- 1 -
Signature of Promoter/Developer No. of correction Signature of Inviter
GOVERNMENT OF MAHARASHTRA
WATER RESOURCES DEPARTMENT
PRE-QUALIFICATION DOCUMENT NO. CE(E)/HP/SHP/CPP/IPP/78
FOR
DEVELOPMENT OF GOSIKHURD (L.B.C.)HYDRO ELECTRIC
PROJECT ( 0.500 MW) THROUGH PRIVATE SECTOR
PARTICIPATION IN DEVELOPMENT OF SMALL HYDRO
ELECTRIC PROJECTS BY PRIVATE PARTICIPATION
Superintending Engineer, Vidarbha Hydro Electric & Lift
Irrigation Circle, Wainganga Nagar,
Near Ajani Railway Station, Ajani,
NAGPUR-440003 PHONE NO. 0712-2420922 FAX NO.- 0712-2440058
PRICE Rs. 7350 /-
- 2 -
Signature of Promoter/Developer No. of correction Signature of Inviter
GOVERNMENT OF MAHARASHTRA
WATER RESOURCES DEPARTMENT
PRE-QUALIFICATION DOCUMENT
NO. CE(E)/HP/SHP/CPP/IPP/78 FOR
DEVELOPMENT OF GOSIKHURD (L.B.C.)HYDRO ELECTRIC
PROJECT ( 0.500 MW) THROUGH PRIVATE SECTOR
PARTICIPATION IN DEVELOPMENT OF SMALL HYDRO
ELECTRIC PROJECTS BY PRIVATE PARTICIPATION
Issued to/ Downloaded by: -
Superintending Engineer, Vidarbha Hydro Electric & Lift Irrigation Circle,Wainganga Nagar, Near Ajani Railway Station, Ajani, NAGPUR-440003 PHONE NO. 0712-2420922 FAX NO.- 0712-2440058
- 3 -
Signature of Promoter/Developer No. of correction Signature of Inviter
PRE-QUALIFICATION DOCUMENT FOR DEVELOPMENT OF GOSIKHURD
(L.B.C.)HYDRO ELECTRIC PROJECT ( 0.500 MW) THROUGH PRIVATE
SECTOR PARTICIPATION IN DEVELOPMENT OF SMALL HYDRO
ELECTRIC PROJECTS BY PRIVATE PARTICIPATION
INDEX
CLAUSE DESCRIPTION
PAGE NO.
SECTION-I A) Press Notice in English
B) Press Notice in Marathi
C) Detailed Tender Notice in English
5
6
7
SECTION-II Instructions to the Promoters/Developers 9
SECTION-III Annexures 16
i) Annexure-I Procedure for evaluation 17
ii) Annexure-II
Information to be furnished by Promoter/Developer who has been earlier allotted the SHP for development
20
iii) Annexure-III
Information to be furnished by Promoter/Developer
21
iv) Annexure-IV
State Hydel Policy of the Government of Maharashtra, Water Resources Department
25
SECTION-IV A) Salient Features of Gosikhurd (L.B.C.) H.E. Project 46
B) Brief Description & Present Status of the Gosikhurd
(L.B.C.)H.E.P.
49
C) Appendices
Appendix - I Information submitted as per GOVT. of Maharashtra W. R. D. Mumbai letter NO. 1206/ (369/06)/HP/dtd. 24-4-2007
54
Appendix - II Working Table 56
Appendix - III Reservoir Operation Table 58
Appendix - IV Area capacity table for Gosikhurd (L.B.C.) Hydro Electric Project
59
SECTION-V Drawings 60
1) Drawing No. I Index map 61
2) Drawing No. 2 Cross Section of Earth Dam 62
3) Drawing No. 3 General Layout Plan 63
4) Drawing No. 4 Area capacity Curve 64
- 4 -
Signature of Promoter/Developer No. of correction Signature of Inviter
SECTION - I
1) Press Notice in English
2) Press Notice in Marathi
3) Detailed Press Notice
- 5 -
Signature of Promoter/Developer No. of correction Signature of Inviter
E-tender notice
GOVERNMENT OF MAHARASHTRA WATER RESOURCES DEPARTMENT
Main Portal : http://maharashtra.etenders.in
WRD Portal: http://wrd.maharashtra.etenders.in
Online Pre-Qualification proposals are invited for and on behalf of
Governor of Maharashtra by the Superintending Engineer, Vidarbha Hydro Electric & Lift Irrigation Circle, Wainganga Nagar, Ajni, Nagpur-440003
Maharashtra (INDIA), Ph.No. and Fax No.: 0712-2440058, for Prequalification of the Promoters / Developers who intend to develop SMALL HYDRO ELECTRIC PROJECTS, as Captive Power Producer
(CPP) / Independent Power Producer (IPP) for electricity generation in the State of Maharashtra by the Promoter / Developer company as stipulated in
Hydro Power Policy declared vide Govt. of Maharashtra, Water Resources Department, G.R.No. PVT-1204/ (160/2004)/HP, dated 15.9.2005.
Following Pre-Qualification Documents are available on web site from 20.03.2013 at 10.00am. to 15.04.2013 upto 3.00 pm
Sr. No
Pre-Qualification Document No.
Name of Hydro Electric Project and capacity (MW)
1. CE(E)/HP/SHP/CPP/
IPP/67D
Lower Wardha HEP Tal.: Arvi,
Dist.: Wardha (0.750 MW)
2 CE(E)/HP/SHP/CPP/
IPP/68 D
Shahanoor Canal Drop, HEP
Tal. Achalpur, Dist. Amravati
(0.350MW)
3 CE(E)/HP/SHP/CPP/ IPP/69 D
Bawanthadi – 1 HEP, Tal. Tumsar, Dist. Bhandara (0.350 MW)
4 CE(E)/HP/SHP/CPP/
IPP/70 D
Bawanthadi – 2 HEP Tal. Tumsar,
Dist. Bhandara (0.600 MW)
5 CE(E)/HP/SHP/CPP/
IPP/71D
Kalisarar HEP, Tal. Saleksa ,
Dist. Gondia (0.400MW)
6 CE(E)/HP/SHP/CPP/ IPP/50 B
Chandrabhaga HEP, Tal. Achalpur, Dist. Amaravati ( 1.0 MW)
7 CE(E)/HP/SHP/CPP/ IPP/77
Gosikhurd (R.B.C.) HEP Tal.: Pawni, Dist. Bhandara
( 2X1.250MW)
8 CE(E)/HP/SHP/CPP/ IPP/78
Gosikhurd (L.B.C.)HEP Tal.: Pawni, Dist. Bhandara (0.500MW)
The e-tendering will be strictly governed by the schedule of key dates available on the web site. Interested promoter/developer are requested to
visit web site for further details. The Promoter/Developers participating first time in e-Tendering process
will have to procure Digital Signature Certificate, Username & Password from competent authorities as per guidelines mentioned on homepage of the website.
If any assistance is required regarding e-Tendering (upload / download)
please contact e-tendering help desk contact Phone No. 020 – 25315555/
9167969601/04, support.gom@nextenders.com,
The Government reserves the right to reject any or all the proposals or annul the process without assigning any reason and without being
responsible for the cost incurred by the Promoter / Developer in preparing his P.Q. proposal / Price-Bid.
Superintending Engineer
Vidarbha Hydro Electric and Lift Irrigation Circle, Nagpur
- 6 -
Signature of Promoter/Developer No. of correction Signature of Inviter
<Ç-ÊxÉÊ´ÉnùÉ ºÉÚSÉxÉÉ ¨É½þÉ®úɹ]Åõ ¶ÉɺÉxÉ
VɱɺÉÆ{ÉnùÉ Ê´É¦ÉÉMÉ, Main Portal : http://maharashtra.etenders.in
WRD Portal: http://wrd.maharashtra.etenders.in
¨ ɽ þ É® úÉ ¹] Åõ É SªÉ É ® úÉ VªÉ {ÉÉ ± ÉÉÆSª É É ´ É iÉ Ò x Éä, +ÊvÉIÉEò +ʦɪÉÆiÉÉ, Ê´Énù¦ÉÇ VɱÉÊ´ÉtÖiÉ ´É = {ɺÉÉ ËºÉSÉxÉ ¨ÉÆb÷³ý, ´ÉèxÉMÉÆMÉÉ xÉMÉ®ú, +VÉxÉÒ, xÉÉMÉ{ÉÚ®ú-440003 ¨É½þÉ®úɹ]Åõ (¦ÉÉ®úiÉ) nÚù®úv´ÉxÉÒ GÆò. ´É ¡ìòCºÉ Gò. 0712-2440058 ½ äþ ¨É ½ þ É ® úÉ ¹] Åõ ¶ É É º É xÉ , VÉ ±É º ÉÆ{ É n ùÉ Ê ´É ¦É É M É ªÉ ÉÆxÉ Ò ¶ ÉÉ ºÉ xÉ Ê x Éh ÉǪ É Gò .{ ÉÒ ´ ½þ Ò ]õ Ò -12 04 /(16 0/2 004 ) /BSÉ {É Ò ,Ê n ù. 15 -9-2 005 +x´ É ªÉ ä VÉ É® ú Ò Eäò ± Éä± ªÉ É ± É ½þ É xÉ VÉ ±É Ê ´ ÉtÖiÉ | É Eò± {ÉÉ ºÉ Æ¤É ÆvÉÒ SªÉÉ vÉÉ ä® ú h ÉÉ x ÉÖº É É® ú VÉ ä |É ´É iÉ ÇEò /=tÉ äVÉ Eò JÉ É ±É Ò ±É ±É ½ þÉ xÉ VÉ ±É Ê ´É tÖi É |É Eò±{ É Ê ´É EòºÉÒ iÉ Eò¯ û <Î SUôi É É i É +¶ É É JÉ É VÉMÉ Ò =tÉ äVÉ EòÉ ÆEò bÚ÷x É iªÉ ÉÆSÉ Ò {É Ú ÉÇ +½ Çþ iÉ É Ê xÉÎ ¶ SÉ iÉ Eò® ú h ªÉÉ ºÉ É öÒ +É ìxÉ ±ÉÉ <Çx É | É º iÉ É ´É ¨É É MÉ Ê ´ É iÉ +É ½äþ iÉ . JÉ É± ÉÒ ±É {É Ú É Ç + ½Çþ i É É Ê xÉ Ê ´É nùÉ º ÉÆSÉ ´ É ® úÒ ±É º ÉÆEäòi É º lÉ ³ýÉ´ É ® ú Ê n ùxÉ ÉÆEò 2 0.03.2 01 3 º É EòÉ ³ ýÒ 10. 00 ´ ÉÉ VÉ iÉÉ iÉ ä 15 .04 . 201 3 n Öù{ É É ® úÒ 3. 00 ´ ÉÉ VÉä{ É ªÉ ÇxiÉ ={É ± É ¤vÉ ½ þÉ ä>ð ¶ É Eò iÉÒ ± É . + Gò .
{É Ú ÉÇ +½ Çþ iÉ É n ùº iÉ Bä É VÉ GÆò . |É Eò± {É É SÉ ä xÉ É Æ É ´ É º lÉ É {É Ò iÉ I É ¨É iÉÉ (¨Éä.´ Éì] )
1 º ÉÒ <Ç(<Ç) /BSÉ {É Ò /Bº É BS É {É Ò / º ÉÒ {É Ò {É Ò / +É ªÉ {É Ò {É Ò /6 7 b÷
Ê xÉ ¨xÉ ´É vÉ É Ç VÉ ±É Ê´ É tÖiÉ |É Eò± {É iÉÉ .: +É ´É Ô÷, Ê VÉ .: ´É vÉ ÉÇ (0.7 50 ¨É ä.´É ì] õ)
2 º ÉÒ <Ç(<Ç) /BSÉ {É Ò /Bº É BS É {É Ò / º ÉÒ {É Ò {É Ò / +É ªÉ {É Ò {É Ò /6 8 b÷
¶ É ½þÉ xÉ Ú® ú EòÉ ±É ´ É É |É { ÉÉ iÉ VÉ ± ÉÊ ´ É tÖiÉ |É Eò±{ É ., iÉ É . +SÉ ± É {É Ú® ú Ê VÉ . +¨É ® úÉ ´É iÉ Ò ( 0.350¨É ä.´ É ì] õ)
3 º ÉÒ <Ç(<Ç) /BSÉ {É Ò /Bº É BS É {É Ò / º ÉÒ {É Ò {É Ò / +É ªÉ {É Ò {É Ò /6 9 b÷
¤É É´ É xÉ lÉ b÷ýÒ – 1 VÉ ± ÉÊ ´É tÖiÉ |É Eò±{ É, iÉ É - iÉ Ö É ºÉ ® ú ,Ê VÉ ±½ þ É -¦É Æb÷É ® ú É (0.35 0 ¨É ä.´ Éì] õ )
4 º ÉÒ <Ç(<Ç)/BSÉ {É Ò /Bº É BSÉ {É Ò / º ÉÒ {É Ò {É Ò / +É ªÉ {É Ò {É Ò /7 0 b÷
¤É É´ É xÉ lÉ b÷ýÒ – 2 VÉ ±É Ê´ Ét ÖiÉ | É Eò± {É , iÉÉ - iÉ Ö É ºÉ ® ú ,Ê VÉ ±½ þ É -¦É Æb÷É ® ú É (0.6 00 ¨Éä. ´ Éì] õ )
5 º ÉÒ <Ç(<Ç) /BSÉ {É Ò /Bº É BS É {É Ò / º ÉÒ {É Ò {É Ò / +É ªÉ {É Ò {É Ò /7 1 b÷
EòÉ ±É Ò º É® úÉ ® ú VÉ ±É Ê ´ ÉtÖiÉ |É Eò± {É , iÉÉ .- º ÉÉ ±ÉäEòº É É Ê VÉ . M É ÉåÊ n ùªÉÉ (0.4 00 ¨É ä.´ Éì] õ )
6 º ÉÒ <Ç(<Ç) /BSÉ {É Ò /Bº É BS É {É Ò / º ÉÒ {É Ò {É Ò / +É ªÉ {É Ò {É Ò /5 0 ¤É
SÉ Æp ù¦É ÉM ÉÉ VÉ ± ÉÊ ´É tÖiÉ |É Eò±{ É, iÉ É .- +SÉ ±É {É Ö® ú Ê VÉ . +¨É ® úÉ ´ É iÉ Ò (1.0 ¨É ä.´ É ì] õ )
7 º ÉÒ <Ç(<Ç) /BSÉ {É Ò /Bº É BS É {É Ò / º ÉÒ {É Ò {É Ò /+É ªÉ {É Ò{ ÉÒ /7 7
M É Éäº É Ò JÉÖn Çù (= .i É .EòÉ ) VÉ ±É Ê ´É tÖiÉ |É Eò ± {É iÉ É - {É ´É xÉ Ò ú ,Ê Vɱ ½ þ É -¦É Æb÷É ® ú É (2 X 1.2 50 ¨É ä.´ É ì)
8 º ÉÒ <Ç(<Ç) /BSÉ {É Ò /Bº É BS É {É Ò /º ÉÒ {É Ò {É Ò /+É ªÉ {É Ò{ ÉÒ /7 8
M É Éäº É Ò JÉÖn Çù (bÉ . iÉ . Eò É ) VÉ ± ÉÊ ´ É tÖiÉ | É Eò±{ É iÉ É - { É ´É xÉÒ ú ,Ê VÉ ± ½ þÉ -¦É Æb÷É ® ú É (1 X 0.500 ¨É ä.´ É ì)
<Ç- Ê xÉ Ê ´É n ùÉ |ÉÊ GòªÉ É ºÉÆEäò iÉ º lÉ ³ ýÉ´ É ® úÒ ± É ÊEò-bä÷]ÂõºÉ xÉ Öº ÉÉ® ú EòÉ ]äõEò Éä® ú {É hÉä +¨É ±É É iÉ +É hÉ ± ÉÒ VÉ É <DZ É . <SUÖôEò =tÉ äVÉ Eò /|É ´É iÉÇEòú ªÉÉ ÆxÉ Ò <Ç-Ê x ÉÊ ´ É n ùÉ |É Ê GòªÉÉ º É Æn ù¦É ÉÇi É {É Öf øÒ ± É º É Ê ´É º iÉ® ú ¨É ÉÊ ½ þiÉÒ ºÉÉ ` öÒ ´É ® ú Ò± É ºÉ ÆEäòiÉ º lÉ ³ ýÉ ´É ® ú ºÉÆ{É EÇò Eò®ú É ´ ÉÉ . VÉ ä =tÉ äVÉ Eò /| É ´É iÉÇEò ú {É Ê½ þ ± ªÉ É Æn ùÉ SÉ <Ç-Ê xÉ Ê ´ É n ùÉ |É Ê GòªÉäiÉ ¦É ÉM É P ÉäiÉ +É ½ äþi É iªÉ ÉÆxÉ É ´ É ®ú Ò ±É º É ÆEäò iÉ º lÉ ³ýÉ´É ® ú Ê n ù± Éä± ªÉ É ¨É É MÉ Çn ù¶ ÉÇEò iÉ i´ É É xÉ Öº ÉÉ ® ú | É lÉ ¨É Ê b÷ZÉÒ ] õ±É Ë ºÉM É xÉ äSÉ ® ú º É ] õÔ Ê ¡òEäò ] õ, ªÉ ÖVÉ ® ú +É ªÉ b÷Ò ´ É {É Éº É ´ É bÇ÷ |É É {iÉ Eò¯ ûxÉ PÉäh É ä +É ´ É ¶ ªÉ Eò +É ½äþ. <Ç-Ê xÉ Ê´É n ùÉ ºÉÆ¤É ÆvÉÒ EòÉ ½ þÒ ºÉ ½ þÉ ªªÉi ÉÉ +É ´É ¶ ªÉ Eò +ºÉ ± ªÉ ɺ É (b÷É >ð xÉ ± ÉÉ äb÷ / +{ É ± É É äb÷) <Ç-Ê x É Ê ´ É n ùÉ Eò É ªÉ Ç|É hÉ É± É Ò ¨É n ùiÉ Eò IÉ ¡òÉäxÉ x É Æ. 020 – 25315555/
9167969601/04, support.gom@nextenders.com, ªÉ ÉÆSªÉ É ¶É Ò º ÉÆ{É EÇò º ÉÉ vÉ h ªÉ É iÉ ªÉ É´ É É . |ɺ iÉ É ´É ºÉ É n ù® ú Eò ®ú h ªÉ É ºÉ É ` öÒ |É ´É iÉ ÇEò /=t É äVÉ Eò ª ÉÉ Æx ÉÒ Eäò± É ä± ªÉÉ +É Ì lÉ Eò JÉ SÉ É Çº É VÉ ¤ÉÉ ¤Én ùÉ ® ú xÉ ® úÉ ½ þiÉÉ EòÉ äh É iÉÉ ½ þÒ BEò Ë Eò´ ÉÉ º É ´É Ç | É º iÉ É ´É ¡äò ] õÉ ³ýh ªÉ É SÉ ä Ë Eò´ ÉÉ º ÉÆ{É Úh ÉÇ | É º iÉ É ´É |É Ê GòªÉ É ® ú q ù Eò® úh ªÉÉ S Éä +Ê vÉ EòÉ ®ú ¶É É ºÉ xÉ É x Éä ® úÉ JÉ ÚxÉ ` äö´ É ±Éä +É ½ äþi É .
+ Ê vÉ IÉ Eò +Ê ¦É ªÉ ÆiÉ É , Ê ´ É n ù¦É Ç VÉ ±É Ê ´ É tÖiÉ ´É ={É ºÉÉ Ë ºÉ SÉ xÉ ¨É Æb÷³ ý, xÉ É M É {É Ú® ú
- 7 -
Signature of Promoter/Developer No. of correction Signature of Inviter
DETAILED E- TENDER NOTICE Govt. of Maharashtra
Water Resources Department
Main Portal : http://maharashtra.etenders.in
WRD Portal: http://wrd.maharashtra.etenders.in PRIVATE SECTOR PARTICIPATION IN DEVELOPMENT OF SMALL HYDRO ELCETRIC PROJECTS FOR
ELECTRICITY GENERATION
A) Online digital signed Pre-Qualification proposals are invited for and on behalf of Governor of Maharashtra by
Superintending Engineer, Vidarbha Hydro Electric & Lift Irrigation Circle, Wainganga Nagar, Ajni,
Nagpur-440003 Maharashtra (INDIA), Ph.No. & Fax No.: 0712-2440058, for Prequalification of the Promoters / Developers who intend to develop SMALL HYDRO ELECTRIC PROJECTS, as Captive Power
Producer (CPP) / Independent Power Producer (IPP) for electricity generation in the State of Maharashtra by the Promoter / Developer company as stipulated in Hydro Power Policy declared vide Govt. of Maharashtra, Water Resources Department, G.R.No. PVT-1204/ (160/2004)/HP, dated 15.9.2005.
The Pre-Qualification Documents are available on web site from 20.03.2013 to 15.04.2013 upto 3.00 PM The Price bid Documents are available on web site from 22.05.2013 at 10.00 AM to 1.06.2013 upto 5.00 PM
The Hydo Electric Projects proposed to be offered are as below: -- Sr N
o
Pre-Qualification Document No./price
bid Document No.
Name of the Hydro Electric Project and Estimated Installed Capacity
(in MW)
Cost of blank PQ Document
( Including VAT) (Non refundable)
Cost of blank Price bid Document
( Including VAT) (Non refundable)
1 2 3 4 5
1 CE(E)/HP/SHP/CPP/ IPP/ 67D
Lower Wardha HEP Tal.: Arvi, Dist.: Wardha (0.750 MW)
For each document
Rs. 7000 + 350/- VAT
= 7350
( Rs Seven thousand Three
Hundred Fifty only)
For each document Rs. 10000
+ 500/-VAT
=10500 ( Rs Ten thousand
Five Hundred only)
2 CE(E)/HP/SHP/CPP/ IPP/68 D
Shahanoor Canal Drop, HEP Tal. Achalpur, Dist. Amravati( 0.350MW)
3 CE(E)/HP/SHP/CPP/
IPP/69 D
Bawanthadi – 1 HEP,
Tal. Tumsar,Dist. Bhandara (0.350 MW)
4 CE(E)/HP/SHP/CPP/
IPP/70 D
Bawanthadi – 2 HEP
Tal. Tumsar, Dist.Bhandara(0.600 MW)
5 CE(E)/HP/SHP/CPP/ IPP/71 D
Kalisarar HEP, Tal. Saleksa , Dist. Gondia (0.400MW)
6 CE(E)/HP/SHP/CPP/
IPP/50 B
Chandrabhaga HEP,
Tal. Achalpur, Dist. Amaravati (1.0MW)
7 CE(E)/HP/SHP/CPP/
IPP/77
Gosikhurd (R.B.C.) HEP
Tal. Pawni, Dist. Bhandara ( 2X1.250MW)
8 CE(E)/HP/SHP/CPP/ IPP/78
Gosikhurd (L.B.C.)HEP Tal:Pawni,Dist. Bhandara(0.500MW)
B) P.Q.DOCUMENT SCHEDULE 1. The Pre-Qualification Documents are available on e-tendering web site of WRD Portal
http://wrd.maharashtra.etenders.in, 2. The cost of each Pre Qualification Document to be downloaded from Web site is Rs.7350/- (Rs. Seven
Thousand Three Hundred Fifty Only) & payable in the form of crossed D.D. in favour of Executive Engineer, Vidarbha Hydro Electric & Lift Irrigation Division, Nagpur , for PQ document at sr. No.1 above,
in favour of Executive Engineer, Vidarbha Hydro Electric & Lift Irrigation Division, Bhandara, for PQ document at sr. No 3,4, 5, 7& 8 above & in favour of Executive Engineer, Vidarbha Hydro Electric & Lift Irrigation Division, Akola for PQ document at Sr. No. 2 & 6 above. The D.D. drawn within the downloading
period of P.Q. Document will only be accepted. 3. The scanned copy of D.D. should be uploaded alongwith P.Q. document.
4. Original D.D. and hard copy of the P.Q. Document & other information required vide Annexure-II & III of P.Q. Document along with supporting documents should be submitted in the office of the Superintending
Engineer, Vidarbha Hydro Electric & Lift Irrigation Circle, Nagpur on or before the last date and time of uploading of proposal as per schedule of key dates. The proposal will be rejected if original D.D. and hard copy as mentioned above are not received within stipulated time.
5. Pre-Qualification Document will be opened in the office of the Superintending Engineer, Vidarbha Hydro
Electric & Lift Irrigation Circle, Nagpur as per stipulated date & time mentioned in key dates.
6. The Promoter/Developer will have to prove his Financial and Technical capability by uploading the necessary “Information/Documents” as mentioned in Pre-Qualification Document. After scrutiny of the proposals with supporting document uploaded by the Promoter/Developer on website, a list of qualified Promoter/Developer
will be prepared and only qualified Promoter/Developer will be communicated in this regard. Pre-qualified Promoters/Developers will be allowed to participate in Price Bids for allotment of project by downloading the
Price Bid document.
- 8 -
Signature of Promoter/Developer No. of correction Signature of Inviter
E) KEYDATES:
Note – Pre-Bid meeting will be held on 18.05.2013
C) PRICE BID DOCUMENT SCHEDULE 1. The Price Bid Documents are available on e-tendering web site of WRD Portal
http://wrd.maharashtra.etenders.in 2. The cost of each Price Bid Document to be downloaded from Web site is Rs. 10500/- (Rs. Ten Thousand Five
Hundred Only) & payable in the form of crossed D.D. in favour of Executive Engineer, Vidarbha Hydro
Electric & Lift Irrigation Division, Nagpur , for PQ document at sr. No.1 above, in favour of Executive Engineer, Vidarbha Hydro Electric & Lift Irrigation Division, Bhandara, for PQ document at sr. No 3,4, 5,7 & 8 above & in
favour of Executive Engineer, Vidarbha Hydro Electric & Lift Irrigation Division, Akola for PQ document at Sr. No. 2 & 6 above. The D.D. drawn within the downloading period of Price Bid Document will only be accepted.
3. The scanned copy of D.D. should be uploaded alongwith Price Bid document.
4. D.D and EMD in the form of Bank Guarantee in Original alongwith hard copy of uploaded Documents as per Envelope No. I & II should be submitted in the office of the Superintending Engineer, Vidarbha Hydro Electric &
Lift Irrigation Circle, Nagpur on or before the last date and time of uploading of Price Bid as per schedule of key dates. The Price Bid will be rejected if D.D and EMD in the form of Bank Guarantee in Original along with hard copy as mentioned above are not received within stipulated time.
5. Price Bid Document will be opened in the office of the Superintending Engineer, Vidarbha Hydro Electric & Lift Irrigation Circle, Nagpur
6. Pre-Bid Conference of pre- qualified Promoter/Developers will be held on 18.05.2013 at 11.00 A.M. in the office of the Chief Engineer (Electrical), Hydro Projects, Mumbai-01 / Chief Engineer (Civil), Hydro Projects, Sinchan
Bhavan, Barane Road, Mangalwar Peth, Pune-11. All Pre-qualified, Promoters/Developers who have downloaded
Price Bid Document may attend the Pre-bid conference. D) 1. All subsequent corrigendum/amendment shall be available only on web site. Hence Promoters/Developers are
advised to visit web site until the Pre –Qualification proposal/Price Bid is finally opened. 2. In case of any dispute between uploaded document and copy submitted by Promoter, Pre –Qualification
proposal/Price Bid Documents uploaded by Promoter on web site will be treated as final. 3. Promoters/Developers are not allowed to make any changes in the uploaded document after last date and time
of uploading. If found so, his tender will be rejected outright & he will be liable for other legal action.
4. The Government reserves the right to reject any or all the proposals or annul the process without assigning any reason and without being responsible for the cost incurred by the Promoter / Developer in preparing his PQ
proposal / Price-Bid.
Seq. No.
WRD Stages Vendor Stage Start Expiry
Date Time Date Time
1 Tender preparation and Release of
NIT
.. 11.03.213 10.00 19.03.2013 17.00
2 PQ document Purchase 20.03.2013 10.00 15.04.2013 15.00
3 Pre-Qualification
Document Download & Online Bid-Preparation
20.03.2013 10.00 15.04.2013 15.00
4 Close for Bidding of PQ(Super –Hash Generation)
15.04.2013 15.01 20.04.2013 17.00
5 …. Online PQ submission and (Re-encryption)
20.04.2013 17.01 25.04.2013 17.00
6 PQ opening and short listing …. 26.04.2013 10.00 10.05.2013 17.00
7 Main Tender Preparation … 11.05.2013 10.00 21.05.2013 17.00
8 Price bid Tender Document
purchase
22.05.2013 10.00 01.06.2013 17.00
9 Price bid Tender Download
& Online Bid Preparation
22.05.2013 10.00 01.06.2013 17.00
10 Close for Bidding of Main Tender …. 02.06.2013 17.01 04.06.2013 17.00
11 Online Main Tender
submission and (Re-encryption)
04.06.2013 17.01 10.06.2013 17.00
12
Main Tender opening Envelope T 1 11.06.2013 10.00 17.06.2013 17.00
13
Main Tender opening Envelope C 1 11.06.2013 10.00 17.06.2013 17.00
Superintending Engineer, Vidarbha Hydro Electric & Lift Irrigation Circle,
Nagpur
- 9 -
Signature of Promoter/Developer No. of correction Signature of Inviter
SECTION - II
Instructions to Promoters/Developers.
- 10 -
Signature of Promoter/Developer No. of correction Signature of Inviter
SECTION – II
INSTRUCTIONS TO PROMOTERS / DEVELOPERS
2.1 General Instructions
2.1.1 The Promoters / Developers shall carefully examine the instructions of this
Pre-qualification document No.CE(E)/HP/SHP/CPP/IPP/78 . The Promoters /
Developers shall upload the pre-qualification proposals with supporting
documents.
2.1.2 The Promoter / Developer shall bear all costs associated with the
preparation and uploading of his proposals. The Government of
Maharashtra, Water resources Department (GOMWRD) will in no case be
responsible or liable for those costs regardless of the conduct or outcome
of the bidding process.
2.2 Requirement of Preparation of Proposal for Pre-qualification
2.2.1 The Promoters / Developers shall upload the pre-qualification proposals
duly filled and signed along with all necessary documents. The Promoter /
Developer shall upload the pre-qualification document downloaded by him
duly signed on all pages along with his proposal.
2.2.2 The uploaded document comprising the proposals for Pre-qualification shall
consist of the following documents: -
i) Scanned copy of Demand draft
ii) Forwarding letter of the proposal. The information shall be furnished
completely and duly signed as required vide Annexure – II & III,
alongwith supporting documents.
iii) Downloaded Pre-qualification documents
2.2.3 Original Demand Draft and hard copy of the information required vide
Annexure-II & III alongwith supporting documents should be submitted in
the office of the Superintending Engineer, Vidarbha Hydro Electric &Lift
Irrigation Circle, Nagpur on or before the last date and time of uploading of
proposal.
- 11 -
Signature of Promoter/Developer No. of correction Signature of Inviter
2.2.4 In case of any discrepancy / dispute between uploaded Document and hard
copy submitted by Promoter, Pre-qualification proposal uploaded by
Promoter on website will be treated as final.
2.2.5 Promoter shall submit the information / documents strictly as per
requirement of Annexure No.II & III. Additional supporting document shall
not be attached unless called for. If any additional documents are attached,
the same shall be returned to the Promoter as they are. Inviter may obtain
additional information / documents if required from Promoter.
2.2.6 All subsequent corrigendum / amendment shall be available only on
website. Hence Promoters / Developers are advised to visit website until
the PQ proposal is finally opened.
2.2.7 Over writing should be avoided. Any wrong word should be scratched by a
line over it and correct word should be written separately. Such a
correction should be signed or initialed.
2.2.8 Corrections, made by hand writing should be duly initialed near to such
correction. Any such correction by hand writing will not be accepted if not
initialed or signed.
2.2.9 Each page of the proposals shall be signed by Promoters / Developers.
2.2.10 The proposals sent telegraphically or by fax will not be acceptable.
2.2.11 GOMWRD will not be responsible for delay in uploading / receipt of
proposals.
2.3 Uploading of proposal for Pre-qualification
2.3.1 The Promoter / Developers shall upload his proposal comprising of all
documents stated in Para 2.2 above.
- 12 -
Signature of Promoter/Developer No. of correction Signature of Inviter
2.3.2 If the proposals are not uploaded in stipulated time, the GOMWRD will not
be responsible.
2.3.3 The proposals shall be uploaded on or before stipulated time & date
mentioned as per schedule of key dates. Proposal uploaded after the
dead line for uploading of proposals will not be accepted.
2.3.4 Submission of Proposal for Pre-qualification
Original Demand Draft and hard copy of the information required vide
Annexure – II and III along with the supporting documents should be
submitted in the office of the Superintending Engineer, Superintending
Engineer, Vidarbha Hydro Electric & Lift Irrigation Circle, Nagpur on or
before the last date and time of uploading of proposal. The proposal will
be rejected if original Demand Draft and hard copy as mentioned above
are not received within stipulated time.
2.4 Opening of proposal
2.4.1 The PQ proposals of only those Promoters will be opened who have
submitted the Demand Draft as per requirement of S.No.B(2) of Detailed
Tender Notice.
2.4.2 The uploaded copy of Pre-Qualification proposals will be opened in the
office of Superintending Engineer, Vidarbha Hydro Electric & Lift Irrigation
Circle, Wainganga Nagar, Ajni, Nagpur - 440003.
Note for Clause No.2.3 & 2.4: In the event of specified date for opening of
proposals, being declared a holiday for the GOMWRD, the proposals will
be opened as per appointed time on the next working day.
- 13 -
Signature of Promoter/Developer No. of correction Signature of Inviter
2.5 Evaluation of proposals
2.5.1 Following procedure will be adopted for evaluation of proposal.
2.5.2 A pre-qualification proposals uploaded from the prospective Promoters /
Developers will be evaluated by allotting certain marks for their status,
experience, financial position etc. as given in Annexure-I, II & III enclosed.
2.5.3 This procedure is only for short listing of Promoters / Developers. The
qualified Promoters / Developers will only be allowed to participate in the
price bidding for CPP/ IPP allotment whenever it will be finalised in future.
The pre-qualification does not guarantee any allotment of CPP / IPP.
2.5.4 Pre-qualified Promoters/Developers shall be communicated to participate in
price bidding for allotment of the project. The bidding shall be on the basis
of premium offered by the bidder over and above THRESHOLD PREMIUM.
2.5.5 The pre-qualification document will not form the part of agreement to be
made with the successful bidder for allotment of the project.
2.5.6 The promoters /developers shall note the following while, participating in
uploading of proposals for pre-qualification and subsequent price bids.
1) The installed capacity and estimated annual generation of the
project is indicative only and GOMWRD does not take any
responsibility in this respect.
2) Annual generation figures estimated by GOMWRD are based on
available data. The Promoter may see this data in the office of the
Superintending Engineer, Gosikhurd Project Circle, Nagpur /
Superintending Engineer, Vidarbha Hydro Electric & Lift Irrigation
Circle,Wainganga Nagar, Ajani, Nagpur. However, it shall be
responsibility of the Promoter to validate the hydrological data made
available by GOMWRD in PQ document or any other GOMWRD
document through its consultant and draw his own inferences only
after such validation. Promoter shall estimate installed
capacity/annual generation only by using such validated data. As
the upfront premium to be quoted in price bid needs to be quoted
based on such Validated data, Upfront Premium amount cannot be
- 14 -
Signature of Promoter/Developer No. of correction Signature of Inviter
curtailed at later stage. GOMWRD shall not take responsibility
regarding correctness of data & its consequential losses if any. No
claims for less generation due to any reasons including
incorrectness of data, less rainfall shall be entertained.
Promoter shall note that releases of water shall be strictly as
per irrigation / domestic/ Industrial demands and the generation will
have to be synchronised with these releases. GOMWRD reserves
right to decide the release schedule and modify it from time to time
as per the requirement. Further, when the Irrigation / Domestic/
Industrial requirements is more than discharging capacity of power
outlet GOMWRD may release additional discharge through other
outlets. The decision of GOMWRD in this regard shall be final and
binding. No claims of compensation on these grounds shall be
entertained.
3) During the rainy season the GOMWRD shall review the reservoir
contents and trend of monsoon time to time and may allow to
release water through power outlet when spills are likely. However,
decision of the GOMWRD shall be final in this regard.
4) GOMWRD shall not compensate for less generation due to any
reasons.
5) Generation Restrictions:
In extraordinary circumstances arising out of threat to security of the
state, public order or a natural calamity or such circumstances
arising out of public interest, the developer shall have to operate &
maintain generating station in accordance with the directives of state
government subject to the provisions of section 11 of EA, 2003.
6) No Compensation for Grid Failure:
Developer/ Third party consumer/ Captive user/ Licensee
(authorised consumer) shall abide by grid discipline & will not be
entitled for any compensation in the event of grid failure, shut down,
interruption in power supply etc.
- 15 -
Signature of Promoter/Developer No. of correction Signature of Inviter
7) Exclusive Jurisdiction Of MERC:
MERC has exclusive jurisdiction on those provisions of this Policy
which are within its regulatory mandate under the provision of
Electricity Act, 2003, especially regarding electricity sales rates,
power purchase agreements and provisions regarding wheeling,
banking distribution and transmission loss charges etc. Similarly,
MERC has jurisdiction as per the provisions of EA 2003 as regards
the promotion of non-conventional energy sources, facilities for
transmission of energy, sale of power to any interested consumer
and sharing of purchase of power amongst the STU/Transmission
Licensee/Distribution Licensee. Orders regulations, directives,
guidelines issued by MERC regarding these issues from time to time
shall be binding on all.
In the event of dispute in interpretation of this policy or any
clause in the agreement between developer & GoMWRD or
STU/Transmission Licensee/Distribution Licensee, the same shall
be referred to MERC to the extent of its jurisdiction under section
86(1) and other provisions of EA. 2003.
- 16 -
Signature of Promoter/Developer No. of correction Signature of Inviter
SECTION - III
ANNEXURES
i) Annexure - I : Procedure for evaluation.
ii) Annexure - II : Information to be furnished by
Promoter/Developer who has
been earlier allotted the SHP
for development
iii) Annexure – III : Information to be furnished by
Promoter/Developer
iv) Annexure - IV : State Hydel Policy of the
Government of Maharashtra,
Water Resources Department
- 17 -
Signature of Promoter/Developer No. of correction Signature of Inviter
SECTION-III
ANNEXURE – I
PROCEDURE FOR EVALUATION
Each Developer / Promoter shall furnish the information as indicated in
Annexure –II and Annexure – III. An eligibility of Developer / Promoter shall be
decided on scrutiny of this information. The scrutiny shall be based on following
criterions. Promoter/Developer who secure minimum 15 marks in Group A and
minimum 5 marks each in Group B1 and Group B2 individually specified
hereunder shall be declared eligible for bidding and accordingly main bidding
document shall be issued to him. Group wise required marks must be obtained for
eligibility fulfillment i.e. if the Promoter/Developer secures 25 marks in Group A
and do not secure any marks in Group B, he is not eligible for bidding.
For Promoters/Developers, who have earlier been allotted SHP projects for
development; those intended Promoters / Developers shall carefully upload the
requisite information in Annexure-II. The evaluation of PQ document will be done
only for those intending Promoters / Developers who are found eligible after the
scrutiny of the information uploaded by them in Annexure-II. The Promoter
/Developer who has—
1) Signed the HPDA but not started the work for the period of two years or
more from the date of signing HPDA.
2) Been issued LoA after approval of TEFR but HPDA not signed within the
period of two years or more from the date of issue of LoA.
3) Started the actual execution of work but has not commissioned the project
within three years from the date of starting of work.( except for projects
where infrastructure to be provided by GOMWRD is incomplete)
Will be disqualified and no further evaluation of his qualifying criteria will be
done.
- 18 -
Signature of Promoter/Developer No. of correction Signature of Inviter
MARKING SYSTEM MARKS
GROUP A – FINANCIAL CRITERIA
1. STATUS OF THE FIRM
1.1 Unit from Co-Operative sector 10 1.2 Public Limited Company 8 1.3 Private Limited Company 6 1.4 Partnership / Proprietary 5 2. DEBT: EQUITY RATIO 2.1 Less than 1.5:1 10 2.2 1.5 to 1.75:1 6 2.3 More than 1.75 to 2:1 5 2.4 More than 2:1 0
3. PROMOTERS CONTRIBUTION 3.1 60% or more 10 3.2 between 60% to 33 % 5 3.3 Less than 33 % 0 GROUP B- TECHNICAL CRITERIA
1.0 B1) BACK UP OF DESIGN ENGINEERS 1.1
In house Civil & Electrical Designers (1.1.1) In house Civil Designers - (4Marks) (1.1.2) In house Electrical Designers -( 4Marks)
8
1.2 Consulting firm having both Civil as well as electrical engineer is Proposed to be engaged. (1.2.1 ) Consulting firm having Civil engineers is proposed to be engaged. - ( 3 Marks)
(1.2.2 ) Consulting firm having Electrical engineers is proposed to be engaged. - ( 3 Marks)
6
1.3 Separate Civil & Electrical design Consultants proposed 5
- 19 -
Signature of Promoter/Developer No. of correction Signature of Inviter
(1.3.1) Separate Civil design Consultants proposed - (2.5 Marks) (1.3.2) Separate Electrical design Consultants proposed - (2.5 Marks)
2 B2) EXPERIENCE OF H.E.P. CONSTRUCTION / ERECTION IN E & M WORKS.
A) Experience of civil construction
2.1a Construction of 3 Power Houses completed. 4 2.2a Construction of 2 Power Houses completed 3 2.3a Construction of 1 power house completed 2 B) Experience of E&M works in power house (The
experience shall indicate erection of at least one Turbine- Generator plant)
2.1b Erection of 3 power houses completed
8
2.2b Erection of 2 power houses completed 6 2.3b Erection of 1 power house completed 3 Maximum Marks 50 NOTE 1) Promoter/Developer shall be necessarily a profit making company.
2) The Promoter/Developer shall not be eligible for marks unless necessary supporting documents as mentioned in Annexure-III are enclosed.
3) All the terms and conditions of G.R.No. PVT-1204/(160/2004)/HP, dtd.
15th September, 2005 will be applicable.
4) The previous experience of Promoter for development of small HEP will also be a criteria as mentioned earlier in the document. All the necessary documents shall be uploaded by Developer / Promoter to qualify the stipulated criteria.
- 20 -
Signature of Promoter/Developer No. of correction Signature of Inviter
Annexure-II
(To be uploaded by the Promoters/Developers who have been earlier allotted SHPs for development.) Sr. No.
Name of allotted project
Date of issue of LoA
Date of signing of HPDA
Date of completion of project
Remarks
1
2
Signature and seal of Developer/Promoter
- 21 -
Signature of Promoter/Developer No. of correction Signature of Inviter
ANNEXURE – III
INFORMATION TO BE UPLOADED/FURNISHED BY PROMOTER /
DEVELOPER
1. GENERAL INFORMATION.
1.1 Name of Promoting Company / Developer.
1.2 Constitution of Company (Enclose registration certificate under
companies act 1956).
(Public / Private Limited Company / Co-Operative Society/
Partnership / Proprietary Concern)
1.3 Date of incorporation / Registration
1.4 Date of Commencement of business.
1.5 Sector
(Public sector / Joint Sector / Private Sector / Co-Operative sector)
1.6 Location
(Indicate Village, Tahasil, District & State)
(a) Registered Office
(b) Controlling / Head Office.
1.7 Postal Address of Promoting Company.
2. PROMOTER’S BIO-DATA
2.1 Give bio-data of main promoters including information on name,
address. age, educational qualification, past industrial / business
experience in particular industry. Brief write up on other companies
if any promoted by him or with which he is associated, together with
copy of latest audited balance sheet (to be furnished separately in
case of each Promoter).
2.2 In case the promoter is a limited company, furnish brief write up on
the activities & the past performance of the company.)
(Audited balance sheets and profit loss accounts for the last three
years of the Promoter Company to be enclosed.)
- 22 -
Signature of Promoter/Developer No. of correction Signature of Inviter
3. DETAILS OF CONSUMPTION UNIT.
PROPOSAL OF PROMOTER /DEVELOPER FOR CAPTIVE POWER
PRODUCER (CPP) / INDEPENDENT POWER PRODUCER (IPP).
3.1 Details of existing industrial units for which generated energy would
be utilized.
3.1.1 Name & address of registered office of industrial unit / units. 3.1.2 Location of industrial unit / units.
3.1.3 Unit wise energy consumption in MUs per annum for last three years.
3.1.4 Unit wise maximum & minimum demand in KVA for last three years.
3.2 Do you propose to start new industrial unit for consumption of
Captive power? If yes, give following details.
3.2.1 Give nature of unit.
3.2.2 Give location of unit.
3.2.3 Give energy requirements of proposed unit in MUs per annum
3.2.4 Give maximum & minimum demand in KVA.
3.2.5 What would be the estimated cost of this unit?
3.2.6 What would be the promoters equity share capital in this unit.
4. FINANCIAL CAPABILITIES:
4.1 Anticipated cost of the proposed hydroelectric project, duly certified
by the consultant along with brief details of estimate.
4.2 Give the details regarding means of financing.
(The details given by Promoter under Sr.No.4.2.1 to 4.2.3 with
documentary proof will be considered as Equity)
4.2.1 Subscription of the promoter. Give valid details of source along with documentary proofs.
4.2.2 Arrangements through friends / relatives / associates
alongwith commitment letters.
- 23 -
Signature of Promoter/Developer No. of correction Signature of Inviter
4.2.3 Internal accruals. 4.2.4 Unsecured loans to be arranged by promoters. 4.2.5 Institutional contribution as a Co-promoter if any. 4.2.6 Through Public Issue. 4.2.7 Term Loans.
4.3 Debt: Equity ratio.
5. TECHNICAL ARRANGEMENTS:
5.1 Backup of Design Engineers.
5.1.1. Do you have in house design capabilities for both Civil as well
as electrical design engineers?
If yes, give the organizational set up of design wing, bio-data
of design engineers, particulars of work done in past & work
in hand. Give documentary evidence regarding personnel's
engaged in design wing. Documentary evidence for design of
Civil and Electrical works of Hydro Power Projects shall also
be furnished.
5.1.2 Do you propose to engage design-consulting firm having both
Civil as well as Electrical design engineers? If yes, give
complete credentials as well as past experience of such firm
along with notarized MOU with the consulting firm on stamp
paper of requisite value. Documentary evidence for design of
Civil and Electrical works of Hydro Power Projects carried out
by the consulting firm shall also be furnished.
- 24 -
Signature of Promoter/Developer No. of correction Signature of Inviter
5.1.3 Do you propose to engage separate consulting firms for Civil
& Electrical designs? If yes, give complete credentials as well
as past experience of such firms along with notarized MOU
with the consulting firm on stamp paper of requisite value.
Documentary evidence for design of Civil and Electrical works
of Hydro Power Projects carried out by both the consulting
firms shall also be furnished.
5.2 Backup of Experienced Construction Firm / Erection Expert
5.2.1 Do you have experience of construction of H.E. Projects / erection of
H.E. Machinery? If yes, give details of projects executed in last 10
years. (State no. of projects and their details such as Name,
location, capacity & status of each project). Enclose work done
certificates certified by an officer not below the rank of Executive
Engineer. The work done certificate shall indicate construction of at
least one power house construction for Civil works and erection of at
least one HE project and commissioned successfully.
5.2.2 Do you propose to engage experienced construction / Erection
firm? If yes, give details of projects executed in last 10 years
along with work done certificates certified by an officer not below the
rank of Executive Engineer and notarized MOU with construction /
Erection firm on stamp paper of requisite value (State No. of projects
and their details such as Name, location, capacity & status of each
project). The work done certificate shall indicate construction of at
least one power house construction for Civil works and erection of at
least one HE project and commissioned successfully.
- 25 -
Signature of Promoter/Developer No. of correction Signature of Inviter
ANNEXURE – IV
State Hydel Policy For Development Of Small Hydro Power Projects through
Private Sector Participation
GOVERNMENT OF MAHARASHTRA WATER RESOURCES DEPARTMENT
Government Resolution No. PVT-1204/(160/2004)/ HP Mantralaya, Mumbai 400032 Dated: 15th September 2005.
I. PREAMBLE:
Power is a critical infrastructure on which the socio-economic development
of the country depends. The growth of the economy and its global
competitiveness hinges on the availability of quality power at competitive rates.
Therefore, it is imperative that electricity is made available at globally competitive
cost.
The Government of Maharashtra (GoM) has laid maximum emphasis on
the full development of its hydro potential being a clean & renewable source of
energy. It has been therefore decided to encourage private sector participation in
development of Small Hydro Projects ( SHPs). Accordingly GoM declared policy
vide Water Resources Department’s (previously known as Irrigation Department’s
(ID)) G.R. No. HEP (7/2002)/HP, dated 28th November 2002. This policy is
applicable to CPP through hydropower projects up to 25 MW installed capacity
which is considered as one of the non-conventional energy source.
Electricity Act 2003 (EA 2003) has come into force since 10th June, 2003.
This act has replaced the Indian Electricity Act 1910, the Electricity (Supply) Act
1948 and Electricity Regulatory Commissions Act, 1998.
The act has delicensed the generation and permitted direct commercial
relationship between generating company and consumer/trader. The act has
awarded generating company a right to open access to State Transmission
Utilities (STU) for the purpose of wheeling electricity. The EA 2003 has also
enlarged the definition of Captive user.
- 26 -
Signature of Promoter/Developer No. of correction Signature of Inviter
During the policy implementation process of GoM’s policy dated 28.11.02
number of suggestions have been received requesting for certain amendments to
the provisions in the state policy in light of provisions of EA 2003.
On this background and with an intention to harmonise the provisions in the
state policy with that in EA 2003 , GoM is pleased to declare revised policy for
development of SHPs up to 25 MW capacity, through the private sector
participation. This policy seeks to replace the earlier policy dated 28th November,
2002. The revised policy is intended to encourage the participation of both the
Captive Power Producers (CPPs) and Independent Power Producers (IPPs) in
development of SHP in the state.
II. Objectives :
The objective of the policy is
� to harness the green power with the help of private sector.
� to create suitable environment for attracting private sector investment .&
� to lay down the framework for the implementation of the policy.
Part A : Policy Guide Lines:
A-1 Scope:
The list of identified SHPs (up to 25 MW) sites is available with
Government of Maharashtra , Water Resources Department (GoMWRD). The
same shall be updated from time to time. The projects from this list shall be
offered for development as CPP/IPP. Unidentified SHP sites proposed by the
developers for development of CPP/IPP shall also be governed by this policy.
For the purpose of this policy, Captive Power Plant (CPP) is defined as a
SHP set up under section 9 read with clause (8) of section 2 of EA 2003 and
compiling the requirements stipulated in Electricity Rules 2005 notified by Ministry
of Power, Govt. of India (GoI) on 8th June, 2005.
For the purpose of this policy IPP is defined as SHP set by any person as
defined in EA 2003 for generating electricity, which can be sold to any consumer
- 27 -
Signature of Promoter/Developer No. of correction Signature of Inviter
located in the state of Maharashtra or any other willing distribution licensee or any
Power Trading Company.
The provisions of this policy are also applicable for any governmental or
semi governmental organisation of GoM who owns the water reservoirs.
A-2 Operative Period:
The policy shall be in operation from the date of publication of this
resolution till it is cancelled/revised. All the projects awarded within this period
shall be governed by this policy.
The SHP allotted under this policy shall be on Build, Operate & Transfer
Basis (BOT). The BOT period shall be 30 years. The BOT period shall start from
the date of commissioning of the project. At the end of the BOT period the
absolute ownership of the SHP along with land, switchyard & allied equipment
shall automatically stand transferred to GoMWRD free of cost.
MERC has initiated the tariff determination process for SHPs. Tariff and
other dispensation determined through this process may or may not apply for a
period coterminous with BOT and/or lease period agreed to between the
developer and GoMWRD.
GoMWRD may extend the BOT period at its discretion. If the period is
extended GoMWRD reserves the right to review the charges specified in section
A-14 of this policy.
A-3 The procedure for selection of Developers:
The procedure for selection of developers shall be as under.
A-3.1 The list of sites for SHPs to be offered for privatisation is available with
GoMWRD. This list shall be displayed on the web site of GoMWRD and shall be
updated from time to time. GoMWRD shall offer projects from this list for
development through public notification. The bidding process shall be open to
both CPP and IPP.
- 28 -
Signature of Promoter/Developer No. of correction Signature of Inviter
A-3.2 Prequalification evaluation of the interested developers shall be done. The
criteria for pre-qualification shall be technical & financial capabilities, past
experience and other relevant attributes of the developer. The necessary
information regarding attributes to be evaluated, their inter-se weightage,
guidelines for evaluation, passing score on attributes required for pre-qualification
shall be specified in pre-qualification document. Based on the above criteria the
developers shall be pre-qualified.
A-3.3 The bidding procedure shall be as under.
A-3.3.1 Main bidding documents shall be issued only to pre-qualified developers.
The minimum threshold premium shall be mentioned in the bidding document.
The bidders shall quote a premium payable to GoM over and above threshold
premium and support his bid by Earnest money Deposit (EMD). Upfront premium
will be the primary consideration for allotment of the project. Upfront premium
offered by both IPPs/CPPs will be evaluated. The highest bid so evaluated will be
the criteria for selection.
A-3.3.2 In most of the projects GoMWRD already constructed intake structure
hosting trash rack & sluice gates. Reinforced concrete lined penstock is also laid
in the body of the dam. GoMWRD intends to recover its exclusive investment on
power component viz. trash rack and steel penstock by fixing the threshold
premium for bidding. This threshold premium shall be Rs. 50 Lakhs/MW in case of
SHPs in which GoMWRD has already made investment on trash rack and
penstock. In other cases it shall be zero.
- 29 -
Signature of Promoter/Developer No. of correction Signature of Inviter
A-3.4 The GoMWRD shall intimate developer regarding his selection and Letter of
Permission (LoP) to the developer. This LoP will empower the developer to make
necessary investigations and prepare Techno-Economic Feasibility Report
(TEFR). The data available with GoMWRD if any shall be made available to the
selected developer, free of cost. The Developer shall draw his own inferences
from this data.
A-3.5 If the developer comes forward with his own site for development of the
project, GoMWRD shall issue LoP directly provided the proposed project is not
already investigated by GoMWRD. Decision of Secretary (CAD), GoM in this
regard shall be final.
A-4 Development of Project:
A-4.1 After receipt of the LoP the developers shall prepare Techno Economic
Feasibility Report (TEFR). The TEFR shall be prepared considering the fact that
the release of water shall be strictly as per irrigation/domestic/industrial demands
and the generation will have to be synchronised with these releases. GoMWRD
reserves the right to decide the release schedule and modify it from time to time
as per the requirements. GoMWRD shall make serious efforts to release
maximum volume of water in such a manner that it can be used for generation of
electricity at desired time. However, the decision of GoMWRD in this regard shall
be final and binding. No claims of compensation on these grounds shall be
entertained.
If the developer is satisfied about the techno-economic viability of the
project he shall submit the TEFR to GoMWRD within three months from the date
of LoP alongwith the processing fees as indicated hereinafter.
Sr. No. Installed Capacity Processing Fees in Rs. lakhs.
1. Up to 999 kW 1
2. 1000 KW to 1999 KW 3.5
3 2000 KW to 4999 KW 5
4. 5000 KW to 25000 KW 10
- 30 -
Signature of Promoter/Developer No. of correction Signature of Inviter
Under any circumstance (whether the project is viable or not) the developer
is not entitled for any claim for reimbursement of expenditure that he has made on
investigations, preparation of TEFR and its scrutiny.
A-4.2 GoMWRD before concurring with TEFR shall ascertain whether or not in its
opinion,
A-4.2.1 Proposed scheme will prejudice the prospect for best ultimate
development of the hydro potential of the site consistent with the requirements of
the domestic/irrigation/industrial water, navigation, flood control or other public
purposes.
A-4.2.2 Proposed company exploits the full potential of the site allotted to the
developer. In normal situation development in stages will not be allowed.
However, due to any project specific reasons if stage wise development of the
project is necessary, Secretary (CAD), GoM is authorised to allow stage wise
development.
A-4.2.3 Proposed scheme meets the norms regarding dam design & safety.
A-4.3 If the TEFR satisfies all the above prerequisites GoMWRD shall approve the
TEFR and issue Letter of Allotment (LoA) within one month from the date of
submission of TEFR or date of giving all the clarifications by developer, whichever
is later. On receipt of LoA developer shall deposit the Performance Security and
sign the Hydro Power Development Agreement (HPDA) with GoMWRD within
eight days. Amount of Security deposit shall be such that yearly charges payable
to GoMWRD on account of water royalty, maintenance charges and land lease
charges could be recovered from it.
- 31 -
Signature of Promoter/Developer No. of correction Signature of Inviter
A-4.4: Developer shall arrange for all the necessary clearances & financial closure
within 6 months from the date of signing HPDA. GoMWRD shall facilitate
developer in getting clearances. However, it shall be the primary responsibility of
developer to arrange for various clearances within stipulated time. This period
shall be extended if there are valid reasons for such extension, which shall be
decided by Secretary (CAD), GoM. Failure of developer in arranging the various
clearances & finance within a stipulated period will result into automatic
cancellation of HPDA and forfeiture of Performance Security. In case, any of the
state level or central level clearance is denied for a particular reason the
performance Security shall be refunded to the developer. However, cost incurred
by developer for investigations, preparing TEFR, getting clearances and arranging
finance shall not be refunded in any case.
A-4.5: After getting necessary clearances & financial closure within stipulated
period & submitting the documentary proof there of GoMWRD shall issue letter to
the developer (within 8 days) to deposit the amount of Upfront Premium offered by
him within one month.
Failure of developer to deposit amount of Upfront Premium within stipulated
period will result into automatic cancellation of HPDA and forfeiture of
Performance Security. GoMWRD shall authorise the developer to start the
development work within 8 days from payment of amount of Upfront Premium.
A-4.6 In case of surrender of allotment by developer due to any reason he will be
penalised as under and no compensation would be payable to the developer in
such instance...
Sr. No
Stage at which project is surrendered
Penalty
1 Before signing HPDA Forfeiture of Earnest Money Deposit except in the event the project is found unviable
2 After signing HPDA Forfeiture of Performance Security except when any state/central level clearances are denied
3 After permission for development is given
Forfeiture of Performance Security plus amount of Upfront Premium.
- 32 -
Signature of Promoter/Developer No. of correction Signature of Inviter
A-4.7 The project shall be made operational within 24 months from the
date of authorisation for development. However, any project specific issues shall
be considered and project implementation schedule shall be drafted accordingly
and incorporated in HPDA. The land under the possession of the government will
be handed over to the developer on lease rent. If no government land is available
for setting the unit, the developer has to arrange for land acquisition from private
parties at his cost.
A-4.8: During the project implementation the progress of the developer
shall be reviewed at various milestones & if the progress is not found satisfactory
reasons for the delay shall be called for. If the reasons for the delay are found to
be beyond the control of the developer, necessary time extension shall be given
otherwise developer would be liable to pay a penalty as decided by GoMWRD.
The details regarding various milestones and rate of penalty shall be included in
the HPDA.
A-4.9 The developer shall be responsible for carrying out the work with
due diligence with regard to his responsibilities under various Central/ State /
Local laws, rules and regulations & ensure the compliance of the same.
A-4.10 The developer shall insure the assets of the project and keep them
insured during the term of HPDA.
A-5 Consultancy:
In case, the developer opt to utilise the Consultancy services of GoMWRD
in respect of further investigations, preparation of TEFR, estimates, designs &
drafting specifications etc. he can avail the same at mutually agreed rates &
conditions. GoMWRD has ISO 9001-2000 recognized design organization which
has expertise in this field.
- 33 -
Signature of Promoter/Developer No. of correction Signature of Inviter
A-6 Generation:
Developer can establish, operate & maintain a generating power plant
without any license, subject to following requirements.
A-6.1 TEFR is approved by GoMWRD.
A-6.2 All the Statutory Clearances are received.
A-6.3 Technical standards relating to connectivity with the grid referred to in
clause (b) of Section 73, provisions in section 10 and other applicable
provisions of EA 2003 are followed.
A-7 Grid Interfacing & Evacuation Arrangements:
This will be as per dispensation emerging from the tariff and procurement
process determination exercise initiated by MERC.
A-8 Transmission/Distribution entities:
Developer may construct and maintain dedicated transmission lines as
defined in EA, 2003 from the generation plant to the destination of his use.
However, he will have the right to access for existing transmission facilities in the
State as per the provisions of EA, 2003 and the Regulations and other
dispensations of MERC regarding Transmission Open Access. The local
distribution licensee shall be permitted to evacuate power from SHP directly if he
desires to do so. The developer shall sign Energy wheeling agreement with
Transmission entity / distribution licensee. When transmission lines of
Transmission entities are used, rates of wheeling charges and transmission
losses shall be as decided by MERC from time to time, and wheeling transactions
shall be settled accordingly.
- 34 -
Signature of Promoter/Developer No. of correction Signature of Inviter
When an open access is provided by MERC under subsection (2) of
section 42 of Electricity Act 2003 the developer shall be responsible for payment
of transmission charges & surcharge thereon as decided by MERC for the energy
sold to Third Party Consumer/Distribution Licensee/Power Trading Company.
The metering of energy generated at generating station and corresponding
credit at the consumption point shall be on ToD (Time of Day) tariff slots.
A-9 Banking :
This will be as per dispensation emerging from the tariff and procurement
process determination exercise initiated by MERC.
A-10 Generation Restrictions:
In extraordinary circumstances arising out of threat to security of the state,
public order or a natural calamity or such circumstances arising out of public
interest, the developer shall have to operate & maintain generating station in
accordance with the directives of state government subject to the provisions of
section 11 of EA, 2003.
A-11 No Compensation for Grid Failure:
Developer/ Third party consumer/ Captive user/ Licensee (authorised
consumer) shall abide by grid discipline & will not be entitled for any
compensation in the event of grid failure, shut down, interruption in power supply
etc.
- 35 -
Signature of Promoter/Developer No. of correction Signature of Inviter
A-12 Developers to Pay to GoMWRD:
A-12.1 Water royalty : Developer shall pay the water royalty at the rate of
Rs.0.05 per unit of energy generated .
A-12.2 Charges for maintenance of intake structure, penstock etc. at the
rate of Rs 0.05 for every unit generated.
A-12.3 Land lease charges for the GoMWRD land at the rate of Rs.1/kW of
installed capacity/ Year.
A-12.4 The above rates of royalty charges, maintenance charges and lease
charges are for the first year and the same shall be increased in every subsequent
years by 5% by compounding.
A-12.5 The above rates of royalty charges , maintenance charges and lease
charges shall be reviewed after 30 years if lease period is extended.
A-12.6 Water royalty charges and maintenance charges shall be invoiced
quarterly at the end of each quarter and land lease charges shall be invoiced at
the beginning of every financial year. All these charges will have to be settled
within 30 days after the receipt of the invoice. Thereafter the interest at S.B.I.
prime lending rate plus 2% (Two percent) per annum on delayed payment for
delayed period shall be made applicable.
A-12.7 During first 10 years after commissioning, if in any particular year,
75% of the 75% dependable water could not be made available to the developer,
then water royalty charges and maintenance charges for that year shall be waived
off.
A-13 Taxes & Duties:
The developer shall pay taxes, duties & other levies as applicable from time
to time to the respective departments of the State & Central and Local
Governments unless developers are specifically exempted from paying such taxes
& duties. It will be presumed that developer has considered all these aspects
before bidding.
- 36 -
Signature of Promoter/Developer No. of correction Signature of Inviter
However, to encourage and promote sale of available surplus captive
power within the state and to avoid undue overburden on CPP with further levy of
Electricity Duty, Govt. of Maharashtra exempt CPPs under this policy from
Electricity Duty and Tax on Sale of Electricity.
A-14 Transfer of Allotment:
If the developer wants to transfer ownership of generating unit completely
to other developer he will be permitted to do so on prior approval of GoMWRD.
GoMWRD may give such approval provided,
A-14.1 Financial institution has consented such transfer.
A-14.2 GoMWRD is satisfied that the new developer shall consume the
generated energy primarily for his own use ( in case of CPP only).
A-14.3 Proposed developer agrees to all the terms & conditions agreed to
by the original developer.
A-14.4 And new developer deposits the transfer fees with GoMWRD as RS.
1 Lakhs/MW of installation. This transfer fee may vary as per prevailing Whole
Sale Price Index with base index of 2003-04. This transfer fees are in addition to
transfer fees payable if any, to other authority.
A-15 Sale of Power:
Generated electricity can be sold to any consumer locate in the state of
Maharashtra or any willing distribution licensee or any power trading company.
However, Maharashtra Electricity Distribution Company shall have the first right of
refusal. Sale of power shall be as per dispensation emerging from the tariff and
procurement process determination exercise initiated by MERC.
- 37 -
Signature of Promoter/Developer No. of correction Signature of Inviter
A-16 Inspection of Project :
The GoMWRD engineers before and after the monsoon shall inspect the
power project from safety point of view. The developer shall render all requisite
help and cooperation for such inspection. Similarly, statutory inspection from
Factory inspector / Electrical Inspector shall be got done. The Inspection Reports
shall be furnished to GoMWRD annually.
Developer shall maintain all the record regarding capacity, generation, PLF,
downtime with relevant constraints etc. and make available all these records to
inspecting authority for inspection.
A-17 Exclusive Jurisdiction Of MERC:
MERC has exclusive jurisdiction on those provisions of this Policy which
are within its regulatory mandate under the provision of Electricity Act, 2003,
especially regarding electricity sales rates, power purchase agreements and
provisions regarding wheeling, banking distribution and transmission loss charges
etc. Similarly, MERC has jurisdiction as per the provisions of EA 2003 as regards
the promotion of non-conventional energy sources, facilities for transmission of
energy, sale of power to any interested consumer and sharing of purchase of
power amongst the STU/Transmission Licensee/Distribution Licensee. Orders
regulations, directives, guidelines issued by MERC regarding these issues from
time to time shall be binding on all.
In the event of dispute in interpretation of this policy or any clause in the
agreement between developer & GoMWRD or STU/Transmission
Licensee/Distribution Licensee, the same shall be referred to MERC to the extent
of its jurisdiction under section 86(1) and other provisions of EA. 2003.
- 38 -
Signature of Promoter/Developer No. of correction Signature of Inviter
A-18 : Obligations of GoMWRD:
A-18.1: Nodal officer of GoMWRD shall extend all the possible assistance
for getting the various clearances required.
A-18.2: GoMWRD shall approve the TEFR within 1 month from the date of
submission or date of giving all the clarifications by developer whichever is later.
A-18.3: GoMWRD shall hand over the site for development of the project
within 15 days from the permission accorded to commence the work.
A-18.4: Developer shall be allowed to use the approach road to the power
house if it is in possession of GoMWRD . However, the developer at his own cost
shall carry out the maintenance of the same.
A-18.5: GoMWRD shall provide residential quarters of suitable type, if and
as available near the project site for developer for his staff during construction
period on rental basis. However, the developer at his own cost shall carry out the
maintenance of the same.
A-18.6: GoMWRD shall make available the piece(s) of land if available to the
developer for construction of residential quarters/office of maintenance staff on
reasonable terms to be agreed between GoMWRD & developer. The period of
such agreement shall be the same as that of HPDA. In such case the developer
shall handover such buildings to the GoMWRD at the end of the agreement free of
cost. However, the developer shall not be allowed to make any commercial use of
such land.
Part-B General Provisions:
B-1 The developers to whom CPP is allotted by GoMWRD under previous
policy & willing to opt for the provisions of this policy may apply for the same
alongwith the necessary processing fee. GoMWRD shall accord such permission
if requisite requirements are complied by the developer. The processing fees for
this purpose shall be of Rs. 0ne lakh per MW of installation. This processing fee
may vary as per prevailing Whole Sale Price Index with base index of 2003-04.
However, this permission of GoMWRD shall be subjected to provisions of Section
A-17 of this policy and dispensation emerging from the tariff and procurement
process determination exercise initiated by MERC.
- 39 -
Signature of Promoter/Developer No. of correction Signature of Inviter
B-2: IPPs & CPPs are free to change their option (entity) in due course of time.
However, this permission shall be subjected to provisions of Section A-17 of this
policy and dispensation emerging from the tariff and procurement process
determination exercise initiated by MERC.
B-3: Change in option from sale to third party to Licensee and vice versa and
switching from one third party consumer to other third party consumer without
change in entity shall also be governed by provisions of Section A-17 of this policy
and dispensation emerging from the tariff and procurement process determination
exercise initiated by MERC.
B-4: Provisions in the Policy shall be periodically reviewed in view of the
dynamic economics of the sector. In normal circumstances next review shall be
after three years. However, GoM reserves the right to amend / delete certain
provisions of this policy and include additional provisions, if found necessary for
operational ease or to deal with unforeseen issues or if found necessary due to
any further dispensation of GoI or MERC as the case may be. GoM may from time
to time issue orders and practice directions in regard to the implementation of this
policy and matters incidental or ancillary thereto as the GoM may consider
appropriate. However, such amendments shall be made applicable with
prospective effects only.
Part-C : Promotional Incentives Offered by GoM
SHPs are the renewable non-polluting energy sources. However, like any
other nonconventional source they are costlier as compared to conventional
sources. With an intention to make available energy from these sources at
competitive rates Ministry of Nonconventional Energy Sources (MNES) GoI has
offered some incentive schemes. On the same lines GOM is pleased to offer
following incentives.
- 40 -
Signature of Promoter/Developer No. of correction Signature of Inviter
C-1 The developer is supposed to commission the project within 24 months
from the date of authorisation. If the developer commissions the project at earlier
date, he will be exempted from water royalty charges & maintenance charges to
an extent of units generated before scheduled date of commissioning.
C-2 CPPs shall be exempted from Electricity Duty on the self consumption of
electricity only for first five years after commissioning if the consumption unit is
located in Maharashtra.
C-3 CPPs shall be exempted from tax on Sale of Electricity only if the
consumption unit is located in Maharashtra.
C-4 Technical Consultancy at nominal charges.
C-5 Maharashtra Energy Development Agency, (MEDA), Pune shall assist the
developers in getting incentives for SHPs from MNES, GoI.
This resolution is issued in concurrence of Finance, Energy, Planning and
Industry Departments. This resolution is being in supersession of Irrigation
Department's GR No. HEP (118/99) HP dated, 22nd September 1999 and G.R.
No. HEP (7/2002)HP, dt. 28th November, 2002.
By order and in the name of the Governor of Maharashtra,
Sd/-
(V.M. KulKarni)
Deputy Secretary to Government of Maharashtra.
Copy to:
The P.S. to Hon. Chief Minister, Maharashtra State, Mantralaya, Mumbai-400 032
The P.S. to Hon. Dy. Chief Minister, Maharashtra State, Mantralaya, Mumbai-400 032
The P.S. to Hon. All Ministers, Maharashtra State, Mantralaya, Mumbai-400 032
The P.S. to Hon. All State Ministers, Maharashtra State, Mantralaya, Mumbai-400 032
The Chief Secretary, Maharashtra State, Mantralaya, Mumbai-400 032
The Additional Chief Secretary (Finance), Finance Department, Mantralaya, Mumbai-400032.
The Additional Chief Secretary (Planning), Planning Department, Mantralaya, Mumbai-400 032.
The Principal Secretary (Energy and Environment), Industries, Energy & Labour Deptt.,
- 41 -
Signature of Promoter/Developer No. of correction Signature of Inviter
Mantralaya, Mumbai-32.
The Secretary (Industries), I.E.& L.Department, Mantralaya, Mumbai-400 032.
The Secretary (Legal Remembrancer), Law & Judiciary Department, Mantralaya, Mumbai-32.
The Secretary (Water Resources), Water Resources Department, Mantralaya, Mumbai-400 032.
The Secretary (CAD), Water Resources Department, Mantralaya, Mumbai-400 032.
All CE & Joint Secretaries, Water Resources Department, Mantralaya, Mumbai-400 032
The Chairman, Maharashtra Electricity Regulatory Commission, Mumbai (By letter)
The Managing Director, MSEB Holding Company Ltd. , Prakashghad, Mumbai-400 051.
The Managing Director, Maharashtra State Transmission Company Ltd. , Prakashghad,
Mumbai-400 051.
The Managing Director, Maharashtra State Electricity Distribution Company Ltd. ,
Prakashghad, Mumbai-400 051.
The Managing Director, Maharashtra State Power Generation Company Ltd. ,
Prakashghad, Mumbai-400 051.
Executive Directors and Chief Engineers of all Irrigation Development Corporations
Chief Engineer (Electrical), Hydro Projects, Mumbai-400 023
All Regional Chief Engineers of Water Resources Department.
Directorate General of Information & Public Relations, Maharashtra State, Mantralaya,
Mumbai (2 copies)
Director, Maharashtra Energy Development Agency (MEDA), MHADA Commercial
Complex, 2nd floor, Opp. Tridal Nagar, Yerwada, Pune-411 006
All Superintending Engineers and Executive Engineers in Water Resources Department,
HP Desk (for collection)
- 42 -
Signature of Promoter/Developer No. of correction Signature of Inviter
Modification in clause No. A-15 Sale of Power Of Hydel Policy dated 15.09.2005, regarding Development of Small Hydro Projects through private sector participation.
Government of Maharashtra Water Resources Department
Government Resolution No. HEP-1209/(143/2009)/HP.
Mantralaya, Mumbai-400032. Dated: 31/10/2009.
Read : 1) G. R. No. PVT-1204/(160/2004) /HP, dated 15th September 2005.
2) G. R. No. PVT-1207/(406/2007) /HP, dated 22nd December 2008.
Preamble:
There is a deepening crisis of power shortage in Maharashtra State. In
view of this following provision “Maharashtra Electricity Distribution Company
shall have first right of refusal” was included in clause No.A-15 “Sale of Power”
of Government Resolution dated 15.09.2005 regarding hydel policy for
development of small hydro projects through private sector participation.
The clause “Sale of Power” is further reproduced by MERC in order dated
9th November 2005 for fixation of tariff for Small Hydro Projects as clause
No. 3.58.
In light of the provisions of Electricity Act, 2003, an entrepreneur had filed a
petition under Case No. 85 of 2006 requesting MERC to review the provision of
“Maharashtra Electricity Distribution Company shall have first right of refusal”
appearing in the clause No. 3.58 of MERC’s order dated 9th November 2005.
Accordingly MERC vide order dated 7th November 2007 has considered
the petitioner’s request and deleted the provision of “Maharashtra Electricity
Distribution company shall have first right of refusal” from their order dated 9th
November 2005.
- 43 -
Signature of Promoter/Developer No. of correction Signature of Inviter
In light of these development, clause No.A-15 “Sale of Power” of Hydel
Policy dated 15th September, 2005 was modified, vide G.R.No. PVT-
1207/(406/2007)/HP, dated 22nd December 2008. In view of this modified clause,
it is mandatory that fifty percent (50%) of the generated electricity shall be sold to
Maharashtra State Electricity Distribution Company Ltd. (MSEDCL) and remaining
fifty percent (50%) of the generated electricity shall be sold in Maharashtra to any
consumer or distribution Licensee.
However, Industry, Energy & Labour Department vide GR No. +{ÉÉ>ð-2009/
|É.Gò.1528/=VÉÉÇ-, ÊnùxÉÉÆEò 03 +ÉìMɺ]õ 2009 has permitted 100% generated electricity
from Small Hydro Projects (upto 25 MW) to be sold in Maharashtra to any
consumer or distribution Licensee.
In view of these developments, further modifications to clause No.A-15
“Sale of Power” of G.R. dated 22.12.2008 are necessary.
RESOLUTION :
Clause No. A-15 “Sale of Power” of Government Resolution, Water
Resources Department dated 22.12.2008 shall be read as under :
A-15 “ SALE OF POWER ”
“ Considering the present acute power shortage situation in
Maharashtra, it is necessary in larger public interest that, the power generated
from Hydro projects (upto 25 MW Capacity) shall be consumed in
Maharashtra. Therefore exercising the powers as per provisions of section
108 of Electricity Act, 2003, it is mandatory that, hundred percent (100%) of
generated electricity shall be sold in Maharashtra to any consumer or
distribution Licensee.”
- 44 -
Signature of Promoter/Developer No. of correction Signature of Inviter
The modified clause is applicable from the date of issue of this Government
Resolution.
The Government Resolution is available on the website
www.Maharashtra.gov.in of Government of Maharashtra and its computer code no. is
20091031183927001.
By order and in the name of the Governor of Maharashtra.
sd/-
(S.R.Bavaskar)
Under Secretary
to Govt. of Maharashtra
Copy to :
The P.S. to Hon.Chief Minister, Maharashtra State, Mantralaya, Mumbai - 400032
The P.S. to Hon.Deputy Chief Minister, Maharashtra State, Mantralaya, Mumbai - 400032
The P.S. to Hon.All Minister, Maharashtra State, Mantralaya, Mumbai - 400032
The P.S. to Hon.All State Minister, Maharashtra State, Mantralaya, Mumbai - 400032
The Chief Secretary, Maharashtra State, Mantralaya, Mumbai - 400032
The Additional Chief Secretary (Finance) Finance Department, Mantralaya, Mumbai - 400032
- 45 -
Signature of Promoter/Developer No. of correction Signature of Inviter
SECTION – IV
GOSIKHURD (L.B.C.)HYDRO ELECTRIC PROJECT (0.500 MW)
(A) Salient features of Gosikhurd (L.B.C.)Hydro Electric Project (B) Brief Description & Present Status of Gosikhurd (L.B.C.)
Hydro Electric Project (C) Appendices: Appendix I Information submitted as per GOVT. of
Maharashtra W.R.D. Mumbai letter NO. 1206/ (369/06)/HP /dtd. 24-4-2007.
Appendix II Statement showing month wise discharge for
1 X 0.500MW. Appendix III Resorvoir operation table & Power generation for
75% dependable yield (2 sheet). Appendix IV Area capacity table for Gosikhurd (L.B.C.) Hydro
Electric Project.
- 46 -
Signature of Promoter/Developer No. of correction Signature of Inviter
SECTION – IV
A) SALIENT FEATURES OF GOSIKHURD (L.B.C.)HYDRO ELECTRIC
PROJECT
1) Location
I. Name of project : Gosikhurd ( L.B.C.)
II. State : Vidarbha
III. District : Bhandara
IV. Taluka : Pauni
V. Village : Near Village Gosikhurd
VI. Topo sheet No. : 55P/9
VII. Latitude : 200
- 52' - 15"N
VIII. Longitude : 79 0 - 37’ -00”E
2) River Basin
1. Name of River : Wainganga River
2. Sub Basin : Pranhita
3. Basin : Godavari.
3) Hydrology & Water Planning
i) Catchment area : 34862 Sq.Km.
ii) Intercepted Catchment area : ------.
iii) Net Catchment area :
a) Madhya Pradesh : 24243 Sq. Km.
b) Maharashtra : 10619 Sq. Km.
Total : 34862 Sq. Km.
iv) Average monsoon Rainfall : 1200 mm
v) 75 % Dependable yield : 14196 Mm3
iv) Total Yield at site : 3410 Mm3
v) Annual utilization proposed : 1633.74 Mm3
vi) Saleable energy : 7.3228 Mus
4) Utilization :- 1) Irrigation
i) With flow canal on L.B.C. : 125.120 Mm3
ii) On lift canal on L.B.C. : 100.150 Mm3
iii) L.B.fore shore lift : 158.86 Mm3
iv) R.B. flow canal
: 335.51 Mm3
- 47 -
Signature of Promoter/Developer No. of correction Signature of Inviter
v) R.B. fore shore lift : 191.360 Mm3
vi) Water Supply to ordanance factory : 23.69 Mm3
at Bhandara
vii) Feeding to existing Asolamendha : 433.08 Mm3
tank through R.B.C.
viii) Annual evaporation losses : 265.97 Mm3
Total( i to viii ) : 1633.74 Mm3
Say : 1634.00 Mm
3
5) Dam & Storage
(i) Gross Storage up to FRL : 1146.075 Mm3
(ii) Dead Storage : 405.907 Mm3
(iii) Live Storage : 740.168 Mm3
(iv) Lake Losses : 265.97 Mm3
(v) Type of dam : Rolled filled earth dam with central
Gated ogee shaped masonry
spillway.
(vi) Length of Dam : 11.36 Km (Including Spillway)
(vii) Top Width of Dam : 11.00m
(viii) Maximum Height : 28.37m
6) Controlling Levels
(i) TBL : 250.05 m
(ii) MWL : 245.70 m
(iii) FRL : 245.50 m
(iv) MDDL : 241.29 m
(v) RBL : 221.68 m
(vi) Sill Level : 235.50 m
(vii) Crest of Spillway : 228.74 m
(viii) C.B.L.at start of canal : 238.00 m
(ix) C.B.L. ( L.B.C) : 238.00 m
7) Irrigation Outlet details & Canal
(i) Location : R.D.7905m
(ii) Discharge : 45.22 m3/sec.
(iii) Out let sill level (L.B.C.) : 238.50m
(iv) Out let sill level (R.B.C.) : 235.60m
(v) Size of conduit : 2.30mX3.0m , 2Nos
8) Irrigation cum Power outlet
(i) Location : CH: 780 m
(ii) Design discharge for penstock : 13.50 m3/sec.
- 48 -
Signature of Promoter/Developer No. of correction Signature of Inviter
(iii) No of penstock : 1 No
(iv) Diameter of penstock : 3.30 m diameter
(v) Thickness of plate : 12 mm
(vi) Length of penstock
(a) Inside body of dam : 57m
(viii) Location of power outlet : CH:780 m
9) Power House & Switch Yard
(i) Location and Size :
(ii) No of units & installed capacity : 1 X 0.500MW
(iii) Minimum Head : 2.84 m
(iv) Maximum Head : 6.18 m
(v) Designed Head : 5.087 m
(vi) Designed discharge of Penstock : 1X13.50 m3/sec
(viii) Generation Voltage : 0.415 KV
(ix) Step up voltage : 11 KV
10) Tail Race Channel :
i) Bed Width : 14.50 m
ii) FSD : 2.70 m
iii) Total Length : 70.0 m
iv) F.B. : 1.00m
v) Side Slope of TRC : 1 : 5:1
vi) Bed gradient : 1:10000
vii) Discharge : 45 m3/sec
viii) Type : Lined.
- 49 -
Signature of Promoter/Developer No. of correction Signature of Inviter
B) BRIEF DESCRIPTION & PRESENT STATUS OF
GOSIKHURD (L.B.C.) HYDRO ELECTRIC PRIJECT
(1X0.500MW)
1.0 Project Description:
Gosikhurd (L.B.C.) hydro electric project is proposed on Gosikhurd irrigation
Dam as dam foot of Gosikhurd dam of Wainganga river. Wainganga river is the
major tributary of Pranhita river in the Godavari basin. The project is located near
Gosikhurd village Tah. Pawani in Bhandara district. The Gosikhurd project is at
distance of about 14 Km. from Pawani.The Pawani village is situated on Nilaj-
Bhandara road.The Gosikhurd Project is about 100 Km from Nagpur and 40Km
from Bhandara.
2.0 Present proposal :
It is proposed to generate power from the irrigation releases to be made available
from the Gosikhurd dam utilizing the variable head. The steel penstock is already
embedded in the body of dam. To utilize the irrigation releases for power
generation a power scheme with appropriate capacity is proposed to be
constructed. The GOMWRD has assessed this potential as 0.5 MW. The Promoter/
Developer is free to Design the installed capacity. However it is obligatory on
Promoter/ Developer to utilize the optimum available Hydro potential.
3.0 Present Status :
3.1 Approaches to site :
Gosikhurd (L.B.C.) Hydro Electric Project is proposed on Gosikhurd dam
of Wainganga river .It is located near Gosikhurd Village, Taluka Pawani,District
Bhandara.
The Gosikhurd (L.B.C.) Hydro Electric Project is approachable from
PawaniVillage situated on Nilaj- Bhandara road.The Gosikhurd Project is about
100 Km from Nagpur and 40Km from Bhandara.
The nearest railway station is Bhandara Road railway station which is about 50Km
from the dam site. Bhandara Road railway station is on Bombay- Kolkata line of
central Railway.
3.2 Construction power:
The construction power supply required during erection stage shall be arranged by
the promoter / Developer @ their own cost.
- 50 -
Signature of Promoter/Developer No. of correction Signature of Inviter
3.3 Other facilities:
All other facilities such as drinking water, office shed, Stores etc. shall be arranged
by Promoter / Developer at their own cost.
3.4 Present status of Work:
Gosikhurd ( L.B.C.) project comprises of earthen dam of 11.20Km ( Including
spillway ) long and 28.37 meter maximum height. The gross capacity of dam at
FRL is 1146.075 Mm3. The spillway of Gosikhurd irrigation project is located at
R.D.5905m. to 6808.90 m. and the length is 927m. The construction work of the
dam is completed and partial storage upto R.L. 237.20M is done.
3.5 Power outlet and power planning:-
One penstock of diameter 3.30 m with 12mm thickness at power outlet at
CH:780 m is proposed for carrying discharge for power generation of
13.50cumecs..
The releases for irrigation purpose will be released through power house. The
water released after generation will be diverted for irrigation through tail race
canal.
The power house with installed capacity 1X0.500MW, and power generated will
be evacuated at 11KV by constructing out door switchyard of 11KV near to power
house.
4.0 Hydrology and water planning:
4.1 As per Executive Engineer, Gosikhurd Dam Division, Wahi ( Pawani) of
GOMWRD study the 75% dependable yield at Gosikhurd dam is 3410 Mm3.
Water release table can be seen in the office of Executive Engineer, Gosikhurd
Dam Division, Wahi (Pawani).However Promoter/Developer shall obtain
Hydrological data from their own sources.
4.2 Power generation :-
4.2.1 The releases of water in the canal shall be strictly as per irrigation
/domestic/industrial water demands. The power generation will have to be
synchronized with these releases to cope up with variation in irrigation
requirements. GOMWRD has proposed one unit of 0.500 MW. The installed
capacity is indicative only and GOMWRD does not take any responsibility in this
respect.
GOMWRD reserves right to decide the release schedule and modify it from
time to time depending on yield available in dam and irrigation / domestic /
industrial water requirements.
4.2.2 The water releases as per irrigation / domestic/industrial requirements will be
routed through power out let to the possible extent. However in exceptional
circumstances, if the irrigation / domestic/industrial water demands is more than
that of discharge capacity of power outlet, the excess
- 51 -
Signature of Promoter/Developer No. of correction Signature of Inviter
irrigation / domestic/industrial water requirements shall be fulfilled by releasing
additional water from other outlet /by passes.
Irrigation/Domestic/Industrial water requirement shall be fulfilled by releasing
additional water from other outlets/by passes.
5.0 INTAKE WORKS, POWER HOUSE AND ALLIED WORKS:
5.1 Intake:
Intake structure consist of R.C.C. framed structure accommodate two trash rack.
Two Stop log gate is provided at upstream side of dam is to be operated from the
top of the dam, with suitable gantry type hoisting arrangement.
5.2 Penstock :
One penstock of diameter 3.30 m with thickness 12.00 mm thickness is already
embedded in the body of dam at power outlet CH:780 m is proposed for carrying
design discharge for power generation of 13.50cumecs.
5.3 Power House & Switchyard:
The promoter/Developer shall access the location of the power house and shall
submit the detailed proposal for approval of GOMWRD.
The space and land acquired by GOMWRD for construction of power house,
switchyard etc. is indicated in the drawing attached as Annexure. This space will
be handed over to Promoter/Developer. If any additional space is required by the
promoter/Developer, he will have to arrange for it himself. Switchyard of suitable
size shall be planned near to the power house building.
5.4 Draft tube gate structure:
The draft tube gate structure shall be provided immediately downstream of the
power house to accommodate D.T. gates and hosting arrangement. The D.T. gate
structure shall be R.C.C. structure constructed by promoter/Developer. A deck slab
shall be provided @ suitable levels for repair and maintenance of gate. The suitable
access to the deck slab shall be provided.
5.5 Tail Race channel:
Trapezoidal C.C. lined tail race channel of suitable capacity and length and length
shall be provided by promoter/Developer to let out the water after power
generation into the Irrigation canal for further downstream use. The bed shall be of
the concrete of suitable grade. Arrangement of anchorage and for drainage to
minimize uplift pressure shall be made.
- 52 -
Signature of Promoter/Developer No. of correction Signature of Inviter
6.0 INTERCONNECTION WITH GRID:
Nearest MSEDCL 33kV. substation at Paghora which is approximately
18Km. away from proposed Hydro Electric Project.
Technical standards relating to connectivity with the grid referred to in
clause (b) of section 73, provision in section 10 and other applicable provisions of
EA 2003 shall be followed by the Promoter/Developers. Grid Interfacing &
Evacuation Arrangements shall be as per dispensation emerging from the tariff and
procurement process determination exercise initiated by MERC.
7.0 SCOPE OF WORK:
The Promoter/Developer shall inspect the project site and shall get them-
selves satisfied with all the details of the project site including its area,
demarcation, location, access and geological conditions. The Promoter/Developer
shall be responsible for execution, commissioning and operation of the Project
successfully as per terms and condition stipulated in Price Bid document No.
CE(E)/ HP / SHP / CPP / IPP / …. The work covered under the scope of work shall
comprise of but not limited to following works.
7.01 CIVIL ENGINEERING WORKS:
i) Individual Penstock upto power house including concrete encasing etc.
ii) Construction of power house.
iii) Construction of tail race channel.
iv) Civil works for switchyard including fencing.
v) Draft Tube gate, embedment, concreting and D.T. gate hoisting
arrangement.
7.02 ELECTRICAL AND MECHANICAL ENGINEERING WORKS:
i) Turbine – Generator plant with Turbine – Generator auxiliaries including
main inlet Valve, control & protection, excitation system etc.
ii) Power transformer.
iii) Switchyard equipments.
iv) Unit Auxiliary transformer
v) Station Auxiliaries including A. C. Distribution, D. C. D. B., Battery charger
& Batteries, XLPE cables, Control & L.T. power cables.
vi) Inter connection with grid, evacuation arrangements etc.
vii) EOT crane
viii) D. G. Set.
ix) Earth mat, Illumination, Fire fighting equipments.
- 53 -
Signature of Promoter/Developer No. of correction Signature of Inviter
x) Communication, Air conditioning plant, work shop equipment etc.
Given above details of works are indicative only. The Promoter /Developer
shall have to complete the project with successful commissioning of Generating
Plant with all respect as per Hydro Policy declared vide Government of
Maharashtra, Water Resources Department G. R. No. PVT – 1204/(160/2004)/HP,
dated 15/09/05.
Note:-
Promoter/Developer shall be deemed to be fully acquainted of all local
conditions at various level availability of labor, electricity, water, present status of
works i.e. Dam, Intake structure, Penstock etc. communication & space available
at site and factors which may have any effect on the execution of the works
covered under these documents and specifications.
7.03 Promoter through its consultant shall validate the hydrological data made available
by the GOMWRD in PQ document / Price bid or in any other GOMWRD
document and draw his own inferences only after such validation. Promoter shall
estimate Installed capacity / annual generation only by using such validated data.
GOMWRD shall not take responsibility regarding correctness of data and its
consequential losses if any.
- 54 -
Signature of Promoter/Developer No. of correction Signature of Inviter
APPENDIX - I
( C ) INFORMATION SUBMITTED AS PER GOVT. OF MAHARASHTRA
W.R.D. MUMBAI LETTER NO. 1206/ (369/06)/HP/DATED 24-4-2007
GOSIKHURD ( L.B.C.) HYDRO ELECTRIC PROJECT
Sr.No Item Description Data
1 As per Govt. web site list
2 Name of project Gosikhurd ( L.B.C.) H.E.P.
3 Installed capacity (in MW) 1x0.500MW
4 Taluka Pawani
5 District Bhandara
6 Type of project Rolled Filled Dam
7 Project Description
7.1 General topography of region
7.1.1 Toposheet 55P/9
7.1.2 Latitude 200-52’-15”N
7.1.3 Longitude 790 - 37’-00”E
7.2 Origin of the river Godavari
7.3 Location of reservoir Gosikhurd village
7.4 Catchment area in Sq. Km. 34862 Sq. Km.
7.5 Primary objective of project Storage Dam
7.6 Year of first filling of reservoir -
8 Salient feature of the project Furnished
9 Topography / climatology
9.1 Max & Min. temperature at reservoir site -
9.2 Monthly rate of evaporation at reservoir
site
21.96mm3
10 Hydrology
10.1 Catchment area Sq. Km. 34862 Sq. Km.
10.2 Average annual rainfall in mm 1320 mm.
10.3 75% dependable yield in mm3 14196
10.4 Yield series Year 1914 to 1977
10.5 Actual yield data after completion of
reservoir
Dam completed in the year
2009
- 55 -
Signature of Promoter/Developer No. of correction Signature of Inviter
Sr.
No
Description Data
11 Reservoir data
11.1 Average monthly fortnightly inflow
pattern in M cum in last 20 years
Dam completed in the year
2009
11.2 Dependability considered for reservoir
planning
75%
11.3 Gross storage Mcum 1146.075(With 100years
siltation)
11.4 Dead storage Mcum 405.907(With 100years
siltation)
11.5 Live storage Mcum 740.168(With 100years
siltation)
11.6 Carry over storage --
11.7 MDDL (in m.) 241.29
11.8 FRL (in m.) 245.50
11.9 TBL (in m.) 250.05
12 Detail of intake
12.1 Area capacity table in metric system -
12.2 Intake structure present status At CH 780.0m
12.3 ICPO provided/planned I.C.P.O. provided
12.4 Irrigation sluices work completed
13 Utilisation pattern
13.1 Penstock details 3.30m diameter
14 Area available for P.H. & ancillary
buildings
14.1 pattern -
14.2 P.H. location map --
14.3 Survey No. and location map on village
map
--
14.4 Possession status of land required --
15 Maps
15.1 Index Yes
15.2 Cross section of the dam --
15.3 Contour plan of the area on D/s side of dam --
15.4 Village map with survey No. & gat No. ---
15.5 Area Capacity Curve Yes
16 Details of nearest M.S.E.B.S/S M.S.E.B. power station ,
Paghora.
- 56 -
Signature of Promoter/Developer No. of correction Signature of Inviter
APPENDIX II GOSIKHURD (L.B.C) H.E.P. (1X500KW) (REVISED)
Sr.
No.
As per
Govt.
web
site
Name of the
project
Installed
capacity
MW
Taluka District Type of
Project
Project Description Salient
feature of
project
General topography,
Meteorology,
Climatology General topography of region Origin of
river
Locaon of
reservoir
Catchme
nt area in
sq.km.
Primary
objective of
project
Year
of first
filling
of
reserv
oir
Toposheet Latitude Longitude
Max. &
Min.
temperatu
re at
reservoir
site
Monthly
rate of
eveporat
ion
at
reservoir
site
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
1 30 Gosikhurd
L.B.C.
0.50 Pauni Bhanda
ra
Dam
foot
55P/9 200-52’-
15”N
790-37’-0” E Seoni
district in
Madhya
pradesh
Gosikhurd 34862 Irrigation 2009 Attached
separately
470C Max
& 50C
Min.
Attache
d in
working
Table
Hydrology Reservoir data
Catchment area
Sq.Km.
Average
annual rain
fall in mm.
75% & 50%
dependable
yield in Mcum
Yield
series
Actual yield
data after
complition of
reservoir
Avearge monthly
/fortnightly inflow
pattern in Mcum
in last 20Years
Dependail
ity
considere
d for
reservoir
planning
Gross
storage
Mcum
Dead
storage
Mcum
Live storage
Mcum
Carry over
storage
MDDL m
(Irri.)
FRL m TBL m Average
capacity table in
metric system
19 20 21 22 23 24 25 26 27 28 29 30 31 32 33
34862 1320 3410 Mm³
75%
Year
1914 to
1977
Dam completed
in the year
2009
Dam completed in
the year 2009
75% 1146.075M
m³
769.483
Mm³
376.592Mm³ -- 241.29m 245.50m 250.05m Attached
separately
Hydrology Reservoir data
Catchment area
Sq.Km.
Average
annual rain
fall in mm.
75% & 50%
dependable
yield in Mcum
Yield
series
Actual yield
data after
complition of
reservoir
Avearge monthly
/fortnightly inflow
pattern in Mcum
in last 20Years
Dependail
ity
considere
d for
reservoir
planning
Gross
storage
Mcum
Dead
storage
Mcum
Live storage
Mcum
Carry over
storage
MDDL m
(Irri.)
FRL m TBL m Average capacity table in metric
system
19 20 21 22 23 24 25 26 27 28 29 30 31 32 33
34862 1320 3410 Mm³
75%
Year
1914 to
1977
Dam completed
in the year
2009
Dam completed in
the year 2009
75% 1146.075M
m³
769.483
Mm³
376.592Mm³ -- 241.29m 245.50m 250.05m Attached separately
- 57 -
Signature of Promoter/Developer No. of correction Signature of Inviter
APPENDIX II
Gosikhurd National Project
Taluka- Pauni Dist.- Bhandara.
WORKING TABLE FOR THE YEAR 1953-54
( Corresponding to 75% dependable yield)
PARTICULARS LEVEL AREA CONTENTS
F.R.L. 245.500 222.577 740.168
M.D.D.L. 241.290 77.709 150.338
Sr.No
.
Month Opening condition of reservoir
Observed
Run-off
from
catchment
area(Mm³)
Total
content
(Mm³)
Withdrawal Evaporation Total
Water
Withhdrawal
(Mm³)
Closing condition of reservoir Spillov
er
(Mm³)
Remar
ks
Crop
water
require
ment
(Mm³)
Diversion
to
Asolamend
ha
(Mm³)
Water
required
for
ordnance
factory
(Mm³)
Water supply
to NTPC
Mauda
(Mm³)
Total
withdrawal
(Mm³)
8+9+10+11
Depth
In (m)
Qty
(Mm³
)
Capacity
(Mm³)
Area
(Mm²)
Level
(m) Water sprade
area (Mm²)
Capacit
y
(Mm³)
Water
level
(m)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
1 Jun15-30 115.07 533.789 241.7
5
18.618 552.407 26.713 12.61 1.04 4.17 44.533 0.126 9.891 54.424 497.983 107.86 241.5
2 July 107.86 497.983 241.5 503.192 1001.17
5
89.53 92.56 2.01 8.33 192.43 0.133 15.02
9
207.459 793.716 166.09 243.7
3 August 166.09 793.716 243.7 1541.951 2335.66
7
0.00 166.66 2.01 8.33 177.00 0.105 20.46
8
197.468 1146.26 222.96 245.5 991.9
39
4 Sept. 222.96 1146.26 245.5 826.758 1973.01
8
0.254 106.22 1.95 8.33 116.754 0.103 22.92
5
139.679 1146.26 222.96 245.5 678.0
79
5 Oct. 222.96 1146.26 245.5 165.715 1311.97
5
93.46 45.84 2.01 8.33 149.64 0.113 25.15 174.79 1137.185 221 245.45
6 Nov. 221 1137.18
5
245.4
5
91.365 1228.55 91.96 0.00 1.95 8.33 102.24 0.1 21.82
5
124.065 1104.485 216.15 245.3
7 Dec. 216.15 1104.48
5
245.3 68.789 1173.27
4
136.45 0.00 2.01 8.33 146.79 0.75 15.26
2
162.052 1011.222 202.76 244.9
8 Jan. 202.76 1011.22
2
244.9 42.933 1054.15
5
159.31 0.00 2.01 8.33 169.65 0.85 15 184.65 869.505 177.41 244.1
9 Feb. 177.41 869.505 244.1 46.657 916.162 151.89 0.00 1.82 8.33 162.04 0.135 19.77 181.81 734.352 155.21 243.3
10 Mar. 155.21 734.352 243.3 46.566 780.918 73.03 0.00 2.01 8.33 83.37 0.200 25.4 108.77 672.148 144.34 242.9
11 Apr. 144.34 672.148 242.9 32.683 704.831 47.3 0.00 1.95 8.33 57.58 0.248 28.58
2
86.162 618.669 133.46 242.5
12 May 133.46 618.669 242.5 16.25 634.919 33.2 5.55 2.01 8.33 49.09 0.362 36.73
9
85.829 549.09 117.47 241.9
13 Jun1-14 117.47 549.09 241.9 6.492 555.582 8.34 3.64 0.91 4.17 17.06 0.400 9.949 27.009 528.573 115.06 241.8
TOTAL 3407.969 911.43
7
433.08 23.69 99.97 265.9
9
1734.197 1679.0
18
Sd/- Sd/-
Subdivisional Engineer Executive Engineer
Gosikhurd Dam Sub-Division No.3 Gosikhurd Dam Division
Gosikhurd Wahi (Pavani)
- 58 -
Signature of Promoter/Developer No. of correction Signature of Inviter
APPENDIX III
GOSIKHURD (L.B.C.) HYDRO ELECTRIC PROJECT (1 x 500 K.W.)
FRL Storge (MW3) 740.168 MDDL 241.290 M
FRL (M) 245.50 RESERVOIR OPERATION TABLE AND POWER GENERATION MDDL Capacity 376.092 Mm3
MDDL (Power) (m) 241.873 FOR 75% DEPENDABLE YIELD CORRESPONDING YEAR 1955-54 MDDL Area 102.822 Mm2
MDDL (Irrigation) (M) 241.29 FRL 245.500 M
CBL (m) 238 FRL Capacity 740.170 Mm3
Av.TWL (m) 239.330 FRL Area 222.972 Mm2
Sr.No. Month
Days Irrg.
Power
Mean lake
level (m)
Utilization
for Area
24495 ha.
(Mm³)
Diversion
of spill for
power
generation
(Mm³)
Discharge cumecs
m³/sec.
T.W.L.
(m)
Head in
meter.
Power
generation
8xQxH
Restricted
to
installed
capacity
1x500KW
Energy
generation in
Mus.
∑QHT ∑QT Remarks
21 22 23 24 25 26 27 28 29 30 31 32 33 34 35
1 June-II 12/12 241.666 4.75 - 4.58 238.83 2.836 103.911 103.911 0.02992 155.866 54.96 Below MDDL Power
2 July 24/24 242.966 15.92 - 7.68 239.29 3.676 225.853 225.853 0.13009 677.560 184.32
Installed
Capacity
1 X 500 KW
3 August 24/24 244.90 26.40 - 12.73/11.60 239.51 5.39 548.917 500.00 0.288 1500.576 278.40
4 Sept. 24/24 245.50 26.40 - 12.73/10.44 239.51 5.99 610.021 500.00 0.288 1500.854 250.56
5 Oct. 24/24 245.483 16.62 - 8.015 239.30 6.183 396.453 396.453 0.22835 1189.361 192.36
6 Nov. 24/24 245.400 16.35 - 7.89 239.30 6.10 385.032 385.032 0.22177 1155.096 189.36
7 Dec. 24/24 245.166 24.27 - 11.71/10.96 239.46 5.706 534.538 500.00 0.288 1500.906 263.04
8 Jan. 24/24 244.633 28.33 - 12.75/12.20 239.51 5.123 522.546 500.00 0.288 1500.014 292.80
9 Feb 24/24 243.833 27.01 - 12.75 239.51 4.323 440.946 440.946 0.25398 1322.838 306.00
10 March 24/24 243.166 12.99 - 6.26 239.23 3.936 200.119 200.119 0.11526 591.344 150.24
11 April 24/24 242.766 8.41 - 4.06 238.77 3.996 129.790 129.790 0.07475 389.370 97.44
12 May 24/24 242.300 5.90 - 2.85 238.63 3.67 83.676 83.676 0.04819 251.028 68.40 Neglected due to low
generation
13 June-I 12/12 241.866 1.48 - 1.43 238.40 3.466 39.651 39.651 0.01141 59.476 17.16 Below MDDL Power
11327.919 2204.52
M.D.D.L. (Power) = Av. T.W.L. + 50% of design head 2.0674 weighted head = QHT / QT
= 239.330+ 5.087 /2 Deduct 1% other consumption (-) 0.0206 = 11327.919 /2204.52
= 239.330 + 2.543 Saleable Energy = 2.0468Mus. = 5.138m.
= 241.873m. Deduct 1% for Water conductor system(-) = 0.051m
5.087m. Prepared by:- Sd/- Sd/-
(S.S. Khare ) Subdivisional Engineer Executive Engineer
A.E.-II Gosikhurd Dam Sub-Division No.3 Gosikhurd Dam Division
Gosikhurd Wahi (Pavani)
- 59 -
Signature of Promoter/Developer No. of correction Signature of Inviter
APPENDIX IV
AREA CAPACITY TABLE AS PER VOLUME Q = H/3 ( A1+A2+√A1*A2 )
SR.NO. R.L.IN M R.L.IN
FEET
CONTOUR
INTERVAL
IN M
WATER
SPREAD
AREA IN
MM²
ROOT OF
AREA IN
MM²
CAPACITY
BETWEEN
TWO
SUCCESSIVE
CONTOUR
CUMMULATIVE
CAPACITY IN
MM³
CUMMULATIVE
CAPACITY IN
MCFT
REVISED
AREA IN
MM²
REVISED
CAPACITY
IN
MM³
REMARKS
1 2 3 4 5 6 7 8 9 10 11 12
1 222.675 730.561 REVISED
BED LEVEL
WHERE –
H =
CONTOUR
INTERVAL,
A1&A2 =
AREA OF
SUCCESSIVE
CONTOUR,
Q =
CAPACITY
BETWEEN
TWO
SUCCESSIVE
CONTOURS.
F.R.L. =
245.50M
CAPACITY-
1146 MM³
2 224.00 734.9082 1.325 0.39897 0.63164 0.17621 0.17621 6.222800 0 0
3 226.000 741.4698 2.00 228364 1.51117 2.42475 2.60096 91.85212 0 0
4 226.000 746.0315 2.00 6.16612 2.48317 8.13485 10.73579 379.13120 0 0
5 230.000 754.5932 2.00 11.29948 3.36147 17.20847 27.94426 986.84316 3.972 3.73136
6 232.000 761.1549 2.00 15.84810 3.98097 27.01996 54.96392 1941.03435 8.075 16.652
7 234.000 757.7166 2.00 24.35545 4.93512 39.90007 94.36399 3350.09335 16.391 39.815
8 236.000 774.2782 2.00 35.19740 5.93274 59.22109 154.08508 5441.46837 27.296 83.171
9 238.000 780.8349 2.00 53.5250 7.31608 88.08453 242.16961 8552.14713 45.573 155.804
10 240.000 787.4016 2.00 71.84240 8.47599 124.91895 376.08856 12963.62237 65.015 266.849
11 242.000 793.9633 2.00 119.87270 10.94864 189.67711 556.7657 19662.01261 144.408 443.759
12 244.000 800.5300 2.00 174.24724 13.200027 292.42996 849.19563 29989.08891 174.247 732.546
13 245.000 803.8052 1.00 205.93091 14.35030 189.86856 1039.06429 36694.24369 - -
14 246.000 - 1.00 240.00 - - 1220.000 - - -
“TRUE COPY”
Sd/-
Sub- Divisional Officer
Irrigation & Hydro Electric Project Investigation
Sub-Division No.1, Amravati.