PANTHER VILLAGEPhase II

11/16/2012 ConstructionUpdate

CURRENT WORK

West Wing- Exterior: Masonry and shingles finished, fascia and soffit work ongoing - 1st Floor: Final coat

of paint, casework installed, tile and grout installed- 2nd Floor: Final coat of paint, tile and casework installed- 3rd Floor: Tile and casework installed- Attic: doors installed (no hardware yet)

East Wing- Exterior: Masonry and shingles complete, fascia and soffit work ongoing- 1st Floor: Final coat of paint, casework and counter tops being installed - 2nd Floor: Painting, tile work mostly completed, casework being installed- 3rd Floor: Mudding and taping drywall, rough sanding

Central Lounge Area- Masonry completed

West Parking Lot- Paving completed

PANTHER VILLAGE

PANTHER VILLAGE

Brick and cast stone completed at Northwest lounge and stair area, curtain walls nearing completion .

PANTHER VILLAGE

Northwest lounge area curtain walls nearing completion.

PANTHER VILLAGE

Brick and cast stone complete on East wing. Northeast stair curtain wall not yet installed, flashing has started.

PANTHER VILLAGE

Brick and cast stone completed at central lounge and stair. Weather barrier also installed on cornice.

PANTHER VILLAGE

Temporary exterior enclosures installed.

PANTHER VILLAGE

Temporary heat installed throughout entire building to accommodate acceptable working conditions and protection for products.

PANTHER VILLAGE

First floor West corridor study/lounge area, metal stud framing completed.

PANTHER VILLAGE

First floor West corridor four bedroom apartment, kitchen cabinets and some counter tops installed.

PANTHER VILLAGE

First floor West corridor bedrooms, final coat of paint applied, visual display rails installed, shelving installed.

PANTHER VILLAGE

First floor East corridor studio apartment, kitchen cabinets installed, counter tops soon to be installed.

PANTHER VILLAGE

First floor East corridor bathrooms, tile floor and cabinets installed.

PANTHER VILLAGE

Cabinet Unit Heater installed in West corridor staircase.

PANTHER VILLAGE

West corridor third floor, curtain walls installed in private study room.

PANTHER VILLAGE

East corridor two bedroom corner apartment ready for first coat of paint.

PANTHER VILLAGE

Third floor central lounge area drywall being installed.

PANTHER VILLAGE

Forms set for stoops located at the Northwest entrance. Will soon be pouring concrete.

PANTHER VILLAGE

Bioswale located between the West wing of the building and the West parking lot.

PANTHER VILLAGE

Storm sewer line running from West parking lot to bioswale in place.

PANTHER VILLAGE

West parking paving complete.

PANTHER VILLAGE

Concrete work completed at loading dock area.