Post on 06-Apr-2020
Quarter Ending June 30, 2014
POSITIVE TRAIN CONTROL (PTC)
Quarterly Report
NCTD PTC Monthly Report Page i Quarter Ending June 30, 2014
CONTENTS
1. EXECUTIVE SUMMARY ............................................................................................................... 1
1.1. Project Overview ........................................................................................................................ 1
1.1.1. PTC Inter-Agency Coordination......................................................................................... 1
1.1.2. PTC Operations and Maintenance .................................................................................... 2
1.2. Scope of Work Overview ......................................................................................................... 3
1.3. Key Issues ............................................................................................................................... 5
1.3.1. Network ............................................................................................................................. 5
1.3.2. Federal Communications Commission (FCC) ................................................................... 5
1.3.3. Wayside Interface Units (WIUs) ........................................................................................ 6
1.3.4. WRE’s Individual Composite CRC (Cyclic Redundancy Check) Calculator (IC3) ............. 6
1.3.5. Non-compliant Components .............................................................................................. 6
1.3.6. Back Office ........................................................................................................................ 6
1.3.7. Federated Link .................................................................................................................. 6
2. PROGRAM MANAGEMENT .......................................................................................................... 7
2.1. Integration Management .......................................................................................................... 7
2.1.1. Program Governance ........................................................................................................ 7
2.1.2. Program Control ................................................................................................................ 7
2.1.3. Change Management ........................................................................................................ 7
2.1.4. Program/Project Management Information Systems ......................................................... 8
2.2. Scope Management ................................................................................................................ 9
2.3. Configuration Control Management ......................................................................................... 9
2.4. Quality Management ............................................................................................................... 9
2.4.1. Quality Plans ..................................................................................................................... 9
2.4.2. Deficiency Notices (DN), Nonconformance Reports (NCR), Corrective Action Reports (CAR) .......................................................................................................................................... 9
2.4.3. PTC Quality Audits and Surveillances ............................................................................. 10
2.4.4. Corrective Action Reports (CAR) ..................................................................................... 10
2.4.5. Quality Tasks................................................................................................................... 11
2.5. Risk Management .................................................................................................................. 12
2.6. Stakeholder and Communications Management ................................................................... 12
3. PROGRAM SAFETY ................................................................................................................... 13
4. PROGRAM PROGRESS ............................................................................................................. 14
4.1. Schedule Development ......................................................................................................... 14
4.2. Critical Path ........................................................................................................................... 14
NCTD PTC Monthly Report Page ii Quarter Ending June 30, 2014
5. POSITIVE TRAIN CONTROL CONTRACTS AND STATUS ....................................................... 17
6. EXPENDITURES / FUNDING SOURCES ................................................................................... 37
6.1. Expenditures .......................................................................................................................... 37
6.2. Funding Sources ................................................................................................................... 38
7. PROJECT PHOTOS .................................................................................................................... 39
NCTD Purchase Order 11046: PTC for the LOSSAN Corridor ........................................................ 39
NCTD Purchase Order 13020: South COASTER Fiber .................................................................. 40
NCTD Purchase Order 13035: San Diego Fiber ............................................................................. 41
NCTD Purchase Order 30073: PTC Signal Maintainer & WIU Installation ...................................... 41
NCTD Purchase Order 13007: CP Friar Signal Project ................................................................... 42
APPENDIX A: ABBREVIATIONS ........................................................................................................ 43
NCTD PTC Monthly Report Page 1 of 44 Quarter Ending June 30, 2014
1. EXECUTIVE SUMMARY
1.1. Project Overview North County Transit District (NCTD) is implementing an interoperable Positive Train Control (PTC) System on the San Diego Subdivision where passenger and freight operations are conducted (as set forth in the Rail Safety Improvement Act of 2008 (RSIA08) and 49 CFR 236 Subpart I).
The purpose of a PTC System is to prevent the following:
Train-to-train collisions
Over speed accidents
Incursion into work zones
Movements through a misaligned switch by requiring automatic control systems to override mistakes by human operators
This PTC System will be designed and implemented to follow the standard and guidelines established by the Interoperable Train Control (ITC) Committee. The ITC Committee is comprised of the four largest US freight railroads – BNSF Railway, CSX, Norfolk Southern Railway (NS), and Union Pacific Railroad (UPRR). The NCTD goal for PTC implementation is the required December 31, 2015 completion date as stipulated in the Federal Rail Safety Act of 2008. In August 2011, NCTD procured a Vendor/Integrator contractor, Herzog Technologies Inc. (HTI), to design, install, commission, and maintain the PTC System.
In addition to and in advance of the implementation of the PTC System, NCTD has assumed the management control of the San Diego Subdivision by installing a new computer-aided dispatch system, Train Management and Dispatching System (TMDS), and assumes responsibility for railroad dispatching. Previously, NCTD’s dispatching was managed by Southern California Regional Rail Authority (SCRRA) using the DIGICON CTC system. NCTD awarded a contract to HTSI for CTC installation and dispatch services. The San Diego Subdivision dispatch cutover was April 2012, and the Escondido Subdivision dispatch cutover was December 2011.
The new PTC system will be located at the Rail Operations Center (ROC) within the Sprinter Operations Facility (SOF) in Escondido CA. NCTD’s General Administration Office (GAO) has been identified as a second location to provide geographic redundancy for both the command and control functions as well as the PTC back office functions. Once the Operations Control Center at GAO has been fully built out, GAO will be transitioned to the primary location with the ROC becoming the backup center.
1.1.1. PTC Inter-Agency Coordination Inter-Agency Coordination is one of the keys for successful implementation of the project. The PTC system must be fully and mutually compatible with host and tenant railroads. Interoperability will enable safe operation of mixed freight and passenger services to allow seamless uninterrupted movement among different host railroads. Interoperability shall be based on the ITC Committee standard and guidelines, and member governance currently in development by the UPRR, BNSF Railway, CSX, and NS. Host and tenant railroads may also execute Interoperability Agreements, which are envisioned as being similar to Shared Use Agreements. NCTD has executed Interoperability Agreements with BNSF Railway (April 2010), SCRRA (April 2010), Amtrak (March 2010) and Pacific Sun Railroad (August 2010).
The San Diego Subdivision rail corridor is 60.3 miles in length from the Orange County/San Diego County line (MP 207.4) to 200 feet south of Broadway Street in San Diego (MP 267.7).
NCTD PTC Monthly Report Page 2 of 44 Quarter Ending June 30, 2014
The entire line is signaled CTC territory with 50% of the territory having segments of multiple main track and passing sidings. Passenger train operations on the corridor are COASTER (22 trains/weekday), Amtrak Pacific Surfliner intercity service (22-24 trains/day), and SCRRA Metrolink commuter rail services (up to 14 trains/day). Freight service on the Subdivision is BNSF Railway (4-6 trains/day) and Pacific Sun Railroad (5-10 trains/week).
NCTD's COASTER service operates between the Oceanside Transit Center in Oceanside (MP 226.4) and Santa Fe Depot in San Diego (MP 267.5). NCTD’s Maintenance facility is located at Stuart Mesa (MP 221.9), north of Oceanside on Camp Pendleton. This yard is also used by SCRRA Metrolink. A layover facility is located at the San Diego Trolley Yard (MP 268.4) at 12th and Imperial in Centre City San Diego where COASTER train sets are stored during midday.
In addition to the NCTD COASTER service area, the tenant railroads use the corridor as follows:
Amtrak's Pacific Surfliner Service - Entire subdivision,
BNSF Railway - Entire subdivision,
SCRRA's Metrolink Orange County Line - From Oceanside to the Orange County Line,
BNSF Railway’s contracted operator Pacific Sun Railroad, a Watco Company - Local freight service operating between Stuart Mesa Maintenance Facility and Miramar freight spur, and Escondido Subdivision with occasional trips to San Onofre near the Orange County Line.
NCTD has organized monthly interoperability calls that include the Federal Railroad Administration (FRA), Caltrans Division of Rail, Pacific Sun, Southern California Regional Rail Authority (SCRRA), BNSF Railway, and Amtrak.
NCTD also attends the LA Regional PTC Conference quarterly meeting hosted by SCRRA and attended by BNSF Railway, UPRR and Amtrak.
1.1.2. PTC Operations and Maintenance HTI was selected as NCTD’s Vendor/Integrator, and included in their proposal was an option for PTC System Maintenance Services for a base period of five years with an additional five year option. Should this option be exercised, HTI would be responsible for maintenance of back-office PTC systems, on-board equipment on locomotives and cab cars, communications equipment at other base station locations, and Roadway Worker Protection (portable) equipment. At the time of award, the total original contracted amount was $32,819,671. The estimated cost for the base period of five years maintenance would be an additional $5,629,042, with a second five year maintenance period at a cost of an additional $6,624,426. The maintenance scope and fee will need to be revisited as the project progresses.
For the purpose of the Office Maintenance Services, the office includes back office and network management equipment. For the office maintenance, HTI would provide a technology refresh of the hardware and technology as part of the scheduled maintenance during year four of both the five year contract and the optional five year contract. The technology refresh would consist of replacing the back office hardware, software, and firmware with the latest proven operating platform, subject to NCTD approval.
NCTD PTC Monthly Report Page 3 of 44 Quarter Ending June 30, 2014
1.2. Scope of Work Overview HTI and its subcontractors are solely responsible for designing and implementing a PTC system that meets FRA and other applicable requirements and is FRA approved for NCTD rail operations. HTI is required to follow the Positive Train Control Development Plan (PTCDP) submitted by the NS, CSX, and UPRR railroads and utilize it as the basis for the NCTD PTC system. This PTCDP, revised on June 1, 2011 and subsequently approved by the FRA on August 26, 2011, is known as Interoperable – Electronic Train Management System (I-ETMS). HTI and its subcontractors are scoped to be following the I-ETMS Rung 1 model, which fully adheres to AAR/ITC standards and specifications, while designing the NCTD PTC system. This is in an effort to ensure FRA required "type approval" as well as streamlining the final FRA acceptance process. Any deviations from I-ETMS functionalities will require Request(s) for Amendment (RFA) to the FRA and may extend the timeline for FRA acceptance. The Contract has been awarded as a single Contract to be executed in two phases (based on available funding). Phase I includes the initial surveys, studies, and all design work necessary to amend the PTCDP submitted by NS, CSX, and UP to the FRA. Phase 2 includes all other work necessary for the design, installation and implementation of the PTC system. The PTC System is scoped to be completed by the mandated date of December 31, 2015 in accordance with the schedule defined in the Positive Train Control Implementation Plan (PTCIP), and must be compliant with standards and specifications developed by the ITC Committee for forthcoming publication by the Association of American Railroads (AAR). Safety is paramount. Consideration must also be given during the PTC System design to the NCTD level of service. The throughput (capacity) of the commuter railroad system must be maintained after PTC deployment, and the PTC System needs to support future capacity improvements and ridership growth.
a. Phase 1
HTI is scoped to: i. Perform the necessary studies and surveys; attend meetings; and perform the
engineering analysis, design and systems engineering necessary to amend the PTCDP per the RFA procedural requirements of 49 CFR 236.1009. HTI is scoped to provide all documentation, research, validation and verification services to ensure a "Type-Approved" system is provided to NCTD prior to commissioning.
ii. Provide for the development and submittal of a project schedule and planning for each task of the overall PTC program. HTI is scoped to develop a design, procurement and installation milestone schedule and plan construction, testing, and certification of the specified NCTD PTC System for full deployment in accordance with the milestones and deadlines established by NCTD. As part of HTI's coordination with tenant railroads, HTI shall prepare and submit an Interoperability Coordination Plan (ICP).
iii. Provide services necessary to perform detailed onboard surveys: a. Perform data collection subtasks for onboard systems. These data shall be used
in designing the removal, relocation, and installation of on board systems (both existing and new systems).
b. Develop and submit a Locomotive Survey Report and a Cab Car Survey Report. The survey report is intended to identify probable equipment mounting locations
NCTD PTC Monthly Report Page 4 of 44 Quarter Ending June 30, 2014
for all Interoperable-Electronic Train Management System (IETMS) system components, create the preliminary BOM, measure probable cable lengths required, and identify probable relocations of existing equipment.
c. Develop and submit a preliminary Bill of Materials (BOM) and a baseline Installation and Relocation manual and schematics for each locomotive, cab car, and Hy-Rail vehicle type.
b. Phase 2 Upon issuance of the second NTP for Phase 2 by NCTD, HTI is scoped to:
i. Continue with the development, procurement, and installation of the PTC System for NCTD's PTC program.
ii. Prepare all required documents for submittal to and approval by the FRA, including the PTC Safety Plan (PTCSP).
iii. Provide a complete functional PTC System in accordance with the Contract Documents in compliance with the NCTD approved milestone schedule. The system is scoped to include wayside, onboard, radio communications network, and back office server segments.
iv. Develop an installation milestone schedule. v. Plan construction, testing, and certification of the specified NCTD PTC System including
full deployment. vi. Complete an initial design incorporating all PTC System components, including pre-PTC
equipment. The PTC System proposed shall be based on NCTD's PTCIP deferred track area of the San Diego Subdivision.
vii. Be responsible for ensuring proper systems engineering processes, systems integration, system function, and correct sub-systems interaction for all aspects of the NCTD PTC System and its inter-relationships, inter-dependencies, and interfaces with other equipment and systems. The furnished PTC System shall be interoperable with the PTC Systems that are being deployed in Southern California by SCRRA and BNSF. Interoperability refers to the ability of trains to cross property boundaries under PTC at territory speed without stopping to acquire authorities. The PTC System shall also require direct or throughput communications among the PTC offices of NCTD, SCRRA, and BNSF.
viii. Coordinate all PTC activities with the FRA and the California Public Utilities Commission (CPUC) as necessary.
ix. Establish a safety program that conforms with the requirements of 49 CFR 236 Parts 214, 218, 219, CPUC General Orders, and NCTD Operating Rules; and obtain roadway worker safety training certification for all HTI and supplier, subcontractor and subconsultant personnel who may enter the NCTD San Diego Subdivision and project right-of way.
Figure 1.1 provides an overview of the NCTD PTC System Architecture.
NCTD PTC Monthly Report Page 5 of 44 Quarter Ending June 30, 2014
Figure 1.1: NCTD PTC System Architecture
1.3. Key Issues This section describes the key issues that are contributing to, or have the potential to contribute to, schedule slippage.
1.3.1. Network The fiber backbone was anticipated to be completed by NCTD in 2013; completion is now anticipated in the beginning of the third quarter of 2014. The Program Management Team is working to mitigate impacts to the PTC project.
Final design for the network component of the PTC system was transferred into the PTC project (PO #11046) from the original contract for the PTC Network Design (PO #30066) effective in November 2013. Material has been received on-site. North segment installations are complete; south segment installations are 50% complete; San Diego installations will begin in July.
1.3.2. Federal Communications Commission (FCC) As a Federal licensing agency, the Federal Communications Commission (FCC) fulfills its responsibilities under National Environmental Policy Act (NEPA) by requiring licensees to review their proposed actions for environmental consequences (47 CFR 1.1301 to 1.1319). HTI is responsible for implementing NEPA through submitting a NEPA Environmental Assessment (EA) Checklist and supporting documentation to the FCC. Of the 19 base stations, nine base stations fall outside the Nationwide Programmatic Agreement or the Collocation of Wireless Antennas, Section III – Collocation of Antennas on Towers Constructed
NCTD PTC Monthly Report Page 6 of 44 Quarter Ending June 30, 2014
on or Before March 16, 2001. HTI is required to submit an EA Checklist and supporting documentation for the remaining nine base stations prior to construction. The FCC required documentation includes: public notification, Native American consultation and Tower Construction Notification System, Survey and Viewshed Analysis, FCC 620 and 621 Application, and an EA Checklist submission. The FCC process is anticipated to complete in August 2014.
1.3.3. Wayside Interface Units (WIUs) NCTD negotiated a change order for full validation tests at select locations, as opposed to the currently contracted reduced validation tests. A dark red bulb condition was discovered by SCRRA. PRE was informed as to what change was required, and PRE incorporated a dark red bulb fix into the first revision of NCTD’s vital application programs. The modifications at EL1A and EC4 signal locations required a larger percentage of program step re-arrangement than VHLC locations. This larger percentage of re-arrangement required a full validation test instead of the reduced validation test currently contracted with TASI. This work completed in June 2014.
1.3.4. WRE’s Individual Composite CRC (Cyclic Redundancy Check) Calculator (IC3) The IC3 proposal is anticipated in the third quarter of 2014. IC3 is in development, originating as a requirement from ITC – Hazard Mitigation functionality. IC3 will be required to receive Safety Certification from the FRA. I-ETMS requires IC3, which is a new subsystem and will be a component of I-ETMS release 6.3.9, to reach full Phase 1 Independent Validation Server (IVS) functionality.
1.3.5. Non-compliant Components Some PTC components installed in the locomotives and the Bombardier Cab Car (BCC) were non-compliant with 49 CFR 238.103 Passenger Fire Safety requirements. Components were removed, and HTI and their subcontractor have provided new kits with compliant materials for reinstallation into the locomotives and BCC. The Fire Safety Analysis was accepted in June.
1.3.6. Back Office Integration between the Back Office Server (BOS), Interoperable Train Control Messaging (ITCM), and Computer Aided Dispatch (CAD) is a challenge, with ITCM being the most challenging. HTI is working with Meteorcomm, who is producing the design. The ITCM lab installation has been completed and test cases were successfully run. A fully functional BOS/CAD system is expected to be delivered in July.
1.3.7. Federated Link Each railroad has its own communications network. When networks are connected together so that communications can take place between nodes of one network and the nodes or central server of another network, the networks are termed federated. The connection from a railroad office to the federated network is the federated link.
The NCTD federated link needs to be worked through, including connections, security protocols, and business plans. HTI is currently working to link the NCTD test lab with the BNSF test lab. The Class 1 railroads are working to develop contracts and business documents to establish the link. This is an issue the industry is working through.
NCTD PTC Monthly Report Page 7 of 44 Quarter Ending June 30, 2014
2. PROGRAM MANAGEMENT
2.1. Integration Management This section describes the status of integration management, program governance, program controls, and change management process and program/project management information systems.
2.1.1. Program Governance The governance for the PTC program is organized as follows:
NCTD Organization
Chief Development Officer: Peykan Abbassi
Deputy Chief Operating Officer – Rail Systems: Eric Roe
Chief Technology Officer: Ryan Cashin
Chief Financial Officer: Ryan Bailey
Chief of Safety: Don Filippi
Deputy Chief Operating Officer – Rail Operations: Damon Blythe
Senior Network Engineer: Roy Gilbert
Rail Systems Engineer: Robert Paladino
Right of Way Officer: Tim Morehead
Public Outreach: Jill Gibson
HNTB Organization
PTC Program Manager: Mary Holland
PTC Deputy Program Manager: Anna Borrell
PTC Construction Manager and Program Scheduler: Essie Rahbari
Document Control Coordinator: Cara Smith
Business Manager: Robert Hartley
Project Analyst: Matt Daniels
PTC Quality Manager: Mike Phillips
2.1.2. Program Control The PTC program has 21 active vendor-implemented projects within the PTC program. The status of each of the 21 projects is described in section 5 of this report. The following projects are in the process of closing out:
Centralized Traffic Control (PO # 10054 OS)
Centralized Traffic Control System Design (PO # 29314)
Wayside Interface Unit (WIU) Design & Installation (PO # 29485)
Centralized Traffic Control & Operations Control Center Support Services (PO # 11032)
The total dollar value of the 21 vendor-implemented (active and closed) projects is $59,998,114.
2.1.3. Change Management The changes that are currently in process for the 21 active vendor-implemented projects are:
NCTD PTC Monthly Report Page 8 of 44 Quarter Ending June 30, 2014
PTC for the LOSSAN Corridor (PO # 11046 OS) – Herzog Technologies, Inc.
Change Order 4 includes the deletion of existing scope associated with the Wayside Segment and peer to peer radio communications network, and the addition of installation and testing of the fiber network. Change Order 4 was executed in June. The total value of this change order is $1,089,567.03 and includes 364 calendar days of concurrent, noncompensable delay. The time extension is due to scope additions that affected the contract including:
FCC process to install PTC towers
Interoperable Train Control Messaging hardware and software development requiring additional integration testing, and
Network design, installation, and testing.
South COASTER Fiber (PO # 13020 OS) - MP Nexlevel of California, Inc. Field Work Directive 5/ Change Order 9 includes the Solana Beach conduit repairs from CP Craven to Solana Beach station and also at Lomas Santa Fe Drive. Change Order 9 was executed in May. The total value of this change order is $297,256 and extends the contract 46 calendar days. Field Work Directive 6/ Change Order 4 includes added and changed Contract work due to changed conditions. Change Order 4 was executed in June. The total value of this change order is $1,085,700. Field Work Directive 7/ Change Order 10 includes the adjustment of the contract completion date by 39 days. Included in this time extension is the requirement that impacts to traffic will end on or before July 16.
San Diego Fiber Project (PO#13035 OS) – The Fishel Company Field Work Directive 7 is the repair of an existing damaged two inch duct located south of Juniper Street and includes a contract extension of 7 calendar days. The field work directive was executed in May for an amount of $3,235.06. Field Work Directive 8 is the installation of a patch panel wall mount at CP Ash Communications House. The field work directive was executed in May for an amount of $2,893.39.
Signal Upgrade – CP Friar/Taylor Street (PO#13007 OS) – Herzog Technologies, Inc. Field Work Directive 1 Includes added and changed contract work. HTI and NCTD have been negotiating this change order during the month of June. Change order approval is anticipated in July.
2.1.4. Program/Project Management Information Systems The current document control software was assessed for adequacy and will be maintained at this time.
NCTD PTC Monthly Report Page 9 of 44 Quarter Ending June 30, 2014
2.2. Scope Management The Contract Document Requirements List (CDRL) for the PTC project is being cross-checked against the schedule to ensure contract requirements. This task will be repeated several times throughout the duration of the program so that adjustments can be made where applicable.
2.3. Configuration Control Management The Configuration Control Management Plan (CCMP) and the Field Control Management Plan (FCMP) went through additional internal reviews in May and June. The FCMP was issued to the FRA for informal review; the FCMP and CCMP are planned for formal submittal to the FRA third quarter 2014. HTI continues to develop the Interface Management Plan (IMP) with submittal to NCTD anticipated in July.
The next Configuration Control Board (CCB) meeting is scheduled for July; action items include establishing logistics of the CCB workflow.
2.4. Quality Management
2.4.1. Quality Plans The quality plans being used for the PTC program include:
NCTD Quality Plan, Rev A, January 2012
HTI PTC Project
FTA Quality Management System Guidelines, FTA-PA-27-5194-12.1, December 2012
HTI System Quality Plan, Rev 1, April 2012
Wabtec Quality Plan – Onboard Installation, Rev 2, August 2013
Wabtec I-ETMS Onboard Software Quality Assurance Plan, Rev 1, August 2013
CCI Quality Documents, Rev 0, May 2013
HTI Quality Assurance Manual, Rev G, July 2013
NCTD Program Support and Design
HNTB Quality Assurance/Quality Control Manual, Rev 1, October 2004
PRE Design Quality Process, 10/2/2010
2.4.2. Deficiency Notices (DN), Nonconformance Reports (NCR), Corrective Action Reports (CAR)
The HNTB Quality Manager and the HTI System Quality Manager meet on a weekly basis to review the current status of the project DNs, NCRs, and CARs. These items are defined as follows:
DNs are items that have been identified as being deficient but not in nonconformance. These items can remain installed and in operation until they are either repaired or otherwise brought out of deficient standing.
NCRs are items that have been identified where there is a discrepancy in characteristic, documentation or procedure which affects form, fit, or function and renders the quality of an item unacceptable or indeterminate in regard to meeting relevant project requirements.
CARs are measures taken to rectify conditions adverse to quality and to avoid repetition.
NCTD PTC Monthly Report Page 10 of 44 Quarter Ending June 30, 2014
Table 2.1 summarizes the total number of DNs, NCRs, and CARs that the HNTB Quality Manager is tracking for the PTC project:
Table 2.1: Quality Tracking
Item Quantity Open items Closed items
Deficiency Notices 13 5 8
Nonconformance Reports 0 0 0
Corrective and Preventative Actions 4 4 0
The work needed to resolve deficiency notices will be scheduled to coincide with other work taking place at the same locations in order to be as efficient and productive as possible.
2.4.3. PTC Quality Audits and Surveillances The HNTB Quality Manager is working with the HTI System Quality Manager on the following:
Quality Records - HTI uses a project management software program called Fogbugz to conduct quality checks and to maintain quality records. Although this program is proprietary and only accessible by HTI employees, the HTI System Quality Manager will be coordinating efforts with the HNTB Quality Manager to provide quality documents in a timely fashion when requested. HTI is developing a plan to transfer all quality records over to NCTD per the contract requirements for the project. Once developed, the plan will be submitted for review.
Audits - The HTI System Manager conducted an audit of Convergent Communications, Inc. (CCI) in October 2013 and submitted the Audit to NCTD in June 2014. This Audit and the procedures added to the CCI Quality Plan are under review. HTI conducted an internal audit on Process Control.
2.4.4. Corrective Action Reports (CAR) The HNTB Quality Manager is monitoring the progress of the following Corrective Action Reports for the PTC project:
2.4.4.1. CAR – 001 (220 MHz Antenna) Issue Date of 11/22/13 NCTD inspected and documented that the HTI subcontractor did not follow the installation guide with regard to the 220 MHz Antenna installation on top of the roof of the locomotive. This issue has been addressed by HTI directing their subcontractor to comply with the NCTD approved installation guide.
Update: Corrective and Preventative Actions have been incorporated into the Installation Guides. The preventative action will be inserted into the CAR by the HTI System Quality Manager. The antennas will be reinstalled in their new location during the BCC pilot installation which began on June 25, 2014.
Estimated Closure Date: 7/31/14 DN Log No. 003
2.4.4.2. CAR – 002 (F59 Conduit Clamp Welding Protocol) Issue Date of 12/05/13 The HNTB Quality Manager attended a final PTC equipment installation construction inspection (surveillance) for the F59 Locomotive. It was during this surveillance when it was discovered that there was a possible welding issue that is resulting in additional monitoring by TASI staff. A conduit clamp on the wheel truck was welded by HTI’s subcontractor who
NCTD PTC Monthly Report Page 11 of 44 Quarter Ending June 30, 2014
was not trained by TASI regarding the proper location of where to place the grounding clamps on the locomotive. As a result, the wheel bearing may have been damaged. HTI has noted the potential welding issue on their installation paperwork. The HNTB Quality Manager will be involved with the review of the CAR by HTI.
Update: Information is to be added to the installation guides regarding grounding location approval prior to beginning the welding work. The preventative action will be inserted into the CAR as well as other relevant quality documents by the HTI System Quality Manager.
Estimated Closure Date: 8/31/14 DN Log No. 009
2.4.4.3. CAR – 003 (F40, F59, BCC Non-Compliant Materials) Issue Date of 12/18/13 NCTD received notification on December 17, 2013 that some components installed in the vehicles were non-compliant with 49 CFR 238.103 Passenger Fire Safety requirements as evidenced by a Fire, Smoke, and Toxicity (FST) test.
Update: Fire Safety Analysis has been completed and approved. The installation of compliant components began as part of the new Pilot installation which began on June 25, 2014.
Estimated Closure Date: 7/31/14 DN Log No. 011
2.4.4.4. CAR – 004 (F40 Tri-Mode Antenna) Issue Date of 3/18/14 (est.) During a survey of the F40 for the Fire Safety Analysis, Wabtec discovered that the installer had cut through some structural beams during the installation of the Tri-mode Antenna. Since this was discovered, Wabtec has developed a plan to repair the roof and the structural beams.
Update: The F40 Roof and Beam Repair Procedure was approved and will be performed during the Pilot Installation.
Estimated Closure Date: 8/31/14 DN Log No. 012
2.4.5. Quality Tasks The HNTB Quality Manager coordinated and participated in a Software Quality Assurance Plan webinar that took place on April 15 whereby HNTB, NCTD, and HTI staff were allowed to view and to ask questions pertaining to the quality procedures that Wabtec is following in the development of their software for the I-ETMS and the TMDS programs for PTC. Additional meetings have taken place to continue the review of these documents. Four documents remain to be reviewed by HNTB technical staff prior to approval of the Software Quality Assurance Plan.
The Onboard installations began on June 25 and are anticipated to extend through August. The HNTB Quality Manager and the NCTD Quality Control staff are providing full-time Quality Assurance inspection services during the Pilot Installations. Network installations have also begun with continuous NCTD Quality Inspection oversight during construction.
NCTD PTC Monthly Report Page 12 of 44 Quarter Ending June 30, 2014
2.5. Risk Management Monitoring of project risk is ongoing by the NCTD and HTI project teams. A Risk Management Plan (RMP) has been developed and is reviewed on a monthly basis.
2.6. Stakeholder and Communications Management NCTD communicated to stakeholders about the broader PTC project, antenna installations, and fiber network. This included communications with City Staff, SANDAG, neighbors, written notices, e-mail communications, and website updates. Outreach prior to each tower installation and alongside the fiber work occurred in September and has been subsequently suspended while the team works through the FCC permit issues.
NCTD PTC Monthly Report Page 13 of 44 Quarter Ending June 30, 2014
3. PROGRAM SAFETY
Per the National Transportation Safety Board (NTSB)’s Safety Recommendations dated June 18, 2013, Tables 3.1 and 3.2 reflect the progress being made on the required components and training for the NCTD PTC program.
The on-board installations began in June 2014 upon completion and acceptance of the fire safety analysis. The completion date for the on-board installations is May 2015.
Nearly 75 percent of the wayside units have been installed. HTI’s most recent estimated completion date is September 2014.
Installation of the base station radios is just over 50 percent complete, with 10 of the 19 base station radios installed. The estimated completion date of the FCC process is August 2014, with the tower construction completing in September 2014.
Table 3.1: Components
Component Description Total
Components Completed Remaining
Percent Complete
Estimated Completion Date
Locomotives F40 (x5) F59 (x2)
BCC (x10) 17 0 17 0% May-2015
Wayside Units VHLC EC4
EL-1A 48 36 12 75% Sept-2014
Switches Not Applicable
Base Station Radios Meteorcomm 19 10 9 53% Sept-2014
Locomotive Radios Meteorcomm 17 0 17 0% May-2015
Wayside Radios Not Applicable
New/novel technologies (if applicable)
0 0 0 0% TBD
Training activities, shown in Table 3.2, are anticipated to begin in the first quarter of 2015.
Table 3.2: Training
Classification/ Craft
Training Description
Total Employees
Employees Trained
Employees Remaining
Percent Trained
Estimated Completion Date
NCTD Mgmt/Ops Simulator TBD 0 TBD 0% Feb-2015
NCTD Mgmt/Ops Hy-Rail
Test Vehicle TBD 0 TBD 0% Feb-2015
NCTD Operations General PTC TBD 0 TBD 0% Feb-2015
NCTD Mechanical General PTC TBD 0 TBD 0% Feb-2015
NCTD Dispatch General PTC TBD 0 TBD 0% Feb-2015
NCTD Mgmt/Ops GIS Mapping Tool TBD 0 TBD 0% Mar-2015
NCTD Mgmt/Ops Communications TBD 0 TBD 0% Feb-2015
NCTD Mgmt/Ops Back Office TBD 0 TBD 0% Mar-2015
NCTD PTC Monthly Report Page 14 of 44 Quarter Ending June 30, 2014
4. PROGRAM PROGRESS
4.1. Schedule Development The PTC program schedule is being updated to incorporate Capital Improvement Projects (CIP) inputs affecting the PTC system.
4.2. Critical Path Figure 4.1 presents the critical path graphic for the HTI Contract No. 11046 June 2014 Project Schedule Update, comparing the June 2014 critical path with the October 2013 schedule.
NCTD and FRA coordination efforts have revealed that the estimated one year of FRA Review may be reduced by an estimated six months based on progressive PTCSP submittals rather than a fully complete PTCSP submittal at the conclusion of FRA testing. This has the potential to mitigate approximately six months of project delay, contingent upon the actual occurrence of events.
HTI is reporting Safety Plan submittal in September 2015. Figure 4.2, Milestone Summary, shows the new PTC System Certification by the FRA completion date to be September 12, 2016. This date represents approximately nine months of total delay from the federally mandated date of December 31, 2015. The nine months of delay is partially mitigated by a six month FRA review as opposed to a 12 month FRA review. The June 2014 schedule addsadditional delay from the October 2013 update completion date. The project team continues to work to recover schedule.
Figure 4.3, Schedule Summary, is a rollup of the major elements of work, with Certification and Acceptance concluding in January 2017.
NCTD PTC Monthly Report Page 15 of 44 Quarter Ending June 30, 2014
Figure 4.1: Monthly Progress Report - Critical Path for HTI Contract PO#11046: Oct ’13 vs. June ‘14
NCTD PTC Monthly Report Page 16 of 44 Quarter Ending June 30, 2014
Figure 4.2: Milestone Summary for HTI Contract PO#11046
Figure 4.3: Project Schedule Summary for HTI Contract PO#11046
NCTD PTC Monthly Report Page 17 of 44 Quarter Ending June 30, 2014
5. POSITIVE TRAIN CONTROL CONTRACTS AND STATUS
The PTC Program has 21 vendor-implemented projects from the Orange County Line to the Santa Fe Depot. The total dollar value of the 21 active vendor-implemented projects is $59,998,114, which has increased since the previous reporting due executed change orders. Table 5.1 provides “at-a-glance” information for the 21 projects. Additional detail on the progress and financial status is provided in Tables 5.2 through 5.22.
Table 5.1: PTC Program Projects Summary
NCTD Tracking Number
Project Name Contractor Contract Amount
Status Table #
on report
PTC Vendor-Integrator Project
11046 PTC for the LOSSAN Corridor Herzog Technologies, Inc.
$36,322,949 On-Going 5.2
COASTER Fiber Cable & Conduit Installation Projects
13013 North COASTER Fiber The Fishel Company
$1,308,968 Closed 5.3
13020 South COASTER Fiber MP Nexlevel $5,685,478 On-Going 5.4
13035 San Diego Fiber The Fishel Company
$187,037 On-Going 5.5
Other PTC Program Implemented Projects
10054 Centralized Traffic Control HTSI $2,512,625 Close-Out 5.6
29314 Centralized Traffic Control System Design
Pacific Railway Enterprises, Inc.
$323,633 Close-Out 5.7
29485 Wayside Interface Unit (WIU) Design & Installation
$136,461 Close-Out 5.8
29895 Design Support During Construction $2,325,000 On-Going 5.9
11032 Centralized Traffic Control & Operations Control Center Support Services
Macro Corp. $351,307 Close-Out 5.10
29935 Engineering Support Services HNTB $7,538,339 On-Going 5.11
12024 Configuration Management Software RailCar Management
$688,119 On-Going 5.12
30475 Environmental Support Services BRG Consulting $661,297 On-Going 5.13
29504 CTC/PTC Network Design & Implementation
Datel Systems
$177,528 Closed 5.14
30066 PTC Network Design $81,908 Closed 5.15
13003 Test & Training Facility Equipment $170,799 Closed 5.16
30374 PTC Lab Install (Task 2) $3,880 Closed 5.17
30616 Additional Requirements to PO 30374 $0 Closed 5.18
30265 Task Order: PTC Lab Cabling $12,000 Closed 5.19
30729 TMDS Network Extension $76,233 Closed 5.20
30073 PTC Signal Maintainer & WIU Installation TASI $600,306 On-Going 5.21
13007 Signal Upgrade – CP Friar/Taylor Street Herzog Technologies, Inc.
$834,246 On-Going 5.22
Miscellaneous* TASI Flagging and NCTD Personnel costs Pending
* These miscellaneous items include potential purchase orders. When approved they will become part of the PTC Program active vendor-implemented projects
NCTD PTC Monthly Report Page 18 of 44 Quarter Ending June 30, 2014
Table 5.2: Positive Train Control System for the LOSSAN Corridor; NCTD PO#11046
6/30/2014
NCTD PURCHASE ORDER
11046
PROJECT STATUS
BCC roof repair: Items of work from the February installation remain open. Wabtec is working with Bombardier to order a
replacement panel. Quality close-out documentation is being prepared. The roof repair procedure was approved for work;
Wabtec plans to perform the work during the pilot retrofit.
WAYSIDE:
WIU installations are completed. Preliminary WIU testing is anticipated to be completed at the end of July.
Installations at 10 of 19 base station locations have been completed. Public and newspaper notifications are complete.
HTI/URS and NCTD held an in-person review meeting with SHPO on June 17th. Construction is anticipated to begin once the
FCC process completes in mid-August. Construction anticipated to complete in early September.
HTI received FRA's comments on the Test Waiver; HNTB has reviewed response to comments. HTI is incorporating
responses.
Anticipated completion date for all testing is early September 2014.
NETWORK:
HTI is moving forward with a template approach for the site designs - 80% of site designs are complete; HTI, NCTD, and PRE
meet weekly prior to installations.
Network installations north of OTC have completed; installations are underway south of OTC. Fiber testing north of OTC is
complete. Fiber terminations and testing south of PTC is pending completion of NCTD's fiber installation projects.
DOCUMENTATION:
BRIEF PROJECT DESCRIPTION
The PTC System for the LOSSAN Corridor is the primary contract for implementation of the PTC system.
On-Going
The Interoperability Coordination Plan continues to be under revision with coordination occurring between NCTD and their
tenants.
The Configuration Control Management Plan (CCMP), and Field Configuration Management Plan (FCMP) are under review;
final submittals are anticipated in July. The Field Control Management Plan has been informally reviewed by the FRA and edits
are underway.
The Fire Safety Analysis for compliant materials was completed and approved in mid-June. The onboard pilot installations
have resumed and the first vehicle (Bombardier Cab Car) is scheduled to be completed in mid-July. Change Order 4 has
been executed.
The Configuration Control Management Plan (CCMP) and Field Configuration Management Plan (FCMP) are under review;
final submittals are anticipated in July. The Field Control Management Plan has been informally reviewed by the FRA and edits
are underway.
PTCIP and RFA‐ NCTD has uploaded the PTCIP and RFA have been uploaded to the SIR site.
COMMUNICATIONS:
ATCS Antenna Install Proposal is under review by HTI.
ONBOARD:
The Fire Safety Analysis was approved for work.
BACK OFFICE:
ITCM 1.3 has been deployed and validated in the lab. The lab is being updated to ITCM 1.4. Production validation testing is
anticipated to be complete by the end of July. Production to field pre-testing is anticipated to begin in early August.
A full functional BOS/CAD system is anticipated in mid-July; sub-segment testing will begin upon arrival.
IC3 documentation is under review by HTI.
PROJECT STATUS TABLE FOR PERIOD ENDED
PROJECT NAME CONTRACTOR/CONSULTANT
PTC for the LOSSAN Corridor Herzog Technologies, Inc.
The BCC Pilot retrofit installation started on June 25th and will be followed by the F40 and the F59 pilot.
PTCSP has been returned to HTI as furnish as noted; HTI is working on incorporating responses into the document.
NCTD PTC Monthly Report Page 19 of 44 Quarter Ending June 30, 2014
(Table 5.2 continuation from previous page)
CONTRACT DATES
08/19/2011
07/31/2012
08/15/20141
10/30/2014
12/29/2016
COMPLETION UPDATE COST UPDATE
Contract Amount $36,322,949
Spent to Date $23,196,242
Encumbered $13,126,707
CONTRACT & BUDGET INFORMATION
Description Contract Amount Date Executed
Original Contract Value $31,730,104 5-Aug-11
Change order 001 $237,000 5-Oct-12
Change order 002 $809,415 21-Jan-13
Change order 003 $2,456,863 21-Jun-13
Change order 004 $1,089,567 16-Jun-14
CONTRACTOR/CONSULTANT SUBMITTALS DURING THIS PERIOD
0678 - 2 EMI/EMC Assessment
0682 - 0 Bombardier Cab Car Production Bill of Materials
0682 - 1 Bombardier Cab Car Production Bill of Materials
0687 - 4 90% Network Design CP San Onofre PTC Equipment M.P. 212.3
0381 - 2 PTC Production Schematic - F40 Locomotive
0381 - 3 PTC Production Schematic - F40 Locomotive
0484 - 2 Positive Train Control Safety Plan (PTCSP) Draft
0527 - 4 Configuration Control Management Plan
0623 - 2 Locomotive F40P2HM Onboard Equipment Production Bill of Materials Part 2
0682 - 2 Bombardier Cab Car Production Bill of Materials
Phase 2: Procurement/Installation/Testing 50%
System Safety Certification Not Started
System Commissioning into Revenue Service Not Started
NTP
0623 - 1 Locomotive F40P2HM Onboard Equipment Production Bill of Materials Part 2
0650 - 1 Staging Plan
0677 - 5 90% Network Design CP Songs PTC Equipment M.P. 209.2
0669 - 1 PTC Production Schematic - Bi-Level Cab Car
0669 - 2 PTC Production Schematic - Bi-Level Cab Car
0492 - 1 CCI Quality Documents
0527 - 3 Configuration Control Management Plan
0617 - 2 Production I-ETMS Installation and Relocation Guide - F40 Locomotive
0617 - 3 Production I-ETMS Installation and Relocation Guide - F40 Locomotive
0258 - 2 GPS Study Result for Downtown San Diego Area
Phase 1: Development Completed
Phase 2: Procurement/Installation/Testing
System Safety Certification
0295 - 0 TMDS Back Office Server Requirements Specification
Phase 1 includes the initial surveys, studies, and all design w ork necessary to amend the Positive Train Control Development Plan (PTCDP)
submitted by NS, CSX, and UPRR to the FRA. This Phase has been completed. An amended PTCDP w as not needed at the time this phase w as
completed. Once lab testing is underw ay, the PTCDP may be revisited.
Phase 2 includes all other w ork necessary for the design, installation and implementation of the PTC system.1Date defined in the Professional Services Agreement subsection 20 Liquidated Damages.
Phase 1: Development Completed 100%
System Commissioning into Revenue Service
OTHER ISSUES:
None.
NCTD PTC Monthly Report Page 20 of 44 Quarter Ending June 30, 2014
(Table 5.2 continuation from previous page)
Figure 5.1 shows the S-curve for the PTC project (PO 11046) dollars budgeted versus expended. The equation used to formulate the S-Curve is a logistic differential formula, which creates a graphic display of cumulative estimated costs plotted against time. S-Curve forecasting assumes slow initial growth, subsequent rapid growth, followed by declining growth as saturation levels are achieved. The essential
0833 - 0 90% Design Test and Training Facility EL-1A Simulation Rack
0841 - 0 Locomotive F59PHI Onboard Equipment Production Bill of Materials
0843 - 0 Network Testing (NT)
0826 - 0 Network Installation Templates
0827 - 0 System Network Architecture
0827 - 1 System Network Architecture
0829 - 0 PTC Production Schematic - F59 Locomotive
0831 - 0 Product Vendor List (PTCPVL) May 2014 Update
0819 - 2 Production I-ETMS Installation and Relocation Guide - Bombardier Cab Car
0820 - 0 Reassignment of Key Personnel
0821 - 0 GPS Coverage Analysis
0824 - 0 NCTD Coaster Subdivision Independent Review of Theoretical Train Braking Calculations
0825 - 0 Network Patching Spreadsheet
0810 - 0 CDU Placement and Acceptance
0816 - 0 Project Schedule Update April 2014
0816 - 1 Project Schedule Update April 2014
0819 - 0 Production I-ETMS Installation and Relocation Guide - Bombardier Cab Car
0819 - 1 Production I-ETMS Installation and Relocation Guide - Bombardier Cab Car
0802 - 0 90% Network Design CP Longboard PTC Equipment M.P. 228.4
0802 - 1 90% Network Design CP Longboard PTC Equipment M.P. 228.4
0803 - 0 90% Network Design CP Carl PTC Equipment M.P. 229.6
0803 - 1 90% Network Design CP Carl PTC Equipment M.P. 229.6
0805 - 0 Interim Track Chart
0795 - 2 I-ETMS Fire Safety Analysis Report
0795 - 3 I-ETMS Fire Safety Analysis Report
0795 - 4 I-ETMS Fire Safety Analysis Report
0801 - 0 90% Network Design CP Escondido Jct PTC Equipment M.P. 226.8
0801 - 1 90% Network Design CP Escondido Jct PTC Equipment M.P. 226.8
0784 - 1 90% Network Design CP Eastbrook PTC Equipment M.P. 225.3
0790 - 0 Project Schedule Update March 2014
0790 - 1 Project Schedule Update March 2014
0790 - 2 Project Schedule Update March 2014
0795 - 1 I-ETMS Fire Safety Analysis Report
0781 - 1 WIU Test Procedure CP Cardiff M.P. 239.7
0782 - 1 NCTD Master Test Plan
0784 - 0 90% Network Design CP Eastbrook PTC Equipment M.P. 225.3
0723 - 3 90% Network Design CP Stuart PTC Equipment M.P. 221.7
0733 - 1 Fiber Patch Cable
0758 - 2 F40 Roof and Beam Repair Procedure
0844 - 0 NCTD Radio Test Program
0767 - 2 Project Schedule Update February 2014
0758 - 3 F40 Roof and Beam Repair Procedure
0702 - 3 90% Network Design Intermediate Signal 2155 PTC Equipment M.P. 215.5
0724 - 1 90% Network Design CP Farr PTC Equipment M.P. 231.6
NCTD PTC Monthly Report Page 21 of 44 Quarter Ending June 30, 2014
concept of this function illustrates that the rate of growth is proportional to both the amount of growth already accomplished and the amount of growth remaining to be accomplished.
The expended amount shows the total amount that NCTD has paid to HTI as of June 30, 2014.
Figure 5.1: PTC Project (PO 11046) Budgeted versus Expended
NCTD PTC Monthly Report Page 22 of 44 Quarter Ending June 30, 2014
San Diego Subdivision Fiber Installation
The San Diego Subdivision fiber installation is comprised of three geographically based contracts as listed below and shown in Figure 5.2:
North COASTER – Orange County Line to Oceanside Transit Center
South COASTER – Oceanside Transit Center to Old Town Transit Center
San Diego – Old Town Transit Center to Santa Fe Depot
All three contracts include the installation of fiber conduit and cable along the San Diego Subdivision right-of-way to provide fiber for the PTC communication system. Status and financial information on the individual contracts is provided on Tables 5.3, 5.4 and 5.5.
Figure 5.2: San Diego Subdivision Fiber Installation
North COASTER Fiber (Orange County Line to Oceanside Transit Center)
Status: Closed
South COASTER Fiber (Oceanside Transit Center to Old Town Transit Center)
Status: Construction underway
San Diego Fiber (Old Town Transit Center to Santa Fe Depot)
Status: In close-out
NCTD PTC Monthly Report Page 23 of 44 Quarter Ending June 30, 2014
Table 5.3: North COASTER Fiber; NCTD PO#13013
6/30/2014
NCTD PURCHASE ORDER
13013
PROJECT STATUS
CONTRACT DATES
11/29/2012
06/10/2013
COMPLETION UPDATE COST UPDATE
Contract Amount $1,308,968
Spent to Date $1,308,968
Encumbered $0
CONTRACT & BUDGET INFORMATION
Description Contract Amount Date Executed
Original Contract Value $1,068,136 29-Nov-12
Change order 001 $88,532 22-Jan-13
Change order 002 $56,962 29-Jan-13
Change order 003 $52,260 27-Feb-13
Change order 004 $43,078 2-Oct-13
CONTRACTOR/CONSULTANT SUBMITTALS DURING THIS PERIOD
PROJECT STATUS TABLE FOR PERIOD ENDED
PROJECT NAME CONTRACTOR/CONSULTANT
North COASTER Fiber The Fishel Company
BRIEF PROJECT DESCRIPTION
This contract is one of three contracts for fiber conduit and cable installation along the San Diego Subdivision right-of-way to
provide fiber for the PTC communication system. Project limits are from the Orange County Line to Oceanside Transit Center.
Closed
Fiber test results reviewed with no discrepancies noted.
NTP
None
Contract Completion
Conduit Installation 100%
Fiber Installation 100%
NCTD PTC Monthly Report Page 24 of 44 Quarter Ending June 30, 2014
Table 5.4: South COASTER Fiber; NCTD PO#13020
6/30/2014
NCTD PURCHASE ORDER
13020
PROJECT STATUS
CONTRACT DATES
01/03/2013
09/30/2013
01/28/2014
05/15/2014
08/08/2014
COMPLETION UPDATE COST UPDATE
Contract Amount $5,685,478
Spent to Date $4,671,418
Encumbered $1,014,060
CONTRACT & BUDGET INFORMATION
Description Contract Amount Date Executed
Contract Value $4,959,010 3-Jan-13
Change order 001 $70,218 8-Apr-13
Change order 005 $7,500 23-Jan-14
Change order 006 $197,667 7-Mar-14
Field Work Directive 004 $50,363 10-Apr-14
Change order 007 $0 28-Apr-14
Change order 009 (FWD005) $297,256 19-Jun-14
Change order 004 (FWD006) $1,089,567 19-Jun-14
Change order 010 (FWD007) $0 24-Jun-14
CONTRACTOR/CONSULTANT SUBMITTALS DURING THIS PERIOD
The project is currently 99% complete. NCTD and MP Nexlevel negotiated a final change order (Change Order 4) which was
issued in mid-June; change order 4 incorporated all previous outstanding changes for this Contract. Change Order 9 was issued
to incorporate the repair work at Solana Beach. This work started on June 16th and is anticipated to be completed in July 2014.
The final fiber testing is anticipated to begin in July 2014. Change Order 10 was issued at the end of June, extending the contract
completion date to August 8, 2014.
Contract Completion
Change Order 10 Contract completion
Conduit Installation 100%
Fiber Installation 97%
None
Original Contract NTP
Amendment 1 NTP
Amendment 1 Contract completion
BRIEF PROJECT DESCRIPTION
This contract is one of three contracts for fiber conduit and cable installation along the San Diego Subdivision right-of-way to
provide fiber for the PTC communication system. Project limits are from the Oceanside Transit Center to the Old Town Transit
Station.
On-Going
PROJECT STATUS TABLE FOR PERIOD ENDED
PROJECT NAME CONTRACTOR/CONSULTANT
South COASTER Fiber MP Nexlevel
NCTD PTC Monthly Report Page 25 of 44 Quarter Ending June 30, 2014
Table 5.5: San Diego Fiber; NCTD PO#13035
6/30/2014
NCTD PURCHASE ORDER
13035
PROJECT STATUS
CONTRACT DATES
10/03/2013
05/16/2014
COMPLETION UPDATE COST UPDATE
Contract Amount $187,037
Spent to Date $185,115
Encumbered $1,922
CONTRACT & BUDGET INFORMATION
Description Contract Amount Date Executed
Original Contract Value $161,569 3-Oct-13
Change Order 001 $0.00 26-Dec-13
Change Order 002 $22,914.15 3-Feb-14
Change Order 003 $26,011.08 10-Feb-14
Change Order 004 -$29,226.47 4-Mar-14
Change Order 005 $5,769.49 2-Apr-14
Change Order 006 $3,358.70 25-Apr-14
Change Order 007 $3,235.06 5-May-14
Change Order 008 $2,893.39 14-May-14
CONTRACTOR/CONSULTANT SUBMITTALS DURING THIS PERIOD
None
NTP
Contract Completion
Conduit Installation 98%
Fiber Installation 98%
BRIEF PROJECT DESCRIPTION
This contract is one of three contracts for fiber conduit and cable installation along the San Diego Subdivision right-of-way to
provide fiber for the PTC communication system. Project limits are from the communication house at Old Town Transit Station
to Santa Fe Depot.
On-Going
All construction activity was completed on May 16,2014. The contract is not closed yet, awaiting resolution of as-built
discrepancy.
PROJECT STATUS TABLE FOR PERIOD ENDED
PROJECT NAME CONTRACTOR/CONSULTANT
San Diego Fiber The Fishel Company
NCTD PTC Monthly Report Page 26 of 44 Quarter Ending June 30, 2014
Table 5.6: Centralized Traffic Control; NCTD PO#10054
6/30/2014
NCTD PURCHASE ORDER
10054
PROJECT STATUS
CONTRACT DATES
01/21/2011
02/20/2012
COMPLETION UPDATE COST UPDATE
Contract Amount $2,512,625
Spent to Date $1,973,214
Encumbered $539,411
CONTRACT & BUDGET INFORMATION
Description Contract Amount Date Executed
Contract Value $1,912,815 21-Jan-11
Change order 001 $497,684 8-Jul-11
Change order 002 - 8-Jul-11
Change order 003 $46,140 14-Sep-11
Change order 004 $49,834 8-Dec-11
Change order 005 $2,500 30-Jan-12
Change order 006 $3,652 24-Apr-13
CONTRACTOR/CONSULTANT SUBMITTALS DURING THIS PERIOD
Contract Completion1
1Note: Date reflects PTC portion of purchase order
-
None
NTP
PROJECT STATUS TABLE FOR PERIOD ENDED
PROJECT NAME CONTRACTOR/CONSULTANT
Centralized Traffic Control HTSI
BRIEF PROJECT DESCRIPTION
This contract is for design and support of centralized traffic control for the PTC project
Close-Out
Final acceptance completed. Software license agreement is under continuing review. HTI is handling all future changes to
TMDS, per HTSI maintenance agreement.
This contract is complete and is in the process of being closed.
NCTD PTC Monthly Report Page 27 of 44 Quarter Ending June 30, 2014
Table 5.7: Centralized Traffic Control System Design; NCTD PO#29314
Table 5.8: Wayside Interface Unit (WIU) Design & Installation; NCTD PO#29485
6/30/2014
NCTD PURCHASE ORDER
29314
PROJECT STATUS
CONTRACT DATES
01/28/2011
12/31/2015
COMPLETION UPDATE COST UPDATE
Contract Amount $323,633
Spent to Date $235,627
Encumbered $88,006
CONTRACT & BUDGET INFORMATION
Description Contract Amount Date Executed
Original Contract Value $323,633 18-May-12
CONTRACTOR/CONSULTANT SUBMITTALS DURING THIS PERIOD
Contract Completion
-
None
NTP
PROJECT STATUS TABLE FOR PERIOD ENDED
PROJECT NAME CONTRACTOR/CONSULTANT
Centralized Traffic Control System Design Pacific Railway Enterprises, Inc.
BRIEF PROJECT DESCRIPTION
This contract provides design support for the centralized traffic control (CTC) system.
Close-Out
This contract is complete and is in the process of being closed.
6/30/2014
NCTD PURCHASE ORDER
29485
PROJECT STATUS
CONTRACT DATES
05/19/2011
12/31/2015
COMPLETION UPDATE COST UPDATE
Contract Amount $136,461
Spent to Date $136,440
Encumbered $21
CONTRACT & BUDGET INFORMATION
Description Contract Amount Date Executed
Original Contract Value $136,461 11-Apr-12
CONTRACTOR/CONSULTANT SUBMITTALS DURING THIS PERIOD
Contract Completion
-
None
NTP
PROJECT STATUS TABLE FOR PERIOD ENDED
PROJECT NAME CONTRACTOR/CONSULTANT
Wayside Interface Unit (WIU) Design & Installation Pacific Railway Enterprises, Inc.
BRIEF PROJECT DESCRIPTION
This contract provides design support and installation programming services for wayside interface units (WIU).
Close-Out
This contract is complete and is in the process of being closed.
NCTD PTC Monthly Report Page 28 of 44 Quarter Ending June 30, 2014
Table 5.9: Design Support During Construction; NCTD PO#29895
6/30/2014
NCTD PURCHASE ORDER
29895
PROJECT STATUS
CONTRACT DATES
11/08/2011
12/31/2015
COMPLETION UPDATE COST UPDATE
Contract Amount $2,325,000
Spent to Date $1,065,048
Encumbered $1,259,952
CONTRACT & BUDGET INFORMATION
Description Contract Amount Date Executed
Contract Value $2,325,000 8-Nov-11
CONTRACTOR/CONSULTANT SUBMITTALS DURING THIS PERIOD
The consultant is providing ongoing design reviews and inspection services for the PTC project.
Contract Completion
-
None
NTP
BRIEF PROJECT DESCRIPTION
This contract provides signal and communication systems support for the PTC project as well as inspection services.
On-Going
PRE is providing construction inspection services for the San Diego Fiber and the South Fiber Contracts, and monitoring
contract performance, submittals, and schedule for the CP Friar project.
PROJECT STATUS TABLE FOR PERIOD ENDED
PROJECT NAME CONTRACTOR/CONSULTANT
Design Support During Construction Pacific Railway Enterprises, Inc.
NCTD PTC Monthly Report Page 29 of 44 Quarter Ending June 30, 2014
Table 5.10: Centralized Traffic Control & Operations Control Center (OCC) Support Services; NCTD PO#11032
6/30/2014
NCTD PURCHASE ORDER
11032
PROJECT STATUS
CONTRACT DATES
05/13/2011
05/12/2016
COMPLETION UPDATE COST UPDATE
Contract Amount $351,307
Spent to Date $351,307
Encumbered $0
CONTRACT & BUDGET INFORMATION
Description Contract Amount Date Executed
Contract Value $351,307 13-May-11
CONTRACTOR/CONSULTANT SUBMITTALS DURING THIS PERIOD
Task 1 CTC: Final acceptance is underway.
Contract Completion
-
None
NTP
BRIEF PROJECT DESCRIPTION
This contract provides support for the centralized traffic control system and the operations control center.
Close-Out
Task 2: NCTD selected the 810 Mission building as the location for the Primary Operations Command Control Center. The
OCC will support PTC, Code Enforcement, Call Center, Bus Dispatch, and Rail Dispatch. This project is being completed
outside the PTC program; Macro’s purchase order will be closing.
PROJECT STATUS TABLE FOR PERIOD ENDED
PROJECT NAME CONTRACTOR/CONSULTANT
Centralized Traffic Control & Operations Control Center
(OCC) Support Services
Macro Corp.
NCTD PTC Monthly Report Page 30 of 44 Quarter Ending June 30, 2014
Table 5.11: Engineering Support Services; NCTD PO#29935
Table 5.12: Configuration Management Software; NCTD PO#12024
6/30/2014
NCTD PURCHASE ORDER
29935
PROJECT STATUS
CONTRACT DATES
12/07/2011
12/31/2015
COMPLETION UPDATE COST UPDATE
Contract Amount $7,538,339
Spent to Date $3,437,697
Encumbered $4,100,642
CONTRACT & BUDGET INFORMATION
Description Contract Amount Date Executed
Contract Value $2,620,999 7-Dec-11
Amendment 1 $4,917,340 4-Mar-14
CONTRACTOR/CONSULTANT SUBMITTALS DURING THIS PERIOD
PROJECT STATUS TABLE FOR PERIOD ENDED
PROJECT NAME CONTRACTOR/CONSULTANT
Engineering Support Services HNTB
BRIEF PROJECT DESCRIPTION
This contract provides continuing support, guidance and monitoring of the PTC project. Scope includes design submittal
review, as needed design work, scheduling services, and general project management.
On-Going
HNTB Program Management efforts are ongoing. HNTB has assigned six full-time employees to the project. All are co-located
at the NCTD offices in Oceanside (Tremont office); additional staff support is being identified to further support the PTC
program and project management efforts identified as necessary by NCTD management.
NTP
Contract Completion
-
None
6/30/2014
NCTD PURCHASE ORDER
12024
PROJECT STATUS
CONTRACT DATES
09/05/2012
09/05/2017
COMPLETION UPDATE COST UPDATE
Contract Amount $688,119
Spent to Date $360,698
Encumbered $327,421
CONTRACT & BUDGET INFORMATION
Description Contract Amount Date Executed
Original Contract Value $688,119 5-Sep-12
CONTRACTOR/CONSULTANT SUBMITTALS DURING THIS PERIOD
PROJECT STATUS TABLE FOR PERIOD ENDED
PROJECT NAME CONTRACTOR/CONSULTANT
Configuration Management Software RailCar Management
BRIEF PROJECT DESCRIPTION
This contract scope provides track configuration management software, including implementation.
On-Going
RailDOCS software is in use for all NCTD field work by TASI contractors and quality control and enforcement is underway by
NCTD.Track and signal crews are using RailDOCS since January 8th, 2014.
On-going expenditures are for licensing.
NTP
Contract Completion
-
None
NCTD PTC Monthly Report Page 31 of 44 Quarter Ending June 30, 2014
Table 5.13: Environmental Support Services; NCTD PO#30475
Table 5.14: CTC/PTC Network Design & Implementation; NCTD PO#29504
6/30/2014
NCTD PURCHASE ORDER
30475
PROJECT STATUS
CONTRACT DATES
09/18/2012
12/31/2015
COMPLETION UPDATE COST UPDATE
Contract Amount $661,297
Spent to Date $166,976
Encumbered $494,321
CONTRACT & BUDGET INFORMATION
Description Contract Amount Date Executed
Original Contract Value $2,144,097 18-Sep-12
Contract Deduction ($1,482,800) 21-Feb-14
CONTRACTOR/CONSULTANT SUBMITTALS DURING THIS PERIOD
PROJECT STATUS TABLE FOR PERIOD ENDED
PROJECT NAME CONTRACTOR/CONSULTANT
Environmental Support Services BRG Consulting
BRIEF PROJECT DESCRIPTION
This contract provides as needed environmental support for PTC project. Initial task order was increased due to extent of
environmental risks and other considerations identified in the PTC program, specifically the fiber project.
On-Going
BRG is reviewing the San Diego COASTER Fiber Project, CP Friar Signal Project, and South Fiber completion.
Efforts are provided on an as-needed basis for environmental and archeological monitoring support for the PTC Program.
A biologist was present on the South Fiber construction site, monitoring while a boring was being drilled at Solana Beach. No
other environmental issues or work window constraints are present. BRG and the construction teams will continue to monitor
the development of the project plans during completion of the construction work.
NTP
Contract Completion
-
None
6/30/2014
NCTD PURCHASE ORDER
29504
PROJECT STATUS
CONTRACT DATES
5/18/2011
10/1/2013
COMPLETION UPDATE COST UPDATE
Contract Amount $177,528
Spent to Date $177,528
Encumbered $0
CONTRACT & BUDGET INFORMATION
Description Contract Amount Date Executed
Original Contract Value $177,528 18-May-11
CONTRACTOR/CONSULTANT SUBMITTALS DURING THIS PERIOD
BRIEF PROJECT DESCRIPTION
This contract provides network design and implementation for the PTC project.
Closed
This contract has been closed.
PROJECT STATUS TABLE FOR PERIOD ENDED
PROJECT NAME CONTRACTOR/CONSULTANT
CTC/PTC Network Design & Implementation Datel Systems
None
NTP
Contract Completion
-
NCTD PTC Monthly Report Page 32 of 44 Quarter Ending June 30, 2014
Table 5.15: PTC Network Design; NCTD PO#30066
Table 5.16: Test & Training Facility Equipment; NCTD PO#13003
6/30/2014
NCTD PURCHASE ORDER
30066
PROJECT STATUS
CONTRACT DATES
5/18/2011
10/1/2013
COMPLETION UPDATE COST UPDATE
Contract Amount $81,908
Spent to Date $81,908
Encumbered $0
CONTRACT & BUDGET INFORMATION
Description Contract Amount Date Executed
Original Contract Value $81,908 18-May-11
CONTRACTOR/CONSULTANT SUBMITTALS DURING THIS PERIOD
NTP
PROJECT STATUS TABLE FOR PERIOD ENDED
PROJECT NAME CONTRACTOR/CONSULTANT
PTC Network Design Datel Systems
BRIEF PROJECT DESCRIPTION
This contract scope includes preliminary and final design for the network component of the PTC system.
Closed
This contract has been closed and remaining work transferred to the Positive Train Control System for the LOSSAN Corridor,
HTI purchase order 11046.
Contract Completion
-
None
6/30/2014
NCTD PURCHASE ORDER
13003
PROJECT STATUS
CONTRACT DATES
9/21/2012
3/31/2013
COMPLETION UPDATE COST UPDATE
Contract Amount $170,799
Spent to Date $170,799
Encumbered $0
CONTRACT & BUDGET INFORMATION
Description Contract Amount Date Executed
Contract Value $170,799 21-Sep-12
CONTRACTOR/CONSULTANT SUBMITTALS DURING THIS PERIOD
NTP
PROJECT STATUS TABLE FOR PERIOD ENDED
PROJECT NAME CONTRACTOR/CONSULTANT
Test & Training Facility Equipment Datel Systems
BRIEF PROJECT DESCRIPTION
This contract provides as needed hardware, software, and licenses for the PTC Test & Training Facility (TTF).
Closed
This contract has been closed.
Contract Completion
-
None
NCTD PTC Monthly Report Page 33 of 44 Quarter Ending June 30, 2014
Table 5.17: PTC Lab Install (Task 2); NCTD PO#30374
Table 5.18: Additional Requirements to PO 30374; NCTD PO#30616
6/30/2014
NCTD PURCHASE ORDER
30374
PROJECT STATUS
CONTRACT DATES
9/21/2012
3/31/2013
COMPLETION UPDATE COST UPDATE
Contract Amount $3,880
Spent to Date $3,880
Encumbered $0
CONTRACT & BUDGET INFORMATION
Description Contract Amount Date Executed
Original Contract Value $3,880 21-Sep-12
CONTRACTOR/CONSULTANT SUBMITTALS DURING THIS PERIOD
NTP
PROJECT STATUS TABLE FOR PERIOD ENDED
PROJECT NAME CONTRACTOR/CONSULTANT
PTC Lab Install (Task 2) Datel Systems
BRIEF PROJECT DESCRIPTION
This contract provides PTC lab installation requirements under task 2.
Closed
This contract has been closed.
Contract Completion
-
None
6/30/2014
NCTD PURCHASE ORDER
30616
PROJECT STATUS
CONTRACT DATES
9/21/2012
3/31/2013
COMPLETION UPDATE COST UPDATE
Contract Amount -
Spent to Date -
Encumbered -
CONTRACT & BUDGET INFORMATION
Description Contract Amount Date Executed
Original Contract Value $8,665 5-Dec-12
CONTRACTOR/CONSULTANT SUBMITTALS DURING THIS PERIOD
NTP
PROJECT STATUS TABLE FOR PERIOD ENDED
PROJECT NAME CONTRACTOR/CONSULTANT
Additional Requirements to PO 30374 Datel Systems
BRIEF PROJECT DESCRIPTION
This contract provides additional requirements to the PTC lab installation purchase order under task 2.
Closed
This contract has been closed.
Contract Completion
None
The costs incurred for this purchase order were applied to
PO #30374. The status of this purchase order is closed.
NCTD PTC Monthly Report Page 34 of 44 Quarter Ending June 30, 2014
Table 5.19: Task Order: PTC Lab Cabling; NCTD PO#30265
Table 5.20: TMDS Network Extension; NCTD PO#30729
6/30/2014
NCTD PURCHASE ORDER
30265
PROJECT STATUS
CONTRACT DATES
9/21/2012
3/31/2013
COMPLETION UPDATE COST UPDATE
Contract Amount $12,000
Spent to Date $12,000
Encumbered $0
CONTRACT & BUDGET INFORMATION
Description Contract Amount Date Executed
Original Contract Value $12,000 21-Jun-12
CONTRACTOR/CONSULTANT SUBMITTALS DURING THIS PERIOD
NTP
PROJECT STATUS TABLE FOR PERIOD ENDED
PROJECT NAME CONTRACTOR/CONSULTANT
Task Order: PTC Lab Cabling Datel Systems
BRIEF PROJECT DESCRIPTION
This contract provides the required cabling to the PTC lab.
Closed
This contract has been closed.
Contract Completion
-
None
6/30/2014
NCTD PURCHASE ORDER
30729
PROJECT STATUS
CONTRACT DATES
3/6/2013
4/26/2013
COMPLETION UPDATE COST UPDATE
Contract Amount $76,233
Spent to Date $76,233
Encumbered $0
CONTRACT & BUDGET INFORMATION
Description Contract Amount Date Executed
Original Contract Value $76,233 6-Mar-13
CONTRACTOR/CONSULTANT SUBMITTALS DURING THIS PERIOD
NTP
PROJECT STATUS TABLE FOR PERIOD ENDED
PROJECT NAME CONTRACTOR/CONSULTANT
TMDS Network Extension Datel Systems
BRIEF PROJECT DESCRIPTION
This contract provides a temporary solution for NCTD to free up fiber for the PTC project.
Closed
This contract has been closed.
Contract Completion
-
None
NCTD PTC Monthly Report Page 35 of 44 Quarter Ending June 30, 2014
Table 5.21: PTC Signal Maintainer & WIU Installation; NCTD PO#30073
6/30/2014
NCTD PURCHASE ORDER
30073
PROJECT STATUS
CONTRACT DATES
3/2/2012
6/30/2013
COMPLETION UPDATE COST UPDATE
Contract Amount $600,306
Spent to Date $464,751
Encumbered $135,555
CONTRACT & BUDGET INFORMATION
Description Contract Amount Date Executed
Contract Value $367,875 2-Mar-12
Change order 001 $232,431 4-Mar-14
CONTRACTOR/CONSULTANT SUBMITTALS DURING THIS PERIOD
Intermediate 2321-2323 CP Crosby
Intermediate 2332-2334 CP Del Mar
CP Ponto Intermediate 2461-2462
Intermediate 2361-2362 Intermediate 2451-2544
CP Craven Intermediate 2561-2564
CP Valley Intermediate 2591-2592
BRIEF PROJECT DESCRIPTION
This contract provides for the installation and testing of the Wayside Interface Units (WIU) and the training, special tools,
equipment and vehicle lease for the signal maintainer.
On-Going
This work was completed in June.
PROJECT STATUS TABLE FOR PERIOD ENDED
PROJECT NAME CONTRACTOR/CONSULTANT
PTC Signal Maintainer & WIU Installation TASI
Contract Completion
-
NTP
NCTD PTC Monthly Report Page 36 of 44 Quarter Ending June 30, 2014
Table 5.22: Signal Upgrade – CP Friar/Taylor Street; NCTD PO#13007
6/30/2014
NCTD PURCHASE ORDER
13007
PROJECT STATUS
CONTRACT DATES
10/17/2013
07/12/2014
COMPLETION UPDATE COST UPDATE
Contract Amount $834,246
Spent to Date $0
Encumbered $834,246
CONTRACT & BUDGET INFORMATION
Description Contract Amount Date Executed
Original Contract Value $834,246 17-Oct-13
CONTRACTOR/CONSULTANT SUBMITTALS DURING THIS PERIOD
Cut-over Plans Hour by Hour San Slurry Backfill
Weekly Work Plan 6-2-2014 Weekly Work Plan 6-25-14
BRIEF PROJECT DESCRIPTION
Contractor will provide modernization upgrade to the civil, signaling, and communication equipment within the signaling
houses at CP Friar and Taylor Street.
On-Going
Project submittals continue to be submitted by HTI, with PRE and HNTB review. HTI has already installed the new house and
the switch machine. HTI has stated the intent is to finish the project in late July, 2014. Change Order number 1 has been
negotiated to incorporate some design changes requested by NCTD. There are few small changes under negotiation for
various minor work. It is anticipated that a final change order will be negotiated and completed by mid-July 2014.
PROJECT STATUS TABLE FOR PERIOD ENDED
PROJECT NAME CONTRACTOR/CONSULTANT
Signal Upgrade - CP Friar/Taylor Street Herzog Technologies, Inc.
NTP
Weekly Work Plan 5-19-2014 Weekly Work Plan 6/12/2014
House lift plan HOS Records
Contract Completion
-
Switch Machine replacement
Weekly Work Plan 6-9-2014
House lift plan rev.1 Fiber Distribution Panel
Interlocking Controller Work Plan MTS under-track conduit crossing Taylor Street
Weekly Work Plan 5-27-2014 Schedule update
Signaling Work Plan Weekly Work Plan 6-18-14
Wayside Signals Fiber Splice Trays
Results of Testing Closet Connector Housing
NCTD PTC Monthly Report Page 37 of 44 Quarter Ending June 30, 2014
6. EXPENDITURES / FUNDING SOURCES
6.1. Expenditures Through June 2014, expenditures to date on the project total $43,343,138, or 50 percent of the project budget.
The period expenditures total $3,292,493 and were primarily composed of contractor charges, followed by NCTD staff, engineering, and consultant charges.
Overall, expenditures are in line with the current $87,292,969 estimate at completion. Without contingency, the project value is currently $80,007,587. NCTD is closely monitoring the budget and the impact of pending contractor change orders and schedule changes.
Figure 6.1 represents the budgeted funding versus the expenditures to-date for the overall PTC Program.
Figure 6.1: PTC Program Budgeted versus Expended
NCTD PTC Monthly Report Page 38 of 44 Quarter Ending June 30, 2014
Table 6.1 summarizes the PTC Program expenditures.
Table 6.1: PTC Program Expenditures
6.2. Funding Sources The FRA and Prop 1A Discretionary funds comprise just over 55 percent of the overall PTC budget. Prop 1A Formula funds total 20 percent of the PTC program budget and Federal Section 5307 Formula Funds total comprise roughly 9 percent. A variety of sources make up the remaining 16 percent, with the largest component being Proposition 1B – TSGP funds. Table 6.2 summarizes the PTC Program Funding.
Table 6.2: PTC Program Funding
Description Total Funding
Federal Section 5307 Formula Funds $7,658,502.00
FRA $24,900,000.00
Prop 1A Discretionary $24,010,000.00
Prop 1A Formula $17,833,000.00
Prop 1B - PTMISEA $1,302,585.00
Prop 1B – TSGP $5,757,164.00
Other State / Local Funding $3,641,402.00
TDA Article 4.0 $1,190,316.00
TransNet Major Corridor $1,000,000.00
Total $87,292,969.00
Alternative Cost Code Original FRA
Budget
Projected
Costs
Current
Budget
Proposed
Budget
Difference
(increase)
decrease
Incurred Costs
to Date
6/30/2014
Open
Encumbrances
Total
Incurred &
Encumbered
Available
Budget
Pre-Award - 512554 4,009,524$ 911,246$ 4,608,367$ 5,027,085$ (418,719)$ 4,115,840$ 911,246$ 5,027,085$ -$
Post-Award 83,283,445$ 43,038,585$ 82,684,602$ 82,265,883$ 418,719$ 39,227,299$ 22,542,495$ 61,769,793$ 20,496,090$
Phase 1: System Development - 512555 7,949,248$ -$ 7,949,248$ 7,949,248$ -$ 7,949,248$ (0)$ 7,949,248$ -$
Phase 2 - 512556 30,270,426$ 17,471,848$ 25,879,840$ 33,089,554$ (7,209,714)$ 15,617,706$ 13,861,765$ 29,479,471$ 3,610,084$
Non Prime Post Award Costs - 512557 28,821,212$ 20,219,190$ 37,790,418$ 35,785,650$ 2,004,768$ 15,566,460$ 8,667,490$ 24,233,950$ 11,551,700$
OCC: Procurement, Installation, Testing,
and Implementation - 51255816,242,559$ 5,347,546$ 11,065,096$ 5,441,431$ 5,623,665$ 93,885$ 13,239$ 107,124$ 5,334,307$
GRAND TOTAL 87,292,969$ 43,949,831$ 87,292,969$ 87,292,969$ -$ 43,343,138$ 23,453,740$ 66,796,879$ 20,496,090$
NCTD PTC Monthly Report Page 39 of 44 Quarter Ending June 30, 2014
7. PROJECT PHOTOS
NCTD Purchase Order 11046: PTC for the LOSSAN Corridor
During the months of May and June 2014, the following photos were taken during construction:
PTC for the LOSSAN corridor – Switches and radio install at CP Songs – May 14, 2014
PTC for the LOSSAN corridor – Switch CISCO at CP Songs – May 15, 2014
PTC for the LOSSAN corridor – PTC installs at CP Escondido Jct. – June 13, 2014
PTC for the LOSSAN corridor – Wye Communication Tower – June 18, 2014
NCTD PTC Monthly Report Page 40 of 44 Quarter Ending June 30, 2014
NCTD Purchase Order 13020: South COASTER Fiber
During the month of June 2014, the following photos were taken during construction:
South COASTER Fiber Project – setting up traffic and pedestrian control at Lomas Santa Fe Drive – June 16, 2014
South COASTER Fiber Project – Located splice in conduits and shoring in place at Lomas Santa Fe Drive – June 17, 2014
South COASTER Fiber Project – handhole set and final compaction test at Lomas Santa Fe Drive – June 18, 2014
South COASTER Fiber Project – potholing for water main at Lomas Santa Fe Drive – June 20, 2014
NCTD PTC Monthly Report Page 41 of 44 Quarter Ending June 30, 2014
NCTD Purchase Order 13035: San Diego Fiber
During the month of May 2014, the following photos were taken during construction:
San Diego Fiber Project – splice tray placed into the termination box at CP Convair and CP Ash – May 5, 2014
San Diego Fiber Project – testing between CP Ash and CP Convair – May 8, 2014
NCTD Purchase Order 30073: PTC Signal Maintainer & WIU Installation
During the month of May 2014, the following photos were taken during construction:
PTC Signal Maintainer & WIU Installation – Application validation testing at CP Songs – May 20, 2014
PTC Signal Maintainer & WIU Installation – setting up for WIU testing at CP Songs – May 29, 2014
NCTD PTC Monthly Report Page 42 of 44 Quarter Ending June 30, 2014
NCTD Purchase Order 13007: CP Friar Signal Project
During the month of May 2014, the following photos were taken during construction:
CP Friar Signal Project – TIS boxes setup for pre-testing at CP Friar FAT Test in Texas – May 8, 2014
CP Friar Signal Project – straw waddles installed along drainage area at MP 264.1 – May 21, 2014
CP Friar Signal Project – digging trench at MP 264.1– June 13, 2014
CP Friar Signal Project – Cables coiled & going into pull box to cross tracks at MP 264.1 – June 17, 2014
NCTD PTC Monthly Report Page 43 of 44 Quarter Ending June 30, 2014
APPENDIX A: ABBREVIATIONS
AAR Association of American Railroads FHWA Federal Highway Administration ABS Automatic Block Signal System FIT Field Integration Test AFR Audit Finding Report FIT-I Field Integration Test – Interoperable ALI Application Layer Interface FMEA Failure Modes and Effects Analysis AMQP Advanced Message Queuing Protocol FMECA Failure Modes, Effects and Criticality Analysis AMTRAK National Railroad Passenger Corporation FQT Field Qualification Test ANSI American National Standards Institute FQT-I Field Qualification Test – Interoperable APTA American Public Transportation Association FRA Federal Railroad Administration AREMA American Railway Engineering and Maintenance-
of Way Association FRACAS Failure Reporting Analysis and Corrective Action
System AREMA C&S
American Railroad Engineering and Maintenance of Way Association Signal and Communications Manual of Recommended Practices
FTA Fault Tree Analysis
ASCE American Society of Civil Engineers GCOR General Code of Operating Rules ASQ American Society For Quality GIS Geographic Information System ASTM American Society for Testing and Materials GPS Global Positioning System ATCS Automatic Train Control System HFA Human Factors Analysis ATS Automatic Train Stop HL Hazard Log BCP Base Communications Package HMI Human Machine Interface BER Bit Error Rate HTI Herzog Technologies, Inc. BMP Best Management Practices HVAC High Volume Air Conditioning BNSF BNSF Railway HW Hardware BOS Back Office Server HwDD Hardware Design Document BPRA Baseline Pre-Release Audit I Interface C Carrier IA Impact Analysis CA California IC3 Individual Composite CRC (Cyclic Redundancy
Check) Calculator CAD Computer Aided Dispatch ICD Interface Control Document CADD Computer Aided Drafting and Design ICM Interface Control Module CAR Corrective Action Request ICWG Interface Control Working Group CBTC Communications Based Train Control ID Identifier CCB Change Control Board IEEE Institute of Electrical and Electronic Engineers CCMP Configuration Control Management Plan IETF Internet Engineering Task Force CDR Critical Design Review I-ETMS
® Interoperable Electronic Train Management
System CDRL Contract Deliverable Requirements List IM Inter-Modulation CDU Computer Display Unit (onboard) IMM Interface Management Matrix CFR Code of Federal Regulation IO Input / Output CHM Crash Hardened Memory IOC Input Output Concentrator (module) CI Configuration Item IP Ingress Protection CIL Configuration Item Library ISO International Organization for Standardization CIPAA Configuration Item Pre-Acceptance Audit IT Information Technology CM Configuration Management ITC Interoperable Train Control CMU Communication Management Unit ITCM ITC Messaging COM Communications Network (PTC Subsystem) ITP Interoperable Transport Protocol CONOPS Concept of Operations JRST Joint Railroad Safety Team COT Current Of Traffic LAN Local Area Network COTS Commercial Off the Shelf LCD Liquid Crystal Display CP Control Point LIEE Laboratory Integration End to End CPM Critical Path Method LIEE-I Laboratory Integration End to End – Interoperable CPU Central Processor Unit LINN Laboratory Integration Nearest Neighbor CPUC California Public Utilities Commission LOB Locomotive On-Board (PTC Subsystem) CRC Cyclic Redundancy Check LQEE Laboratory Qualification End to End CSA Configuration Status Accounting LQS Laboratory Qualification Segment CTC Centralized Traffic Control LRU Lowest Replaceable Unit DIO Digital Input / Output (module) MA Message Agent DIP Design Integration Plan MAH Model-Approved Hardware DOD Department of Defense MAS Maximum Authorized Speed DT Double Track MCC Meteorcomm LLC DVCS Distributed Version Control System MCP Mobile Communications Package eCIL Electronic Configuration Item Library MDT Maintainability Demonstration Test EIA Electronic Industries Alliance ME Message Exchange EIC Employee in Charge (Work Crew) MGT Million Gross Tons EMC Electromagnetic Compatibility MHz Megahertz EMD Electro Motive Diesel MIS Management Information System EMI Electromagnetic Interference ML Mainline ETL Electrical Testing Laboratories MO Message Originator ETMS
® Electronic Train Management System MOC Metrolink Operations Center
FAT Factory Acceptance Testing MOE Maintenance of Equipment FCC Federal Communications Commission MOW Maintenance of Way FCMP Field Configuration Management Plan MP Mile Post FFT Functional Fault Tree MPH Miles per Hour
NCTD PTC Monthly Report Page 44 of 44 Quarter Ending June 30, 2014
MPP Maintainability Program Plan SCM Software Configuration Management MQ Message Queue SHA System Hazard Analysis MR Message Recipient SHA-1 Secure Hash Algorithm – 1 MRB Message Routing and Binding SMCP Software Management Control Plan MTBF Mean Time Between Failures SME Subject Matter Expert MTBSDF Mean Time Between Service-Disrupting Failure SOF Sprinter Operations Facility MTEA Mainline Track Exclusion Addendum SRS Systems Requirements Specification MTS Master Test Strategy SSHA Subsystem Hazard Analysis MTTHE Mean Time to Hazardous Event SSID System Safety Integration Document MTTRS Mean Time to Restore Service SSIP System Safety Integration Packet MUTCD Manual on Uniform Traffic Control Devices Subpart H 49 CFR Part 236 Subpart H N Noise Subpart I 49 CFR Part 236 Subpart I NAD North American Datum SW Software NAVD North American Vertical Datum SwDD Software Design Document NCTD North County Transit District SyDS System Design Specification NDGPS Nationwide Differential Global Positioning System SyRS System Requirements Specification NEC National Electrical Code TASI TransitAmerica Services, Inc. NEMA National Electrical Manufacturers Association TBD To Be Determined NESC National Electrical Safety Code TCNS Tower Construction Notification System NETA National Electrical Testing Association, Inc. TCP / IP Transmission Control Protocol / Internet Protocol NPI Notice of Product Intent TEC Test Environment Configuration NS Norfolk Southern Railroad TIA Telecommunications Industry Association NTP Notice to Proceed TIH Toxic Inhalation Hazard O&SHA Operation and Support Hazard Analysis TMC Train Management Computer OBC Onboard Segment Hardware Chassis TMDS Train Management and Dispatching System OCC Operations Control Center TSR Temporary Speed Restrictions OEM Original Equipment Manufacturer TWC Track Warrant Control OS Office Segment UBC Uniform Building Code OSHA Occupational Safety and Health Administration UHF Ultra High Frequency OSI Open Systems Interconnection UI User Interface OTA Over The Air UL Underwriters Laboratories, Inc. OTE On-Track Equipment UPRR Union Pacific Railroad PC Printed Circuit UPS Uninterruptible Power Supply PCBA Production Current Baseline Audit USB Universal Serial Bus PCIL Physical Configuration Item Library USC United States Code PHA Preliminary Hazard Analysis V&V Verification & Validation PIH Poison by Inhalation Hazard VCS Version Control System PMP Project Management Plan VHF Very High Frequency PRE Pacific Railway Enterprises WAAS Wide Area Application System PSP Product Safety Plan (per FRA Subpart H) Wabtec Westinghouse Air Brake Technologies
Corporation PSR Permanent Speed Restrictions WAN Wide Area Network PTC Positive Train Control WIU Wayside Interface Unit
PTCDP PTC Development Plan WLAN Wireless Local Area Network PTCIP PTC Implementation Plan WMS Wayside Message Server PTCPVL PTC Product Vendors List WRE Wabtec Railway Electronics PTCSP PTC Safety Plan WSWS Wayside Status Message PTCSPDD PTC Safety Plan Definition Document WS Wayside Segment PTCSYS PTC System WSRS Wayside Status Relay Service PTS Positive Train Stop QA Quality Assurance QC Quality Control QM Quality Management RA Risk Assessment RAM Reliability, Availability, Maintainability RF Radio Frequency RFA Request for Amendment RFC Request for Comment RFI Request for Information RFP Request for Proposal ROW Right of Way RPP Reliability Program Plan RSAC Railway Safety Advisory Committee RSD Revenue Service Demonstration RSIA08 Rail Safety Improvement Act of 2008 RSPP Railroad Safety Program Plan RTM Requirements Traceability Matrix SAC Safety Assurance Concept SANDAG San Diego Area Governments SAT Site Acceptance Test SBD Safe Breaking Distance SCIL Safety-Critical Items List (same as Hazard Log)