ISPA Measure 200 5 BG 16 P PE 00 1. 1.Reconstruction of WWTP Sliven ( FIDIC Yellow Book ) 2.Construction/Reconstruction of Water Supply and Sewerage Network of Sliven (stage 1); LOT 1: Construction/Reconstruction of Sewerage Network. Integrated Water Project for the town of Sliven. - PowerPoint PPT Presentation

Transcript of ISPA Measure 200 5 BG 16 P PE 00 1

Integrated Water Project for the town of Sliven

1.Reconstruction of WWTP Sliven (FIDIC Yellow Book)

2.Construction/Reconstruction of Water Supply and Sewerage Network of Sliven (stage 1); LOT 1:Construction/Reconstruction of Sewerage

Network

ISPA Measure 2005 BG 16 P PE 001

Works Contract 1Reconstruction of WWTP Sliven

(FIDIC Yellow Book)

• Commencement Date: March 24, 2009

• Taking Over Certificate: July 21, 2011

• DNP started on: July 21, 2011

• Performance Certificate: October 18, 2012

• Physical Execution: 100 %

• Financial Execution: 83 %

WWTP Sliven

before reconstruction

Reconstruction of WWTP Sliven

Inlet chamber

Entrance and control building

Reconstruction of WWTP Sliven

Screening building

Reconstruction of WWTP Sliven

Grid tank

Blowers

Reconstruction of WWTP Sliven

Reconstruction of WWTP Sliven

PS for primary sludge - reconstruction

Primary Settlement Tank

Reconstruction of WWTP Sliven

Aeration Tank

Distribution Chamber of SSTSecondary Settlement Tank

Reconstruction of WWTP Sliven

Service Building at Heated Digesters

Reconstruction of WWTP Sliven

Facilities for Sludge treatment and utilization of biogas

Reconstruction of WWTP Sliven

Reconstruction of WWTP Sliven

SCADA MCC

Gasholder Torch

Reconstruction of WWTP Sliven

Reconstruction of WWTP Sliven

Commemorative table

Supervision Contracts

Contract № 1

• Commencement Date: March 23, 2009

• Completion Date: April 23, 2012

• Financial Execution: 100 %

Contract № 2 – funded by national budget

• Completion Date: December, 2012

Reconstruction of WWTP Sliven

Construction/Reconstruction of Sewerage Network – LOT1

• The final assessment for the result achieved in LOT 1 is about 23 % (excluding recovering of the roads).

• Sliven Municipality has submitted in MoEW documentation to apply for financing under the OP Environment. The new project includes the activities of LOT1 that were not completed by ISPA.

Compliance with Article 8of the Financing Memorandum

All conditions under Article 8 of the FM related to payments are considered fulfilled.

ISPA Measure 2005 BG 16 P PE 001

Integrated Water Project for the town of

Sliven

• Final Report was presented to the European Commission