1Amtrak and the Future of the Northeast CorridorProprietary – Not for distribution without Amtrak permission

1July 9, 2013

Lancaster StationCapstone Project 

Overview

Presented to Lancaster Traffic Commission

Lancaster Station Capstone Project Overview: July 9, 2013, Amtrak presentation to Lancaster Traffic Commission

2Amtrak and the Future of the Northeast CorridorProprietary – Not for distribution without Amtrak permission

2

STATION FACTS

Opened in 1929 by the Pennsylvania Railroad

3rd busiest station on the Keystone Corridor (559,364 passengers for FY12)

Provides access to Keystone Service and the Pennsylvanian

Lancaster Train Station

Lancaster Station Capstone Project Overview: July 9, 2013, Amtrak presentation to Lancaster Traffic Commission

3Amtrak and the Future of the Northeast CorridorProprietary – Not for distribution without Amtrak permission

3

The Challenge

Aging facility

Deterioration

Not compliant with ADA requirements

Public perception

Lancaster Station Capstone Project Overview: July 9, 2013, Amtrak presentation to Lancaster Traffic Commission

4Amtrak and the Future of the Northeast CorridorProprietary – Not for distribution without Amtrak permission

The Solution

The Capstone Project 

–Addresses both  interior and exterior renovations

–Restores the station to its historic significance

Lancaster Station Capstone Project Overview: July 9, 2013, Amtrak presentation to Lancaster Traffic Commission

5Amtrak and the Future of the Northeast CorridorProprietary – Not for distribution without Amtrak permission

The Capstone Project

Consists of two phases

–Phase 1‐ Amtrak Short‐Term work

–Phase 2‐ Contracted Long‐Term work 

Lancaster Station Capstone Project Overview: July 9, 2013, Amtrak presentation to Lancaster Traffic Commission

6Amtrak and the Future of the Northeast CorridorProprietary – Not for distribution without Amtrak permission

Phase 1‐ Short‐Term Work

Before After

Restoration of benches in Main Waiting Room and Concourse Bridge

Lancaster Station Capstone Project Overview: July 9, 2013, Amtrak presentation to Lancaster Traffic Commission

7Amtrak and the Future of the Northeast CorridorProprietary – Not for distribution without Amtrak permission

Phase 1: Short‐Term Work

Ceiling Repairs Completed Ceiling Repairs

Plaster and Paint repairs in the station foyer

Lancaster Station Capstone Project Overview: July 9, 2013, Amtrak presentation to Lancaster Traffic Commission

8Amtrak and the Future of the Northeast CorridorProprietary – Not for distribution without Amtrak permission

Phase 1: Short‐Term Work

Before After

Concourse Bridge Paint and Plaster Repairs

Lancaster Station Capstone Project Overview: July 9, 2013, Amtrak presentation to Lancaster Traffic Commission

9Amtrak and the Future of the Northeast CorridorProprietary – Not for distribution without Amtrak permission

Phase 1: Short‐Term Work

Exterior Sidewalk Repairs

Lancaster Station Capstone Project Overview: July 9, 2013, Amtrak presentation to Lancaster Traffic Commission

10Amtrak and the Future of the Northeast CorridorProprietary – Not for distribution without Amtrak permission

Phase 1: Short‐Term Work

Before After

Donation of (6) Clocks from Brent Miller Jewelers

Lancaster Station Capstone Project Overview: July 9, 2013, Amtrak presentation to Lancaster Traffic Commission

11Amtrak and the Future of the Northeast CorridorProprietary – Not for distribution without Amtrak permission

Phase 2: Contracted Long‐Term work

Peeling Paint and Plaster Ceiling deterioration

LoBar Construction currently making paint and plaster repairs to main waiting room

Lancaster Station Capstone Project Overview: July 9, 2013, Amtrak presentation to Lancaster Traffic Commission

12Amtrak and the Future of the Northeast CorridorProprietary – Not for distribution without Amtrak permission

Phase 2: Long‐Term Contracted Work

Concourse HVAC ReplacementContract awarded to Fluidics of PhiladelphiaEstimated completion by end of summer 2013

ASDP‐ ADA ProjectDesign phase

Lancaster Station Capstone Project Overview: July 9, 2013, Amtrak presentation to Lancaster Traffic Commission

13Amtrak and the Future of the Northeast CorridorProprietary – Not for distribution without Amtrak permission

The Capstone Project

Completion date: Fall 2013

Lancaster Station Capstone Project Overview: July 9, 2013, Amtrak presentation to Lancaster Traffic Commission

14Amtrak and the Future of the Northeast CorridorProprietary – Not for distribution without Amtrak permission

14

Thank You!