proceedissuance end of 2013
> Design/Build activities begin
7/28/2019 Regional Connector PPT
5/22
Project Update
5
3rd Party Utility Relocation
> Excavation and conduit installation by AT&T
> 1st
St from Central Av. to E/O Alameda St.> Anticipated to start this summer
> Anticipated work hours are Monday Friday:
9am -3:30pm; Saturday: 8am 6pm> Work with community to ensure Nisei Week
is a successful event (August)
7/28/2019 Regional Connector PPT
6/22
Information on Metros Requestfor an Extended Work Hours
6
7/28/2019 Regional Connector PPT
7/22
Summary of Work HoursDaytime Allowable Hours Extended HoursMonday Friday: 7am - 9pm Monday Friday: 9pm - 7am of the
following day
Saturday: 8am -6pm Saturday: Before 8am & after 6pm
No Sunday work All day Sunday
7
Peak Traffic Hour: Restricts construction from 6am 9am and from3:30pm 7pm, Monday through Friday.
Holiday Moratorium: Restricts construction from before Thanksgivingto after New Years Day holidays.
7/28/2019 Regional Connector PPT
8/22
Extended Work Hours Request
8
> Metro requests extended work hourvariances from City codes
> Variances allow longer work hours,including nights and on Sundays
> Continued approval is conditional onperformance
> All work will be scheduled in advance,with notice to community
7/28/2019 Regional Connector PPT
9/22
Extended Work Hours Request
9
> Compliance with the Mitigation Monitoringand Reporting Program (MMRP) is required
> Project Hotline operates 24 hours per dayand 7 days a week
> Metros team has used these variances onthe successful Eastside Gold Lineconstruction
7/28/2019 Regional Connector PPT
10/22
Extended Work Hours Request
10
Why is needed
> Minimize construction impacts to thecommunity
> Shorten the overall duration of construction
> Reduce construction impacts to traffic
> Complete project early 2020
7/28/2019 Regional Connector PPT
11/22
1st St/Central Av Station
11
7/28/2019 Regional Connector PPT
12/22
1st St/Central Av Station> Central Av, south
of 1st St
> Intersection ofAlameda St andTemple Av
> 1st St, West andEast of Alameda St
12
7/28/2019 Regional Connector PPT
13/22
Conceptual Construction Sequencing
13
7/28/2019 Regional Connector PPT
14/22
14
Soldier Pile Installation
7/28/2019 Regional Connector PPT
15/22
Deck Installation> Deck support system
in place during MetroGold LineConstruction
15
7/28/2019 Regional Connector PPT
16/22
Deck Installation> Temporary Deck
maintainsmobility of trafficwhile
constructionactivities takeplace below it
16
7/28/2019 Regional Connector PPT
17/22
17
Excavation below street surface
Existing utilities and support systems arevisible.
Construction Overview Cut and Cover
7/28/2019 Regional Connector PPT
18/22
18
Tunneling Equipment
7/28/2019 Regional Connector PPT
19/22
Summary
19
> Receive support for extended work hours tominimize construction duration
> Reduction in overall duration and relatedconstruction impacts
> Deliver project to the community andbusinesses by 2020
7/28/2019 Regional Connector PPT
20/22
Next Steps
20
> LAPD Commission Staff may contact youabout Metros variance request
> Questions or Comments can be directed toMetro Construction Relations
> Letters of Support
7/28/2019 Regional Connector PPT
21/22
Community Outreach and Notification
21
> Advance look-ahead of activities provided atCommunity Leadership Council Committee(CLCC) and community meetings
> CLCC presentation on activities in advance ofwork starting
> Notification to stakeholders one week in
advance of work starting> Construction updates on Project website,
Facebook and Twitter
7/28/2019 Regional Connector PPT
22/22
22
How to Contact UsRegionalConnector@metro.net
Facebook.com/metroregionalconnector
@metroconnector
www.Metro.net/regionalconnector
Project Hotline: 213-922-7277
https://www.facebook.com/MetroRegionalConnectorhttps://www.facebook.com/MetroRegionalConnectorhttp://twitter.com/metroconnectorhttp://www.metro.net/regionalconnectorhttp://www.metro.net/regionalconnectorhttp://www.metro.net/regionalconnectorhttp://twitter.com/metroconnectorhttp://twitter.com/metroconnectorhttps://www.facebook.com/MetroRegionalConnectorhttps://www.facebook.com/MetroRegionalConnectorhttps://www.facebook.com/MetroRegionalConnectorhttps://www.facebook.com/MetroRegionalConnector