Transcript of Item 1.5
UNIT RATE ANALYSIS
'ITEM DESCRIPTION : BOQ 1.5
Progress Photographs and Video documentary film.
Assumed Quantity =
S. NO. DESCRIPTION NO. UNIT QUANTITY UNIT COST
1.00 EQUIPMENT
2.00 MANPOWER
Document Controler 1.00 No 24 10,000.00
3.00 MATERIAL
Consumables 1 Lot 1 116,000.00
Documentary Film 1.00 Months 24 25,000.00
Photo Graphs(5Sets) 1.00 Months 24 10,000.00
Foulders 1.00 Months 24 2,500.00
Documentation/Stantionary 1.00 Months 24 2,500.00
4.00 Sub-Total
5.00 Indirect Costs(Site facilities/Supervision/tools), Overheads & Margin % 30
6.00 Total
7.00 Advance Tax % 6
8.00
9.00 Unit Price per Lot
10.00 Say
Total Price for : Lot
UNIT RATE ANALYSIS
Progress Photographs and Video documentary film.
Unit = L.SAssumed Quantity = 1 Lot
PARTIAL COST TOTAL (Rs.)
0
240,000
240,000
116,000
600,000
240,000
60,000
60,000
1,076,000
1,316,000
564,000
1,880,000
120,000
2,000,000
2,000,000
2,000,000