Nuclear Regulatory Commission-Licensed Disposal Area (NDA) 2020/NDA_Armoring_Project_final...

Post on 03-Mar-2020

0 views 0 download

Transcript of Nuclear Regulatory Commission-Licensed Disposal Area (NDA) 2020/NDA_Armoring_Project_final...

www.energy.gov/EM 1Approved for Public Release; Further Dissemination Unlimited

Nuclear Regulatory Commission-Licensed Disposal Area (NDA)

Armoring Project

Stephen BousquetFederal Project Director

Quarterly Public MeetingFebruary 26, 2020

www.energy.gov/EM 2Approved for Public Release; Further Dissemination Unlimited

NDA Armoring Project

Approved for Public Release; Further Dissemination Unlimited

• Purpose of the NDA Armoring Project:

• Reduce future erosion risk if NDA Cap’s design basis is exceeded with the resulting potential overtopping and erosion of the NDA north slope.

• Design Basis:

• The design flood was chosen based on precipitation from 1/2 Probable Maximum Precipitation (PMP) per NRC recommendation, in accordance with NUREG-1623, Design of Erosion Protection for Long-Term Stabilization, Section 2.2.

• Design Review: Multi-agency design review (DOE, NRC, NYSERDA, U.S. Army Corp of Engineers, NYSDEC)

• Installation: June 3, 2019 – September 20, 2019

• Inspections: Annually and after rain events exceeding 1” over 24 hours

www.energy.gov/EM 3Approved for Public Release; Further Dissemination Unlimited

WVDP Aerial View

www.energy.gov/EM 4Approved for Public Release; Further Dissemination Unlimited

NDA Armoring Project Aerial View

Location of NDA Armoring Project

www.energy.gov/EM 5

Armoring Project Progress Photos

Approved for Public Release; Further Dissemination Unlimited

Before Armoring Excavation Initiated Early Stages of Excavation

www.energy.gov/EM 6

Armoring Project Progress Photos (Cont.)

Approved for Public Release; Further Dissemination Unlimited

Continuing Excavation Temporary Stormwater Bypass Pipes

www.energy.gov/EM 7

Armoring Project Progress Photos (Cont.)

Approved for Public Release; Further Dissemination Unlimited

Stormwater Bypass Pipe Outlets and Erosion Control

Final Stages of Excavation

www.energy.gov/EM 8

Armoring Project Progress Photos (Cont.)

Approved for Public Release; Further Dissemination Unlimited

Final Stages of Excavation Placement of Articulated Concrete Block (ACB)

Mats

www.energy.gov/EM 9

Armoring Project Progress Photos (Cont.)

Approved for Public Release; Further Dissemination Unlimited

Placement of ACB Mats

www.energy.gov/EM 10

Armoring Project Progress Photos (Cont.)

Approved for Public Release; Further Dissemination Unlimited

Grouted seams

www.energy.gov/EM 11

Armoring Project Progress Photos (Cont.)

Approved for Public Release; Further Dissemination Unlimited

Backfill placement Tying in North Slope of NDA Cap with Armoring

www.energy.gov/EM 12

Armoring Project Progress Photos (Cont.)

Approved for Public Release; Further Dissemination Unlimited

Vegetation starting within ACB on North Slope Grass growing

www.energy.gov/EM 13Approved for Public Release; Further Dissemination Unlimited

NDA Armoring Project Summary & Conclusion

• Installation from June 3, 2019 – September 20, 2019

• 18,000 cubic feet of soil excavated with 90% reused within the project boundary with the remainder disposed of, or waiting disposal offsite

• 35,000 cubic feet of new backfill placed

• 13,000 square feet of ACB placed (each block in the matt weighing 100 lbs.)

• 7,000 hours of work without an injury

• Conclusion: If the NDA’s north slope berm were to ever overtop, the now armored north side slope of the NDA would not be prone to erosion.

www.energy.gov/EM 14Approved for Public Release; Further Dissemination Unlimited

Questions?