EXECUTIVE SUMMARY REPORT Windsor Elementary School June 30 th , 2017 Questions? Contact: Project Manager, Sara Michalski (608) 729-2144 [email protected] Superintendent, Jeff Schuchardt (608) 220-2041 [email protected] Did you know? Findorff's in-house MEP department leads and supports commissioning tasks with regular visits to the project site to monitor construction and completion of the MEP systems. They use equipment start-up checklists to schedule the installation and testing of each system. This is valuable for project teams who do not have third-party commissioning agents. Summer Strides! Everything is making great progress at Windsor Elementary! The 4 th Grade resource area is framed and drywall is starting. The classrooms are getting primed and painted as well. Finishes are in full force for the 3 rd Grade space. Cubby and floor installation is coming up soon! The markerboards and tackboards are going up, and light fixtures are in all of the classrooms. The large exterior gym windows are going in, which will bring plenty of natural light to the space. Outside, the light poles for the new parking lot are being set and grading is about to start. It’s a busy summer, and Windsor is coming along beautifully and on time! The 4 th Grade Resource Area is framed and moving along great! Coming Up Flooring Cubby Install Nichiha Panel Tapping and Painting The Past Weeks Ceiling Grid Install Resource Area Framing Lighting Fixtures Glazing Install The large gym windows are being installed. What a great source of natural light!.

Transcript of EXECUTIVE SUMMARY REPORT - DeForest High School Winds… · EXECUTIVE SUMMARY REPORT Windsor...

Page 1: EXECUTIVE SUMMARY REPORT - DeForest High School Winds… · EXECUTIVE SUMMARY REPORT Windsor Elementary School June 30 th, 2017 Questions? Contact: Project Manager, Sara Michalski

EXECUTIVE SUMMARY REPORTWindsor Elementary School

June 30th, 2017

Questions? Contact: Project Manager, Sara Michalski (608) 729-2144 [email protected]

Superintendent, Jeff Schuchardt (608) 220-2041 [email protected]

Did you know? Findorff's in-house MEP department leads and supports commissioning tasks with regular visits to the project site to monitor construction and completion of the MEP systems. They use equipment start-up checklists to schedule the installation and testing of each system. This is valuable for project teams who do not have third-party commissioning agents.

Summer Strides!

Everything is making great progress at Windsor

Elementary! The 4th Grade resource area is

framed and drywall is starting. The classrooms

are getting primed and painted as well. Finishes

are in full force for the 3rd Grade space. Cubby

and floor installation is coming up soon! The

markerboards and tackboards are going up, and

light fixtures are in all of the classrooms. The

large exterior gym windows are going in, which

will bring plenty of natural light to the space.

Outside, the light poles for the new parking lot

are being set and grading is about to start. It’s a

busy summer, and Windsor is coming along

beautifully and on time!

The 4th Grade Resource Area is framed and moving along great!

Coming Up

• Flooring

• Cubby Install

• Nichiha Panel

• Tapping and Painting

The Past Weeks

• Ceiling Grid Install

• Resource Area Framing

• Lighting Fixtures

• Glazing Install The large gym windows are being installed. What a great source of natural light!.

Page 2: EXECUTIVE SUMMARY REPORT - DeForest High School Winds… · EXECUTIVE SUMMARY REPORT Windsor Elementary School June 30 th, 2017 Questions? Contact: Project Manager, Sara Michalski

EXECUTIVE SUMMARY REPORTWindsor Elementary School

June 30th, 2017

Questions? Contact: Project Manager, Sara Michalski (608) 729-2144 [email protected]

Superintendent, Jeff Schuchardt (608) 220-2041 [email protected]

Shown above, the countertop and casework for the 3rd grade resource area is being installed. There’s even a sink for easy hand-washing!

Above, Tackboards and Markerboards are being installed in the 3rd Grade Area!

Site light poles are being set in the new parking lot! The yellow base matches the lights in the existing parking lot.

Shown above, interior windows are going in throughout the building.