Nuclear Regulatory Commission-Licensed Disposal Area (NDA) 2020/NDA_Armoring_Project_final...
Transcript of Nuclear Regulatory Commission-Licensed Disposal Area (NDA) 2020/NDA_Armoring_Project_final...
www.energy.gov/EM 1Approved for Public Release; Further Dissemination Unlimited
Nuclear Regulatory Commission-Licensed Disposal Area (NDA)
Armoring Project
Stephen BousquetFederal Project Director
Quarterly Public MeetingFebruary 26, 2020
www.energy.gov/EM 2Approved for Public Release; Further Dissemination Unlimited
NDA Armoring Project
Approved for Public Release; Further Dissemination Unlimited
• Purpose of the NDA Armoring Project:
• Reduce future erosion risk if NDA Cap’s design basis is exceeded with the resulting potential overtopping and erosion of the NDA north slope.
• Design Basis:
• The design flood was chosen based on precipitation from 1/2 Probable Maximum Precipitation (PMP) per NRC recommendation, in accordance with NUREG-1623, Design of Erosion Protection for Long-Term Stabilization, Section 2.2.
• Design Review: Multi-agency design review (DOE, NRC, NYSERDA, U.S. Army Corp of Engineers, NYSDEC)
• Installation: June 3, 2019 – September 20, 2019
• Inspections: Annually and after rain events exceeding 1” over 24 hours
www.energy.gov/EM 3Approved for Public Release; Further Dissemination Unlimited
WVDP Aerial View
www.energy.gov/EM 4Approved for Public Release; Further Dissemination Unlimited
NDA Armoring Project Aerial View
Location of NDA Armoring Project
www.energy.gov/EM 5
Armoring Project Progress Photos
Approved for Public Release; Further Dissemination Unlimited
Before Armoring Excavation Initiated Early Stages of Excavation
www.energy.gov/EM 6
Armoring Project Progress Photos (Cont.)
Approved for Public Release; Further Dissemination Unlimited
Continuing Excavation Temporary Stormwater Bypass Pipes
www.energy.gov/EM 7
Armoring Project Progress Photos (Cont.)
Approved for Public Release; Further Dissemination Unlimited
Stormwater Bypass Pipe Outlets and Erosion Control
Final Stages of Excavation
www.energy.gov/EM 8
Armoring Project Progress Photos (Cont.)
Approved for Public Release; Further Dissemination Unlimited
Final Stages of Excavation Placement of Articulated Concrete Block (ACB)
Mats
www.energy.gov/EM 9
Armoring Project Progress Photos (Cont.)
Approved for Public Release; Further Dissemination Unlimited
Placement of ACB Mats
www.energy.gov/EM 10
Armoring Project Progress Photos (Cont.)
Approved for Public Release; Further Dissemination Unlimited
Grouted seams
www.energy.gov/EM 11
Armoring Project Progress Photos (Cont.)
Approved for Public Release; Further Dissemination Unlimited
Backfill placement Tying in North Slope of NDA Cap with Armoring
www.energy.gov/EM 12
Armoring Project Progress Photos (Cont.)
Approved for Public Release; Further Dissemination Unlimited
Vegetation starting within ACB on North Slope Grass growing
www.energy.gov/EM 13Approved for Public Release; Further Dissemination Unlimited
NDA Armoring Project Summary & Conclusion
• Installation from June 3, 2019 – September 20, 2019
• 18,000 cubic feet of soil excavated with 90% reused within the project boundary with the remainder disposed of, or waiting disposal offsite
• 35,000 cubic feet of new backfill placed
• 13,000 square feet of ACB placed (each block in the matt weighing 100 lbs.)
• 7,000 hours of work without an injury
• Conclusion: If the NDA’s north slope berm were to ever overtop, the now armored north side slope of the NDA would not be prone to erosion.
www.energy.gov/EM 14Approved for Public Release; Further Dissemination Unlimited
Questions?