KCI New Terminal Project Update
Transportation, Infrastructure, & Operations / August 19, 2020
8/19/2020
Agenda Executive Report Status Update
Project Progress MWBE & Workforce Participation Terminal Workforce Enhancement Programs
(TWEP)
Upcoming Milestones
8/19/2020
8/19/2020
Executive Status ReportJuly 2020
8/19/2020
8/19/2020
8/19/2020
8/19/2020
8/19/2020
8/19/2020
8/19/2020
8/19/2020
Procurements
8/19/2020
August Procurements Planned
Painting
Carpet
Terrazzo
Misc. Metals
Breach Control
September Procurements Planned
Millwork
Expansion Joints
Tile
Signage
Interior Glass
Ornamental Metal
Fountain
Landscape
Specialties
Project Progress
8/19/2020
PARKING GARAGE
8/19/2020
CONCOURSE B
CONCOURSE A BREAK TENT
ELEVATED ROADWAY
CONNECTOR
HEAD HOUSE
BOX CULVERT
New Terminal Project Site
8/19/2020
Underground Utilities – 16” Waterline
Structural Steel & Metal Decking
8/19/2020
Technology Enforces Social Distancing
8/19/2020
National Steel City workers wear devices on helmets that enforce social distancing on the project site
When workers are less than 6 feet apart, the devices will beep
Featured in Ironworkers Magazine
Proximity Trace Sensor
Headhouse Pre-cast Concrete
8/19/2020
Y Column Installation
8/19/2020
8/19/2020
Landside Roadways
Elevated Roadway
8/19/2020
Parking Garage Mock-up
8/19/2020
M/WBE & Workforce Participation
8/19/2020
M/WBE Participation Verified Payments
SERVICE TYPE FIRM TYPEFAIRNESS IN
CONSTRUCTION/HRD GOALS
EDGEMOOR DEVELOPER’S
PLEDGE
PAID TO DATEAS OF AUG. 14, 2020
Professional Services
MBE 17.0% 20.0% 19.56% $9.84 M
WBE 12.0% 15.0% 10.76% $5.41 M
Construction Services
MBE 15.0% 20.0% 17.79% $27.07 M
WBE 9.0% 15.0% 7.45% $11.33 M
Source: B2G Now
8/19/2020
Workforce Participation
CONSTRUCTION EMPLOYMENT
WORKFORCE PARTICIPATION GOALS
WORKFORCE TOTALS AS OF AUG. 14, 2020
Minority Workforce* 20.00% 18%
Women Workforce* 2.75% 5%
KCMO Workforce* N/A 11%
KC Metro Workforce** N/A 80.23%
*Source: B2G Now**Source: E-comply
8/19/2020
8/19/2020
Built by Kansas CityA new video series that features Kansas Citians working on the KCI New Terminal Project construction site
For videos and project news visit the KCI Edgemoor Facebook Page
Mike RocheIRONWORKER
NATIONAL STEEL CITY
WATCH
Chad SalsburyIRONWORKER
NATIONAL STEEL CITY
WATCH
Ariel DavisPLUMBER
U.S. ENGINEERING
WATCH
“When everything is all said and done, I think I’ll be pretty proud to say that I helped build the KCI airport. I feel pretty special. I feel like I’m somebody.”
Terminal Workforce Enhancement Programs (TWEP)
8/19/2020
Terminal Workforce Enhancement Programs (TWEP) Update Workforce Training Program (WTP)
Class 3 concludes this week
Graduation on Friday, Aug. 21, 2020 at 4 p.m.
Kansas City Strategic Partnership Program (KC SPP)Reviewing applications
Class to start virtually in September
Summer Associates Program 7 project interns
8/19/2020
Summer Associates Program College & graduate students
engineering, architecture, business & real estate degrees
Roles on the project project communications and
public outreach
monthly/quarterly reporting
TWEP planning and support
construction design management
on-site project management support
estimating and procurement
7/22/202029
Upcoming Project Milestones
Summer 2020 Headhouse Precast Elevated Roadway Parking Garage Grading WTP Class 3 Roofing Parking Garage
Foundation
Fall 2020 Interior Masonry Design CompletionKC SPP Class 4WTP Class 4
► Winter 2020/21►Curtain Wall►Steel Structure Complete
8/19/2020
8/19/2020
New Terminal Construction Status Underground MEP Work – All Complete This Month Except Bldg. 10B
Slab-on-Grade Bldgs. 1 - 8, 10A, 11A, 12A, 13 & 14 – Complete Bldg. 9 Finishing in August
Structural Steel Bldgs. 1, 2, 3, 9 10A, 12A, 13 & 14 – Complete Bldg. 7 – Start mid-August. Finish early Sept. Bldg. 8 – Start early Sept. Y-Columns & Box Beams – Start week of August 10th
Elevated Deck Concrete Slabs Bldg. 1, 2, & 14 – Complete Bldgs. 3, 9 & 13 Complete in August
Precast Exterior Panels Bldg. 10B – 12B East Side Completed in July Start Bldg. 2 (East Side) – August 10 Complete Bldg. 3 (West Side) – early September
Masonry Starting in Bldg. 1 – Week of August 10th
8/19/2020
Landside & Airside Civil Projects Elevated Roadway
Columns - Complete Beam & Double-T Placement – Seq. 2 Complete. Starting Seq. 3 Roadway Pavement – Seq. 1 Complete. Seq. 2 – August 12
Landside Roadways Continue Bonn Circle Exit Road (Phase 1) Begin Excavation for MSE (Mechanically Stabilized Earth) Walls 1, 2 & 3 – July Start Grade Work for Garage Entrance Roads - July
GSE Fueling Pad Unleaded Fuel Tank – Set August 4th
Mechanical & Electrical Connection Diesel Fuel Tank – Mid-September
Surface Parking Lot Rough Grade for New Police & Visitor Parking Lots – Complete Contractor Mobilization - August
Evergy Electric Service Terminal Power Redundant Power
8/19/2020