Fidic Contracts Red & Yello

Post on 02-Oct-2015

15 views 3 download

description

Brief

Transcript of Fidic Contracts Red & Yello

FIDIC CONTRACTS Red & Yellow 1999

1. General Structure

CLAUSESDESCRIPTION

Clause 1General provisions

Clause 2 to 5The Employer, Employers Administration OR Engineer, Contractor, Nominated Subcontractors OR Design

Clause 6 - 7Staff and labour, Plant, materials and workmanship

Clause 8 to 11/12Commencement, delays and suspension, Tests on completion, Employers taking over, Defects Liability, Tests after completion

Clause 12 to 14Measurement and Evaluation OR Variations and Adjustments, Contract Price and Payment

Clause 15 to 16Termination by Employer, Suspension and Termination by Contractor

Clause 17Risk and Responsibility

Clause 18Insurance

Clause 19Force Majeure

Clause 20Claims, Disputes and Arbitration

2. Tender Documents & Employer Requirements

The employer requirements and specifications interface with contractual terms as envisaged by FIDIC. The following clauses rely either on the content of the specification or generally cross-refer to the specification:

Definition of Employers Equipment (clause 1.1.6.3) Permissions obtained by employer (clause 1.13(a)) Opportunities for works by others (clause 4.6) Values for emissions and discharges (clause 4.18) Details of employers equipment and free-issue materials (clause 4.19) Criteria for designers (clause 5.1) Technical documents to be included in contractors documents and language for contractors documents (clause 5.2) Contractors documents to be submitted for review and/or approval (clause 5.3) Other standards for compliance (clause 5.4) Training to be provided for employers personnel (clause 5.5) Numbers and types of copies of as-built drawings (clause 5.6) O&M manuals (clause 5.7) Arrangements for staff and labour (clause 6.1) Facilities for staff and labour (clause 6.6) Payment of royalties (clause 7.8)