EXECUTIVE SUMMARY REPORTWindsor Elementary School
June 30th, 2017
Questions? Contact: Project Manager, Sara Michalski (608) 729-2144 smichalski@findorff.com
Superintendent, Jeff Schuchardt (608) 220-2041 jschuchardt@findorff.com
Did you know? Findorff's in-house MEP department leads and supports commissioning tasks with regular visits to the project site to monitor construction and completion of the MEP systems. They use equipment start-up checklists to schedule the installation and testing of each system. This is valuable for project teams who do not have third-party commissioning agents.
Summer Strides!
Everything is making great progress at Windsor
Elementary! The 4th Grade resource area is
framed and drywall is starting. The classrooms
are getting primed and painted as well. Finishes
are in full force for the 3rd Grade space. Cubby
and floor installation is coming up soon! The
markerboards and tackboards are going up, and
light fixtures are in all of the classrooms. The
large exterior gym windows are going in, which
will bring plenty of natural light to the space.
Outside, the light poles for the new parking lot
are being set and grading is about to start. It’s a
busy summer, and Windsor is coming along
beautifully and on time!
The 4th Grade Resource Area is framed and moving along great!
Coming Up
• Flooring
• Cubby Install
• Nichiha Panel
• Tapping and Painting
The Past Weeks
• Ceiling Grid Install
• Resource Area Framing
• Lighting Fixtures
• Glazing Install The large gym windows are being installed. What a great source of natural light!.
EXECUTIVE SUMMARY REPORTWindsor Elementary School
June 30th, 2017
Questions? Contact: Project Manager, Sara Michalski (608) 729-2144 smichalski@findorff.com
Superintendent, Jeff Schuchardt (608) 220-2041 jschuchardt@findorff.com
Shown above, the countertop and casework for the 3rd grade resource area is being installed. There’s even a sink for easy hand-washing!
Above, Tackboards and Markerboards are being installed in the 3rd Grade Area!
Site light poles are being set in the new parking lot! The yellow base matches the lights in the existing parking lot.
Shown above, interior windows are going in throughout the building.