Optimization in Practice - Wisconsin Wastewater … Suspended Solids (DSS, FSS) Vertical Solids...

Post on 11-Mar-2018

224 views 8 download

Transcript of Optimization in Practice - Wisconsin Wastewater … Suspended Solids (DSS, FSS) Vertical Solids...

1

Bruce Bartel, NEW Water Nathan Cassity, Donohue

Optimization in Practice: Case Studies from NEW Water’s

Phosphorus and TSS Optimization Plans

WWOA, 51st Annual Conference October 2017

2

Outline

Background

Phosphorus Optimization

TSS Optimization

Future/Ongoing Optimization

Acknowledgments NEW Water

• Phil Mentink

• Pat Wescott

• Jake Becken

• Bill Oldenburg

• Aaron Eichhorst

• Matt Hooker

• Jon Strandberg

• Corey Evers

CPE Services

• John Esler

• Tim Miller

Donohue

• Andrew Dow

3

Background

2014 permit renewal

Combined permit for Green Bay Facility and De Pere Facility

Part of Lower Fox River TMDL

Included mass allocation limits for P and TSS

Included 9 year compliance schedule

4

Background

NEW Water’s Permit Compliance Reports

Operational Evaluation

Report Due: June

2015

Status Report #1

Due: June 2016

Status Report #2

Due: June 2017

Operational Evaluation

Report Amendment

Due: Dec 2017

Pre-Compliance Alternatives

Plan Due: March

2018

Status Report #4

Due: June 2018

Final Compliance Alternatives

Plan Due: Dec 2018

We are here

5

Green Bay Facility (GBF)

Design: 49 MGD Current: 32 MGD

Primary Clarifiers

North Aeration

Basins

North Final Clarifiers

South Final Clarifiers

South Aeration Basins

6

De Pere Facility (DPF)

Design: 10 MGD Current: 8 MGD

Tertiary Filters

Aeration Basins

Intermediate Clarifiers

Final Clarifiers

7

Phosphorus – Combined DPF + GBF

6-month Average Limit: 68 lbs/day

8

TSS – Combined DPF + GBF

Monthly Average Limit: 2,404 lbs/day

9

Optimization Strategy

Overall Strategy:

Optimize Biological Performance

• Minimize Soluble Phosphorus Discharge

• Minimize Biological Causes of Poor Settling

Identify/Evaluate Potential Clarifier Performance Improvements

Adapt to R2E2 Changes

• Use Biological Optimization and Trouble-Shooting Tools

• Use Supplemental Chemical Polishing as Needed

Optimize Solids Removal (Minimize TSS and TP)

10

Phosphorus Optimization

11

P Optimization Highlights

Facility Modifications (Aeration Basin Selectors)

Aeration Basin Profile Sampling

Phosphorus Speciation Data Collection

12

Facility Modifications

13

Selector Sizing Modifications

Phosphorus Action Item (GBF)

Goal: Measure phosphorus performance impact of increasing selector size (additional zone)

Original selectors:

• North Plant Basins: 1 zone each, 2 mixers per zone

• South Plant Basins: 1 zone each, 1 mixer per zone

Selector Additions:

• North Plant Basins: Additional larger zone, 4 mixers each

• South Plant Basins: Additional larger zone, 2 mixers each

14

Selector Sizing Modifications

North Plant

South Plant

NEW

15

Measuring Facility Modification Impacts

Modified and Un-Modified Basin Operating Simultaneously

16

North Complex Performance

Modified Basin Put in Service

17

South Complex Performance

Modified Basin Put in Service

2

18

Aeration Basin Profile Sampling

19

Basin Profile Sampling

Phosphorus Action Item (GBF)

Goal: Develop EBPR trouble-shooting tool

0

1

2

3

4

5

6

7

8

0 200 400 600

Soluble Phosphorus

(mg/L)

Basin Length

P Release: Endogenous

Activity

P Release Ratio: Selector P/Influent P

Parameters of Interest:

• Soluble P

• Ammonia

• Nitrate/Nitrite

• Alkalinity

20

December Phosphorus Profiles

1 2 Middle End

1 2 Middle

End

21

January Phosphorus Profiles

1 2 Middle End

1 2 Middle

End

22

December Nitrogen Profiles

23

January Nitrogen Profiles

24

Phosphorus Speciation

25

Phosphorus Speciation Background

Phosphorus Optimization Action Item

Goals:

• Prioritize strategies for improved phosphorus removal based on the forms of phosphorus in the effluent (soluble vs. particulate, reactive vs. non-reactive)

• Measure impacts of upgrades or piloted improvements

• Document phosphorus speciation profiles in collection system and among industrial contributors to identify potential source reduction priorities

26

Phosphorus Speciation Background

Red fraction: Difficult to remove

Dark blue: Conversion to PP

Dark green: Settle/filter

Light green: Settle/filter

27

July 2016 Effluent Speciation

28

Significant Industrial User Speciation

SIU Focus, 3 Days of Composite Sampling:

29

SIU Next Steps

Talk with top contributors (SIUs) to determine sources of phosphorus

Identify pollution prevention strategies for phosphorus reduction

30

Clarifier Field Testing

31

Clarifier Testing Background

TSS Optimization Action Item

Goal: Identify hydraulic improvements through field testing to improve clarifier performance (TSS performance)

Results of testing used to identify potential clarifier improvements

32

Clarifier Field Evaluation

CPE Services

John Esler – founder and president

Specializes in clarifier field evaluations

Author of Field Testing Chapter 7 WEF MOP FD-8

33

Green Bay Facility Clarifiers

South Plant

Clarifier #4

North Plant

Clarifiers #5 & #6

#5 #6

34

Field Tests

Conducted in April 2016

Timed to fall during elevated spring flows

Dye Tracer Tests

Drogue Current Tests

Dispersed/Flocculated Suspended Solids (DSS, FSS)

Vertical Solids Profiles

35

Dye Tracer Tests

36

Dye Tracer Tests

37

Dye Tracer Tests

38

Drogue Current Measurements

39

Drogue Current Measurements

40

Vertical Solids Profiles

41

North - Dye Tracer Test Results

Imbalance in launders

42

North - Dye Tracer Test Results

North Plant Clarifier No. 5: Outside weirs favored at elevated flow

43

Drogue Current Measurements

North Plant Clarifier No. 5 at elevated flow: strong density currents

44

Identified Performance Characteristic

Supporting Field Test Data

Potential Improvement

Density currents: short-circuiting

• Drogue current

measurements

• Dye testing results

• Increase centerwell

diameter to 20-25%

• Reduce centerwell depth

• Install energy dissipating

inlet

• Install mid-radius cylindrical

baffle

Out-of-balance launder: short-circuiting

• Dye testing results

• Replace launders in Clarifier

No. 6

Inboard launder: short-circuiting at perimeter

• Dye testing results

• Replace launders with

launders attached to outer

wall

Potential Improvements – North

45

Bruce Bartel, NEW Water Nathan Cassity, Donohue

Optimization in Practice: Case Studies from NEW Water’s

Phosphorus and TSS Optimization Plans

WWOA, 51st Annual Conference October 2017