UNIT RATE ANALYSIS

'ITEM DESCRIPTION : BOQ 1.5

Progress Photographs and Video documentary film.

Assumed Quantity =

S. NO. DESCRIPTION NO. UNIT QUANTITY UNIT COST

1.00 EQUIPMENT

2.00 MANPOWER

Document Controler 1.00 No 24 10,000.00

3.00 MATERIAL

Consumables 1 Lot 1 116,000.00

Documentary Film 1.00 Months 24 25,000.00

Photo Graphs(5Sets) 1.00 Months 24 10,000.00

Foulders 1.00 Months 24 2,500.00

Documentation/Stantionary 1.00 Months 24 2,500.00

4.00 Sub-Total

5.00 Indirect Costs(Site facilities/Supervision/tools), Overheads & Margin % 30

6.00 Total

7.00 Advance Tax % 6

8.00

9.00 Unit Price per Lot

10.00 Say

Total Price for : Lot

UNIT RATE ANALYSIS

Progress Photographs and Video documentary film.

Unit = L.SAssumed Quantity = 1 Lot

PARTIAL COST TOTAL (Rs.)

0

240,000

240,000

116,000

600,000

240,000

60,000

60,000

1,076,000

1,316,000

564,000

1,880,000

120,000

2,000,000

2,000,000

2,000,000