Owasso Public Schools 2009 Bond Issue
VOTE Tuesday, October 13th
Barnes Elementary School
• New elementary school• Completed in 2004
Owasso Public Schools
Northeast Elementary School
• 12 classrooms• Restrooms• Computer lab • Canopy, sidewalk, and parking
additions• Completion in August 2007
Owasso Public Schools
Seventh Grade Center• 7 classrooms• Admin suite, secure
entry• Art suiteˉ 2 classroomsˉ Kiln room• Science suiteˉ 2 classroomsˉ Prep room• Parking lot addition• Completion in August
2007
Owasso Public Schools
Larkin Bailey Elementary School
• 3 classrooms• Computer Lab• Restrooms• Completion in August
2007
Owasso Public Schools
Pamela Hodson Elementary School
• 3 classrooms• Restrooms• Completion in October 2007
Owasso Public Schools
Mills Elementary School• 4 classrooms• Math Lab• Computer Lab• Restrooms• Completion in October 2007
Owasso Public Schools
Ator Elementary School• 10 classrooms• Restrooms• Entry canopy • Completion in December 2007
Owasso Public Schools
Sixth Grade Center• 13 classrooms• Admin suite, secure
entry• Science lab• Commons
addition/renovation• Completion in
December 2007
Owasso Public Schools
Eighth Grade Center• Admin suite, secure
entry• 4 Science labs• Computer lab• Media Center• Commons
renovation• Completion in
December 2007
Owasso Public Schools
Vocational Agriculture• New Vocational Agriculture
building• Completion in February 2008
Owasso Public Schools
High School Phase I• 120,000 square feet
addition• interior remodel• secure entry• 50 additional
classrooms• commons/ kitchen
addition• athletics entry and
offices• new locker rooms• fine arts addition• cafeteria seating for
280• separate bus loop and
parent drop off• computer labs• wrestling room
addition• Science and art suites• Counseling suiteContinued….
Owasso Public Schools
High School Phase I• complete site redesign• administration offices• Complete HVAC remodel (Phase II)• Substantially Complete on April
2009
Owasso Public Schools
Tennis Courts• New tennis courts• Completion in June
2009
Owasso Public Schools
Stone Canyon Elementary School
• 95,000 square feet• Admin suite, secure entry• pod design with outdoor
learning centers• cafeteria seating 250• media center with reading
area• separate bus loop and parent
drop off• computer labs• separate kindergarten play
area• special needs area• competition gym• 26 acre site• asphalt playground• PlayfieldsContinued…
Owasso Public Schools
Stone Canyon Elementary
• Substantially Complete August 2009
Owasso Public Schools
Wellness Center• 36,000 square feet• district wide fitness center• hospitality room• concession stand• public restrooms• football offices• locker rooms• athletic training center
Owasso Public Schools
Wellness Center• hydrotherapy pool area• hall of fame gallery• classroom space• balconies overlooking
field• 90% complete as of
August 2009
Owasso Public Schools
Mid-High School• Admin suite, secure entry• Counseling suite• Renovations of commons areas• Renovations of classrooms• Renovations of restrooms• Front and back canopies• 60% complete as of August
2009
Owasso Public Schools
Track & Soccer Building• Renovation of existing
8,516 square foot track & soccer building
• 40% complete as of August 2009
Owasso Public Schools
Owasso Schools Bond Issue Needs List VOTE October 13th 2009
Security Entrances Bailey, Hodson, Smith, Ator, Mills & NE $4,200,000
Build-Out 2nd Floor of New High School Wing $3,500,000
Technology Upgrades District Wide $2,500,000
Maintenance/Equipment Upgrades @ All School Sites $1,800,000
Replacement of FB/Soccer, BB Infield Turf & Track Surface $1,105,000
Textbooks $1,000,000
Transportation $1,000,000
HVAC Upgrades for Old High School Wing $ 415,000
PAC Equipment Upgrades/Concert Band Shell $ 350,000
Total With Int. & Fees $19,700,000
***This Bond Issue Will Not Raise Taxes!!! 9-9-09