I-69 Major Moves 2020 Expansion Project –

Public Information Meeting

Tony Jones, PEProject Manager, INDOT

April 21, 2016

I-69 Major Moves 2020 Expansion Project

Meeting Agenda

Introduce Design-Build Team

Describe Project Delivery Strategy

Describe Project Construction Schedule

Discussion of Exit 210 Reconstruction

Discussion of Noise Barriers

Open Discussion

I-69 Major Moves 2020 Expansion Project

Project Team

Indiana Department of Transportation

Indiana Finance Authority

Parsons Corporation (front end design)

Milestone Contractors (construction)

United Consulting (back end design)

I-69 Major Moves 2020 Expansion Project

I-69 Major Moves 2020 Expansion Project

Project Delivery Strategy

Package 1:

Overlay and Partial Depth Patching of existing lanes.

Median outlet pipe installation and culvert lining.

Night-time lane restrictions.

I-69 Major Moves 2020 Expansion Project

Project Delivery Strategy

Package 2 (116th Street to north of Brooks School Road):

Added travel lane construction in median.

Use of barrier rail to separate construction and travel lanes.

Maintain two lanes in each direction at all times.

I-69 Major Moves 2020 Expansion Project

Project Delivery Strategy

Package 3:

Reconstruction of Campus Parkway / Southeastern Parkway at Exit 210.

Multi-phase maintenance of traffic.

Maintain through traffic at all times.

I-69 Major Moves 2020 Expansion Project

Project Delivery Strategy

Package 4 (north of Brooks School Road to north of SR 13):

Added travel lane construction in median.

Use of temporary barrier to separate construction from the travel lanes.

Maintain two lanes in each direction at all times.

I-69 Major Moves 2020 Expansion Project

Project Delivery Strategy

Package 5 (north of SR 13 to north of SR 38):

Added travel lane construction in median.

Use of temporary barrier to separate construction from the travel lanes.

Maintain two lanes in each direction at all times.

I-69 Major Moves 2020 Expansion Project

MOT Plan – I-69, Phase I (pkg 2, 4, 5)

I-69 Major Moves 2020 Expansion Project

MOT Plan – I-69, Phase II (pkg 2, 4 & 5)

I-69 Major Moves 2020 Expansion Project

MOT Plan – I-69, Phase III (pkg 2,4 & 5)

I-69 Major Moves 2020 Expansion Project

MOT Plan – I-69, Phase IV (pkg 2, 4 & 5)

I-69 Major Moves 2020 Expansion Project

MOT Plan – Exit 210, Phase 1 (pkg 3)

I-69 Major Moves 2020 Expansion Project

MOT Plan – Exit 210, Phase 2 (pkg 3)

I-69 Major Moves 2020 Expansion Project

MOT Plan – Exit 210, Phase 3 (pkg 3)

I-69 Major Moves 2020 Expansion Project

MOT Plan – Exit 210, Phase 4 (pkg 3)

I-69 Major Moves 2020 Expansion Project

MOT Plan – Exit 210, Phase 5 (pkg 3)

I-69 Major Moves 2020 Expansion Project

MOT Plan – Exit 210, Phase 6 (pkg 3)

I-69 Major Moves 2020 Expansion Project

MOT Plan – SR 13, Phase 1 (pkg 2)

I-69 Major Moves 2020 Expansion Project

MOT Plan – SR 13, Phase 2 (pkg 2)

I-69 Major Moves 2020 Expansion Project

Project Schedule

Overall Schedule:

Construction to begin in May, 2016

Construction to be complete in November, 2017

Final acceptance in October, 2018

Campus Parkway / Southeastern Parkway Construction limited to 360 days

I-69 Major Moves 2020 Expansion Project

Project Schedule

I-69 Construction:

Location106th to SR 37

SR 37 to North of Brooks School Road

North of Brooks

School Road to North of

SR 13

North of SR 13 to North of SR 38

Phase Ia/Ib 6/2017 5/2016 6/2016 7/2016

Phase II6/2017 -9/2017

5/2016 -9/2016

9/2016 -7/2017

7/2017 -9/2017

Phase IIIa/IIIb 9/2017 5/2017 6/2017 7/2017

Phase IV 10/2017 8/2017 9/2017 10/2017

I-69 Major Moves 2020 Expansion Project

Project Schedule

Exit 210 Construction:

Campus Parkway / Southeastern Parkway

Phase 1 7/5/2016

Phase 2 tbd

Phase 3 tbd

Phase 4 tbd

Phase 5 tbd

Phase 6

tbdComplete by 6/30/2017

I-69 Major Moves 2020 Expansion Project

Project Schedule

Exit 215 Construction:

Overhead Bridge Construction:

SR 13

Phase 1

2017 (tbd)Phase 2

Brooks School Road

5/2017 –8/2017

Madison County CR 650 W

5/2017 –8/2017

I-69 Major Moves 2020 Expansion Project

Detour – Brooks School Road Overpass

I-69 Major Moves 2020 Expansion Project

Detour – Madison Co. CR 650 W Overpass

I-69 Major Moves 2020 Expansion Project

Noise Barriers

Cumberland Crossing / Cumberland Woods

I-69 Major Moves 2020 Expansion Project

Noise Barriers

Whispering Woods

I-69 Major Moves 2020 Expansion Project

Noise Barriers

Brooks Chase

I-69 Major Moves 2020 Expansion Project

Noise Barriers

Roselake

I-69 Major Moves 2020 Expansion Project

Thank you for attending!

Visit www.in.gov/indot/3440.htmfor project updates.