Llvd and blvd trial report 90574 manggarai utara

Post on 21-Apr-2017

564 views 23 download

Transcript of Llvd and blvd trial report 90574 manggarai utara

HUAWEI TECHNOLOGIES CO., LTD. Huawei proprietary. No spread without permission. Page 1

Site Investigation Report Trial of Increasing LVLD Voltage Level

Alwan Ramadan WX289116, July-31-2015

HUAWEI TECHNOLOGIES CO., LTD. Huawei proprietary. No spread without permission. Page 2

Site ID : 90574

Site Name : Manggarai Utara

Category Site : End site

Site information

HUAWEI TECHNOLOGIES CO., LTD. Huawei proprietary. No spread without permission. Page 3

View of Equipments

HUAWEI TECHNOLOGIES CO., LTD. Huawei proprietary. No spread without permission. Page 4

View of Equipments

APM30H DC Power System Battery Rack

HUAWEI TECHNOLOGIES CO., LTD. Huawei proprietary. No spread without permission. Page 5

View details Rectifier Systems

Equipment Connected 3*30 Rectifier Modules

HUAWEI TECHNOLOGIES CO., LTD. Huawei proprietary. No spread without permission. Page 6

View of Battery Banks

Connected to Rectifier System

2 Bank Battery * 100Ah

ACME-F 12NDF100

HUAWEI TECHNOLOGIES CO., LTD. Huawei proprietary. No spread without permission. Page 7

Battery Current Measurement

HUAWEI TECHNOLOGIES CO., LTD. Huawei proprietary. No spread without permission. Page 8

Load measurement on Rectifier System

Load BTS and NodeB = 26.6 A

Load BTS and NodeB

Connected to

RFC1

HUAWEI TECHNOLOGIES CO., LTD. Huawei proprietary. No spread without permission. Page 9

Load measurement on Rectifier System

Load RTN= 2.73 A Load FAN = 0.25 A

HUAWEI TECHNOLOGIES CO., LTD. Huawei proprietary. No spread without permission. Page 10

Load measurement on Rectifier System

Load FAN

Load RTN

HUAWEI TECHNOLOGIES CO., LTD. Huawei proprietary. No spread without permission. Page 11

View Source information's Current Loads: Rectifier System = 30.96 A

DC Voltage

53.51 Load Current

RECT

HUAWEI TECHNOLOGIES CO., LTD. Huawei proprietary. No spread without permission. Page 12

Begin Trial Test LLVD parameter setting Through M2000 (Before)

HUAWEI TECHNOLOGIES CO., LTD. Huawei proprietary. No spread without permission. Page 13

Begin Trial Test LLVD parameter setting Through M2000 (After)

HUAWEI TECHNOLOGIES CO., LTD. Huawei proprietary. No spread without permission. Page 14

Load measurement on Rectifier System (AFTER / LLVD OPEN)

View status of DC Voltage a moment after switch off AC Source. We can see images above, when the Voltage goes down and reached 48.7 VDC, The loads (BTS) Disconnected (0.5 Adc).

Output Voltage Load BTS and Node B after LLVD Open

HUAWEI TECHNOLOGIES CO., LTD. Huawei proprietary. No spread without permission. Page 15

Load measurement on Rectifier System (AFTER / LLVD OPEN)

Load

Disconnected

HUAWEI TECHNOLOGIES CO., LTD. Huawei proprietary. No spread without permission. Page 16

View of Loads current

Value of DC Current

on RECT SYST =

8.66 A

HUAWEI TECHNOLOGIES CO., LTD. Huawei proprietary. No spread without permission. Page 17

Load Measurements of the Transmissions

The Priority loads still On, during LLVD Open.

Load FAN Load RTN

HUAWEI TECHNOLOGIES CO., LTD. Huawei proprietary. No spread without permission. Page 18

Final Conclusion:

The parameter level for LLVD and BLVD set directly to the Rectifier

system on site.

The LLVD and BLVD level parameter set only through M2000 and directly

test on site with switch OFF AC Source for the Rectifier.

The Trial of Decreasing Voltage level with setting the LVD parameter was

successful.

The NON Priority loads (BTS) which connected to RECTIFIER System

(APM30) are disconnected when the voltage drop to 49.0 VDC (base on

parameter set through M2000)

The Priority Loads which connected to RECTIFIER System (APM30) still

ON.

HUAWEI TECHNOLOGIES CO., LTD. Huawei proprietary. No spread without permission. Page 19

End of Report