Perdido Installation program- Transport & Installation -
Perdido Project
2
AGENDA
IntroductionPerdido field specificsResourcesProgram / scheduleExecution
- Mooring pile installation- Flowline installation- Hull transportation & Installation- SCR installation.
3
Perdido Subsea Project overview
Perdido site
Alaminos Canyon, block 857
Company / Operator: Shell Exploration & ProductionPartners: BP/ Chevron
Location:Alaminos Canyon block 857Water depth: ~7,850 - 9,800 feet Truss Spar Subsea development
4
Far away offshore
Corpus Christi – 150 milesGalveston – 180 miles
Approx. 1.5 - 2 hours by helicopterNearest platform – 80 miles
Perdido site
Alaminos Canyon, block 857
5
Perdido field detailsWater Depths:
• N mooring cluster 2,460 m
• DVA site 2,380 m
• Tobago 2,950 m ! RECORD
• SE mooring cluster 2,630 m ! RECORD
• SW mooring cluster 2,330 m
DVA = Direct Vertical Access
6
Perdido Records
7
SPAR waterdepth development
8
• Mooring piles• SPAR• Topsides• Production Flowlines• Water Injection system• Export Steel Catenary Risers• Manifold piles & manifolds• Electrical SubmersiblePump (ESP) caissons &inlet assemblies
Heerema Scope
9
The offshore program
Jun Jul Aug Sep Oct
2008
1 Perdido Mooring piles
2 Perdido Flowlines
3 Perdido HOST hook-on
4 Perdido SCR’s
5 Perdido topsides (2009)
10
The resources
DCV Balder
SSCV Thialf
Support vessel Union Manta
Transport Barges etc.
400 ft.
300 ft.
250 ft.
Spar tugs
Fixed ballast
11
The people
12
Geneva
Delft, Zwijndrecht, Vlissingen, Leiden.
Houston
Lagos
Perth
Heerema Group Worldwide
Hartepool, Surrey
Mexico City, Villahermosa
Luanda
Heerema Group - worldwide
Bangalore
• subsea
• Moorings / hull• subsea
analysis support
13
Balder Work Area split
• Dedicated pipelay
• Storage
• Material handling
• Dedicated mooring
Accommodation for 350 persons
14
Upgrades for the deep
Greater waterdepth than before. Equipment upgrades required:A&R wire 4,000 m, 5.5 inch diameterL&P wire 4,000 m, 4.5 inch diameterCrane wires 2 * 19km, tuned constructionPositioning equipment more sensitive equipmentROV frame & winch capacity.
Type 8023Type 8023More DirectionalMore Directional
beam shape beam shape below transceiver facebelow transceiver face
15
9 leg taut mooring system in three clusters
Perdido Regional Host Installation- Spar mooring configuration
Lines 1, 2, 4, 5, 7 & 8 Lines 3, 6 & 9
Platform chain:Max. 345m of 135mm studless chainPolyester rope: 229mm diameter1830m + 1830m + 37m insertGround chain:54m of 135mm studless chain
Platform chain:Max. 345m of 135mm studless chainPolyester rope: 229mm diameter1220m + 1220m + 137m insertGround chain:67m of 135mm studless chain
1616
The 9 piles are transported on 2 barges each 260ft long
Phase 1 - Pile installation
Mooring Pile components:Suction piles: 5.5m dia. – 31m long, 250 tons
Pile shackle Between pile and pile chainPile chain: 75’ of 5.3” (134mm) studless chainMooring connector: BSW Ballgrab female connector + shackle
1717
Transfer from barge to Balder deck
Phase 1 - Pile installation
1818
Pile and mooring component assembly on Balder deck
Phase 1 - Pile installation
1919
Phase 1 - Pile installationUpend pile above deck using two cranes
Slew overboard and lower
2020
Phase 1 - Pile installation
Lower pile to seabedPositionApply suction with pump mounted on ROV
21
Phase 2 - Flowline phase work
Production flowlines2 no.’s 8.625” OD * 18.1 mm 3 no.’s 10.75” OD * 22.2 mmcoated with Glass sphere polyurethane (GSPU)
Water Injection flowline1 no.’s 10.75” OD * 22.2 mmOutside & inside coated with fusion bonded epoxy (FBE)
All with Pipeline end terminations (PLET’s) on both ends
22
PLET transfer
Phase 2 - Flowline phase work
23
Start-up PLET upending
Phase 2 - Flowline phase work
24
Phase 2 - Flowline phase work
Pipe layOn deck: 2 double Joints + 1 collar Joint = 1 Hex Joint
Hex Joints in tower
25
End PLET in tower
Phase 2 - Flowline phase work
2626
Phase 3a - Mooring line pre-deployment
The mooring components are transported on 2 barges, 300ft & 400ft long
3 Mooring line pre-deployed :Hurricane contingencyDecrease of critical spar exposure timeLearning curve for assembling components
2727
Phase 3a - Mooring line pre-deployment
The mooring components are transferred to Balder deck for assembly
2828
The polyester ropes are spooled from their transport reel on to Balder’s Mooring Line Deployment Winch
Phase 3a - Mooring line pre-deployment
Assemble mooring components on Balder deck
2929
Phase 3a - Mooring line pre-deployment
Connect ground chain to bottom polyester Overboard connection
Hang-off bottom polyester rope Spool on next polyester rope
3030
Phase 3a - Mooring line pre-deployment
Assemble mooring components on Balder deck
Connect bottom polyester rope with top rope…
Overboard connection and spool off top polyester rope
Connect & overboard buoy
3131
Inshore tow-out route
Phase 3b - Wet tow & Spar upending
Perdido site
Alaminos Canyon, block 857
3232
Phase 3b - Wet tow & Spar upending
Connect ballast hoses to spar
3333
Phase 3b - Wet tow & Spar upending
3434
Prepare Layout top of Spar
Install pull-in equipment
Make safe
Phase 3c - Mooring line hook-up
3535
Hand over polyester to tug to keep polyester off seabedSpool off top segment of poly rope
Phase 3c - Mooring line hook-up
3737
Install and deploy platform and messenger chainTug holds Poly wire from seabed
Phase 3c - Mooring line hook-up
3838
Lower chain clamp to transfer the load to the sparDisconnect using ROV
Phase 3c - Mooring line hook-up
3939
Slurry suspension to be pumped to soft tank
Phase 3d - Fixed ballast installation
Fixed ballast material: magnetite (iron ore), 13,533 mtontransported with hopper barge Peggy Palmer and push boat Naida Ramil, moored along Balder
4040
Install piping on Balder deckInstall ballast boom
Phase 3d - Fixed ballast installation
Install piping on spar deck
Connect piping to the soft tank filling points on top of spar
4141
Mix magnetite with seawater using front loaders and water from BalderPump slurry into spar
Phase 3d - Fixed ballast installation
42
Haul in 3 * 750’
(440 links)
Step 2
Pay out 2 * 750’(440 links)
Cluster 1 tension at stoppers ~1260 kips
Further increase tension of line 1 (~1860 kips). This will be above stall capacity (=1600 kips)
Step 1
Phase 3e – Mooring line stretching
43
Phase 4 SCR installation
Pick-up pre-laid pipe
Install final VIV strakes
flex joint welded
1 no.’s of 10.75” OD * 22.2 mm WT Water Injection SCR (ID coated)2 no.’s of 16” OD * 25.4 mm WT export SCR
44
Transfer headFlexjoint
3½″ SCR pull-in wire pre-installed on spar.
Socket
Phase 4 SCR installation
45
Phase 4 SCR installation
46