Metro Riyadh, Underground Stations1B2+1C3+1C4+1D2

Facts Project DescriptionMetro Riyadh, Stations 1B2+1C3+1C4+1D2Civil works for 4 deep underground metro stations in Riyadh including concrete, steel andformworks.

Use of DYWIDAG DOKA System formwork and scaffolding.The civil works for the 4 stations are similar:- 30 m below the ground level.- length: 135 m, width: 25 m- outer wall thickness: 75 cm- 6 slabs at different elevations (5 floors)- 2 tower cranes for each station

The outer wall (75 cm thickness) will be casted with one side formwork against naturalground by using special climbing formwork. Concrete and reinforcement supplied by client.

Project Data:Concrete: 148,600 m³Masonry: 54,500 m²Reinforcement: 29,654 tFormwork: 209,873 m²

City/Country

Riyadh / Saudi Arabia

Client

BACS Riyadh Metro Project, Riyadh

Contract Value

€ 36,80 Mio.

Construction Period

12/2016 - 08/2018 (20 Months)

.