pmu_prot5

Post on 03-Apr-2018

214 views 0 download

Transcript of pmu_prot5

  • 7/28/2019 pmu_prot5

    1/8

    1

    AbstractPhasor Measurement Units (PMUs) have been

    increasingly widespread throughout the power network. As a

    result, several researches have been made to locate the PMUs for

    complete system observability. Many protection applications are

    based upon the PMUs locations. This paper introduces an

    important application in power system protection which is the

    detection of single line outage. In addition, a detection of the

    outaged line is achieved depending on the variations of phase

    angles measured at the system buses where the PMUs arelocated. Hence, a protection scheme from unexpected overloading

    in the network that may lead to system collapse can be achieved.

    Such detections are based upon an artificial intelligence

    technique which is the support Vector Machine (SVM)

    classification tool. To demonstrate the effectiveness of the

    proposed approach, the algorithm is tested using offline

    simulation for the 14-bus IEEE system.

    Index TermsPhasor measurement units, PSCAD, Support

    vector machines, Transmission line measurements.

    I. INTRODUCTION

    INE outage study provides a measure of the overall effect

    on the system due to that line outage. The power flow ofthe system is affected by the line outage. Therefore, this may

    lead to overloading for certain lines. Also, this causes changes

    in the power angles for several buses. A protective action

    should be made to prevent large system disturbances (over

    loading of lines) leading to cascaded tripping results in a

    system collapse. However, connectivity information over the

    wide area is very important for system operations [1, 2].

    In recent years, PMUs are the only devices which are

    deployed over the entire power grid and are capable of

    providing geographically dispersed accurate synchronized

    measurements [3]. Therefore, they are used for system control,

    protection, state estimation and topology estimation [4 - 8].

    Consequently, PMUs became a powerful technology in power

    system protection.

    Mikolinnas and Wollenberg [9] have presented a version of

    the Megawatt Performance Indices (PI) whish are function of

    bus voltages and line flows and the corresponding limits. They

    A. Y. Abdelaziz, S. F. Mekhamer and M. Ezzat are with Electrical Power and

    Machines Department, Faculty of Engineering, Ain Shams University, Cairo,

    Egypt.

    E. F. El-Saadany is with Electrical and Computer Engineering Department,

    University of Waterloo, Canada

    include all terms in the infinite Taylors series expansion for

    all the change in the performance index due to different

    outage. Irissari and Sasson [10] have proposed an improved

    computational procedure based on DC load flow method.

    Vemuri and Usher [11] have presented a unified approach to

    find sensitivity of performance index for single branch outage,

    generation/load outage and combination of them. D. Hazarika

    et al. [12] describe an algorithm for determining the line

    outage contingency of a line taking into account of line overload effect in remaining lines and subsequent tripping of over

    loaded line(s) leading to system split or islanding of a power

    system using fast decoupled load flow analysis. J. Tate and T.

    Overbye [13, 14] introduce two researches for single line

    outage and double line outage respectively using phasor angle

    measurements. This is done by utilizing an optimization

    technique for event detection. Authors of [13] presented

    accurate results for a line outage case for a certain line in the

    37-bus IEEE system.

    This paper focuses on the line outage problem and proposes

    an artificial intelligence based technique for outage detection.

    The outaged line is determined by means of an SVM

    classification tool. The task of SVM is to utilize the outputinformation from the PMUs to determine a status for each line

    if it is outaged or not. The PMUs calculate the phasor angles atthe certain buses based on the complete observability

    approach discussed in [15]. Section II of this paper describes

    how to use the SVM approach in line outage detection and

    determination of outaged line. Section III proposes anapproach for detection of the outaged line based on the

    variations of the phasor angles at different buses with the aid

    of the SVM tool. Section IV introduces a numerical simulation

    for the 14-bus IEEE system using an offline simulation

    program EMTDC/PSCAD [19] and the mathematical analysiswith the aid of MATLAB. Section V clarifies the extracted

    conclusions.

    II. SUPPORT VECTORMACHINE

    Support vector machine [16, 17] was originally introduced

    by Vapnik and co-workers in the late 1990s. It is a

    computational learning method based on the statistical

    learning theory. SVM mainly has two classes of applications,

    classification and regression. In this paper, only the

    application of classification is considered.

    The classification problem can be restricted to consideration

    of the two-class problem without loss of generality. In this

    Line Outage Detection Using Support Vector

    Machine (SVM) Based on the Phasor Measurement

    Units (PMUs) Technology

    A. Y. Abdelaziz, S. F. Mekhamer, M. Ezzat and E. F. El-Saadany

    L

    978-1-4673-2729-9/12/$31.00 2012 IEEE

  • 7/28/2019 pmu_prot5

    2/8

    pr

    (a

    wo

    th

    (m

    of

    se

    core

    va

    ca

    pe

    A

    m

    thr

    lin

    lo

    ca

    sat

    Th

    no

    |1

    ho

    ag

    |

    m

    blem, the go

    classifier), w

    rk well on un

    here are man

    data, but th

    aximizes the

    each class).

    arating hyper

    Given a set o

    { ,i iy

    ach xi is a

    responding yiresent a non-

    ue of 1 to re

    e. The points

    here w is n

    pendicular di

    ding the off

    rgin. In its

    ough the orig

    early separabl

    ks for the sep

    be formulate

    isfy the follo

    .i

    x

    .i

    x

    hese can be c

    (i

    y x

    ow consider

    ese points lie

    mal w and

    b|/||w||. Simi

    lds lie on the

    ain w, and

    1b|/||w||. It i

    rgin is simply

    l is to separat

    ich is induce

    een examples,

    y possible lin

    ere is only o

    istance betwe

    This linear cl

    plane.

    training data

    , 1,...,i n=

    d-dimensio

    is a numericaatching train

    resent a mat

    x which lie on

    .w x

    ormal to the

    stance from

    et parameter

    bsence, the

    n. ||w|| is the

    e case, the s

    arating hyper-

    d as follows (s

    ing constraint

    1w b+ +

    1w b+

    mbined into

    . ) 1i

    w b+

    he points for

    on the hyper-

    perpendicul

    larly, the poin

    yper-plane H

    perpendicula

    s noticed that

    2/||w|| which

    e the two clas

    from availa

    i.e. it generali

    ar classifiers

    e that maxi

    en it and the

    assifier is ter

    { 1,1iy

    al real vect

    decision hasing data to th

    hing training

    the hyper-pla

    0b+ =

    hyper-plane a

    he hyper-pla

    b allows us

    yper-plane i

    Euclidean no

    pport vector

    plane with lar

    uppose that al

    s):

    1i

    for y = +

    1i

    or y =

    ne set of ineq

    0, for all

    hich the equ

    plane H1: xi .

    r distance

    ts for which t

    :xi . w + b =

    distance f

    H1 and H2 ar

    is observed in

    ses by a funct

    le examples

    zes well.

    that can sepa

    izes the mar

    earest data p

    ed the opti

    , dix R

    r Rd, and

    the value of -1e study case o

    data to the st

    e satisfy:

    nd b/||w|| is

    e to the ori

    to increase

    forced to p

    rm of w. For

    algorithm sim

    est margin. T

    the training d

    alities:

    i

    lity in (3) hol

    w + b = 1

    rom the ori

    e equality in

    1, with nor

    om the ori

    parallel and

    Fig. 1.

    ion

    nd

    ate

    gin

    int

    al

    (1)

    the

    tor a

    dy

    (2)

    the

    in.

    the

    ass

    the

    ply

    his

    ata

    (3)

    (4)

    (5)

    ds.

    ith

    gin

    (4)

    al

    gin

    the

    Fig. 1.

    samples

    Traini

    support

    maxim

    can be

    to solv

    root.

    Fortu||w|| wi

    accoun

    optimal

    convex

    Mini

    Subje

    Wher

    constan

    maximi

    number

    increas

    better.

    In SV

    the ge

    linearly

    general

    determi

    original

    product

    A co

    in this

    mappin

    An inn

    input sp

    This

    plane i

    polyno

    aximum margin

    rom two classes.

    ng points for

    vectors. The

    m margin by

    found. The op

    because it d

    ately it is posth 0.5||w||

    2 wi

    the noise wit

    hyper-plane

    quadratic pro

    ize

    m||ct to

    y

    i

    e i is measu

    t C > 0 de

    zation and tr

    of samples.

    s the margin

    M, the optim

    eralization a

    separable, th

    ization abili

    ned optimally

    input space

    space called t

    struction of t

    high dimens

    g of the input

    r product in

    ace as in (13).

    k

    llows the alg

    n the transfo

    ial kernel fu

    (,k x

    hyper-plane and

    which the equ

    pair of hyp

    minimizing |

    timization pro

    epends on ||w|

    sible to alter tthout changin

    slack variabl

    can be found

    ramming (QP

    in|| 12 ||||

    ( . )i ix w b+

    0, for i

    ing the degre

    ermines the

    aining error

    inimizing the

    /||w||, so that

    l hyper-plane

    ility. But if

    e obtained cla

    ty although

    . Thus to enh

    is mapped in

    he feature spa

    he linear sepa

    ional feature

    data to featur

    eature space

    .

    ( ), ( ),x x x =

    rithm to fit th

    rmed feature

    ction used wit

    ) (,x x =

    margins for a SV

    lity in (5) hol

    r-planes whi

    |w||, subject t

    blem presente

    || which invol

    e equation bg the solution.

    e and error p

    by solving t

    ) problem:

    1 ,i 1,..., n

    e of misclassi

    rade-off bet

    inimization

    optimization

    the classificat

    is determined

    the training

    ssifier may n

    the hyper-

    ance linear se

    o a high-dim

    e.

    ating hyper-p

    space, after

    space as sho

    as an equival

    ( )x

    e maximum-

    space. In thi

    h a degree of

    )1

    n

    x +

    2

    M trained with

    ds are called

    h gives the

    constraints

    d is difficult

    ves a square

    substitutingTaking into

    enalty C, the

    e following

    6

    (7)fication, the

    een margin

    nd n is the

    ariable ||w||

    ion becomes

    to maximize

    ata are not

    t have high

    planes are

    paration, the

    ensional dot

    lane is done

    a nonlinear

    n in Fig. 2.

    ent kernel in

    (8)

    argin hyper-

    s work, the

    :

    (9)

  • 7/28/2019 pmu_prot5

    3/8

    Fig

    dis

    vo

    ar

    m

    coco

    ap

    ap

    de

    vo

    of

    Fo

    20

    ve

    lo

    Ea

    ou

    Th

    ha

    w

    of

    i, j

    lin

    an

    ele

    I

    fu

    Sex

    re

    res

    de

    I

    is

    Th

    lo

    th

    sa

    Th

    eq

    fo

    pr

    lo

    co

    . 2 Mapping the tr

    he line outa

    tribution of t

    ltages phase a

    the buses n

    asurements a

    sideration. Tplete observ

    lied to cal

    roach uses t

    ends on succ

    ltage magnitu

    training of t

    the line outag

    r the proposed

    lines connec

    ctors is 20 sin

    ding cases at

    ch vector con

    tage case. Th

    ese vectors fo

    he y vector o

    s the values o

    ich the test d

    -1 represents

    and k in the

    e. Hence, wh

    d kth elements

    ments in the y

    n the testing

    ction is appli

    M functionsracted throug

    o show the

    eated at diffe

    ults as a fun

    scribing the pr

    n order to test

    erformed usi

    e 14-bus IEE

    ated upon th

    buses 2, 7, 1

    ples are tak

    en, the angles

    ations introd

    he training o

    each line to

    posed approa

    ding cases a

    sidered in theNormal loadiAn increase o

    aining data into a

    III. PROPOS

    e in a trans

    e lines power

    ngles are achi

    ar the outage

    ll over the

    he PMUs arability [15].

    ulate the p

    e Rockefeller

    essive three s

    e and angle. I

    e SVM is m

    e scenarios at

    study case (1

    ting the buse

    le line outage

    different bus

    ains the resul

    eses vectors a

    m a matrix X.

    f the SVM fo

    1 and -1. Th

    ta matches th

    a non-matchin

    matrix repre

    n studying th

    in the y vect

    vector should

    f the studied

    d for each lin

    are collectedthe results of

    ffect of the

    rent values o

    ction of C.

    oposed approa

    IV. SIMULA

    the proposed

    g EMTDC/P

    system is sho

    complete ob

    0 and 13 resp

    n at the buse

    of voltage p

    ced in Appen

    f SVM requir

    record the an

    ch suggests m

    t different b

    SVM trainin

    ng case as the

    f 25% in loadi

    higher-dimension

    D APPROACH

    ission netw

    flow. Hence,

    eved. The mo

    d lines. Ther

    etwork shoul

    located athen, a mathe

    asors angles.

    and Udren al

    amples to cal

    is introduced

    de using all t

    several differ

    buses IEEE

    s. So, the nu

    cases multipl

    es, (i.e. 120

    s of phase an

    re the x vect

    r a certain lin

    value of 1 re

    training data

    g data (e.g. if

    sent an outage

    outage of th

    or should equ

    equal to -1)

    system, an S

    and the predi

    . Hence, thethe testing of

    error penalty

    C, to get the

    ig. 3 introdu

    ch.

    ION RESULTS

    algorithm, an

    CAD simulat

    wn in Fig. 4,

    servability ap

    ectively. Ther

    where the P

    asors are cal

    ix A.

    es many stud

    les variations

    aking such tra

    ses. The foll

    using the pol

    standard IEEE

    ng at bus 4.

    al feature space.

    rk causes a

    variations in

    st affected bu

    fore, large sc

    d be taken i

    ertain busesmatical model

    The propo

    orithm [18] t

    ulate the pha

    in Appendix

    e possible ca

    nt loading ca

    ystem), there

    ber of train

    ed by 6 differ

    raining vecto

    les for each l

    rs of the SV

    e is a vector t

    resents a cas

    . While the va

    the rows num

    case of a cert

    t line, the ith,

    al to 1 and ot

    M classificat

    cted values of

    outaged lineSVM.

    C, the testing

    accuracy of

    es a flow c

    ffline simulat

    on package [1

    nd the PMUs

    roach in [15]

    fore, the volt

    Us are locat

    ulated using

    cases of out

    in all cases.

    ining at differ

    owing cases

    nomial kernel

    system states.

    re-

    the

    ses

    ale

    nto

    foris

    sed

    hat

    sor

    .

    ses

    es.

    are

    ing

    ent

    s).

    ine

    M.

    hat

    in

    lue

    ber

    ain

    jth,

    her

    ion

    the

    is

    is

    the

    art

    ion

    9].

    are

    at

    ge

    ed.

    the

    ge

    he

    ent

    are

    .

    An iAn iAn iAn i

    Fig. 3 Flo

    Fig. 4 IE

    ncrease of 25

    ncrease of 25

    ncrease of 25

    ncrease of 25

    wchart describin

    E 14 bus system.

    Samp

    SVM

    Output

    YES

    in loading a

    in loading a

    in loading a

    in loading a

    the proposed ap

    END

    Input:les of PMUs meas

    START

    Collect output res

    Extract outaged l

    Calculate thehase an les

    Form a vectorcontainin the a

    SVM

    Line 2

    Output

    Need to vary Pen

    error'C'

    NO

    bus 6.

    bus 9.

    bus 10.

    bus 12.

    roach.

    urements

    ults

    ine

    xles

    SVM

    Line 20

    Output

    alty

    3

    SVM

    raining

  • 7/28/2019 pmu_prot5

    4/8

    4

    Each of the six loading cases has an internal 20 cases of line

    outage for the 20 lines in the system. Therefore, 120 vectors

    are available to perform the required training of SVM.

    The training vector consists of a number of parts arranged

    together. Each part clarifies the angle variations at the buses

    where the PMUs are located. The next step is to apply a

    different loading case to test the SVM including all possible

    line outages. Then, the results are tabulated and the accuracy

    is calculated. It is proposed to perform such testing atconditions that differ from the training conditions.

    Firstly, to study the importance of complete observability of

    the power system, the training and testing are performed by

    considering two, three and four PMUs. Table I gives detailed

    results for a study case where the load at bus 14 is increased

    25% than the normal loading in the standard IEEE 14-bus

    system and two PMUs located at buses 2 and 10 are used.

    Table II gives similar results while three PMUs at buses 2, 7,

    and 10 are utilized. And Table III shows the same analysis

    with four PMUs located at the buses 2, 7, 10, and 13.

    Secondly, In order to ensure the superiority of the SVM

    classification tool in the field of line outage detection, several

    study cases have been studied including the complete

    observability principle. The study cases are given as follow:

    Study case (1): An increase of 25% in loading at bus 14.Study case (2): An increase of 25% in loading at bus 3.Study case (3): An increase of 40% in loading at bus 9.The targets of studying more study cases are; (1) to get an

    approximated accuracy of the proposed approach, (2) to select

    the appropriate range of penalty error for each line outage

    detection case.

    The results of the first study case are given in Table III,

    while the other study cases are presented in Table IV and

    Table V. The results are compared, and the comparison is

    introduced in Fig. 5.

    It is clear from Tables I, II and III that for each line, there is

    a detectable range of penalty error "C" for the line outage.

    When two PMUs are used, many lines are subjected to lack of

    classification, either no detection or a miss of classification,

    the accuracy in this case reaches a 16 correct classificationover 20 line outage cases. The remaining four cases are for

    lines far away from the PMUs locations that results in a wrong

    detection. The accuracy is improved when using three PMUs

    and the correct detections reach 19 detections over 20 line

    outage cases. Finally, when four PMUs are used and located

    upon the complete observability approach, a complete

    detection scenario is achieved and the correct detections reach

    20 detections over 20 line outage cases and with a more wide

    range of penalty error.

    It is clear from Fig. 5 that for each line, there is a detectable

    range of penalty error "C" for the line outage. Some lines are

    classified clearly even the value of C is small which means

    narrow range of classification or large which means wide

    margin of classification (e.g. line connecting bus 6 and bus

    13), where the result is correct for all tested range of C. While

    other line needs a specified range of C (e.g. line connecting

    bus 6 and bus 12), it requires a greater value of C starting from

    1x104. On the opposite, some lines need small values of C

    (e.g. line connecting bus 9 to bus 14), it requires lower value

    of C up to 10, after that a miss-classification may occur and

    the result becomes confusing.

    TABLE I

    RESULTS OF STUDY CASE (1) WITH 2PMUS LOCATED AT BUSES 2 AND 10

    Study Case (1): An increase of 25% at bus 14 and PMUs are located at buses 2 and 10

    Outage

    Case

    Result at

    C = 1

    Result at

    C = 10

    Result at

    C = 100

    Result at

    C = 1000

    Result at

    C = 1x104

    Result at

    C = 1x105

    Result at

    C = 1x106

    Result at

    C = 1x107

    Line 1-2 No outage 1-2 1-2 1-2 1-2 1-2 1-2 1-2

    Line 1-5 No outage No outage 1-5 1-5 1-5 1-5 1-5 1-5

    Line 2-3 No outage No outage 2-3 2-3 2-3 2-3 2-3 2-3

    Line 2-4 No outage 2-4 2-4 2-4 2-4 2-4 2-4 2-4

    Line 2-5 No outage No outage No outage No outage 2-5 2-5 2-5 2-5

    Line 3-4 No outage No outage No outage No outage No outage No outage 3-4 3-4

    Line 4-5 No outage No outage No outage No outage 4-5 4-5 4-5 4-5

    Line 4-7 No outage No outage No outage No outage No outage No outage 7-9 7-9

    Line 4-9 No outage No outage No outage No outage No outage No outage No outage 4-9

    Line 5-6 No outage No outage No outage No outage No outage 5-6 5-6 5-6

    Line 6-11 6-11 6-11 6-11 6-11 6-11 6-11 6-11 6-11Line 6-12 No outage No outage No outage No outage No outage No outage No outage No outage

    Line 6-13 No outage No outage No outage No outage No outage No outage 6-13 6-13

    Line 7-8 No outage No outage No outage No outage No outage No outage No outage No outage

    Line 7-9 No outage No outage No outage No outage No outage No outage 7-9 7-9

    Line 9-10 No outage No outage No outage No outage No outage No outage 9-10 9-10

    Line 9-14 No outage 9-14 9-14 9-14 , 1-5 9-14 , 1-5 9-14 , 1-59-14, 7-9,

    1-5, 6-13

    9-14, 7-9,

    1-5, 6-13Line 10-11 No outage No outage No outage No outage No outage 10-11 10-11 10-11

    Line 12-13 No outage No outage No outage No outage No outage No outage No outage No outage

    Line 13-14 No outage No outage No outage No outage No outage No outage 13-14 13-14

  • 7/28/2019 pmu_prot5

    5/8

    5

    TABLE II

    RESULTS OF STUDY CASE (1) WITH 3PMUS LOCATED AT BUSES 2,7, AND 10

    Study Case (1): An increase of 25% at bus 14 and PMUs are located at buses 2,7, and 10

    Outage

    Case

    Result at

    C = 1

    Result at

    C = 10

    Result at

    C = 100

    Result at

    C = 1000

    Result at

    C = 1x104

    Result at

    C = 1x105

    Result at

    C = 1x106

    Result at

    C = 1x107

    Line 1-2 No outage 1-2 1-2 1-2 1-2 1-2 1-2 1-2

    Line 1-5 No outage 1-5 1-5 1-5 1-5 1-5 1-5 1-5

    Line 2-3 No outage No outage 2-3 2-3 2-3 2-3 2-3 2-3Line 2-4 2-4 2-4 2-4 2-4 2-4 2-4 2-4 2-4

    Line 2-5 No outage No outage No outage No outage 2-5 2-5 2-5 2-5

    Line 3-4 No outage No outage No outage 3-4 3-4 3-4 3-4 3-4

    Line 4-5 No outage No outage No outage 4-5 4-5 4-5 4-5 4-5

    Line 4-7 4-7 4-7 4-7 4-7 4-7 4-7 4-7 4-7

    Line 4-9 No outage No outage No outage No outage No outage No outage 4-9 4-9

    Line 5-6 No outage No outage No outage No outage 5-6 5-6 5-6 5-6

    Line 6-11 6-11 6-11 6-11 6-11 6-11 6-11 6-11 6-11

    Line 6-12 No outage No outage No outage No outage No outage No outage No outage 6-12

    Line 6-13 No outage No outage No outage No outage No outage No outage 6-13 6-13

    Line 7-8 No outage No outage No outage No outage No outage No outage No outage 7-8

    Line 7-9 7-9 7-9 7-9 7-9 7-9 7-9 7-9 7-9

    Line 9-10 No outage No outage No outage No outage No outage 9-10 9-10 9-10

    Line 9-14 9-14 9-14 , 3-49-14, 3-4,

    1-5

    9-14, 3-4,

    1-5

    9-14, 3-4,

    1-5

    9-14, 3-4,

    1-5

    9-14, 3-4,

    1-5, 6-13

    9-14, 3-4,

    1-5, 6-13Line 10-11 No outage No outage No outage 10-11 10-11 10-11 10-11 10-11

    Line 12-13 No outage No outage No outage No outage No outage No outage No outage No outage

    Line 13-14 No outage No outage No outage No outage No outage No outage 13-14 13-14

    TABLE III

    RESULTS OF STUDY CASE (1) WITH 4PMUS LOCATED AT BUSES 2,7,10, AND 13(COMPLETE OBSERVABILITY)

    Study Case (1): An increase of 25% at bus 14 and PMUs are located for complete observability

    Outage

    Case

    Result at

    C = 1

    Result at

    C = 10

    Result at

    C = 100

    Result at

    C = 1000

    Result at

    C = 1x10

    4

    Result at

    C = 1x10

    5

    Result at

    C = 1x10

    6

    Result at

    C = 1x10

    7

    Line 1-2 No outage 1-2 1-2 1-2 1-2 1-2 1-2 1-2

    Line 1-5 No outage 1-5 1-5 1-5 1-5 1-5 1-5 1-5

    Line 2-3 No outage 2-3 2-3 2-3 2-3 2-3 2-3 2-3

    Line 2-4 2-4 2-4 2-4 2-4 2-4 2-4, 10-11 2-4, 10-11 2-4, 10-11

    Line 2-5 No outage No outage No outage No outage 2-5 2-5 2-5 2-5

    Line 3-4 3-4 3-4 3-4 3-4 3-4 3-4 3-4 3-4

    Line 4-5 No outage No outage No outage 4-5 4-5 4-5 4-5 4-5

    Line 4-7 4-7 4-7 4-7 4-7 4-7 4-7 4-7 4-7

    Line 4-9 No outage No outage No outage No outage No outage No outage 4-9 4-9

    Line 5-6 No outage No outage No outage No outage 5-6 5-6 5-6 5-6

    Line 6-11 6-11 6-11 6-11 6-11 6-116-11,

    10-11

    6-11,

    10-11

    6-11,

    10-11

    Line 6-12 No outage No outage No outage No outage 6-12 6-12 6-12 6-12Line 6-13 6-13 6-13 6-13 6-13 6-13 6-13 6-13 6-13

    Line 7-8 No outage No outage No outage No outage No outage No outage 7-8 7-8

    Line 7-9 7-9 7-9 7-9 7-9 7-9 7-9 7-9 7-9

    Line 9-10 No outage No outage No outage No outage 9-10 9-10 9-10 9-10

    Line 9-14 9-14 9-14 9-14, 3-4 9-14, 3-4 9-14, 3-4 9-14, 3-4 9-14, 3-4 9-14, 3-4

    Line 10-11 No outage No outage No outage 10-11 10-11 10-11 10-11 10-11

    Line 12-13 No outage No outage No outage No outage No outage No outage No outage 12-13

    Line 13-14 13-14 13-14 13-14 13-14 13-14 13-14 13-14 13-14

  • 7/28/2019 pmu_prot5

    6/8

    6

    TABLE IV

    RESULTS OF STUDY CASE (2) WITH 4PMUS LOCATED AT BUSES 2,7,10, AND 13(COMPLETE OBSERVABILITY)

    Study Case (2): An increase of 25% at bus 3 and PMUs are located for complete observability

    Outage

    Case

    Result at

    C = 1

    Result at

    C = 10

    Result at

    C = 100

    Result at

    C = 1000

    Result at

    C = 1x104

    Result at

    C = 1x105

    Result at

    C = 1x106

    Result at

    C = 1x107

    Line 1-2 No outage 1-2 1-2 1-2 1-2 1-2 1-2 1-2

    Line 1-5 No outage 1-5 1-5 1-5 1-5 1-5 1-5 1-5

    Line 2-3 No outage No outage 2-3 2-3 2-3 2-3 2-3 2-3Line 2-4 2-4 2-4 2-4 2-4 2-4 2-4 2-4 2-4

    Line 2-5 No outage No outage No outage No outage 2-5 2-5 2-5 2-5

    Line 3-4 3-4 3-4 3-4 3-4 3-4 3-4 3-4 3-4

    Line 4-5 No outage No outage No outage 4-5 4-5 4-5 4-5 4-5

    Line 4-7 4-7 4-7 4-7 4-7 4-7 4-7 4-7 4-7

    Line 4-9 No outage No outage No outage No outage No outage 4-9 4-9 4-9

    Line 5-6 No outage No outage No outage No outage 5-6 5-6 5-6 5-6

    Line 6-11 6-11 6-11 6-11 6-11 6-11 6-11 6-11 6-11

    Line 6-12 No outage No outage No outage No outage 6-12 6-12 6-12 6-12

    Line 6-13 6-13 6-13 6-13 6-13 6-13 6-13 6-13 6-13

    Line 7-8 No outage No outage No outage No outage No outage No outage 7-8 7-8

    Line 7-9 7-9 7-9 7-9 7-9 7-9 7-9 7-9 7-9

    Line 9-10 No outage No outage No outage No outage 9-10 9-10 9-10 9-10Line 9-14 9-14 9-14 9-14 9-14 9-14 9-14 9-14 9-14

    Line 10-11 No outage No outage No outage 10-11 10-11 10-11 10-11 10-11

    Line 12-13 No outage No outage No outage No outage No outage No outage No outage 12-13

    Line 13-14 13-14 13-14 13-14 13-14 13-14 13-14 13-14 13-14

    TABLE V

    RESULTS OF STUDY CASE (3) WITH 4PMUS LOCATED AT BUSES 2,7,10, AND 13(COMPLETE OBSERVABILITY)

    Study Case (3): An increase of 40% at bus 9 and PMUs are located for complete observability

    Outage

    Case

    Result at

    C = 1

    Result at

    C = 10

    Result at

    C = 100

    Result at

    C = 1000

    Result at

    C = 1x104

    Result at

    C = 1x105

    Result at

    C = 1x106

    Result at

    C = 1x107

    Line 1-2 No outage 1-2 1-2 1-2 1-2, 10-11 1-2, 10-11 1-2, 10-11 1-2, 10-11

    Line 1-5 No outage 1-5 1-5 1-5 1-5, 2-5 1-5, 2-5 1-5, 2-5 1-5, 2-5Line 2-3 No outage 2-3 2-3 2-3 2-3 2-3 2-3 2-3

    Line 2-4 2-4 2-4 2-4 2-4 2-4, 2-52-4, 2-5,

    7-8

    2-4, 2-5,

    4-9, 7-8,

    2-4, 2-5,

    4-9, 7-8,

    Line 2-5 No outage No outage No outage No outage 2-5 2-5 2-5, 7-8 2-5, 7-8

    Line 3-4 No outage 3-4 3-4 3-4 3-4, 10-11 3-4, 10-11 3-4, 10-11 3-4, 10-11

    Line 4-5 No outage No outage No outage 4-5 4-5 4-5 4-5 4-5

    Line 4-7 4-7 4-7 4-7 4-7 4-7, 10-11 4-7, 10-11 4-7, 10-11 4-7, 10-11

    Line 4-9 No outage No outage No outage No outage No outage No outage 4-9 4-9

    Line 5-6 No outage No outage No outage No outage 5-6 5-6, 10-115-6,10-11,7-8, 9-10

    5-6,10-11,7-8, 9-10

    Line 6-11 6-11 6-11 6-11 6-11 6-11 6-11 6-11, 4-9 6-11, 4-9

    Line 6-12 No outage No outage No outage No outage 6-12 6-12 6-12 6-12

    Line 6-13 6-13 6-13 6-13 6-13 6-13 6-13 6-13 6-13Line 7-8 No outage No outage No outage No outage No outage No outage 7-8 7-8, 10-11

    Line 7-9 7-9 7-9 7-9 7-9 7-9 7-9 7-9, 4-9 7-9, 4-9

    Line 9-10 No outage No outage No outage No outage No outage 10-11 10-11, 7-8 10-11, 7-8

    Line 9-14 No outage 9-14 9-14 9-14 9-14, 10-11 9-14, 10-11 9-14, 10-11 9-14, 10-11

    Line 10-11 No outage No outage No outage No outage No outage 10-11 10-11 10-11

    Line 12-13 No outage No outage No outage No outage No outage No outage No outage 12-13

    Line 13-14 13-14 13-14 13-14 13-14 13-14 13-1413-14,

    9-10

    13-14,

    9-10

  • 7/28/2019 pmu_prot5

    7/8

    Fig

    Fig

    . 5 Comparison o

    . 6 Phase angle va

    PhaseangleatBus2

    PhaseangleatBus10

    different study c

    riation for outage

    0 0.1-20

    -15

    -10

    -5

    0

    0 0.1-20

    -15

    -10

    -5

    0

    ses using polyno

    of line 6-13 at the

    0.2 0.3

    Time in seconds

    0.2 0.3

    Time in seconds

    ial kernels.

    instant t = 0.3 sec

    0.4

    0.4

    Fig. 6

    all pha

    near b

    decreas

    accurat

    Fig. 7

    effect o

    line 7-

    accordioutage.

    outage

    from Fi

    For t

    than th

    and (2).

    case (2)

    a miss

    grey s

    1x104.

    40% o

    cases e

    permits

    bus 10.

    approa

    detectio

    The c

    value o

    for som

    classifi

    case o

    process

    subrout

    "C" tha

    to getof the S

    cases o

    onds for study ca

    .5 0-20

    -15

    -10

    -5

    0

    PhaseangleatBus7

    .5 0-20

    -15

    -10

    -5

    0

    PhaseangleatBus13

    clarifies that

    ors at all bus

    s to the outa

    e of about 4

    e classificatio

    shows that t

    n the phase a

    8 is normall

    ng to the loaHowever, thi

    of line 7-8 for

    g. 5.

    e study case

    standard syst

    . The differen

    , the SVM fai

    classification

    adow. It det

    The reason of

    er loading le

    specially near

    a miss classi

    Even a miss

    h still has 1

    n which mean

    onclusion is t

    f C increases

    e cases the in

    ations. There

    f line outage

    ing for all

    ine operates

    t to be adjust

    orrect decisioVM classifica

    er 60 cases w

    se (1).

    0.1

    0.1

    the outage of

    s. But, the gr

    ged line (i.e.o). Therefore,

    in that case.

    e outage of li

    gle variations

    y loaded wi

    d flow studys may lead t

    a great range

    3), the bus nu

    em that differ

    e between th

    ls in the detect

    as shown in T

    cts line 10-1

    this miss cla

    ts the study

    the heavy lo

    ication for the

    classification

    9 correct det

    s a percentage

    at the overall

    to have much

    rease in C all

    fore, to have

    , it is impo

    lines with p

    ith the suitabl

    d through dif

    ns. Consequetion tool for t

    ith a percenta

    0.2 0.3

    Time in seconds

    0.2 0.3

    Time in seconds

    line 6-13 has

    eatest effect i

    bus 13 phase

    this result

    e 7-8 is almo

    . This happens

    h a very s

    before the ao a miss dete

    of penalty err

    mber 9 is 40

    from both st

    two study ca

    ion of line 9-1

    able V by bol

    1 instead of

    sification ma

    ase far from

    ded bus (i.e.

    line connecti

    ccurs, the ac

    ctions versus

    of 95 % of ac

    accuracy inc

    classification

    ws an appear

    correct deci

    tant to mak

    arallel subro

    e or optimum

    ferent study c

    tly, the obtaiese study cas

    e of 98.3%

    0.4 0.5

    0.4 0.5

    7

    an effect for

    at the most

    angle has a

    elps for an

    st having no

    because the

    all loading

    tion of linection of the

    or as noticed

    overloaded

    dy cases (1)

    ses is that in

    0 and makes

    ded font and

    -10 at C =

    be that the

    the training

    bus 9). This

    g bus 9 and

    uracy of the

    one wrong

    curacy.

    eases as the

    margin. But,

    nce of miss-

    ion for any

    a parallel

    tines. Each

    enalty error

    ses in order

    ed accuracys reaches 59

  • 7/28/2019 pmu_prot5

    8/8

    Fig

    de

    th

    re

    (i.

    en

    pr

    er

    co

    in

    T

    w

    tra

    be

    wi

    S

    ne

    cl

    un

    se

    al

    T

    [1]

    . 7 Phase angle va

    he paper

    termination o

    technology o

    ults when the

    e. the PMUs

    tire power net

    ocessing for e

    or. Therefore

    rrect detectio

    luding three s

    e research c

    en the regul

    ining of SVM

    so far from t

    ll be achieve

    M related to

    twork dispatc

    ssifications

    loaded or ligh

    ere action. F

    he operating

    orithm [18]

    e amplitude a

    US-Canada Po14, 2003 the Bl

    riation for outage

    V. CO

    resents the

    the outaged li

    f PMUs. The

    concept of c

    are located i

    work). The pa

    ach line with

    , the approa

    s over 60 po

    tudy cases for

    n be applica

    r daily loadi

    . Hence, the a

    e training cas

    . It is suggest

    he variations

    center. The

    ay occur du

    t loaded line

    ture work will

    VI. AP

    equations o

    ,

    d phase angle

    VII. RE

    wer System Outaackout in the Uni

    0 0.1-6

    -5.5

    -5

    -4.5

    -4

    PhaseangleatBus2

    0 0.1-17

    -16.5

    -16

    -15.5

    -15

    PhaseangleatBus10

    of line 7-8 at the i

    CLUSIONSVM classi

    ne in a power

    proposed appr

    mplete obser

    certain buse

    per suggests a

    the optimum

    h reaches an

    sible cases of

    the 14-bus IE

    le for any n

    g cases are

    tual case of li

    s. As a result,

    ed to get a dy

    f network loa

    paper also sh

    e to a case

    hich cannot b

    consider larg

    ENDIX A

    f the Rocke

    of the sample

    ,

    ERENCES

    e Task Force. Fied States and Can

    0.2 0.

    Time in secon

    0.2 0.

    Time in secon

    nstant t = 0.3 seco

    ication tool

    network based

    oach has accu

    ability is appl

    s to observe

    pplying a para

    range of pen

    accuracy of

    outage scena

    E power syst

    twork especi

    onsidered in

    e outage will

    a good detect

    namic trainin

    ding stated by

    ws that the

    of an outage

    e considered

    r systems.

    eller and Ud

    d signal are:

    nal Report on Auada, 2004.

    3 0.4

    s

    3 0.4

    s

    nds for study cas

    in

    on

    ate

    ied

    the

    llel

    lty

    59

    ios

    em.

    lly

    the

    not

    ion

    of

    the

    iss

    of

    s a

    ren

    gust

    [2] US-Imp

    [3] B. Sof p

    inco

    Eng

    [4] WeiEsti

    Tra

    [5] Geoad

    mea152

    [6] A.esti

    Aug

    [7] M.Proc

    [8] E. LidenPo

    [9] T.sele

    no.

    [10] G.met

    Syst[11] S. V

    algo

    pp.

    [12] D.anal

    Ene

    [13] J. E.mea

    pp.[14] J. E.

    angl

    Proc

    [15] S.meaon P

    [16] S.Spri

    [17] I. StSpri

    [18] Q.mat

    [19] PSC

    0.5 0-15

    -14.5

    -14

    -13.5

    -13

    PhaseangleatBus7

    0.5 0-17

    -16.5

    -16

    -15.5

    -15

    PhaseangleatBus13

    (1).

    Canada Power S

    lementation of the

    ingh, N. Sharma,hasor measureme

    rporated with

    ineering, Science

    qing Jiang, Vijayator Utilizing

    sactions on Powe

    rge N. Korres, a

    data processin

    surements", Elect, March 2011.

    onticelli, Mode

    ation, IEEE T

    . 1993.

    ezunovic, Mon

    . 39th Hawaii Int.

    oureno, A. Costtification method

    er Syst., vol. 21,

    . Mikolinnas ,tion algorithm,

    , pp. 608617, F

    . Irissari, and A.

    od for online s

    ., vol. PAS-100,emuri, and R. E.

    rithms, IEEE T

    46354, Feb. 19

    azarika, S. Bhuyysis including th

    gy Systems, vol.

    . Tate, and T. J.

    surements, IEE

    16441652, Nov.. Tate, and T. J. Oe measurements,

    eeding, pp. 15, J

    hakrabarti, and

    surement units foower Systems, vo

    be, Support Vec

    nger-Verlag, Lon

    einwart, and A.

    nger, 2008.. Wu, Z. Lu, T.

    ematical Morop

    AD Users Guide

    0.1 0

    Ti

    0.1 0

    T

    ystem Outage T

    Task Force Reco

    A. Tiwari, K. Vet units (PMUs) i

    ACTS controll

    and Technology,

    Vittal, and GeralSynchronized

    r Systems, Vol. 2

    d Nikolas M. M

    g for system

    ric Power System

    ling circuit breake

    ans. Power Syst.

    itoring of power

    . Conf. System Sc

    a, K. Clements, adirectly based o

    o. 4, pp. 192019

    B. F. WollenbeIEEE Trans Powe

    b. 1981.

    . M. Sasson, An

    ecurity analysis,

    no. 4, pp. 18381Usher, On line

    ans Power Appar

    3.

    n, and S.P. Chosystem islandin

    28, no. 4, pp, 232

    verbye, Line out

    Transactions on

    2008.erbye, Double lIEEE Power &

    uly 2009.

    E. Kyriakides,

    r power system ol. 23, no. 3, pp. 1

    tor Machines for

    on, Ltd, 2005.

    hristmann, Supp

    Y. Ji, Protective

    ology, Springer-V

    Ver. 4.2, Manito

    .2 0.3

    me in seconds

    .2 0.3

    me in seconds

    sk Force. Final

    mmendations, 20

    rma, and S. Singelectric power s

    rs, Internation

    ol. 3, no. 3, pp. 6

    d T. Heydt, "A DPhasor Measure

    , No. 2, pp. 563-

    anousakis, "State

    ncluding PMU

    s Research, 81 (2

    rs in weighted le

    , vol. 8, no. 3,

    ystem topology i

    ences, Jan. 2006.

    nd R. Cernev, Acollinearity tests

    29, Nov. 2006.

    rg, An advancer Apparatus Syst.

    automatic contin

    IEEE Trans Po

    44, Apr. 1981.automatic contin

    atus Syst., vol. P

    dhury, Line outascenario Electr

    243, May 2006.

    age detection usi

    Power Systems,

    ine outage detectinergy Society G

    Optimal place

    bservability, IE331440, Aug. 2

    Pattern Classific

    rt Vector Machi

    relaying of powe

    erlag London Li

    a Research Cente

    0.4 0.5

    0.4 0.5

    8

    Report on the

    6.

    , Applicationsstems network

    l Journal of

    482, 2011.

    istributed Statements", IEEE

    71, May 2007.

    estimation and

    and SCADA

    11), pp. 1514-

    st squares state

    p. 11431149,

    n real-time, in

    topology error, IEEE Trans.

    d contingency, vol. PAS-100,

    ency selection

    wer Apparatus

    ency selection

    AS-102, no. 2,

    ge contingencyical Power and

    g phasor angle

    vol. 23, no. 4,

    n using phasoreneral Meeting

    ent of phasor

    E Transactions08.

    tion. England:

    es, New York:

    systems using

    ited 2009.

    r, April 2005.