MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003.

Post on 28-Mar-2015

224 views 5 download

Tags:

Transcript of MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003.

MONDAYMONDAY

1717

MARCH 2003MARCH 2003

Haivan Pass Tunnel Construction ProjectHaivan Pass Tunnel Construction Project

CONSTRUCTION PROGRESS

February 2003

Construction ProgressConstruction ProgressEnd of February 2003

Package Progress (physical)

1A 65%

1B 75%

2A 30%

2B 50%

3 0

4 0

5 55%

6 0

7 100%

Progress of Haivan TunnelProgress of Haivan Tunnel

Tunnel monitoring – End of February 2003

1907.7m (79.12)

1796.6m (75.5%)

2117.6m (54.9%)

2161.7m (56.1%)

1856.3m (97.9%)

Progress of Haivan TunnelProgress of Haivan Tunnel

Package IA – North Tunnel Section

Main tunnel: 3857.0 m, 2 lanes, 89 m2

Evacuation tunnel: 3875.0m, 15.5 m2

Ventilation Adit: 1895.5 m, 36.2 m2

Package IA – North Tunnel Section

Main tunnel: 3857.0 mMain tunnel: 3857.0 mEvacuation tunnel: 3857.0 mEvacuation tunnel: 3857.0 mVentilation Adit: 1896.5 mVentilation Adit: 1896.5 m

February 2003

2161.7m (56.1%)

2117.6m (54.9%)

1856.3m (97.9%)

Package IA – North Tunnel Section

February 2003

North Portal area

Package IA – North Tunnel Section

February 2003

Ventilation Adit Portal area

Package IA – North Tunnel Section

February 2003

Explosive charging at main tunnel

Package IA – North Tunnel Section

February 2003

Installation of waterproofing membrane at Main tunnel

Package IA – North Tunnel Section

February 2003

Installation of waterproofing membrane at Main tunnel

Package IA – North Tunnel Section

February 2003

Completed lining concrete at layby No.3 and Vehicular cross passage connection

Package IA – North Tunnel Section

February 2003

Tunnel face drilling at Evacuation tunnel

Package IA – North Tunnel Section

February 2003

Explosive charging at Ventilation tunnel

Package IA – North Tunnel Section

February 2003

Shotcrete spraying at Electrostatic precipitator

Progress of Haivan TunnelProgress of Haivan Tunnel

Package IB – South Tunnel Section

Main tunnel: 3857.0 m, 2 làn xe, 89 m2

Evacuation tunnel: 3875.0m, 15.5 m2

Package IB - South Tunnel Section

Main tunnel: 2380.0 mMain tunnel: 2380.0 mEvacuation tunnel: 2411.0 mEvacuation tunnel: 2411.0 m

February 2003

1796.6m (75.5%)

1907.7m (79.12)

Package IB - South Tunnel Section

February 2003

South portal area

Package IB - South Tunnel Section

February 2003

Shotcrete for finishing between concrete lining

Package IB - South Tunnel Section

February 2003

Installation of water proofing membrane

Package IB - South Tunnel Section

February 2003

Concrete lining form No. 2

Package IB - South Tunnel Section

February 2003

Placcement of Concrete lining form No. 1

Package IB - South Tunnel Section

February 2003

Drilling of Evacuation tunnel

Package IB - South Tunnel Section

February 2003

Electrostatic precipitator No. 3

Package IB - South Tunnel Section

February 2003

North abutment of Bridge No. 1

Progress of Haivan TunnelProgress of Haivan Tunnel

Tunnel monitoring – End of February 2003

1907.7m (79.12)

1796.6m (75.5%)

2117.6m (54.9%)

2161.7m (56.1%)

1856.3m (97.9%)

Progress of Haivan Pass Tunnel ProjectProgress of Haivan Pass Tunnel Project

Package IIA – Lang Co Bridge Section

Lang Co Bridge, 876.390 m total length

Two lane roadway, 782.61m total length

A northern toll plaza

Construction of 187m2 area enclosed car port

Package IIA – Lang Co Bridge Section

February 2003

Overall Progress: 30%

• North approach: Road and surcharge fill completed 100%

• Lang Co Bridge: 28%

• Total 182 nos of bored piling completed, remaining 64 nos

• Total 10 girders launched

• South approach: embankment finished up to 1000 m3

Package IIA – Lang Co Bridge Section

February 2003

General view of Lang Co view

Package IIA – Lang Co Bridge Section

February 2003

Launching girder span No. 25

Package IIA – Lang Co Bridge Section

February 2003

Launching girder span No. 26

Package IIA – Lang Co Bridge Section

February 2003

Construction of P10

Package IIA – Lang Co Bridge Section

February 2003

Construction of P19

Package IIA – Lang Co Bridge Section

February 2003

Sight view of P21, P22, P23…

Package IIA – Lang Co Bridge Section

February 2003

Completed P24, P25, A2 abutment on site

Package IIA – Lang Co Bridge Section

February 2003

Installation of floating system

Progress of Haivan Pass Tunnel ProjectProgress of Haivan Pass Tunnel Project

Overall Progress: 50%

Bridge No. 2 : 334m, 46%

Bridge No. 3 : 33 m, 50%

Bridge No. 4 : 175 m, 97%

Bridge No. 5 : 133 m, 48%

Bridge No. 6 : 150 m, 47%

Bridge No. 7 : 133 m, 48%

Package IIB – Southern Highway Section

February 2003

Package IIB – Southern Highway Section

February 2003

Bridge No.2: launching spans (A1-P3)

Package IIB – Southern Highway Section

February 2003

Bridge No. 2: Pier P4 - P8

Package IIB – Southern Highway Section

February 2003

Bridge No.4: Completed deck slab view from A1

Package IIB – Southern Highway Section

February 2003

Bridge No.5: Girder casting yard

Package IIB – Southern Highway Section

February 2003

Bridge No.6: Girder casting yard

Package IIB – Southern Highway Section

February 2003

Bridge No.7: Abutment A1 under structural backfilling

Progress of Haivan Pass Tunnel ProjectProgress of Haivan Pass Tunnel Project

Package V: 110/22kV Substation and 110kV Transmission Line

February 2003

Overall progress: 55%

•110/22kV Substation

• Brick work was 90% completed

•110 GIS was delivered on site

• 110kV Transmission Line: 110kV Transmission Line Tower foundation excavation started

South Portal Area

Package V: 110/22kV Substation and 110kV Transmission Line

Package V: 110/22kV Substation and 110kV Transmission Line

February 2003

110/22kV Substation operation and control center building

Package V: 110/22kV Substation and 110kV Transmission Line

February 2003

110kV GIS delivery on site

Package V: 110/22kV Substation and 110kV Transmission Line

February 2003

Earthing register measurement for access

Package V: 110/22kV Substation and 110kV Transmission Line

February 2003

110kV Overhead Transmission Line Tower Foundation Excavation

ConclusionConclusion