ISPA Measure 2000 BG 16 P PE 001Integrated water project – City of Sofia
Performance
100%
• Excluded Components:
-Left Vladaiski Relief Sewer- Will be financed under OP Environment
-Distribution Water Supply Network – Kokalyane & Pancharevo
-DWTP – Stara Reka, Yanchovska, Zheleznishka
• Technical Assistance for Preparation of the Integrated Sofia Water Project-Closed
ISPA Measure 2000 BG 16 P PE 001Integrated water project – City of Sofia
Financial Performance: 93,65%
Contracted Amount: € 57,7 Mio
Certified Amount: € 54,1 Mio
ISPA Measure 2000 BG 16 P PE 001Integrated water project – City of Sofia
Reconstruction of WWTP Kubratovo and construction PS Novi Iskar
Works Contract
• Commencement Date: 03rd April 2009• Completion Date: 30th June 2011• Physical Execution: 100 %• Financial Execution: 99,30 %• 1 year DNP commenced after issuing of TOC
(30 June 2011)• Performance Certificate issued : 09 July2012
Supervision ContractKubratovo & Novi Iskar
• Commencement Date: 23rd March 2009
• Completion Date: 23rd April 2012
• Time elapsed: 100 %
• Financial Execution: 100 %
SOFIA WWTP KUBRATOVO
SOFIA WWTP KUBRATOVO
SOFIA PS Novi Iskar
ISPA Measure 2000 BG 16 P PE 001Integrated water project – City of Sofia
Water Supply and Sewerage Network (Red Book) – Tender I
Dragalevtzi Reservoir Outlet Main
Right Perlovski Main Sewer
Right Slatinski Main Sewer
Buxton Boulevard and Right Vladaiski Main Sewer
Works ContractTender 1
• Commencement Date: 23rd March 2010
• Completion Date: 23th November 2011
• Physical Execution:• Dragalevtzi Reservoir Outlet Main – 100%• Right Slatinski Main Sewer – 100%• Right Perlovski Main Sewer – 100%• Buxton Boulevard and Right Vladaiski Main Sewer – 100%
• Financial Execution: 100%
• 1 year DNP
• Performance Certificate issued: 15 January 2013
Supervision ContractTender 1
• Commencement Date: 08th March 2010
• Completion Date: 23th December 2012
• Time elapsed: 100 %
• Financial Execution: 100 %
Right Perlovski Main Sewer
Right Slatinski Main Sewer
Right Vladaiski Main Sewer
ISPA Measure 2000 BG 16 P PE 001Integrated water project – City of Sofia
Water Supply and Sewerage Network (Red Book) – Tender ІІ
•Rilski Water Main Rehabilitation•Left Vladaiski Main Sewer•Bankya Main Sewer
Works ContractTender II
• Commencement Date: 22nd October 2009• Completion Date: 24th December 2011• Physical Execution:
• Left Vladaiski Main Sewer – 100%
• Bankya Main Sewer – 100%
• Rilski Water Main Rehabilitation – 100%
• Financial Execution: 100 %• 1 year DNP
• Performance Certificate issued: 15 December 2012
Supervision ContractTender II
• Commencement Date: 12th October 2009
• Completion Date: 24th December 2012
• Time elapsed: 100 %
• Financial Execution: 100 %
Works ContractTender II – Bankya Kakach
Works ContractTender II – Bankya Kakach
Works ContractTender II – Left Vladayski Sewer
Works ContractTender II – Left Vladayski Sewer
Works ContractTender II – Left Vladayski Sewer
Works ContractTender II – Rilski Water Main
Works ContractTender II – Rilski Water Main
Works ContractTender II – Rilski Water Main
Works ContractTender II – Simeonovo Water Chamber
Works ContractTender II – Simeonovo Water Chamber
ISPA Measure 2000 BG 16 P PE 001Integrated water project – City of Sofia
Drinking Water Treatment Plants
•DWTP ‘Mala Tzarkva’•DWTP ‘Passarel’
Works ContractDWTP
• Commencement Date: 25th August 2010
• Completion Date: 30th September 2011
• Physical Execution: 100 %
• Financial Execution: 100 %
• 1 year DNP since 30 September 2011
• Performance Certificate issued: 16 October 2012
Supervision ContractDWTP
• Commencement Date: 16th August 2010
• Completion Date: 16th August 2012
• Time elapsed: 100 %
• Financial Execution: 100 %
Works ContractDWTP- Mala Tzarkva
Works ContractDWTP-Mala Tzarkva
Works ContractDWTP-Passarel
DWTP Passarel
ISPA Measure 2000 BG 16 P PE 001Integrated water project – City of Sofia
Billboards
Compliance with Article 8of the Financing Memorandum
Art. 8.3. and Art. 8.4.
According to the received letter from EC No.02973/06.04.2010 all conditions under Art.8.3. and 8.4. are fulfilled.
Art. 8.5.
According to letter from EC No.REGIO12/IV/sd(2012)1236700/12.09.2012, Art 8.5 is fulfilled
Thank you for your attention!