MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003.

51
MONDAY MONDAY 17 17 MARCH 2003 MARCH 2003

Transcript of MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003.

Page 1: MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003.

MONDAYMONDAY

1717

MARCH 2003MARCH 2003

Page 2: MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003.

Haivan Pass Tunnel Construction ProjectHaivan Pass Tunnel Construction Project

CONSTRUCTION PROGRESS

February 2003

Page 3: MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003.

Construction ProgressConstruction ProgressEnd of February 2003

Package Progress (physical)

1A 65%

1B 75%

2A 30%

2B 50%

3 0

4 0

5 55%

6 0

7 100%

Page 4: MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003.

Progress of Haivan TunnelProgress of Haivan Tunnel

Tunnel monitoring – End of February 2003

1907.7m (79.12)

1796.6m (75.5%)

2117.6m (54.9%)

2161.7m (56.1%)

1856.3m (97.9%)

Page 5: MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003.

Progress of Haivan TunnelProgress of Haivan Tunnel

Package IA – North Tunnel Section

Main tunnel: 3857.0 m, 2 lanes, 89 m2

Evacuation tunnel: 3875.0m, 15.5 m2

Ventilation Adit: 1895.5 m, 36.2 m2

Page 6: MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003.

Package IA – North Tunnel Section

Main tunnel: 3857.0 mMain tunnel: 3857.0 mEvacuation tunnel: 3857.0 mEvacuation tunnel: 3857.0 mVentilation Adit: 1896.5 mVentilation Adit: 1896.5 m

February 2003

2161.7m (56.1%)

2117.6m (54.9%)

1856.3m (97.9%)

Page 7: MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003.

Package IA – North Tunnel Section

February 2003

North Portal area

Page 8: MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003.

Package IA – North Tunnel Section

February 2003

Ventilation Adit Portal area

Page 9: MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003.

Package IA – North Tunnel Section

February 2003

Explosive charging at main tunnel

Page 10: MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003.

Package IA – North Tunnel Section

February 2003

Installation of waterproofing membrane at Main tunnel

Page 11: MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003.

Package IA – North Tunnel Section

February 2003

Installation of waterproofing membrane at Main tunnel

Page 12: MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003.

Package IA – North Tunnel Section

February 2003

Completed lining concrete at layby No.3 and Vehicular cross passage connection

Page 13: MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003.

Package IA – North Tunnel Section

February 2003

Tunnel face drilling at Evacuation tunnel

Page 14: MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003.

Package IA – North Tunnel Section

February 2003

Explosive charging at Ventilation tunnel

Page 15: MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003.

Package IA – North Tunnel Section

February 2003

Shotcrete spraying at Electrostatic precipitator

Page 16: MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003.

Progress of Haivan TunnelProgress of Haivan Tunnel

Package IB – South Tunnel Section

Main tunnel: 3857.0 m, 2 làn xe, 89 m2

Evacuation tunnel: 3875.0m, 15.5 m2

Page 17: MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003.

Package IB - South Tunnel Section

Main tunnel: 2380.0 mMain tunnel: 2380.0 mEvacuation tunnel: 2411.0 mEvacuation tunnel: 2411.0 m

February 2003

1796.6m (75.5%)

1907.7m (79.12)

Page 18: MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003.

Package IB - South Tunnel Section

February 2003

South portal area

Page 19: MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003.

Package IB - South Tunnel Section

February 2003

Shotcrete for finishing between concrete lining

Page 20: MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003.

Package IB - South Tunnel Section

February 2003

Installation of water proofing membrane

Page 21: MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003.

Package IB - South Tunnel Section

February 2003

Concrete lining form No. 2

Page 22: MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003.

Package IB - South Tunnel Section

February 2003

Placcement of Concrete lining form No. 1

Page 23: MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003.

Package IB - South Tunnel Section

February 2003

Drilling of Evacuation tunnel

Page 24: MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003.

Package IB - South Tunnel Section

February 2003

Electrostatic precipitator No. 3

Page 25: MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003.

Package IB - South Tunnel Section

February 2003

North abutment of Bridge No. 1

Page 26: MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003.

Progress of Haivan TunnelProgress of Haivan Tunnel

Tunnel monitoring – End of February 2003

1907.7m (79.12)

1796.6m (75.5%)

2117.6m (54.9%)

2161.7m (56.1%)

1856.3m (97.9%)

Page 27: MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003.

Progress of Haivan Pass Tunnel ProjectProgress of Haivan Pass Tunnel Project

Package IIA – Lang Co Bridge Section

Lang Co Bridge, 876.390 m total length

Two lane roadway, 782.61m total length

A northern toll plaza

Construction of 187m2 area enclosed car port

Page 28: MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003.

Package IIA – Lang Co Bridge Section

February 2003

Overall Progress: 30%

• North approach: Road and surcharge fill completed 100%

• Lang Co Bridge: 28%

• Total 182 nos of bored piling completed, remaining 64 nos

• Total 10 girders launched

• South approach: embankment finished up to 1000 m3

Page 29: MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003.

Package IIA – Lang Co Bridge Section

February 2003

General view of Lang Co view

Page 30: MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003.

Package IIA – Lang Co Bridge Section

February 2003

Launching girder span No. 25

Page 31: MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003.

Package IIA – Lang Co Bridge Section

February 2003

Launching girder span No. 26

Page 32: MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003.

Package IIA – Lang Co Bridge Section

February 2003

Construction of P10

Page 33: MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003.

Package IIA – Lang Co Bridge Section

February 2003

Construction of P19

Page 34: MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003.

Package IIA – Lang Co Bridge Section

February 2003

Sight view of P21, P22, P23…

Page 35: MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003.

Package IIA – Lang Co Bridge Section

February 2003

Completed P24, P25, A2 abutment on site

Page 36: MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003.

Package IIA – Lang Co Bridge Section

February 2003

Installation of floating system

Page 37: MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003.

Progress of Haivan Pass Tunnel ProjectProgress of Haivan Pass Tunnel Project

Overall Progress: 50%

Bridge No. 2 : 334m, 46%

Bridge No. 3 : 33 m, 50%

Bridge No. 4 : 175 m, 97%

Bridge No. 5 : 133 m, 48%

Bridge No. 6 : 150 m, 47%

Bridge No. 7 : 133 m, 48%

Package IIB – Southern Highway Section

February 2003

Page 38: MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003.

Package IIB – Southern Highway Section

February 2003

Bridge No.2: launching spans (A1-P3)

Page 39: MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003.

Package IIB – Southern Highway Section

February 2003

Bridge No. 2: Pier P4 - P8

Page 40: MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003.

Package IIB – Southern Highway Section

February 2003

Bridge No.4: Completed deck slab view from A1

Page 41: MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003.

Package IIB – Southern Highway Section

February 2003

Bridge No.5: Girder casting yard

Page 42: MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003.

Package IIB – Southern Highway Section

February 2003

Bridge No.6: Girder casting yard

Page 43: MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003.

Package IIB – Southern Highway Section

February 2003

Bridge No.7: Abutment A1 under structural backfilling

Page 44: MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003.

Progress of Haivan Pass Tunnel ProjectProgress of Haivan Pass Tunnel Project

Package V: 110/22kV Substation and 110kV Transmission Line

February 2003

Overall progress: 55%

•110/22kV Substation

• Brick work was 90% completed

•110 GIS was delivered on site

• 110kV Transmission Line: 110kV Transmission Line Tower foundation excavation started

Page 45: MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003.

South Portal Area

Package V: 110/22kV Substation and 110kV Transmission Line

Page 46: MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003.

Package V: 110/22kV Substation and 110kV Transmission Line

February 2003

110/22kV Substation operation and control center building

Page 47: MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003.

Package V: 110/22kV Substation and 110kV Transmission Line

February 2003

110kV GIS delivery on site

Page 48: MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003.

Package V: 110/22kV Substation and 110kV Transmission Line

February 2003

Earthing register measurement for access

Page 49: MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003.

Package V: 110/22kV Substation and 110kV Transmission Line

February 2003

110kV Overhead Transmission Line Tower Foundation Excavation

Page 50: MONDAY 17 MARCH 2003 Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003.

ConclusionConclusion

Progress of Project is updated monthly at project’s homepage

http://haivan.cup.com

Consultant Team’s email: [email protected]