PANTHER VILLAGE Phase II 11/16/20 12 Constructio n Update

Transcript of CURRENT WORK West Wing - Exterior: Masonry and shingles finished, fascia and soffit work ongoing - 1...

Page 1: CURRENT WORK West Wing - Exterior: Masonry and shingles finished, fascia and soffit work ongoing - 1 st Floor: Final coat of paint, casework installed,

PANTHER VILLAGEPhase II

11/16/2012 ConstructionUpdate

Page 2: CURRENT WORK West Wing - Exterior: Masonry and shingles finished, fascia and soffit work ongoing - 1 st Floor: Final coat of paint, casework installed,

CURRENT WORK

West Wing- Exterior: Masonry and shingles finished, fascia and soffit work ongoing - 1st Floor: Final coat

of paint, casework installed, tile and grout installed- 2nd Floor: Final coat of paint, tile and casework installed- 3rd Floor: Tile and casework installed- Attic: doors installed (no hardware yet)

East Wing- Exterior: Masonry and shingles complete, fascia and soffit work ongoing- 1st Floor: Final coat of paint, casework and counter tops being installed - 2nd Floor: Painting, tile work mostly completed, casework being installed- 3rd Floor: Mudding and taping drywall, rough sanding

Central Lounge Area- Masonry completed

West Parking Lot- Paving completed

PANTHER VILLAGE

Page 3: CURRENT WORK West Wing - Exterior: Masonry and shingles finished, fascia and soffit work ongoing - 1 st Floor: Final coat of paint, casework installed,

PANTHER VILLAGE

Brick and cast stone completed at Northwest lounge and stair area, curtain walls nearing completion .

Page 4: CURRENT WORK West Wing - Exterior: Masonry and shingles finished, fascia and soffit work ongoing - 1 st Floor: Final coat of paint, casework installed,

PANTHER VILLAGE

Northwest lounge area curtain walls nearing completion.

Page 5: CURRENT WORK West Wing - Exterior: Masonry and shingles finished, fascia and soffit work ongoing - 1 st Floor: Final coat of paint, casework installed,

PANTHER VILLAGE

Brick and cast stone complete on East wing. Northeast stair curtain wall not yet installed, flashing has started.

Page 6: CURRENT WORK West Wing - Exterior: Masonry and shingles finished, fascia and soffit work ongoing - 1 st Floor: Final coat of paint, casework installed,

PANTHER VILLAGE

Brick and cast stone completed at central lounge and stair. Weather barrier also installed on cornice.

Page 7: CURRENT WORK West Wing - Exterior: Masonry and shingles finished, fascia and soffit work ongoing - 1 st Floor: Final coat of paint, casework installed,

PANTHER VILLAGE

Temporary exterior enclosures installed.

Page 8: CURRENT WORK West Wing - Exterior: Masonry and shingles finished, fascia and soffit work ongoing - 1 st Floor: Final coat of paint, casework installed,

PANTHER VILLAGE

Temporary heat installed throughout entire building to accommodate acceptable working conditions and protection for products.

Page 9: CURRENT WORK West Wing - Exterior: Masonry and shingles finished, fascia and soffit work ongoing - 1 st Floor: Final coat of paint, casework installed,

PANTHER VILLAGE

First floor West corridor study/lounge area, metal stud framing completed.

Page 10: CURRENT WORK West Wing - Exterior: Masonry and shingles finished, fascia and soffit work ongoing - 1 st Floor: Final coat of paint, casework installed,

PANTHER VILLAGE

First floor West corridor four bedroom apartment, kitchen cabinets and some counter tops installed.

Page 11: CURRENT WORK West Wing - Exterior: Masonry and shingles finished, fascia and soffit work ongoing - 1 st Floor: Final coat of paint, casework installed,

PANTHER VILLAGE

First floor West corridor bedrooms, final coat of paint applied, visual display rails installed, shelving installed.

Page 12: CURRENT WORK West Wing - Exterior: Masonry and shingles finished, fascia and soffit work ongoing - 1 st Floor: Final coat of paint, casework installed,

PANTHER VILLAGE

First floor East corridor studio apartment, kitchen cabinets installed, counter tops soon to be installed.

Page 13: CURRENT WORK West Wing - Exterior: Masonry and shingles finished, fascia and soffit work ongoing - 1 st Floor: Final coat of paint, casework installed,

PANTHER VILLAGE

First floor East corridor bathrooms, tile floor and cabinets installed.

Page 14: CURRENT WORK West Wing - Exterior: Masonry and shingles finished, fascia and soffit work ongoing - 1 st Floor: Final coat of paint, casework installed,

PANTHER VILLAGE

Cabinet Unit Heater installed in West corridor staircase.

Page 15: CURRENT WORK West Wing - Exterior: Masonry and shingles finished, fascia and soffit work ongoing - 1 st Floor: Final coat of paint, casework installed,

PANTHER VILLAGE

West corridor third floor, curtain walls installed in private study room.

Page 16: CURRENT WORK West Wing - Exterior: Masonry and shingles finished, fascia and soffit work ongoing - 1 st Floor: Final coat of paint, casework installed,

PANTHER VILLAGE

East corridor two bedroom corner apartment ready for first coat of paint.

Page 17: CURRENT WORK West Wing - Exterior: Masonry and shingles finished, fascia and soffit work ongoing - 1 st Floor: Final coat of paint, casework installed,

PANTHER VILLAGE

Third floor central lounge area drywall being installed.

Page 18: CURRENT WORK West Wing - Exterior: Masonry and shingles finished, fascia and soffit work ongoing - 1 st Floor: Final coat of paint, casework installed,

PANTHER VILLAGE

Forms set for stoops located at the Northwest entrance. Will soon be pouring concrete.

Page 19: CURRENT WORK West Wing - Exterior: Masonry and shingles finished, fascia and soffit work ongoing - 1 st Floor: Final coat of paint, casework installed,

PANTHER VILLAGE

Bioswale located between the West wing of the building and the West parking lot.

Page 20: CURRENT WORK West Wing - Exterior: Masonry and shingles finished, fascia and soffit work ongoing - 1 st Floor: Final coat of paint, casework installed,

PANTHER VILLAGE

Storm sewer line running from West parking lot to bioswale in place.

Page 21: CURRENT WORK West Wing - Exterior: Masonry and shingles finished, fascia and soffit work ongoing - 1 st Floor: Final coat of paint, casework installed,

PANTHER VILLAGE

West parking paving complete.

Page 22: CURRENT WORK West Wing - Exterior: Masonry and shingles finished, fascia and soffit work ongoing - 1 st Floor: Final coat of paint, casework installed,

PANTHER VILLAGE

Concrete work completed at loading dock area.