Project Status Update Wrangell Junkyard Cleanup

March 17, 2016

C:\Users\Jginter\Desktop\Wrangell NRC JJG Notes\20160317 Photos For Status Update.Docx

Photo 1: Overview of site conditions as of March 16, 2016

Photo 2: Battery collected from excavation area, note liner over clean non “blue clay” material.

Project Status UpdateWrangell Junkyard

March 17, 2016

Page 2C:\Users\Jginter\Desktop\Wrangell NRC JJG Notes\20160317 Photos For Status Update.Docx

Photo 3: Field screening samples are collected at grid nodes every one foot lift, Area B

Photo 4: Engine block tires and other automotive parts among sub-surface debris

Project Status UpdateWrangell Junkyard

March 17, 2016

Page 3C:\Users\Jginter\Desktop\Wrangell NRC JJG Notes\20160317 Photos For Status Update.Docx

Photo 5: POL contamination associated with buried crushed drums

Photo 6: POL leaking from buried drum