KCI New Terminal Project Update · 8/19/2020  · A new video series that features Kansas Citians...

Post on 29-Sep-2020

2 views 0 download

Transcript of KCI New Terminal Project Update · 8/19/2020  · A new video series that features Kansas Citians...

KCI New Terminal Project Update

Transportation, Infrastructure, & Operations / August 19, 2020

8/19/2020

Agenda Executive Report Status Update

Project Progress MWBE & Workforce Participation Terminal Workforce Enhancement Programs

(TWEP)

Upcoming Milestones

8/19/2020

8/19/2020

Executive Status ReportJuly 2020

8/19/2020

8/19/2020

8/19/2020

8/19/2020

8/19/2020

8/19/2020

8/19/2020

8/19/2020

Procurements

8/19/2020

August Procurements Planned

Painting

Carpet

Terrazzo

Misc. Metals

Breach Control

September Procurements Planned

Millwork

Expansion Joints

Tile

Signage

Interior Glass

Ornamental Metal

Fountain

Landscape

Specialties

Project Progress

8/19/2020

PARKING GARAGE

8/19/2020

CONCOURSE B

CONCOURSE A BREAK TENT

ELEVATED ROADWAY

CONNECTOR

HEAD HOUSE

BOX CULVERT

New Terminal Project Site

8/19/2020

Underground Utilities – 16” Waterline

Structural Steel & Metal Decking

8/19/2020

Technology Enforces Social Distancing

8/19/2020

National Steel City workers wear devices on helmets that enforce social distancing on the project site

When workers are less than 6 feet apart, the devices will beep

Featured in Ironworkers Magazine

Proximity Trace Sensor

Headhouse Pre-cast Concrete

8/19/2020

Y Column Installation

8/19/2020

8/19/2020

Landside Roadways

Elevated Roadway

8/19/2020

Parking Garage Mock-up

8/19/2020

M/WBE & Workforce Participation

8/19/2020

M/WBE Participation Verified Payments

SERVICE TYPE FIRM TYPEFAIRNESS IN

CONSTRUCTION/HRD GOALS

EDGEMOOR DEVELOPER’S

PLEDGE

PAID TO DATEAS OF AUG. 14, 2020

Professional Services

MBE 17.0% 20.0% 19.56% $9.84 M

WBE 12.0% 15.0% 10.76% $5.41 M

Construction Services

MBE 15.0% 20.0% 17.79% $27.07 M

WBE 9.0% 15.0% 7.45% $11.33 M

Source: B2G Now

8/19/2020

Workforce Participation

CONSTRUCTION EMPLOYMENT

WORKFORCE PARTICIPATION GOALS

WORKFORCE TOTALS AS OF AUG. 14, 2020

Minority Workforce* 20.00% 18%

Women Workforce* 2.75% 5%

KCMO Workforce* N/A 11%

KC Metro Workforce** N/A 80.23%

*Source: B2G Now**Source: E-comply

8/19/2020

8/19/2020

Built by Kansas CityA new video series that features Kansas Citians working on the KCI New Terminal Project construction site

For videos and project news visit the KCI Edgemoor Facebook Page

Mike RocheIRONWORKER

NATIONAL STEEL CITY

WATCH

Chad SalsburyIRONWORKER

NATIONAL STEEL CITY

WATCH

Ariel DavisPLUMBER

U.S. ENGINEERING

WATCH

“When everything is all said and done, I think I’ll be pretty proud to say that I helped build the KCI airport. I feel pretty special. I feel like I’m somebody.”

Terminal Workforce Enhancement Programs (TWEP)

8/19/2020

Terminal Workforce Enhancement Programs (TWEP) Update Workforce Training Program (WTP)

Class 3 concludes this week

Graduation on Friday, Aug. 21, 2020 at 4 p.m.

Kansas City Strategic Partnership Program (KC SPP)Reviewing applications

Class to start virtually in September

Summer Associates Program 7 project interns

8/19/2020

Summer Associates Program College & graduate students

engineering, architecture, business & real estate degrees

Roles on the project project communications and

public outreach

monthly/quarterly reporting

TWEP planning and support

construction design management

on-site project management support

estimating and procurement

7/22/202029

Upcoming Project Milestones

Summer 2020 Headhouse Precast Elevated Roadway Parking Garage Grading WTP Class 3 Roofing Parking Garage

Foundation

Fall 2020 Interior Masonry Design CompletionKC SPP Class 4WTP Class 4

► Winter 2020/21►Curtain Wall►Steel Structure Complete

8/19/2020

8/19/2020

New Terminal Construction Status Underground MEP Work – All Complete This Month Except Bldg. 10B

Slab-on-Grade Bldgs. 1 - 8, 10A, 11A, 12A, 13 & 14 – Complete Bldg. 9 Finishing in August

Structural Steel Bldgs. 1, 2, 3, 9 10A, 12A, 13 & 14 – Complete Bldg. 7 – Start mid-August. Finish early Sept. Bldg. 8 – Start early Sept. Y-Columns & Box Beams – Start week of August 10th

Elevated Deck Concrete Slabs Bldg. 1, 2, & 14 – Complete Bldgs. 3, 9 & 13 Complete in August

Precast Exterior Panels Bldg. 10B – 12B East Side Completed in July Start Bldg. 2 (East Side) – August 10 Complete Bldg. 3 (West Side) – early September

Masonry Starting in Bldg. 1 – Week of August 10th

8/19/2020

Landside & Airside Civil Projects Elevated Roadway

Columns - Complete Beam & Double-T Placement – Seq. 2 Complete. Starting Seq. 3 Roadway Pavement – Seq. 1 Complete. Seq. 2 – August 12

Landside Roadways Continue Bonn Circle Exit Road (Phase 1) Begin Excavation for MSE (Mechanically Stabilized Earth) Walls 1, 2 & 3 – July Start Grade Work for Garage Entrance Roads - July

GSE Fueling Pad Unleaded Fuel Tank – Set August 4th

Mechanical & Electrical Connection Diesel Fuel Tank – Mid-September

Surface Parking Lot Rough Grade for New Police & Visitor Parking Lots – Complete Contractor Mobilization - August

Evergy Electric Service Terminal Power Redundant Power

8/19/2020