1Amtrak and the Future of the Northeast CorridorProprietary – Not for distribution without Amtrak permission
1July 9, 2013
Lancaster StationCapstone Project
Overview
Presented to Lancaster Traffic Commission
Lancaster Station Capstone Project Overview: July 9, 2013, Amtrak presentation to Lancaster Traffic Commission
2Amtrak and the Future of the Northeast CorridorProprietary – Not for distribution without Amtrak permission
2
STATION FACTS
Opened in 1929 by the Pennsylvania Railroad
3rd busiest station on the Keystone Corridor (559,364 passengers for FY12)
Provides access to Keystone Service and the Pennsylvanian
Lancaster Train Station
Lancaster Station Capstone Project Overview: July 9, 2013, Amtrak presentation to Lancaster Traffic Commission
3Amtrak and the Future of the Northeast CorridorProprietary – Not for distribution without Amtrak permission
3
The Challenge
Aging facility
Deterioration
Not compliant with ADA requirements
Public perception
Lancaster Station Capstone Project Overview: July 9, 2013, Amtrak presentation to Lancaster Traffic Commission
4Amtrak and the Future of the Northeast CorridorProprietary – Not for distribution without Amtrak permission
The Solution
The Capstone Project
–Addresses both interior and exterior renovations
–Restores the station to its historic significance
Lancaster Station Capstone Project Overview: July 9, 2013, Amtrak presentation to Lancaster Traffic Commission
5Amtrak and the Future of the Northeast CorridorProprietary – Not for distribution without Amtrak permission
The Capstone Project
Consists of two phases
–Phase 1‐ Amtrak Short‐Term work
–Phase 2‐ Contracted Long‐Term work
Lancaster Station Capstone Project Overview: July 9, 2013, Amtrak presentation to Lancaster Traffic Commission
6Amtrak and the Future of the Northeast CorridorProprietary – Not for distribution without Amtrak permission
Phase 1‐ Short‐Term Work
Before After
Restoration of benches in Main Waiting Room and Concourse Bridge
Lancaster Station Capstone Project Overview: July 9, 2013, Amtrak presentation to Lancaster Traffic Commission
7Amtrak and the Future of the Northeast CorridorProprietary – Not for distribution without Amtrak permission
Phase 1: Short‐Term Work
Ceiling Repairs Completed Ceiling Repairs
Plaster and Paint repairs in the station foyer
Lancaster Station Capstone Project Overview: July 9, 2013, Amtrak presentation to Lancaster Traffic Commission
8Amtrak and the Future of the Northeast CorridorProprietary – Not for distribution without Amtrak permission
Phase 1: Short‐Term Work
Before After
Concourse Bridge Paint and Plaster Repairs
Lancaster Station Capstone Project Overview: July 9, 2013, Amtrak presentation to Lancaster Traffic Commission
9Amtrak and the Future of the Northeast CorridorProprietary – Not for distribution without Amtrak permission
Phase 1: Short‐Term Work
Exterior Sidewalk Repairs
Lancaster Station Capstone Project Overview: July 9, 2013, Amtrak presentation to Lancaster Traffic Commission
10Amtrak and the Future of the Northeast CorridorProprietary – Not for distribution without Amtrak permission
Phase 1: Short‐Term Work
Before After
Donation of (6) Clocks from Brent Miller Jewelers
Lancaster Station Capstone Project Overview: July 9, 2013, Amtrak presentation to Lancaster Traffic Commission
11Amtrak and the Future of the Northeast CorridorProprietary – Not for distribution without Amtrak permission
Phase 2: Contracted Long‐Term work
Peeling Paint and Plaster Ceiling deterioration
LoBar Construction currently making paint and plaster repairs to main waiting room
Lancaster Station Capstone Project Overview: July 9, 2013, Amtrak presentation to Lancaster Traffic Commission
12Amtrak and the Future of the Northeast CorridorProprietary – Not for distribution without Amtrak permission
Phase 2: Long‐Term Contracted Work
Concourse HVAC ReplacementContract awarded to Fluidics of PhiladelphiaEstimated completion by end of summer 2013
ASDP‐ ADA ProjectDesign phase
Lancaster Station Capstone Project Overview: July 9, 2013, Amtrak presentation to Lancaster Traffic Commission
13Amtrak and the Future of the Northeast CorridorProprietary – Not for distribution without Amtrak permission
The Capstone Project
Completion date: Fall 2013
Lancaster Station Capstone Project Overview: July 9, 2013, Amtrak presentation to Lancaster Traffic Commission
14Amtrak and the Future of the Northeast CorridorProprietary – Not for distribution without Amtrak permission
14
Thank You!